CN105545335A - Support-shield-type cross-slip temporary support bracket and support method thereof - Google Patents

Support-shield-type cross-slip temporary support bracket and support method thereof Download PDF

Info

Publication number
CN105545335A
CN105545335A CN201610128064.9A CN201610128064A CN105545335A CN 105545335 A CN105545335 A CN 105545335A CN 201610128064 A CN201610128064 A CN 201610128064A CN 105545335 A CN105545335 A CN 105545335A
Authority
CN
China
Prior art keywords
group
frame
side arm
interior
support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610128064.9A
Other languages
Chinese (zh)
Other versions
CN105545335B (en
Inventor
马长青
蒋金泉
刘登彪
秦广鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong University of Science and Technology
Original Assignee
Shandong University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong University of Science and Technology filed Critical Shandong University of Science and Technology
Priority to CN201610128064.9A priority Critical patent/CN105545335B/en
Publication of CN105545335A publication Critical patent/CN105545335A/en
Application granted granted Critical
Publication of CN105545335B publication Critical patent/CN105545335B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D23/00Mine roof supports for step- by- step movement, e.g. in combination with provisions for shifting of conveyors, mining machines, or guides therefor
    • E21D23/0004Mine roof supports for step- by- step movement, e.g. in combination with provisions for shifting of conveyors, mining machines, or guides therefor along the working face
    • E21D23/0017Pile type supports
    • E21D23/0021Pile type supports comprising two walking elements
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D23/00Mine roof supports for step- by- step movement, e.g. in combination with provisions for shifting of conveyors, mining machines, or guides therefor
    • E21D23/0086Mine roof supports for step- by- step movement, e.g. in combination with provisions for shifting of conveyors, mining machines, or guides therefor in galleries
    • E21D23/0095Temporary supports at the driving front
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D23/00Mine roof supports for step- by- step movement, e.g. in combination with provisions for shifting of conveyors, mining machines, or guides therefor
    • E21D23/04Structural features of the supporting construction, e.g. linking members between adjacent frames or sets of props; Means for counteracting lateral sliding on inclined floor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D23/00Mine roof supports for step- by- step movement, e.g. in combination with provisions for shifting of conveyors, mining machines, or guides therefor
    • E21D23/16Hydraulic or pneumatic features, e.g. circuits, arrangement or adaptation of valves, setting or retracting devices
    • E21D23/18Hydraulic or pneumatic features, e.g. circuits, arrangement or adaptation of valves, setting or retracting devices of advancing mechanisms
    • E21D23/20Hydraulic or pneumatic features, e.g. circuits, arrangement or adaptation of valves, setting or retracting devices of advancing mechanisms for sequential movement, e.g. one behind the other

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a support-shield-type cross-slip temporary support bracket and a support method thereof. The temporary bracket comprises two four-column bracket bodies with the same structure and a hydraulic system; the four-column bracket bodies are arranged front and back, push-pull oil cylinders are arranged between bottom beams of the front bracket body and bottom beams of the back bracket body, and then a front-pull back-push combined bracket body is formed; cross beams are provided with at least two pairs of jacks, each pair of the jacks are provided with short cross beams, and each short cross beam can rise and fall alone to achieve supporting on partial top plates. When temporary support on an excavation roadway is performed, one group serves as an external group, the other group serves as an internal group, the width of the internal group is smaller than that of the external group, the internal group can enter the external group and penetrate through the external group, therefore, the external group and the internal group achieve transposition and independently move, and the purposes that the temporary support bracket moves flexibly in actual application and can be supported on most of the top plates when the exploded top plates are not flat or the top plates are not a complete plane are achieved.

