CN105544544A - Method for quickly extracting pile under low clearance condition - Google Patents
Method for quickly extracting pile under low clearance condition Download PDFInfo
- Publication number
- CN105544544A CN105544544A CN201510946817.2A CN201510946817A CN105544544A CN 105544544 A CN105544544 A CN 105544544A CN 201510946817 A CN201510946817 A CN 201510946817A CN 105544544 A CN105544544 A CN 105544544A
- Authority
- CN
- China
- Prior art keywords
- pile
- steel sleeve
- stake
- low clearance
- low
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D9/00—Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof
- E02D9/02—Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof by withdrawing
Abstract
The invention discloses a method for quickly extracting a pile under a lower clearance condition, and the method can be used for quickly extracting the pile under the low clearance condition. The method comprises the following steps: screwing in a steel sleeve by use of low-clearance pile extracting equipment to realize pile-soil separation; integrally ascending the whole pile and then cutting off the redundant part on the upper part of the pile body, backfilling a pile hole and tamping the pile hole until designed elevation; and finally, extracting the steel sleeve. The pile extracting process adopts steel sleeve screwing-in to realize pile-soil separation, so that the pile extracting construction has small influence on the surrounding environment; and a barrier pile is lifted outside of a tunnel pass-through range to cut off the redundant part on the upper part, so that the whole pile is prevented from being pulled out, and the construction efficiency is greatly improved. The method also can complete construction in case of limited clearance height, so that the extracting efficiency of the barrier pile within the tunnel pass-through range is greatly improved.
Description
Technical field
The invention belongs to construction engineering technical field, the method for quick pile pulling under being specifically related to a kind of low-headroom condition.
Background technology
Usually because the construction of follow-up building do not considered by the structure of first constructing in construction work, the obstruction run in subsequent construction also gets more and more, and the bored pile especially pulling out existing structure thing is very common.In the work progress of subway and municipal tunnel, shield machine often needs the pile foundation group passed through below existing building or bridge, and these obstacle piles add the difficulty of construction of shield driving, therefore the pile body within the scope of Tunnel Passing must be removed.This type of construction of removing obstacles often need low in headway, construction period is short, carry out under environmental protection requirement high condition, and traditional pile pulling technique because efficiency of construction is low, ambient influnence large, the limitation such as not thorough of removing obstacles cannot meet the demand.
Summary of the invention
Because the above-mentioned defect of prior art, the method of quick pile pulling under the invention provides a kind of low-headroom condition, quick pile pulling can be carried out under low-headroom condition, first use low clearance pile pulling device to be screwed in by steel sleeve and realize the separation of stake soil, the redundance on cutting amputation pile body top after more whole stake entirety being raised, backfill stake holes and tamping to design elevation, finally pull out steel sleeve, the method when headway first, also can complete construction, make the obstacle pile within the scope of Tunnel Passing pull out operating efficiency and greatly improve.
For achieving the above object, the method of quick pile pulling under the invention provides a kind of low-headroom condition, first use low clearance full circle swinging jacketing machine to be screwed in by steel sleeve and realize the separation of stake soil, the redundance on cutting amputation pile body top after more whole stake entirety being raised, backfill stake holes and tamping to design elevation, finally pull out steel sleeve.
A method for quick pile pulling under low-headroom condition, concrete steps comprise:
(1) excavate pile crown, the earth by whole stake top is removed, and carries out preparation of construction work, comprises diameter, the degree of depth, the spacing between stake and stake of determining whole stake;
(2) low clearance pile pulling device, the low clearance pile pulling device of employing is low clearance full circle swinging jacketing machine;
(3) steel sleeve is sunk in rotation, and low clearance full circle swinging jacketing machine blocks steel sleeve, is rotated by steel sleeve and is drowned into whole stake pile body bottom 1-2m, realize whole stake and be separated with surrounding soil;
(4) low clearance full circle swinging jacketing machine transfers wire rope to locking bottom whole stake;
(5), after the debugging of low clearance full circle swinging jacketing machine terminates, started to pull out, risen to design elevation by the bottom of whole stake stake, design elevation should exceed Tunnel Passing scope;
(6) use cutting equipment by whole stake pile body top redundance cutting amputation;
(7) back-filling in layers stake holes tamping are to design elevation, and design elevation exceeds Tunnel Passing scope;
(8) finally start low clearance full circle swinging jacketing machine, pull out steel sleeve, construction completes.
