CN105544400B - A kind of method based on using the interim bridge pier construction of container progress emergency bridge - Google Patents

A kind of method based on using the interim bridge pier construction of container progress emergency bridge Download PDF

Info

Publication number
CN105544400B
CN105544400B CN201510938988.0A CN201510938988A CN105544400B CN 105544400 B CN105544400 B CN 105544400B CN 201510938988 A CN201510938988 A CN 201510938988A CN 105544400 B CN105544400 B CN 105544400B
Authority
CN
China
Prior art keywords
container
bridge
bridge pier
concrete
bearing capacity
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510938988.0A
Other languages
Chinese (zh)
Other versions
CN105544400A (en
Inventor
李聚轩
张云红
张静
程万里
郑义
孙奇
乔伟
雷克平
田广才
汪建伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Army Military Transportation University
Original Assignee
Military Transportation University of PLA
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Military Transportation University of PLA filed Critical Military Transportation University of PLA
Priority to CN201510938988.0A priority Critical patent/CN105544400B/en
Publication of CN105544400A publication Critical patent/CN105544400A/en
Application granted granted Critical
Publication of CN105544400B publication Critical patent/CN105544400B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a kind of based on the method that the interim bridge pier construction of emergency bridge is carried out using container, step 1, container is chosen:Choose the container of suitable dimension;Step 2, by the leveling of container lay down location ground, compacting, to ensure the steady of bridge floor, appropriate sandy soil can be filled in container, increases anti-lateral displacement power, bridge pier is done with the container for filling sandstone or concrete.The beneficial effects of the invention are as follows:1. container sets up bridge pier, it is spaced and highly larger, under-clearance is larger, compared to facilities such as pipe culvert, steel pipe culverts, has the advantage for not blocking river course;2. container with container using generally, being set up, bridge pier is simple to operate, and compared to standard bridge part, convenient material drawing, erection are simple, quick;3. container bearing capacity is larger, the more notable raising of bearing capacity after penetration concrete, the bridge pier that the material such as mixing wooden compared to wooden, steel is set up, bearing capacity is bigger, security is higher.