Description

Support shield type interlocks slippage temporary shoring bracket and supporting method thereof
Technical field
The present invention relates to roadway head temporary lining technology.
Background technology
At present, the temporary lining form that down-hole driving face adopts has the forms such as " post of attaching the names of pre-determined candidates " supporting, front canopy support and temporary shoring bracket.Adopt temporary shoring bracket with the immediate technology of the present invention.Chinese patent 201310022580.X discloses a kind of driving face automatic moving type temporary lining hydraulic support and supporting method thereof, and it comprises the side arm of a four-column type, the after-frame of a four-column type and hydraulic system; Side arm and after-frame are all made up of the back timber of two longitudinal directions, the bottom girder of two longitudinal directions and four retractility columns, the upper frame that many crossbeams form roof supporting is provided with above two rnnning bars, four-column type side arm and after-frame nest together, and form a drawing and pulling type Combined shelf body; By hydraulic system, side arm and after-frame can be elevated and can pull mutually, realize hydraulic support and move forward with work plane.The deficiency of this technology is, 1, because four-column type side arm and after-frame nest together, be subject to distortion in actual applications, cause pull dumb, move forward difficulty, 2, be an integrated member due to upper frame, can only integral elevating, when the top board out-of-flatness of explosion or when top board is not complete plane, can only be supported on several points of lowest part, cause large portion top board unsettled.
Summary of the invention
The object of the invention is to overcome the deficiencies in the prior art, propose a kind of support shield type and to interlock slippage temporary shoring bracket.
The present invention proposes the temporary lining method utilizing this support at roadway head simultaneously.
A kind of support shield type interlocks slippage temporary shoring bracket, comprises two identical four-column type support bodys of structure and hydraulic system; The three-dimensional support body that four-column type support body is made up of bottom girder and four telescopic posts of the back timber of two longitudinal directions, many crossbeams, two longitudinal directions, is characterized in that:
Arrange before and after two four-column type support bodys, be called front frame body and back frame body, between front frame body and the bottom girder of back frame body, be provided with push cylinder, form one and pull in front and others push behind formula Combined shelf body; By hydraulic system, two four-column type support bodys can be elevated and can push-and-pull mutually, realize Combined shelf body and move forward with the advance of the face;
Described crossbeam is also provided with at least two pairs of jack, and often pair of jack is provided with tail trimmer, and every root tail trimmer can be elevated separately, realizes supporting to local top board.
The temporary lining method of this support to roadway head is utilized to be:
The first step, layout initial position
Arrange two groups of falseworks at digging laneway work plane, wherein one group is outer group, and one group is Inner group, Inner group is than outer group of little certain size on width, and Inner group can to enter in outer group and to pass from outer group, makes outer group and Inner group transposition, outer group at front, interior group rear, arrange near work on hand face, their side arm and after-frame are all in contraction state, all tail trimmer roof supportings, under temporary lining, blow out above, discharge refuse, normally tunnel, after carry out permanent support;
Second step, interior group to reach frame
After discharge refuse of blowing out above completes a drilling depth, permanent support also completes below, should immediately by interior group to reach frame, support the sky top after blowing out;
First is moved frame process:
1, top board is left in contracting under the side arm tail trimmer of interior group, then, frame falls in the side arm of group, falls below beam height that frame height organizes outside;
2, in after falling frame, the push cylinder of group is stretched out, and moves up in the after-frame of outer group before promoting side arm;
3, then interior group side arm rises frame, and regulates jack to make tail trimmer be supported on top board;