Preferably, low clearance full circle swinging jacketing machine blocks steel sleeve in described step (3), steel sleeve is rotated to be drowned in the process of whole stake pile body bottom can adjunction steel sleeve until steel sleeve rotated be drowned into 1-2m position, whole stake pile body bottom.
Beneficial effect of the present invention:
The method of quick pile pulling under the invention provides a kind of low-headroom condition, quick pile pulling can be carried out under low-headroom condition, first use low clearance pile pulling device to be screwed in by steel sleeve and realize the separation of stake soil, the redundance on cutting amputation pile body top after more whole stake entirety being raised, backfill stake holes and tamping to design elevation, finally pull out steel sleeve, this pile pulling technique adopts steel sleeve to screw in and realizes the separation of stake soil, pile pulling construction is little on surrounding enviroment impact, obstacle pile is promoted to beyond Tunnel Passing scope, cutting amputation top redundance, thus avoid whole stake and pull out, substantially increase efficiency of construction, the method also can complete construction under the condition that headway is limited, make the obstacle pile within the scope of Tunnel Passing pull out operating efficiency greatly to improve.
Be described further below with reference to the technique effect of accompanying drawing to design of the present invention, concrete structure and generation, to understand object of the present invention, characteristic sum effect fully.
Accompanying drawing explanation
Fig. 1 excavates pile crown schematic diagram in the method for quick pile pulling under low-headroom condition.
Fig. 2 is low clearance full circle swinging jacketing machine schematic diagram in place in the method for quick pile pulling under low-headroom condition.
Fig. 3 rotates in the method for quick pile pulling under low-headroom condition to sink to steel sleeve schematic diagram.
Fig. 4 is adjunction steel sleeve schematic diagram in the method for quick pile pulling under low-headroom condition.
Steel sleeve rotates in the method for quick pile pulling under low-headroom condition to be drowned into whole stake pile body bottom schematic diagram by Fig. 5.
Fig. 6 transfers wire rope to locking schematic diagram bottom whole stake in the method for quick pile pulling under low-headroom condition.
Fig. 7 rises to design elevation schematic diagram by the bottom of whole stake stake in the method for quick pile pulling under low-headroom condition.
Fig. 8 is by whole stake pile body top redundance cutting amputation schematic diagram in the method for quick pile pulling under low-headroom condition.
Fig. 9 be in the method for quick pile pulling under low-headroom condition back-filling in layers stake holes tamping to design elevation schematic diagram.
Figure 10 pulls out steel sleeve schematic diagram in the method for quick pile pulling under low-headroom condition.
In figure: 1, whole stake, 2, low clearance full circle swinging jacketing machine, 3, steel sleeve A, 4, wire rope, 5, stake holes, 6, steel sleeve B.
Detailed description of the invention
The method of quick pile pulling under a kind of low-headroom condition, first use low clearance pile pulling device to be screwed in by steel sleeve and realize the separation of stake soil, the redundance on cutting amputation pile body top after whole stake entirety being raised again, backfill stake holes tamping, to design elevation, finally pull out steel sleeve.