Description

A kind of method based on using the interim bridge pier construction of container progress emergency bridge
Technical field
The present invention relates to Highway and Railway Engineering technical field, is based on being met an urgent need using container more particularly to one kind The method that the interim bridge pier of bridge is built.
Background technology
Bridge is highly prone to destroy in natural calamity or wartime, rescue and relief work and wartime communications and transportation is caused great negative Face is rung, and influences huge, and this point is all demonstrated in Wenchuan earthquake, Lushan earthquake and all previous war.Bridge rush-repair at present Method mainly has three kinds:First, setting up new bridge according to science of bridge building standard, but set up cycle length, it is impossible to meet emergent communications and transportation Needs;Second, temporary bridge is set up using the Uniformed Bridge rush repair equipment of official reserves.During Wenchuan earthquake, just take from expensive The ground such as state, Yunnan, Guangdong, Shandong urgency transportion assembly type steel bridge on highway is used for the method in disaster area, but Uniformed Bridge rush repair equipment Deposit less, transportation range it is remote;Third, the expedient material that can be raised using locality sets up temporary bridge, as volunteered in Korean War The wooden bridge that army sets up, the steel-wood structure mixing bridge that parachutist sets up in the earthquake relief work of Wenchuan, its shortcoming is that bearing capacity is unstable, bridge Headroom is low below beam can not meet that current pass through requirement.
The content of the invention
In view of the technical drawbacks of the prior art, it is an object of the present invention to provide one kind is based on entering using container The method that the interim bridge pier of row emergency bridge is built.
To realize the purpose of the present invention, the technical solution adopted in the present invention is:One kind is based on being answered using container The method that the anxious interim bridge pier of bridge is built, methods described comprise the following steps:
Step 1, container is chosen:Choose the container of suitable dimension;
Step 2, by the leveling of container lay down location ground, compacting, can be filled to ensure the steady of bridge floor, in container suitable Sandy soil are measured, increase anti-lateral displacement power, bridge pier is done with the container for filling sandstone or concrete, when single container height is inadequate, Container is piled up, corner fittings is connected with fastener, as bridge pier, can at most be piled up three layers, be increased under-clearance.
Compared with prior art, the beneficial effects of the invention are as follows:1. container sets up bridge pier, interval and highly larger, bridge Lower headroom is larger, compared to facilities such as pipe culvert, steel pipe culverts, has the advantage for not blocking river course;2. container is used generally, with collection Vanning erection bridge pier is simple to operate, compared to standard bridge part, convenient material drawing, sets up simply, fast;3. container carries energy Power is larger, the more notable raising of bearing capacity after penetration concrete, the bridge pier that the material such as mixing wooden compared to wooden, steel is set up, Bearing capacity is bigger, security is higher.
Brief description of the drawings
Fig. 1 show the beam bridge schematic diagram that the present invention is set up by the use of container as bridge pier;
In figure:1. bottom container, 2. intermediate layer containers, 3. top layer containers, 4. support beams.
Embodiment
The present invention is described in further detail below in conjunction with the drawings and specific embodiments.It is it should be appreciated that described herein Specific embodiment only to explain the present invention, be not intended to limit the present invention.
It should be noted that " connection " described herein and the word for expressing " connection ", such as " being connected ", " connected " etc., it both may refer to a certain part and had been directly connected to another part, and can also refer to a certain part and pass through other portions Part is connected with another part.
As shown in figure 1, technical scheme is used by the embodiment of the present invention:Bridge pier is done with the container for filling sandstone, When single container height is inadequate, container is piled up, corner fittings is connected with fastener, as bridge pier, can at most pile up three layers, high Degree reaches 7.8m, increases under-clearance.Container frame structure bearing capacity is larger, and its surrounding corner fittings can play constraint laterally Mobile effect;When superstructure gross mass and logical load vehicular gross combined weight are more than 20000kg, it is necessary to be poured into container mixed Solidifying soil improves bearing capacity.Using cutting equipment (mechanical cutting device and thermal cutting equipment can be used) before pouring into, by packaging Box top boxboard excision.In perfusion in order to prevent that lateral pressure is excessive, each influx height control is waited to have poured within 1m After 1-2h, continue to irrigate;(3) container is piled up two layers or three layers as bridge pier when, squeezed into container corner HW200 × 200 shaped steel (or the equal shaped steel of sectional area), cross force is resisted, to improve stability.
Container bridge pier container number, can be according to following table arrangement:
For the ease of transporting and laying, container bridge pier selects 20 chi TEU (Twenty-foot Equivalent Unit)s, and the type container structure size is about For 6m × 2.4m × 2.4m.At most added using 3 stackings, every layer of container number is determined according to riverbed geological condition.
If container bridge pier is only intended to the rush repair stage, container lay down location ground need to be flattened, compacting, to protect The steady of bridge floor is demonstrate,proved, appropriate sandy soil can be filled in container, increases anti-lateral displacement power.If bridge pier is needed to use to rebuilding rank Section, needs fill concrete in container, can operation as follows during fill concrete:
1. container roof plate to be cut to two 1m × 1m hole, it is easy to pour and vibrated concrete, chamber door is locked, and gap is fitted Work as sealing;
2. container is placed on setting position, if bottom container then requires levelling of the land, by preliminary consolidation, Prevent lateral tilt;
3. the shaped steel of 4 HW200 × 200 (or other shaped steel of uiform section product), guarantee type are squeezed on the inside of container corner Steel outer rim is not less than 50mm away from side plate distance, and its height is highly identical with bridge pier;
4. laminated pouring C20 concrete, per thickness degree about 1m.Every layer of cast depending on the circumstances or the needs of the situation, can pour at intervals of 1 hour Build early strength concrete;
5. adjacent container is welded at corner fittings with steel plate, support horizontal stroke is installed along bridge cross direction in the superiors' container Beam;
6. floorings are laid on crossbeam, you can use.
The present invention intends, by the use of TEU (Twenty-foot Equivalent Unit) as expedient material, setting up bridge pier.Container compressive property itself is good, section Size is big, deadweight is larger, can bear external force vertically and horizontally, has firm durable, and construction is simple, materials side Just, the time is saved, the advantage such as low to foundation requirement being capable of fast erecting emergency bridge, raising bearing capacity and under-clearance.
Described above is only the preferred embodiment of the present invention, it is noted that for the common skill of the art For art personnel, under the premise without departing from the principles of the invention, some improvements and modifications can also be made, these improvements and modifications Also it should be regarded as protection scope of the present invention.

Claims (1)

  1. It is 1. a kind of based on the method that the interim bridge pier construction of emergency bridge is carried out using container, it is characterised in that methods described is used In the rush repair stage, methods described comprises the following steps:
    Step 1, container is chosen:Choose the container of suitable dimension;
    Step 2, by the leveling of container lay down location ground, compacting, to ensure the steady of bridge floor, appropriate sand can be filled in container Soil, increase anti-lateral displacement power, bridge pier is done with the container for filling sandstone or concrete, when single container height is inadequate, will collect Vanning is piled up, and corner fittings is connected with fastener, and the corner fittings plays a part of constraining transverse shifting;As bridge pier, can at most pile up Three layers, increase under-clearance;
    If bridge pier was needed to use to the stage of rebuilding, using the container of fill concrete, container fill concrete is included such as Lower step:
    Step 101, container roof plate is cut to two 1m × 1m hole, is easy to pour and vibrated concrete, chamber door is locked, gap Appropriate sealing;
    Step 102, container is placed on setting position, if bottom container then requires levelling of the land, by preliminary pressure It is real, prevent lateral tilt;
    Step 103, shaped steel is squeezed on the inside of container corner, ensures that shaped steel outer rim is not less than 50mm, its height away from side plate distance It is highly identical with bridge pier;
    Step 104, laminated pouring concrete, per thickness degree about 1m, every layer of cast depending on the circumstances or the needs of the situation, can pour at intervals of 1 hour Early strength concrete;
    Step 105, adjacent container is welded at corner fittings with steel plate, support horizontal stroke is installed along bridge cross direction in the superiors' container Beam;
    Step 106, floorings are laid on crossbeam, you can use.
CN201510938988.0A 2015-12-15 2015-12-15 A kind of method based on using the interim bridge pier construction of container progress emergency bridge Active CN105544400B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510938988.0A CN105544400B (en) 2015-12-15 2015-12-15 A kind of method based on using the interim bridge pier construction of container progress emergency bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510938988.0A CN105544400B (en) 2015-12-15 2015-12-15 A kind of method based on using the interim bridge pier construction of container progress emergency bridge