4, frame falls in the after-frame of interior group, and in after falling frame, the push cylinder of group is retracted, and pulls after-frame to move forward, and near side arm, now, completes first to reach frame process;
Second is moved frame process:
1, the after-frame of interior group is risen frame, and regulate jack to make tail trimmer be supported on top board, top board is left in contracting under the side arm tail trimmer of interior group, then, frame falls in the side arm of group, falls below beam height that frame height organizes outside;
2, in operation, the push cylinder of group is stretched out, and moves up in the side arm of outer group before promoting side arm;
3, then interior group side arm rises frame, and regulates jack to make;
4, frame falls in the after-frame of interior group, and in after falling frame, the push cylinder of group is retracted, and pulls after-frame to move forward near side arm, makes interior group and outer group of coincidence; Now, second is completed to reach frame process;
3rd is moved frame process:
1, top board is left in contracting under the side arm tail trimmer of interior group, after-frame tail trimmer is supported on top board;
2, in operation, the push cylinder of group is stretched out, and promotes side arm and is advanced to before outer group of side arm, and the work plane after blow out, and then, group side arm rises frame, and on sky top after regulating jack to make tail trimmer be supported on explosion, interior group of after-frame overlaps with outer group of side arm; Now, the 3rd is completed to reach frame process; Under temporary lining, again to blow out, discharge refuse, normally tunnel;
4th is moved frame process:
After having tunneled a drilling depth, should immediately by interior group to reach frame, support the sky top after again blowing out;
Interior group to reach frame process with the 3rd to move frame process identical, make interior group of side arm move to the work plane after again blowing out, organize side arm then and rise frame, and regulate jack to make tail trimmer be supported on top board; In operation, the push cylinder of group is retracted again, pulls interior group of after-frame to be advanced to before outer group of side arm, and regulates jack that tail trimmer is supported on top board, thus make interior group at front, outer group rear;
3rd step, outer group to reach frame
Continue driving to blow out, often tunnel a drilling depth, make outer group to reach frame according to second step, move outrigger in frame process and pass through outside internal frame, until return to the initial position of the first step;
4th step, so circulates, until whole piece tunnelling is complete.
Good effect of the present invention is, 1, because interior group is not mutually nested with outer group, respective independent mobile, be not easy distortion in actual applications, mobile flexibly, 2, because upper frame is provided with telescopic more piece short beam, can be elevated separately, when the top board out-of-flatness of explosion or when top board is not complete plane, can be supported on most of top board.
Accompanying drawing explanation
Fig. 1 is that support shield type interlocks the front view of slippage falsework;
Fig. 2 is the top view of Fig. 1;
Fig. 3 is the right view of Fig. 1;
Fig. 4 is interior group and outer group of initial position arrangement diagram;
Fig. 5, Fig. 6, Fig. 7, Fig. 8, Fig. 9 are interior group and move frame procedure chart;
Figure 10 is interior group and moves in after frame group at front, outer group at rear arrangement diagram.
Marginal data, 1-bottom girder; 2-column; 3-back timber; 4-jack; 5-tail trimmer; 6-push cylinder; 7-crossbeam.
Detailed description of the invention
Technical scheme of the present invention is further illustrated below in conjunction with accompanying drawing.
As shown in Figure 1, Figure 2, Figure 3 shows, support shield type of the present invention interlocks slippage temporary shoring bracket, comprises two identical four-column type support bodys of structure and hydraulic system; The three-dimensional support body that four-column type support body is made up of bottom girder 1 and four telescopic posts 2 of the back timber 3 of two longitudinal directions, many crossbeams 7, two longitudinal directions; Wherein:
Arrange before and after two four-column type support bodys, be called front frame body and back frame body, between the bottom girder 1 of front frame body and back frame body, be provided with push cylinder 6, form one and pull in front and others push behind formula Combined shelf body; By hydraulic system, two four-column type support bodys can be elevated and can push-and-pull mutually, realize Combined shelf body and move forward with the advance of the face;