The technical scheme that the present invention optimizes further, under a kind of low-headroom condition, the method concrete steps of quick pile pulling comprise:
(1) as shown in Figure 1, excavation pile crown, the earth by whole stake 1 top is removed, and carries out preparation of construction work, comprises diameter, the degree of depth, the spacing between different whole stake 1 of determining whole stake 1;
(2) low clearance pile pulling device is in place, and as shown in Figure 2, the low clearance pile pulling device of employing is low clearance full circle swinging jacketing machine 2;
(3) steel sleeve 3 is sunk in rotation, and as shown in Figure 3 and Figure 5, low clearance full circle swinging jacketing machine 2 blocks steel sleeve A3, is rotated by steel sleeve 3 and is drowned into whole stake 1 pile body bottom 1-2m, realize whole stake 1 and be separated with surrounding soil;
(4) low clearance full circle swinging jacketing machine 2 to be transferred bottom wire rope 4 to whole stake 1 and is locked, as shown in Figure 6;
(5), after low clearance full circle swinging jacketing machine 2 debugging terminates, started to pull out, risen to design elevation by the bottom of whole stake 1, design elevation should exceed Tunnel Passing scope, as shown in Figure 7;
(6) use cutting equipment by whole stake 1 pile body top redundance cutting amputation, as shown in Figure 8;
(7) also tamping is to design elevation for back-filling in layers stake holes 5, and design elevation exceeds Tunnel Passing scope, as shown in Figure 9;
(8) finally start low clearance full circle swinging jacketing machine 2, pull out steel sleeve A3, construction completes, as shown in Figure 10.
The technical scheme that the present invention optimizes further, in described step (3), low clearance full circle swinging jacketing machine 2 blocks steel sleeve A3, steel sleeve 3 is rotated to be drowned in the process of whole stake 1 pile body bottom can adjunction steel sleeve B6 until steel sleeve A3 rotated be drowned into whole stake pile body bottom 1m, as shown in Figure 4.
The technical scheme that the present invention optimizes further, low clearance full circle swinging jacketing machine 2 blocks steel sleeve A3 in described step (3), steel sleeve 3 is rotated to be drowned in the process of whole stake 1 pile body bottom can adjunction steel sleeve B6 until steel sleeve A3 rotated be drowned into whole stake pile body bottom 2m.
The method of quick pile pulling under the invention provides a kind of low-headroom condition, quick pile pulling can be carried out under low-headroom condition, first use low clearance full circle swinging jacketing machine 2 to be screwed in by steel sleeve A3 and realize the separation of stake soil, the redundance on cutting amputation pile body top after more whole stake 1 entirety being raised, backfill stake holes 5 and tamping to design elevation, finally pull out steel sleeve A3, this pile pulling technique adopts steel sleeve A3 to screw in and realizes the separation of stake soil, pile pulling construction is little on surrounding enviroment impact, obstacle pile is promoted to beyond Tunnel Passing scope, cutting amputation top redundance, thus avoid whole stake and pull out, substantially increase efficiency of construction, the method also can complete construction under the condition that headway is limited, make the obstacle pile within the scope of Tunnel Passing pull out operating efficiency greatly to improve.
More than describe preferred embodiment of the present invention in detail.Should be appreciated that those of ordinary skill in the art just design according to the present invention can make many modifications and variations without the need to creative work.Therefore, all technician in the art, all should by the determined protection domain of claims under this invention's idea on the basis of existing technology by the available technical scheme of logical analysis, reasoning, or a limited experiment.
Claims (3)
1. the method for quick pile pulling under a low-headroom condition, it is characterized in that, first use low clearance pile pulling device to be screwed in by steel sleeve and realize the separation of stake soil, then after whole stake entirety being raised, cutting amputates the redundance on pile body top, backfill stake holes and tamping to design elevation, finally pull out steel sleeve.
