CN105544983A - Light steel keel gypsum board furred ceiling construction process - Google Patents

Light steel keel gypsum board furred ceiling construction process Download PDF

Info

Publication number
CN105544983A
CN105544983A CN201510935185.XA CN201510935185A CN105544983A CN 105544983 A CN105544983 A CN 105544983A CN 201510935185 A CN201510935185 A CN 201510935185A CN 105544983 A CN105544983 A CN 105544983A
Authority
CN
China
Prior art keywords
gypsum
board
construction process
keels
light steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510935185.XA
Other languages
Chinese (zh)
Inventor
曹雁冰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ANHUI WEIHONG STEEL STRUCTURE GROUP Co Ltd
Original Assignee
ANHUI WEIHONG STEEL STRUCTURE GROUP Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ANHUI WEIHONG STEEL STRUCTURE GROUP Co Ltd filed Critical ANHUI WEIHONG STEEL STRUCTURE GROUP Co Ltd
Priority to CN201510935185.XA priority Critical patent/CN105544983A/en
Publication of CN105544983A publication Critical patent/CN105544983A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Finishing Walls (AREA)

Abstract

The invention discloses a light steel keel gypsum board furred ceiling construction process. The light steel keel gypsum board furred ceiling construction process includes the following steps of: measuring the ceiling designed elevation by using a rule, ejecting a cross intersection point of a steel bar suspender along a wall and a column, and welding and fixing the upper end of the steel bar suspender and an expansion bolt; arranging a hanger on a primary keel in advance, connecting the primary keels, arranging connection pieces, pulling a line to adjust the elevation, performing arching and straightening, and fixing edge keels; hanging secondary keels onto the primary keels through hanging pieces, wherein the spacing between the secondary keels is 450-550mm; Arranging gypsum boards from the center of the ceiling in the direction the secondary keels, wherein the gypsum boards extend toward two sides and are arranged in a block manner, and the gypsum boards are fixed to the primary keels and the secondary keels through self-tapping screws; and inserting gypsum putty into board gaps in twice, pasting board gap connection paper tapes on the board gaps through a varnish jointing agent after the gypsum putty is dry at the second time, and then brushing the board gaps with the gypsum putty again. The light steel keel gypsum board furred ceiling construction process is simple, is easy to operate, is good in decorative effect, is solid in ceiling, is long in service life, and can effectively prevent crack and deformation of the gypsum boards.

Description

A kind of light steel keel gypsum board ceiling construction process
Technical field
The present invention relates to furred ceiling technique, specifically a kind of light steel keel gypsum board ceiling construction process.
Background technology
Gypsum plank take plaster of Paris as a kind of material that primary raw material is made.It is a kind of lightweight, intensity is higher, thinner thickness, easy to process and sound insulation is adiabatic and the constructional materials of the better performances such as fire prevention, is one of novel light sheet material of current development emphatically.Gypsum plank has been widely used in the internal partition wall of the various building such as house, office building, shop, hotel and industrial premises, body of wall cladding boards (replacement floated coat), ceiling, abatvoix, surface based laminate and various decorative panels etc.
Gypsum suspended ceiling decorative plate is most widely used a kind of Novel ceiling ornament materials in the current home decoration of China.Gypseous decorating board mainly contains following several kind and function: moistureproof gypseous decorating board is specially adapted to washroom, the decoration in kitchen; Acoustical gypsum board has very strong noise-proofing function; Complex gypseous decorating board can be incubated, heat insulation, has decoration function again; Thistle board is of many uses, and decoration function is strong, is applicable to room, furred ceiling.But, in engineering practice, easily cause the defects such as furred ceiling loosens, distortion, crack due to a variety of causes.
Summary of the invention
The object of the present invention is to provide a kind of light steel keel gypsum board ceiling construction process.
Object of the present invention can be achieved through the following technical solutions:
A kind of light steel keel gypsum board ceiling construction process, is characterized in that, comprise the following steps:
(1) by dipstick metering ceiling design elevation, along the cross intersection point of wall, post ejection reinforcing bar suspension rod, horizontal allowable variation is less than 5mm; Determine the absolute altitude of reinforcing bar suspension rod lower end, be welded and fixed in reinforcing bar suspension rod upper end and expansion bolt, reinforcing bar suspension rod is apart from main joist end≤300mm;
(2) on main joist, install suspender member in advance, main joist connects, and installs connector, bracing wire adjustment absolute altitude arch camber and straight, and fixed edge keel, select supporting receipts keelson to be fixedly connected with body of wall, and in fixation procedure, guarantee keelson is straight;
(3) secondary joist is passed through suspension member, secondary joist is hung on main joist by the stepping line good by bullet, and the spacing of secondary joist is 450-550mm, when secondary joist needs many continuity spreadings, uses secondary joist connector, connected while hanging secondary joist, and adjusts fixing;
(4) keel installation qualified by inspection after, in the middle of ceiling, install gypsum plank keel direction in turn, extend piecemeal to both sides and install, gypsum plank adopts self-tapping screw and main joist, secondary joist to fix, self-tapping screw spacing≤200mm;
(5) gypsum plank installs, and with gypsum putty elbow-board seam at twice, after second time is dry, with varnish bridging agent pasting board seam connecting paper band, then brushes one times with gypsum putty.
As preferred further, main joist spacing of the present invention is 1000mm.
As preferred further, step of the present invention (1) reinforcing bar suspension rod carries out antirust treatment.
Beneficial effect of the present invention: light steel keel gypsum board ceiling construction process of the present invention is simple, and easy to operate, good decorating effect, furred ceiling is firm, effectively prevents cracking and the distortion of gypsum plank, long service life.
Detailed description of the invention
Embodiment 1
A kind of light steel keel gypsum board ceiling construction process, comprises the following steps:
1, by dipstick metering ceiling design elevation, along the cross intersection point of wall, post ejection reinforcing bar suspension rod, horizontal allowable variation is less than 5mm; Determine the absolute altitude of reinforcing bar suspension rod lower end, be welded and fixed in reinforcing bar suspension rod upper end and expansion bolt, reinforcing bar suspension rod is apart from main joist end≤300mm.
Also comprise base treatment before snap the line, base treatment step is: cleaned out at pipeline sealing hole place before ceiling construction, the foreign material on top also will be cleaned out.
Upper people's furred ceiling adopts the reinforcing bar suspension rod of 10mm diameter, does not go up people's furred ceiling and adopts 6mm diameter reinforcing bar suspension rod.
Reinforcing bar suspension rod carries out antirust treatment, smears 2 volumes with rustproof paint.
2, on main joist, install suspender member in advance, main joist connects, and installs connector, bracing wire adjustment absolute altitude arch camber and straight, fixed edge keel, select supporting receipts keelson to be fixedly connected with body of wall, in fixation procedure, ensure that keelson is straight, main joist spacing is 1000mm.。
3, secondary joist is passed through suspension member, secondary joist is hung on main joist by the stepping line good by bullet, and the spacing of secondary joist is 500mm, when secondary joist needs many continuity spreadings, uses secondary joist connector, connected while hanging secondary joist, and adjusts fixing.
4, keel installation qualified by inspection after, in the middle of ceiling, install gypsum plank keel direction in turn, extend piecemeal to both sides and install, gypsum plank adopts self-tapping screw and main joist, secondary joist to fix, self-tapping screw spacing≤200mm.
5, gypsum plank installs, and with gypsum putty elbow-board seam at twice, after second time is dry, with varnish bridging agent pasting board seam connecting paper band, then brushes one times with gypsum putty.
Main joist of suspended ceiling, secondary joist must be firm, smooth, utilize reinforcing bar suspension rod to adjust camber, and install main joist, secondary joist in strict accordance with HRL assembling periphery skeleton, stressed node installation is tight, firm, ensures the integral rigidity of keel.