Described crossbeam 7 is also provided with at least two pairs of jack 4, and often pair of jack 4 is provided with tail trimmer 5, and every root tail trimmer 5 can be elevated separately, realizes supporting to local top board.
This support is utilized in the temporary lining method of roadway head to be:
The first step, layout initial position
Arrange two groups of falseworks at digging laneway work plane, wherein one group is outer group, and one group is Inner group, Inner group is than outer group of little certain size on width, and Inner group can to enter in outer group and to pass from outer group, makes outer group and Inner group transposition, during layout outer group at front, interior group rear, arrange near work on hand face, their side arm and after-frame are all in contraction state, all tail trimmer 5 roof supportings, under temporary lining, blow out above, discharge refuse, normally tunnel, after carry out permanent support; As shown in Figure 4;
Second step, interior group to reach frame
After discharge refuse of blowing out above completes a drilling depth, permanent support also completes below, should immediately by interior group to reach frame, support the sky top after blowing out;
First is moved frame process:
1, top board is left in side arm tail trimmer 5 times contractings of interior group, then, frame falls in the side arm of group, falls below crossbeam 7 height that frame height organizes outside (as shown in Figure 5);
2, in after falling frame, the push cylinder 6 of group is stretched out, and moves up into (as shown in Figure 6) in the after-frame of outer group before promoting side arm;
3, then interior group side arm rises frame, and regulates jack 4 to make tail trimmer 5 be supported on (as shown in Figure 7) on top board;
4, frame falls in the after-frame of interior group, and in after falling frame, the push cylinder 6 of group is retracted, and pulls after-frame to move forward, near side arm, as shown in Figure 8); Now, first is completed to reach frame process;
Second is moved frame process:
1, the after-frame of interior group is risen frame, and regulate jack 4 to make tail trimmer 5 be supported on top board, top board is left in side arm tail trimmer 5 times contractings of interior group, then, frame falls in the side arm of group, falls below crossbeam 7 height that frame height organizes outside;
2, in operation, the push cylinder 6 of group is stretched out, and moves up in the side arm of outer group before promoting side arm;
3, then interior group side arm rises frame, and regulates jack 4 to make tail trimmer 5 be supported on top board;
4, frame falls in the after-frame of interior group, and in after falling frame, the push cylinder 6 of group is retracted, and pulls after-frame to move forward near side arm, makes interior group and outer group of coincidence; Now, second is completed to reach frame process;
3rd is moved frame process:
1, top board is left in side arm tail trimmer 5 times contractings of interior group, after-frame tail trimmer 5 is supported on top board;
2, in operation, the push cylinder 6 of group is stretched out, and promotes side arm and is advanced to before outer group of side arm, and the work plane after blow out, and then, group side arm rises frame, and on sky top after regulating jack 4 to make tail trimmer 5 be supported on explosion, interior group of after-frame overlaps with outer group of side arm; Now, the 3rd is completed to reach frame process; Under temporary lining, again to blow out, discharge refuse, normally tunnel; (as shown in Figure 9);
4th is moved frame process:
After having tunneled a drilling depth, should immediately by interior group to reach frame, support the sky top after again blowing out; Interior group to reach frame process with the 3rd to move frame process identical, make interior group of side arm move to the work plane after again blowing out, organize side arm then and rise frame, and regulate jack 4 to make tail trimmer 5 be supported on top board; In operation, the push cylinder 6 of group is retracted again, pulls interior group of after-frame to be advanced to before outer group of side arm, and regulates jack 4 to make tail trimmer 5 be supported on top board; Thus make interior group at front, outer group in rear (as shown in Figure 10);
3rd step, outer group to reach frame
Continue driving to blow out, often tunnel a drilling depth, make outer group to reach frame according to second step, move frame process outrigger and pass through outside internal frame, until return to the initial position of the first step, (as shown in Figure 4);
4th step, so circulates, until whole piece tunnelling is complete.