2. the method for quick pile pulling under a kind of low-headroom condition according to claim 1, it is characterized in that, described method concrete steps comprise:
(1) excavate pile crown, the earth by whole stake top is removed, and carries out preparation of construction work, comprises diameter, the degree of depth, the spacing between stake and stake of determining whole stake;
(2) low clearance pile pulling device is in place, and the low clearance pile pulling device of employing is low clearance full circle swinging jacketing machine;
(3) steel sleeve is sunk in rotation, and low clearance full circle swinging jacketing machine blocks steel sleeve, is rotated by steel sleeve and is drowned into whole stake pile body bottom 1-2m, realize whole stake and be separated with surrounding soil;
(4) low clearance full circle swinging jacketing machine transfers wire rope to locking bottom whole stake;
(5), after the debugging of low clearance full circle swinging jacketing machine terminates, started to pull out, risen to design elevation by the bottom of whole stake stake, design elevation should exceed Tunnel Passing scope;
(6) use cutting equipment by whole stake pile body top redundance cutting amputation;
(7) back-filling in layers stake holes tamping are to design elevation, and design elevation exceeds Tunnel Passing scope;
(8) finally start low clearance full circle swinging jacketing machine, pull out steel sleeve, construction completes.
3. the method for quick pile pulling under a kind of low-headroom condition according to claim 2, it is characterized in that, low clearance full circle swinging jacketing machine blocks steel sleeve in described step (3), steel sleeve is rotated to be drowned in the process of whole stake pile body bottom can adjunction steel sleeve until steel sleeve rotated be drowned into 1-2m position, whole stake pile body bottom.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510946817.2A CN105544544A (en) | 2015-12-16 | 2015-12-16 | Method for quickly extracting pile under low clearance condition |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510946817.2A CN105544544A (en) | 2015-12-16 | 2015-12-16 | Method for quickly extracting pile under low clearance condition |
Publications (1)
Publication Number | Publication Date |
---|---|
CN105544544A true CN105544544A (en) | 2016-05-04 |
Family
ID=55824066
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510946817.2A Pending CN105544544A (en) | 2015-12-16 | 2015-12-16 | Method for quickly extracting pile under low clearance condition |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105544544A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106978807A (en) * | 2017-03-10 | 2017-07-25 | 浙江大学城市学院 | Existing bridge pile pulling device and construction method are passed through by a kind of weak soil shield driving area |
CN107338795A (en) * | 2017-06-09 | 2017-11-10 | 中铁建大桥工程局集团第五工程有限公司 | A kind of full-sleeve pulls out post row's formula bored pile construction method |
CN113818440A (en) * | 2021-10-13 | 2021-12-21 | 上海建工七建集团有限公司 | Pile pulling device for reducing soil disturbance and using method |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101173517A (en) * | 2006-10-31 | 2008-05-07 | 上海市基础工程公司 | Pile-pulling construction method |
CN101550697A (en) * | 2008-04-03 | 2009-10-07 | 上海宝冶建设有限公司 | Pulling-out method of underground piles by sleeving, vibrating and punching |
CN101629421A (en) * | 2009-08-04 | 2010-01-20 | 上海隧道工程股份有限公司 | Method for pulling out deep pile foundation by utilizing full slewing drilling machine |
CN101736746A (en) * | 2009-12-04 | 2010-06-16 | 上海智平基础工程有限公司 | Construction method for vibrator pipe sinking high-pressure grouting underpinning pile extracting |
CN101886390A (en) * | 2010-06-12 | 2010-11-17 | 中铁十六局集团有限公司 | All casing static pressure pile pulling technology in narrow space |
CN104532842A (en) * | 2015-01-29 | 2015-04-22 | 浙江省一建建设集团有限公司 | Sleeve rotating friction type breaking pile-extracting construction method |
CN104652436A (en) * | 2014-12-24 | 2015-05-27 | 福建工程学院 | Steel sleeve soil taking and high-pressure water injection soil loosening pile pulling construction method |
CN104775433A (en) * | 2015-04-11 | 2015-07-15 | 葛洲坝集团基础工程有限公司 | Pile extracting construction method |
-
2015
- 2015-12-16 CN CN201510946817.2A patent/CN105544544A/en active Pending