Publications (2)

Publication Number Publication Date
CN105544400A CN105544400A (en) 2016-05-04
CN105544400B true CN105544400B (en) 2018-01-16

Family

ID=55823931

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510938988.0A Active CN105544400B (en) 2015-12-15 2015-12-15 A kind of method based on using the interim bridge pier construction of container progress emergency bridge

Country Status (1)

Country Link
CN (1) CN105544400B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110656576A (en) * 2019-09-26 2020-01-07 中国二十冶集团有限公司 Pier structure and construction method thereof
CN112411404A (en) * 2020-11-26 2021-02-26 合肥工业大学 Multifunctional traffic facility structure for emergency rescue

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09189043A (en) * 1996-01-11 1997-07-22 Pacific Consultants Kk Closing caisson and closing construction method
CN101906751A (en) * 2010-07-20 2010-12-08 郑志文 Ready-package emergency bridge and construction method for changing same into permanent bridge
CN202000284U (en) * 2010-11-17 2011-10-05 杨光华 Protector for bridge pier and anti-collision pier

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20040227051A1 (en) * 2003-05-12 2004-11-18 Bishop Lyndell Kevin Floating structural object protection system

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09189043A (en) * 1996-01-11 1997-07-22 Pacific Consultants Kk Closing caisson and closing construction method
CN101906751A (en) * 2010-07-20 2010-12-08 郑志文 Ready-package emergency bridge and construction method for changing same into permanent bridge
CN202000284U (en) * 2010-11-17 2011-10-05 杨光华 Protector for bridge pier and anti-collision pier

Also Published As

Publication number Publication date
CN105544400A (en) 2016-05-04

Similar Documents

Publication Publication Date Title
CN106522037B (en) Side broad way based structures based on existing railway roadbed and its construction method
CN105155558A (en) Combined retaining structure and construction method thereof
US11698329B2 (en) Vertical counterforce loading device for large-tonnage soil material load test and loading method thereof
CN105568805B (en) A method of it is repaired based on circuit embankment along the river is carried out using container
WO2022016720A1 (en) Temporary passage construction method employing support structure in deep foundation pit
CN109403170B (en) Steep slope road and construction method thereof
CN109356210A (en) A kind of pile foundation building inclination rectification cuts stake and underpins position limiting structure and its construction method
CN209243794U (en) A kind of pile foundation building inclination rectification cuts stake and underpins position limiting structure
CN106522292A (en) Grouting combined prestressed anchor rod static pressure pile rectification and reinforcement method
CN105544400B (en) A kind of method based on using the interim bridge pier construction of container progress emergency bridge
CN105804101B (en) Reduce off-loading supporting and retaining system system and construction method and the application of retaining structure stress
CN204919602U (en) Compound anchored retaining wall by tie rods
CN105568871B (en) A kind of method based on using the interim abutment construction of container progress emergency bridge
CN204940310U (en) A kind of combination retaining structure
CN212670237U (en) Repairing structure for subsidence of karst area pavement
CN206245338U (en) Construction elevator foundation structure of double-layer raft plate
CN205223874U (en) Emergent bridge with novel interim abutment
CN211621441U (en) Vertical dike structure
CN210712576U (en) Multi-hoop truss supporting bailey bracket for cast-in-situ large-span box girder
CN110219248B (en) Anti-overturning simple temporary bridge pier construction method and anti-overturning simple temporary bridge construction method
CN213204139U (en) Cantilever combined soil retaining structure for sinking square
CN205242281U (en) Emergent bridge with novel interim pier
CN109056502B (en) Combined bridge abutment and construction method thereof
CN210369074U (en) Integral steel structural framework ballast weight pile carrier
CN111395082A (en) Light roadbed structure above operation tunnel, design and construction method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address

Address after: 300161 No.1, dongjuzi, Chenglin Road, Hedong District, Tianjin

Patentee after: ARMY MILITARY TRANSPORTATION University

Address before: No.1, dongjuzi, Hedong District, Tianjin, 300361

Patentee before: Military Transportation University of PLA

CP03 Change of name, title or address