CN105544408A - 一种支架现浇箱梁侧模板拆除滑动装置及其应用方法 - Google Patents
一种支架现浇箱梁侧模板拆除滑动装置及其应用方法 Download PDFInfo
- Publication number
- CN105544408A CN105544408A CN201610111775.5A CN201610111775A CN105544408A CN 105544408 A CN105544408 A CN 105544408A CN 201610111775 A CN201610111775 A CN 201610111775A CN 105544408 A CN105544408 A CN 105544408A
- Authority
- CN
- China
- Prior art keywords
- template
- fixed
- slideway
- side template
- box beam
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
Description
Claims (4)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610111775.5A CN105544408B (zh) | 2016-02-29 | 2016-02-29 | 一种支架现浇箱梁侧模板拆除滑动装置及其应用方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610111775.5A CN105544408B (zh) | 2016-02-29 | 2016-02-29 | 一种支架现浇箱梁侧模板拆除滑动装置及其应用方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105544408A true CN105544408A (zh) | 2016-05-04 |
CN105544408B CN105544408B (zh) | 2017-04-05 |
Family
ID=55823939
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610111775.5A Active CN105544408B (zh) | 2016-02-29 | 2016-02-29 | 一种支架现浇箱梁侧模板拆除滑动装置及其应用方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105544408B (zh) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109797657A (zh) * | 2019-01-29 | 2019-05-24 | 中铁九局集团第二工程有限公司 | 现浇桥梁模板支架体系装置及桥梁现浇施工方法 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201172798Y (zh) * | 2008-04-02 | 2008-12-31 | 中铁十三局集团有限公司 | 模板安装与拆除行走台车 |
US7976244B2 (en) * | 2007-03-20 | 2011-07-12 | Keating Joseph W | Method and system for constructing and installing docks |
CN204825674U (zh) * | 2015-08-24 | 2015-12-02 | 中国水利水电第十六工程局有限公司 | 拆模机 |
CN205399223U (zh) * | 2016-02-29 | 2016-07-27 | 科达集团股份有限公司 | 一种支架现浇箱梁侧模板拆除滑动装置 |
-
2016
- 2016-02-29 CN CN201610111775.5A patent/CN105544408B/zh active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US7976244B2 (en) * | 2007-03-20 | 2011-07-12 | Keating Joseph W | Method and system for constructing and installing docks |
CN201172798Y (zh) * | 2008-04-02 | 2008-12-31 | 中铁十三局集团有限公司 | 模板安装与拆除行走台车 |
CN204825674U (zh) * | 2015-08-24 | 2015-12-02 | 中国水利水电第十六工程局有限公司 | 拆模机 |
CN205399223U (zh) * | 2016-02-29 | 2016-07-27 | 科达集团股份有限公司 | 一种支架现浇箱梁侧模板拆除滑动装置 |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109797657A (zh) * | 2019-01-29 | 2019-05-24 | 中铁九局集团第二工程有限公司 | 现浇桥梁模板支架体系装置及桥梁现浇施工方法 |
CN109797657B (zh) * | 2019-01-29 | 2024-04-05 | 中铁九局集团第二工程有限公司 | 现浇桥梁模板支架体系装置及桥梁现浇施工方法 |
Also Published As
Publication number | Publication date |
---|---|
CN105544408B (zh) | 2017-04-05 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102528927B (zh) | 流水线预制梁施工方法 | |
CN105540179B (zh) | 一种箱梁侧模转运机具 | |
CN101518784B (zh) | 大型轧机牌坊在吊装高度受限下的吊装方法 | |
CN107675636A (zh) | 一种通用型的桥梁结构物拆除方法和系统 | |
CN106917356B (zh) | 一种新型钢桁梁桥道砟槽板高效安装方法 | |
CN107254849A (zh) | 一种净高受限状态下钢箱梁安装方法 | |
CN111022079A (zh) | 一种栈桥式全断面仰拱二衬台车设备及其施工方法 | |
CN105507155A (zh) | 小节段钢箱梁安装的施工工艺 | |
CN205399223U (zh) | 一种支架现浇箱梁侧模板拆除滑动装置 | |
CN205364148U (zh) | Pc轨道梁模具 | |
CN104180658B (zh) | 一种烧结机除尘系统的安装方法 | |
CN205591116U (zh) | 用于立交桥钢箱梁底部施工的双梁移动小车操作平台 | |
CN105544408A (zh) | 一种支架现浇箱梁侧模板拆除滑动装置及其应用方法 | |
CN205529923U (zh) | 贝雷梁滑移式拆除装置 | |
CN204754249U (zh) | 一种用于室内大烟道安装的移送装置 | |
CN105171911A (zh) | 一种底模台车 | |
CN201317627Y (zh) | 双导梁架桥机 | |
CN106192761B (zh) | 一种在桥隧狭短过渡段拆解移动模架的方法 | |
CN108086162B (zh) | 一种用于箱梁横移的小车及使用该小车的箱梁施工工法 | |
CN103615262B (zh) | 一种主体结构可整体通过常规断面的钢模台车及其实现方法 | |
CN211342938U (zh) | 一种栈桥式全断面仰拱二衬台车设备 | |
CN206279453U (zh) | 大跨度刚构连续梁0号段现浇支架支承托架结构 | |
CN103382702A (zh) | 一种现浇箱梁的支架及其搭建方法 | |
CN103510436B (zh) | 底座板模板快速转运装置及其快速转运工艺 | |
CN105464000A (zh) | 一种现浇箱梁移动模板 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C41 | Transfer of patent application or patent right or utility model | ||
CB03 | Change of inventor or designer information |
Inventor after: Cao Zhenqing Inventor after: Li Lei Inventor after: Li Jian Inventor after: Wen Tao Inventor after: Chen Gangquan Inventor before: Cao Zhenqing Inventor before: Li Jian Inventor before: Li Lei Inventor before: Wen Tao Inventor before: Chen Gangquan |
|
COR | Change of bibliographic data | ||
TA01 | Transfer of patent application right |
Effective date of registration: 20170302 Address after: 257091 Shandong city of Dongying province Dongying District Front Street No. 65 Applicant after: Shandong Keda infrastructure Co., Ltd. Address before: 257091 Shandong city of Dongying province Dongying District Front Street No. 65 Applicant before: Keda Group Co., Ltd. |
|
GR01 | Patent grant | ||