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101173517A (en) * | 2006-10-31 | 2008-05-07 | 上海市基础工程公司 | Pile-pulling construction method |
CN101550697A (en) * | 2008-04-03 | 2009-10-07 | 上海宝冶建设有限公司 | Pulling-out method of underground piles by sleeving, vibrating and punching |
CN101629421A (en) * | 2009-08-04 | 2010-01-20 | 上海隧道工程股份有限公司 | Method for pulling out deep pile foundation by utilizing full slewing drilling machine |
CN101736746A (en) * | 2009-12-04 | 2010-06-16 | 上海智平基础工程有限公司 | Construction method for vibrator pipe sinking high-pressure grouting underpinning pile extracting |
CN101886390A (en) * | 2010-06-12 | 2010-11-17 | 中铁十六局集团有限公司 | All casing static pressure pile pulling technology in narrow space |
CN104652436A (en) * | 2014-12-24 | 2015-05-27 | 福建工程学院 | Steel sleeve soil taking and high-pressure water injection soil loosening pile pulling construction method |
CN104532842A (en) * | 2015-01-29 | 2015-04-22 | 浙江省一建建设集团有限公司 | Sleeve rotating friction type breaking pile-extracting construction method |
CN104775433A (en) * | 2015-04-11 | 2015-07-15 | 葛洲坝集团基础工程有限公司 | Pile extracting construction method |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106978807A (en) * | 2017-03-10 | 2017-07-25 | 浙江大学城市学院 | Existing bridge pile pulling device and construction method are passed through by a kind of weak soil shield driving area |
CN107338795A (en) * | 2017-06-09 | 2017-11-10 | 中铁建大桥工程局集团第五工程有限公司 | A kind of full-sleeve pulls out post row's formula bored pile construction method |
CN113818440A (en) * | 2021-10-13 | 2021-12-21 | 上海建工七建集团有限公司 | Pile pulling device for reducing soil disturbance and using method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103603342B (en) | Major diameter assembled casing super-long filling pile construction method | |
CN106437798B (en) | A kind of preprocess method of the anchor cable group across shield driving section | |
CN205134331U (en) | Foundation ditch excavation bearing structure | |
CN103321244B (en) | Sand foundation existing building sets up the construction method of basement | |
CN104652436A (en) | Steel sleeve soil taking and high-pressure water injection soil loosening pile pulling construction method | |
CN104060615B (en) | Newly-built foundation pit supporting construction is utilized to remove the construction method of underground obstacle | |
CN103485343A (en) | Pile head processing method of filling pile | |
CN104746519A (en) | Obstacle clearing construction method | |
CN105544544A (en) | Method for quickly extracting pile under low clearance condition | |
CN107338795A (en) | A kind of full-sleeve pulls out post row's formula bored pile construction method | |
CN105673934A (en) | Non-excavation cable laying and pipe arranging method | |
CN103410152A (en) | Construction method for long, narrow and deep foundation pit soil excavation | |
CN104532853A (en) | Deep foundation pit supporting method and system characterized by steel reinforced cement-soil piles, bolts easy to detach and automatic monitoring and early warning | |
CN105544603A (en) | Construction method for underground pipeline reinforcement | |
CN110374091A (en) | A kind of rectangle friction pile mechanical hole building construction method | |
CN106703059A (en) | Construction method of cross-shaped pull trough of open caisson | |
CN105735383A (en) | Partial underground obstacle removing construction method capable of reserving structural system | |
CN103032629A (en) | Pushing device of self-compaction reinforcing and anti-seepage pilot pipe and use method thereof | |
CN109537592A (en) | The anchor cable invaded within the scope of interlocking pile cuts off construction method | |
CN108755719A (en) | Seabed municipal tunnel over strait cofferdam open cutting construction method | |
CN111877321A (en) | Cast-in-place pile applied to underground reinforced concrete structure and construction method thereof | |
CN103161469A (en) | Method for excavating vertical shaft to underground repair pipe-jacking tool pipe | |
CN105064428A (en) | Foundation reinforcement and protection method for telegraph pole near deep foundation pit | |
CN206233232U (en) | A kind of upper and lower part expansion type soil cement is combined pile tube | |
CN104264679A (en) | Construction method of tower transmission iron tower foundation large-diameter underwater cast-in-place piles |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20160504 |