Claims (2)

1. support shield type interlocks a slippage temporary shoring bracket, comprises two identical four-column type support bodys of structure and hydraulic system; The three-dimensional support body that four-column type support body is made up of bottom girder and four telescopic posts of the back timber of two longitudinal directions, many crossbeams, two longitudinal directions, is characterized in that:
Arrange before and after two four-column type support bodys, be called front frame body and back frame body, between front frame body and the bottom girder of back frame body, be provided with push cylinder, form one and pull in front and others push behind formula Combined shelf body; By hydraulic system, two four-column type support bodys can be elevated and can push-and-pull mutually, realize Combined shelf body and move forward with the advance of the face;
Described crossbeam is also provided with at least two pairs of jack, and often pair of jack is provided with tail trimmer, and every root tail trimmer can be elevated separately, realizes supporting to local top board.
2. utilize the temporary shoring bracket described in claim 1 to a temporary lining method for roadway head, it is characterized in that:
The first step, layout initial position
Arrange two groups of falseworks at digging laneway work plane, wherein one group is outer group, and one group is Inner group, Inner group is than outer group of little certain size on width, and Inner group can to enter in outer group and to pass from outer group, makes outer group and Inner group transposition, outer group at front, interior group rear, arrange near work on hand face, their side arm and after-frame are all in contraction state, all tail trimmer roof supportings, under temporary lining, blow out above, discharge refuse, normally tunnel, after carry out permanent support;
Second step, interior group to reach frame
After discharge refuse of blowing out above completes a drilling depth, permanent support also completes below, should immediately by interior group to reach frame, support the sky top after blowing out;
First is moved frame process:
1, top board is left in contracting under the side arm tail trimmer of interior group, then, frame falls in the side arm of group, falls below beam height that frame height organizes outside;
2, in after falling frame, the push cylinder of group is stretched out, and moves up in the after-frame of outer group before promoting side arm;
3, then interior group side arm rises frame, and regulates jack to make tail trimmer be supported on top board;
4, frame falls in the after-frame of interior group, and in after falling frame, the push cylinder of group is retracted, and pulls after-frame to move forward, and near side arm, now, completes first to reach frame process;
Second is moved frame process:
1, the after-frame of interior group is risen frame, and regulate jack to make tail trimmer be supported on top board, top board is left in contracting under the side arm tail trimmer of interior group, then, frame falls in the side arm of group, falls below beam height that frame height organizes outside;
2, in operation, the push cylinder of group is stretched out, and moves up in the side arm of outer group before promoting side arm;
3, then interior group side arm rises frame, and regulates jack to make;
4, frame falls in the after-frame of interior group, and in after falling frame, the push cylinder of group is retracted, and pulls after-frame to move forward near side arm, makes interior group and outer group of coincidence; Now, second is completed to reach frame process;
3rd is moved frame process:
1, top board is left in contracting under the side arm tail trimmer of interior group, after-frame tail trimmer is supported on top board;
2, in operation, the push cylinder of group is stretched out, and promotes side arm and is advanced to before outer group of side arm, and the work plane after blow out, and then, group side arm rises frame, and on sky top after regulating jack to make tail trimmer be supported on explosion, interior group of after-frame overlaps with outer group of side arm; Now, the 3rd is completed to reach frame process; Under temporary lining, again to blow out, discharge refuse, normally tunnel;
4th is moved frame process:
After having tunneled a drilling depth, should immediately by interior group to reach frame, support the sky top after again blowing out;
Interior group to reach frame process with the 3rd to move frame process identical, make interior group of side arm move to the work plane after again blowing out, organize side arm then and rise frame, and regulate jack to make tail trimmer be supported on top board; In operation, the push cylinder of group is retracted again, pulls interior group of after-frame to be advanced to before outer group of side arm, and regulates jack that tail trimmer is supported on top board, thus make interior group at front, outer group rear;
3rd step, outer group to reach frame
Continue driving to blow out, often tunnel a drilling depth, make outer group to reach frame according to second step, move outrigger in frame process and pass through outside internal frame, until return to the initial position of the first step;
4th step, so circulates, until whole piece tunnelling is complete.
CN201610128064.9A 2016-03-07 2016-03-07 Support shield type staggeredly slides temporary shoring bracket and its method for protecting support Active CN105545335B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610128064.9A CN105545335B (en) 2016-03-07 2016-03-07 Support shield type staggeredly slides temporary shoring bracket and its method for protecting support

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610128064.9A CN105545335B (en) 2016-03-07 2016-03-07 Support shield type staggeredly slides temporary shoring bracket and its method for protecting support

Publications (2)

Publication Number Publication Date
CN105545335A true CN105545335A (en) 2016-05-04
CN105545335B CN105545335B (en) 2017-12-26

Family

ID=55824840

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610128064.9A Active CN105545335B (en) 2016-03-07 2016-03-07 Support shield type staggeredly slides temporary shoring bracket and its method for protecting support

Country Status (1)

Country Link
CN (1) CN105545335B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112302695A (en) * 2020-10-22 2021-02-02 中电建南方建设投资有限公司 Temporary supporting method for mine excavation
CN113882889A (en) * 2021-11-01 2022-01-04 安徽理工大学 Head-tail interactive sliding type anchor support integrated equipment and control method
CN114233358A (en) * 2021-12-29 2022-03-25 安阳永安贺驼煤矿有限公司 Bag type filling support device for top of stoping roadway