Claims (3)

1. a light steel keel gypsum board ceiling construction process, is characterized in that, comprises the following steps:
(1) by dipstick metering ceiling design elevation, along the cross intersection point of wall, post ejection reinforcing bar suspension rod, horizontal allowable variation is less than 5mm; Determine the absolute altitude of reinforcing bar suspension rod lower end, be welded and fixed in reinforcing bar suspension rod upper end and expansion bolt, reinforcing bar suspension rod is apart from main joist end≤300mm;
(2) on main joist, install suspender member in advance, main joist connects, and installs connector, bracing wire adjustment absolute altitude arch camber and straight, and fixed edge keel, select supporting receipts keelson to be fixedly connected with body of wall, and in fixation procedure, guarantee keelson is straight;
(3) secondary joist is passed through suspension member, secondary joist is hung on main joist by the stepping line good by bullet, and the spacing of secondary joist is 450-550mm, when secondary joist needs many continuity spreadings, uses secondary joist connector, connected while hanging secondary joist, and adjusts fixing;
(4) keel installation qualified by inspection after, in the middle of ceiling, install gypsum plank keel direction in turn, extend piecemeal to both sides and install, gypsum plank adopts self-tapping screw and main joist, secondary joist to fix, self-tapping screw spacing≤200mm;
(5) gypsum plank installs, and with gypsum putty elbow-board seam at twice, after second time is dry, with varnish bridging agent pasting board seam connecting paper band, then brushes one times with gypsum putty.
2. light steel keel gypsum board ceiling construction process according to claim 1, is characterized in that, described main joist spacing is 1000mm.
3. light steel keel gypsum board ceiling construction process according to claim 1, is characterized in that, described step (1) reinforcing bar suspension rod carries out antirust treatment.
CN201510935185.XA 2015-12-15 2015-12-15 Light steel keel gypsum board furred ceiling construction process Pending CN105544983A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510935185.XA CN105544983A (en) 2015-12-15 2015-12-15 Light steel keel gypsum board furred ceiling construction process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510935185.XA CN105544983A (en) 2015-12-15 2015-12-15 Light steel keel gypsum board furred ceiling construction process

Publications (1)

Publication Number Publication Date
CN105544983A true CN105544983A (en) 2016-05-04

Family

ID=55824497

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510935185.XA Pending CN105544983A (en) 2015-12-15 2015-12-15 Light steel keel gypsum board furred ceiling construction process

Country Status (1)

Country Link
CN (1) CN105544983A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107514087A (en) * 2017-08-26 2017-12-26 沈阳港华装饰股份有限公司 Plaster tablet suspended ceiling expanded joint structure
CN108930350A (en) * 2017-05-23 2018-12-04 太仓顺如成建筑材料有限公司 A kind of technique of gypsum stud L-type Substrate sheet crack resistence
CN111962825A (en) * 2020-07-31 2020-11-20 新十建设集团有限公司 Construction method for decoration and fitment of building ceiling
CN112411851A (en) * 2020-10-30 2021-02-26 业之峰诺华家居装饰集团股份有限公司 Suspended ceiling edge seam cracking prevention process and paving device used by same
CN112502344A (en) * 2020-09-23 2021-03-16 上海美家美沪装饰科技有限公司 Light steel keel gypsum board suspended ceiling construction process

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3864888A (en) * 1973-05-22 1975-02-11 Kaiser Gypsum Company Inc Apparatus and method for employing gypsum board as forms for poured concrete ceiling and floor structures
CN102296815A (en) * 2011-05-24 2011-12-28 江苏江都建设集团有限公司 Construction process for preventing paper surface gypsum board ceiling from cracking
CN103122697A (en) * 2013-02-05 2013-05-29 山西太行建设开发有限公司 Installation method of indoor large-scale suspended ceiling
CN103821373A (en) * 2014-02-28 2014-05-28 四川雅豪房地产开发有限公司 Ceiling hanging construction technology of light steel keel gypsum boards

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3864888A (en) * 1973-05-22 1975-02-11 Kaiser Gypsum Company Inc Apparatus and method for employing gypsum board as forms for poured concrete ceiling and floor structures
CN102296815A (en) * 2011-05-24 2011-12-28 江苏江都建设集团有限公司 Construction process for preventing paper surface gypsum board ceiling from cracking
CN103122697A (en) * 2013-02-05 2013-05-29 山西太行建设开发有限公司 Installation method of indoor large-scale suspended ceiling
CN103821373A (en) * 2014-02-28 2014-05-28 四川雅豪房地产开发有限公司 Ceiling hanging construction technology of light steel keel gypsum boards

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
覃积: "轻钢龙骨纸面石膏板吊顶施工工艺", 《企业科技与发展》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108930350A (en) * 2017-05-23 2018-12-04 太仓顺如成建筑材料有限公司 A kind of technique of gypsum stud L-type Substrate sheet crack resistence
CN107514087A (en) * 2017-08-26 2017-12-26 沈阳港华装饰股份有限公司 Plaster tablet suspended ceiling expanded joint structure
CN111962825A (en) * 2020-07-31 2020-11-20 新十建设集团有限公司 Construction method for decoration and fitment of building ceiling
CN112502344A (en) * 2020-09-23 2021-03-16 上海美家美沪装饰科技有限公司 Light steel keel gypsum board suspended ceiling construction process
CN112411851A (en) * 2020-10-30 2021-02-26 业之峰诺华家居装饰集团股份有限公司 Suspended ceiling edge seam cracking prevention process and paving device used by same
CN112411851B (en) * 2020-10-30 2021-11-09 业之峰诺华家居装饰集团股份有限公司 Suspended ceiling edge seam cracking prevention process and paving device used by same

Similar Documents

Publication Publication Date Title
CN105544983A (en) Light steel keel gypsum board furred ceiling construction process
CN101787761B (en) Special aluminum square tube ceiling and construction method thereof
CN110439169A (en) A kind of Thistle board ceiling construction process
CN210439520U (en) Hollow curtain wall structure
CN105421773A (en) Construction method for light steel skeleton special-shaped model suspended ceiling
CN106284815B (en) Furred ceiling clean board construction technique
CN106703359A (en) Building stone hanger
CN103821373A (en) Ceiling hanging construction technology of light steel keel gypsum boards
CN202064501U (en) Equipment belt suspended ceiling adopting glassfibre sound panel
CN203569780U (en) Overlap joint type skeleton structure
CN110847350A (en) Keel-free ceiling suspended structure and construction method thereof
CN205857509U (en) Acoustic board mounting structure
CN205024928U (en) Furred ceiling expansion joint structure
CN112502344A (en) Light steel keel gypsum board suspended ceiling construction process
CN211421374U (en) Keel-free ceiling suspended ceiling structure with curtain grooves
CN213014936U (en) Suspended ceiling system hides lamp area node structure
CN204456543U (en) Carry keel assembling curtain wall circuit board
CN101158196A (en) Suspended ceiling structure for mobile house
CN107700714B (en) High and large space partition wall with sound insulation function
CN203160503U (en) Invertedly concave connecting structure of indoor ceiling and wall body
CN110821027A (en) Ceiling suspended ceiling structure with adjustable height and construction method thereof
CN203671526U (en) Evacuation lamp bracket for arc-shaped curtain wall
CN108930350A (en) A kind of technique of gypsum stud L-type Substrate sheet crack resistence
CN205330048U (en) GRG decorates structure
CN212613507U (en) Gypsum board seam connection structure of preventing ftractureing

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20160504