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5368369A (en) * 1993-03-23 1994-11-29 Council Of Scientific & Industrial Research Equipment useful for winning ores particularly coal in longwall mining
CN202628150U (en) * 2012-05-31 2012-12-26 山西东华机械有限公司 Self-moving type follow-up end bracket
CN102913268A (en) * 2012-11-16 2013-02-06 山东矿机集团股份有限公司 Mobile support bracket of tunneling machine
CN202946177U (en) * 2012-10-25 2013-05-22 高宇 Improved hydraulic support used for coal mines
CN103306696A (en) * 2012-03-15 2013-09-18 陕西火石咀煤矿有限责任公司 Self-moving roadway advance support bracket
CN203531940U (en) * 2013-07-25 2014-04-09 河南焦煤能源有限公司九里山矿 Stepping type advanced supporting and hydraulic support
CN203756208U (en) * 2014-03-25 2014-08-06 山东科技大学 Top beam telescopic driving working face temporary timbering support

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5368369A (en) * 1993-03-23 1994-11-29 Council Of Scientific & Industrial Research Equipment useful for winning ores particularly coal in longwall mining
CN103306696A (en) * 2012-03-15 2013-09-18 陕西火石咀煤矿有限责任公司 Self-moving roadway advance support bracket
CN202628150U (en) * 2012-05-31 2012-12-26 山西东华机械有限公司 Self-moving type follow-up end bracket
CN202946177U (en) * 2012-10-25 2013-05-22 高宇 Improved hydraulic support used for coal mines
CN102913268A (en) * 2012-11-16 2013-02-06 山东矿机集团股份有限公司 Mobile support bracket of tunneling machine
CN203531940U (en) * 2013-07-25 2014-04-09 河南焦煤能源有限公司九里山矿 Stepping type advanced supporting and hydraulic support
CN203756208U (en) * 2014-03-25 2014-08-06 山东科技大学 Top beam telescopic driving working face temporary timbering support

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112302695A (en) * 2020-10-22 2021-02-02 中电建南方建设投资有限公司 Temporary supporting method for mine excavation
CN113882889A (en) * 2021-11-01 2022-01-04 安徽理工大学 Head-tail interactive sliding type anchor support integrated equipment and control method
CN113882889B (en) * 2021-11-01 2024-02-27 安徽理工大学 Head-tail interactive sliding type anchor support integrated equipment and control method
CN114233358A (en) * 2021-12-29 2022-03-25 安阳永安贺驼煤矿有限公司 Bag type filling support device for top of stoping roadway
CN114233358B (en) * 2021-12-29 2024-04-12 安阳永安贺驼煤矿有限公司 Bag-type filling support device for top of stope

Also Published As

Publication number Publication date
CN105545335B (en) 2017-12-26

Similar Documents

Publication Publication Date Title
CN105545334B (en) Work continuously variable area temporary shoring bracket and its operating method
CN103089286B (en) Driving face self-moving temporary support hydraulic support and support method thereof
CN105545335A (en) Support-shield-type cross-slip temporary support bracket and support method thereof
CN109441497B (en) Complete equipment for advanced support and transportation without repeated support and transportation method
CN105545336A (en) Longitudinal beam interlacing supporting type temporary supporting method for drifting face
CN105089053A (en) Pile frame and using and mounting method thereof
CN105697045A (en) Supporting type temporary supporting method with telescopic top beams for tunneling face
CN110565983B (en) Building jacking and shifting method
CN209761465U (en) Non-repeated support advance support and carrying complete equipment
CN203756208U (en) Top beam telescopic driving working face temporary timbering support
CN112096436B (en) Combined support for cyclic support of tunneling working face
CN212614810U (en) Novel triangular space supporting device
CN110219681B (en) Movable temporary supporting device and construction method thereof
CN203756209U (en) Longitudinal-girder staggered temporary support for heading face
CN210563476U (en) Pipe erecting equipment
CN109578040B (en) Temporary tunneling support equipment with guide support
CN203050754U (en) Self-moving temporary supporting hydraulic support for driving working face
CN110159327A (en) Dig the continuous temporary support device for drivage in tunnel and method of anchor separation
CN106835984B (en) The reverse construction method of installation of slug matching bridge Bridge Erector
US3367448A (en) Mobile elevator
CN211287737U (en) Upright post double-position device of sliding support
CN114233334A (en) Roadway lapping auxiliary device
CN108756984B (en) Fore support and anti-impact fore support system
CN108119173B (en) Self-moving type telescopic front canopy and supporting method thereof
US3854295A (en) Mining equipment

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant