CN105540410A - Lifting device and method for wind turbine generator set - Google Patents

Lifting device and method for wind turbine generator set Download PDF

Info

Publication number
CN105540410A
CN105540410A CN201511022610.2A CN201511022610A CN105540410A CN 105540410 A CN105540410 A CN 105540410A CN 201511022610 A CN201511022610 A CN 201511022610A CN 105540410 A CN105540410 A CN 105540410A
Authority
CN
China
Prior art keywords
hanging
hoisting
base
generator
lifting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201511022610.2A
Other languages
Chinese (zh)
Inventor
俞雪梅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Goldwind Science and Technology Co Ltd
Original Assignee
Jiangsu Goldwind Science and Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Goldwind Science and Technology Co Ltd filed Critical Jiangsu Goldwind Science and Technology Co Ltd
Priority to CN201511022610.2A priority Critical patent/CN105540410A/en
Publication of CN105540410A publication Critical patent/CN105540410A/en
Pending legal-status Critical Current

Links

Classifications

    • B—PERFORMING OPERATIONS; TRANSPORTING
    • B66—HOISTING; LIFTING; HAULING
    • B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C1/00—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
    • B66C1/10—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
    • B66C1/108—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means for lifting parts of wind turbines
    • B—PERFORMING OPERATIONS; TRANSPORTING
    • B66—HOISTING; LIFTING; HAULING
    • B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C1/00—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
    • B66C1/10—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
    • B66C1/12—Slings comprising chains, wires, ropes, or bands; Nets
    • B66C1/18—Band-type slings
    • B—PERFORMING OPERATIONS; TRANSPORTING
    • B66—HOISTING; LIFTING; HAULING
    • B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C13/00—Other constructional features or details
    • B66C13/04—Auxiliary devices for controlling movements of suspended loads, or preventing cable slack
    • B—PERFORMING OPERATIONS; TRANSPORTING
    • B66—HOISTING; LIFTING; HAULING
    • B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C13/00—Other constructional features or details
    • B66C13/04—Auxiliary devices for controlling movements of suspended loads, or preventing cable slack
    • B66C13/06—Auxiliary devices for controlling movements of suspended loads, or preventing cable slack for minimising or preventing longitudinal or transverse swinging of loads

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Wind Motors (AREA)

Abstract

本发明提供一种风力发电机组的吊装设备和吊装方法。所述吊装设备用于吊装发电机和机舱的组合体,机舱里安装有底座,底座上设有吊耳,所述吊装设备包括吊梁以及分别设置在吊梁两端的第一吊装部和第二吊装部,第一吊装部的下端设置有多根第一吊带,第一吊带用于连接在底座的吊耳上,第二吊装部的下端设置有连接板,其中,连接板上设置有与发电机的法兰面上的法兰孔适配的连接孔。采用本发明的技术方案,可以对风力发电机组的机舱和发电机进行高效率地组合吊装,并有效地解决了发电机因吊装位置易发生形变而损坏的问题。

The invention provides a hoisting device and a hoisting method for a wind power generating set. The hoisting device is used for hoisting the combination of the generator and the nacelle. A base is installed in the nacelle, and lifting lugs are arranged on the base. The lower end of the first hoisting part is provided with a plurality of first slings, the first slings are used to connect to the lugs of the base, and the lower end of the second sling is provided with a connecting plate, wherein the connecting plate is provided with a The connection holes that match the flange holes on the flange surface of the machine. By adopting the technical solution of the invention, the engine room and the generator of the wind power generating set can be efficiently hoisted together, and the problem that the generator is easily deformed and damaged due to the hoisting position is effectively solved.

Description

风力发电机组的吊装设备和吊装方法Wind turbine hoisting equipment and hoisting method

技术领域technical field

本发明涉及风力发电设备领域,尤其涉及一种风力发电机组的吊装设备和吊装方法。The invention relates to the field of wind power generating equipment, in particular to a hoisting device and a hoisting method for a wind power generating set.

背景技术Background technique

随着风力发电技术的不断发展,各种环境下的风电场均被开发出来,其中,海上风电场利用资源丰富、风速较大、主导风向稳定的海上风能,具有不占用土地资源、对环境影响小等优点,因此,海上风力发电技术将得到迅速发展。With the continuous development of wind power generation technology, wind farms in various environments have been developed. Among them, offshore wind farms use offshore wind energy with abundant resources, high wind speed, and stable dominant wind direction, which has the advantages of not occupying land resources and having no impact on the environment. Small and other advantages, therefore, offshore wind power technology will be developed rapidly.

在海上风电场的建设过程中,海上风力发电机组的安装主要在海上进行施工,需要吊装运输船及相应吊装设备相配地进行施工,施工难度较大,所以,海上风力发电机组的安装方法主要以减少海上作业时间为主要目的。其中,在直驱式风力发电机组的安装过程中,各大部件的总成是按照顺序进行吊装的,为了缩短施工周期以及减小吊装成本,通常将机舱和发电机组装在一起进行组合吊装。In the construction process of offshore wind farms, the installation of offshore wind turbines is mainly carried out at sea, and the construction needs to be hoisted and transported together with the corresponding hoisting equipment. The construction is difficult. Therefore, the installation method of offshore wind turbines is mainly based on The main purpose is to reduce the working time at sea. Among them, in the installation process of the direct-drive wind turbine, the assembly of the major components is hoisted in sequence. In order to shorten the construction period and reduce the hoisting cost, the nacelle and the generator are usually assembled together for combined hoisting.

但是,现有技术中对机舱和发电机进行组合吊装的吊装设备,利用设置在发电机转轴外侧的吊耳来吊装发电机,会造成发电机在吊运过程中发生形变,使发电机发生损坏,需要对发电机进行修复以及重新吊装,影响整体施工进度,以及增加风力发电机组的安装成本。However, in the prior art, the hoisting equipment for combined hoisting of the engine room and the generator uses the lifting lugs arranged on the outside of the generator shaft to hoist the generator, which will cause deformation of the generator during hoisting and damage to the generator , the generator needs to be repaired and re-hoisted, affecting the overall construction progress and increasing the installation cost of the wind power generating set.

发明内容Contents of the invention

本发明的实施例提供一种风力发电机组的吊装设备和吊装方法,以解决机舱和发电机的组合吊装过程中发电机易发生形变而损坏的问题。Embodiments of the present invention provide a hoisting device and a hoisting method for a wind power generating set to solve the problem that the generator is easily deformed and damaged during the combined hoisting of the nacelle and the generator.

为达到上述目的,本发明的实施例提供一种风力发电机组的吊装设备,用于吊装发电机和机舱的组合体,所述机舱里安装有底座,所述底座上设有吊耳,所述吊装设备包括吊梁以及分别设置在所述吊梁两端的第一吊装部和第二吊装部,所述第一吊装部的下端设置有多根第一吊带,所述第一吊带用于连接在所述底座的所述吊耳上,所述第二吊装部的下端设置有连接板,其中,所述连接板上设置有与发电机的法兰面上的法兰孔适配的连接孔。In order to achieve the above object, an embodiment of the present invention provides a hoisting device for a wind power generating set, which is used for hoisting a combination of a generator and a nacelle, a base is installed in the nacelle, and lifting lugs are provided on the base. The hoisting equipment includes a hoisting beam and a first hoisting part and a second hoisting part respectively arranged at both ends of the hoisting beam. The lower end of the first hoisting part is provided with a plurality of first slings, and the first slings are used to connect On the lifting lug of the base, a connecting plate is provided at the lower end of the second lifting part, wherein the connecting plate is provided with a connecting hole adapted to the flange hole on the flange surface of the generator.

进一步地,所述第二吊装部还包括第二吊带,所述第二吊带的两端分别与所述吊梁和所述连接板连接。Further, the second lifting part further includes a second sling, and the two ends of the second sling are respectively connected to the suspension beam and the connecting plate.

进一步地,所述第二吊带通过第二卸扣与所述连接板连接,所述连接板上设置有用于连接第二卸扣的通孔。Further, the second sling is connected to the connecting plate through a second shackle, and the connecting plate is provided with a through hole for connecting the second shackle.

进一步地,所述连接板的数量至少为两个,所述第二吊带的数量与所述连接板的数量对应。Further, the number of the connecting plates is at least two, and the number of the second straps corresponds to the number of the connecting plates.

进一步地,所述吊装设备还包括与所述吊梁呈T型地设置在所述吊梁的第二端的横梁,所述第二吊带的一端与所述横梁连接。Further, the hoisting device further includes a beam arranged at the second end of the suspension beam in a T-shape with the suspension beam, and one end of the second suspension strap is connected to the beam.

进一步地,所述第一吊装部还包括第一卸扣和第三吊带,所述第三吊带的两端分别与所述吊梁的第一端以及所述第一卸扣连接。Further, the first lifting part further includes a first shackle and a third sling, and the two ends of the third sling are respectively connected to the first end of the suspension beam and the first shackle.

进一步地,所述底座上设置有三个吊耳,分别设置在所述底座的两侧和顶端,所述第一吊带的数量为三个,其中两根第一吊带分别穿过所述第一卸扣连接在所述底座两侧的两个吊耳上,另一根第一吊带穿过所述第一卸扣连接在所述底座顶端的吊耳上。Further, the base is provided with three lifting lugs, which are respectively arranged on the two sides and the top of the base, and the number of the first suspenders is three, and two of the first suspenders pass through the first unloading lugs respectively. The buckle is connected to the two lifting lugs on both sides of the base, and another first sling passes through the first shackle and is connected to the lifting lug on the top of the base.

进一步地,所述吊梁上设置有用于连接起吊设备的起吊部。Further, the lifting beam is provided with a lifting part for connecting lifting equipment.

进一步地,所述吊装设备还包括配重块,所述配重块可拆卸地设置在所述吊梁的第一端。Further, the hoisting device further includes a counterweight, and the counterweight is detachably arranged at the first end of the suspension beam.

根据本发明的另一方面,还提供一种风力发电机组的吊装方法,所述吊装方法使用如前所述的吊装设备对机舱和发电机进行组合吊装,所述吊装方法包括:组合步骤:将机舱和发电机进行组合组装;连接步骤:将第一吊装部的多根第一吊带与底座上的多个吊耳连接;将第二吊装部的连接板与发电机的法兰面连接;吊装步骤:利用起吊设备吊起吊梁将所述机舱和发电机组合吊装到所述风力发电机组的塔架上。According to another aspect of the present invention, there is also provided a hoisting method for a wind power generating set, the hoisting method uses the aforementioned hoisting equipment to carry out combined hoisting of the nacelle and the generator, and the hoisting method includes: a combining step: The engine room and the generator are combined and assembled; connection steps: connect multiple first slings of the first hoisting part to multiple lifting lugs on the base; connect the connecting plate of the second hoisting part to the flange surface of the generator; hoisting Step: using lifting equipment to lift the lifting beam to lift the combination of the nacelle and the generator to the tower of the wind power generating set.

进一步地,所述将第二吊装部的连接板与发电机的法兰面连接的步骤包括:将多个连接板与所述发电机的法兰面连接,并通过数量与多个连接板对应的第二吊带分别连接对应的所述连接板和所述吊梁。Further, the step of connecting the connection plate of the second hoisting part to the flange surface of the generator includes: connecting a plurality of connection plates to the flange surface of the generator, and the number corresponds to the plurality of connection plates The second suspenders are respectively connected to the corresponding connecting plate and the suspension beam.

进一步地,所述底座上设置有三个吊耳,分别设置在所述底座的两侧和顶端,所述第一吊带的数量为三个,所述将第一吊装部的多根第一吊带与底座上的多个吊耳连接的步骤包括:将两根第一吊带分别连接在所述底座两侧的两个吊耳上,将另一根第一吊带连接在所述底座顶端的吊耳上。Further, the base is provided with three lifting lugs, which are respectively arranged on the two sides and the top of the base, the number of the first suspenders is three, and the multiple first suspenders of the first lifting part are connected with The step of connecting multiple lifting lugs on the base includes: connecting two first suspending straps to the two lifting lugs on both sides of the base respectively, and connecting another first suspending strap to the lifting lugs on the top of the base .

本发明实施例的风力发电机组的吊装设备和吊装方法,通过在吊梁的两端分别设置包括多根第一吊带的第一吊装部,以及包括与发电机的法兰面上的法兰孔适配的连接孔的连接板,可以快捷地对风力发电机组的机舱和发电机进行组合吊装,并保证发电机在吊装过程中不发生形变而损坏。According to the hoisting equipment and hoisting method of the wind power generating set in the embodiment of the present invention, the first hoisting parts including a plurality of first slings are respectively arranged at both ends of the hoisting beam, and the flange holes on the flange surface of the generator are included. The connecting plate with the matching connecting hole can quickly and quickly carry out combined hoisting of the nacelle and generator of the wind power generating set, and ensure that the generator will not be deformed or damaged during the hoisting process.

附图说明Description of drawings

图1为本发明实施例的吊装设备的结构示意图;Fig. 1 is the structural representation of the hoisting equipment of the embodiment of the present invention;

图2为本发明实施例的吊装设备的连接板的结构示意图;Fig. 2 is a structural schematic diagram of a connecting plate of a hoisting device according to an embodiment of the present invention;

图3为本发明实施例的吊装设备的工作状态示意图。Fig. 3 is a schematic view of the working state of the hoisting device according to the embodiment of the present invention.

附图标记说明:Explanation of reference signs:

10、吊梁;11、第一端;12、第二端;13、第一吊孔;20、第一吊装部;21、第一吊带;22、第一卸扣;23、第三吊带;30、第二吊装部;31、连接板;32、第二卸扣;33、第二吊带;34、连接孔;35、通孔;40、横梁;41、第二吊孔;50、配重块;60、起吊部;70、机舱;71、底座;72、吊耳;80、发电机。10. Hanging beam; 11. First end; 12. Second end; 13. First lifting hole; 20. First lifting part; 21. First sling; 22. First shackle; 23. Third sling; 30. Second hoisting part; 31. Connecting plate; 32. Second shackle; 33. Second sling; 34. Connecting hole; 35. Through hole; 40. Beam; 41. Second lifting hole; 50. Counterweight 60, lifting part; 70, engine room; 71, base; 72, lifting lug; 80, generator.

具体实施方式detailed description

下面结合附图对本发明实施例的风力发电机组的吊装设备和吊装方法进行详细描述。The hoisting equipment and hoisting method of the wind power generating set according to the embodiment of the present invention will be described in detail below with reference to the accompanying drawings.

图1为本发明实施例的吊装设备的结构示意图,该吊装设备可用于对风力发电机组的机舱和发电机进行组合吊装,并保证发电机在吊装过程中不发生形变,进而实现吊装效率和与吊装质量的同时提高。Fig. 1 is a schematic structural diagram of a hoisting device according to an embodiment of the present invention. The hoisting device can be used for combined hoisting of the nacelle and generator of a wind power generating set, and ensures that the generator does not deform during the hoisting process, thereby achieving hoisting efficiency and compatibility Improve the lifting quality at the same time.

如图1至图3所示,该吊装设备用于吊装发电机80和机舱70的组合体,所述机舱70里安装有底座71,所述底座71上设有吊耳72,包括吊梁10、第一吊装部20和第二吊装部30。第一吊装部20和第二吊装部30分别设置吊梁10的两端,第一吊装部20的下端设置有多根第一吊带21,所述第一吊带21用于连接在所述底座71的所述吊耳72上,第二吊装部30的下端设置有连接板31,其中,连接板31上设置有与发电机80的法兰面上的法兰孔适配的连接孔34。As shown in Figures 1 to 3, the hoisting equipment is used for hoisting the combination of the generator 80 and the nacelle 70, the nacelle 70 is equipped with a base 71, and the base 71 is provided with lifting lugs 72, including the suspension beam 10 , the first hoisting part 20 and the second hoisting part 30 . The first hoisting part 20 and the second hoisting part 30 are provided with the two ends of the suspension beam 10 respectively, and the lower end of the first hoisting part 20 is provided with a plurality of first slings 21, and the first slings 21 are used to be connected to the base 71. On the lifting lug 72 , the lower end of the second lifting part 30 is provided with a connecting plate 31 , wherein the connecting plate 31 is provided with a connecting hole 34 adapted to the flange hole on the flange surface of the generator 80 .

在使用该吊装设备对风力发电机组的机舱70和发电机80进行组合吊装时,第一吊装部20的多根第一吊带21的连接在底座71的吊耳72上,第二吊装部30的连接板31连接在发电机80的法兰面上,使用起吊设备(例如起吊车、起吊船等)吊起吊梁10,即可将机舱70和发电机80的组合总成吊装到风力发电机组的塔架上,使吊装过程具有的吊装效率。由于连接板31与发电机80的法兰面连接,在吊装过程中,刚度较高的法兰面不会发生形变,使发电机80在不会发生损坏,从而避免了使用设置在发电机80转子外侧的吊耳在吊装发电机80时使发电机易发生形变的问题。When using the hoisting equipment to hoist the nacelle 70 and the generator 80 of the wind power generating set in combination, the plurality of first slings 21 of the first hoisting part 20 are connected to the lugs 72 of the base 71, and the first hoisting parts 30 of the second hoisting part 30 The connecting plate 31 is connected to the flange surface of the generator 80, and the lifting beam 10 is hoisted by using a hoisting device (such as a crane, a hoisting ship, etc.), so that the combined assembly of the nacelle 70 and the generator 80 can be hoisted to the wind turbine. On the tower, the hoisting process has the best hoisting efficiency. Since the connecting plate 31 is connected to the flange surface of the generator 80, during the hoisting process, the flange surface with higher rigidity will not be deformed, so that the generator 80 will not be damaged, thereby avoiding the need to use the motor installed on the generator 80. The lifting lugs on the outside of the rotor make the generator prone to deformation when the generator 80 is hoisted.

具体地,吊梁10可以为一字型梁,具有第一端11和第二端12,第一吊装部20和第二吊装部30可以分别设置在吊梁10的第一端11和第二端12,用于分别连接机舱70和发电机80,并对机舱70和发电机80的组合体进行组合吊装,因此,吊梁10的长度对应机舱70和发电机80组合后的长度。Specifically, the suspension beam 10 can be a straight beam with a first end 11 and a second end 12, and the first hoisting part 20 and the second hoisting part 30 can be respectively arranged on the first end 11 and the second end of the suspension beam 10. The end 12 is used to connect the nacelle 70 and the generator 80 respectively, and carry out combined hoisting to the combination of the nacelle 70 and the generator 80 , therefore, the length of the suspension beam 10 corresponds to the combined length of the nacelle 70 and the generator 80 .

第一吊带21的数量与底座71上的吊耳72的数量对应,多个第一吊带21分别与对应的吊耳72连接。而且,第一吊带21的长度根据机舱70整体结构(包括机舱罩和底座71等)的大小,以及吊耳的具体设置位置决定,以方便第一吊装部20吊装机舱70。The number of the first slings 21 corresponds to the number of the hanging ears 72 on the base 71 , and a plurality of first slings 21 are respectively connected to the corresponding hanging ears 72 . Moreover, the length of the first sling 21 is determined according to the size of the overall structure of the nacelle 70 (including the nacelle cover and the base 71 , etc.), and the specific location of the lifting lugs, so as to facilitate the hoisting of the nacelle 70 by the first hoisting part 20 .

连接板31上的连接孔34与发电机80的法兰面的法兰孔适配,可以通过螺栓、铆钉等工具穿过连接孔34,将连接板31固定连接在法兰面上,使第二吊装部30可以吊装发电机80。此外,连接板31与法兰面的贴合面积以及连接孔34的数量,可以根据发电机80的重量确定,用于使连接板31与法兰面稳定连接,保证该吊装设备可以对机舱70和发电机80的组合体进行可靠的吊装。The connecting hole 34 on the connecting plate 31 is adapted to the flange hole of the flange surface of the generator 80, and tools such as bolts and rivets can pass through the connecting hole 34, and the connecting plate 31 is fixedly connected to the flange surface, so that the second The second hoisting part 30 can hoist the generator 80 . In addition, the bonding area between the connecting plate 31 and the flange surface and the number of the connecting holes 34 can be determined according to the weight of the generator 80, so as to make the connecting plate 31 and the flange surface stably connected, so as to ensure that the hoisting equipment can support the nacelle 70 The combination with the generator 80 is reliably hoisted.

较优地,第二吊装部30还包括第二吊带33,第二吊带33的两端分别与吊梁10和连接板31连接。第二吊带33的长度根据发电机80整体结构的大小决定,以方便第二吊装部30在连接板31固定到法兰面上之后吊装发电机80。Preferably, the second hanging part 30 further includes a second hanging belt 33 , and the two ends of the second hanging belt 33 are respectively connected to the hanging beam 10 and the connecting plate 31 . The length of the second sling 33 is determined according to the size of the overall structure of the generator 80, so as to facilitate the second hoisting part 30 to hoist the generator 80 after the connecting plate 31 is fixed on the flange surface.

较优地,第二吊带33通过第二卸扣32与连接板31连接,连接板31上设置有用于连接第二卸扣32的通孔35,将连接有第二吊带33的第二卸扣32穿过通孔35,即可实现第二吊带33与连接板31之间的连接。Preferably, the second sling 33 is connected to the connecting plate 31 through the second shackle 32, the connecting plate 31 is provided with a through hole 35 for connecting the second shackle 32, and the second shackle connected with the second sling 33 32 passes through the through hole 35 to realize the connection between the second sling 33 and the connecting plate 31 .

第二卸扣32可以实现第二吊带33与连接板31之间的稳定连接,使发电机80得到可靠的吊装;而且还方便将第二吊带33与连接板31之间拆卸开,使得在第二吊带33与连接板31中的一个有损坏时,可以快捷地进行更换,而不用全部更换第二吊带33和连接板31,进而一定程度上减小该吊装设备的使用成本。The second shackle 32 can realize the stable connection between the second sling 33 and the connection plate 31, so that the generator 80 can be hoisted reliably; When one of the second sling 33 and the connecting plate 31 is damaged, it can be replaced quickly without completely replacing the second sling 33 and the connecting plate 31, thereby reducing the use cost of the lifting device to a certain extent.

此外,本发明的技术方案对第二吊带33和连接板31的连接方式不做限定,在其他实施例中,第二吊带33还可以通过其他方式与连接板31连接,例如,第二吊带33直接穿过通孔35与连接板31连接,或通过吊环与连接板31连接等方式均可实现第二吊带33与连接板31之间的稳定连接。In addition, the technical solution of the present invention does not limit the connection method between the second sling 33 and the connecting plate 31. In other embodiments, the second sling 33 can also be connected to the connecting plate 31 in other ways, for example, the second sling 33 The stable connection between the second suspender 33 and the connecting plate 31 can be achieved by directly passing through the through hole 35 and connecting with the connecting plate 31 , or connecting with the connecting plate 31 through a suspension ring.

较优地,连接板31的数量至少为两个(图中为两个),且第二吊带33的数量与连接板31的数量对应。Preferably, the number of connecting plates 31 is at least two (two in the figure), and the number of second suspenders 33 corresponds to the number of connecting plates 31 .

连接板31用于连接在发电机80的法兰面上,方便对发电机80进行安全吊装,所以连接板31的数量根据发电机的整体重量决定。在实际的应用场景中,由于发电机80的重量并没有超重,且其法兰面的面积有限,在法兰面中心的两侧设置两个连接板31,足以稳定可靠地对发电机80进行吊装。The connecting plates 31 are used to connect to the flange surface of the generator 80 to facilitate safe hoisting of the generator 80, so the number of connecting plates 31 is determined according to the overall weight of the generator. In the actual application scene, since the weight of the generator 80 is not overweight, and the area of its flange surface is limited, two connecting plates 31 are arranged on both sides of the center of the flange surface, which is enough to stably and reliably install the generator 80. Hoisting.

较优地,该吊装设备还包括横梁40,横梁40与吊梁10呈T型地设置在吊梁的第二端12,且第二吊带33的一端与吊梁10连接。由于发电机80的法兰面的面积相对发电机的整体结构较小,从设置在法兰面两侧的多个连接板31引出的多根第二吊带33较容易地汇聚成一个点,从而方便将多根第二吊带33连接在横梁40上。Preferably, the hoisting device further includes a crossbeam 40 , the crossbeam 40 and the suspension beam 10 are arranged at the second end 12 of the suspension beam in a T shape, and one end of the second suspension belt 33 is connected to the suspension beam 10 . Since the area of the flange surface of the generator 80 is relatively small relative to the overall structure of the generator, a plurality of second suspenders 33 drawn from a plurality of connecting plates 31 arranged on both sides of the flange surface are more easily converged into one point, thereby It is convenient to connect multiple second suspenders 33 to the beam 40 .

较优地,横梁40下端设置有第二吊孔41,第二吊带33通过第二吊孔41与横梁40连接。Preferably, the lower end of the beam 40 is provided with a second hanging hole 41 , and the second hanging belt 33 is connected to the beam 40 through the second hanging hole 41 .

具体地,第二吊孔41的数量优选为与第二吊带33的数量对应,使第二吊带33可以一一对应地连接在第二吊孔41中,进而避免多根第二吊带33连接在一个第二吊孔41,造成局部应力集中而损坏第二吊孔41与横梁的稳定连接。第二吊孔41的形式为销轴,可以方便第二吊带33穿过该销轴连接在横梁40的下端,进而实现吊梁10发电机的法兰面的连接。当然,在其他实施例中,第二吊孔41还可以为其他形式,例如焊接在横梁40下端的吊环。Specifically, the number of the second hanging holes 41 is preferably corresponding to the number of the second hanging straps 33, so that the second hanging straps 33 can be connected in the second hanging holes 41 in a one-to-one correspondence, thereby avoiding that multiple second hanging straps 33 are connected to each other. A second lifting hole 41 causes local stress concentration and damages the stable connection between the second lifting hole 41 and the beam. The second hanging hole 41 is in the form of a pin shaft, which can facilitate the connection of the second sling 33 to the lower end of the beam 40 through the pin shaft, thereby realizing the connection of the flange surface of the generator of the hanging beam 10 . Certainly, in other embodiments, the second lifting hole 41 may also be in other forms, such as a lifting ring welded at the lower end of the beam 40 .

较优地,第一吊装部20还包括第一卸扣22和第三吊带23,第三吊带23的两端分别与吊梁10的第一端11以及第一卸扣22连接。Preferably, the first lifting part 20 further includes a first shackle 22 and a third sling 23 , and the two ends of the third sling 23 are respectively connected to the first end 11 of the suspension beam 10 and the first shackle 22 .

具体地,吊梁10的第一端11设置有第一吊孔13,第三吊带23的一端可以通过与第一吊孔13连接,来实现与吊梁10的第一端11的连接。其中,第一吊孔13的结构与上述的第二吊孔41的结构相似,这里不做赘述。第一卸扣22连接在第三吊带23的另一端,且多根第一吊带21均与第一卸扣22连接,用于实现与吊梁10的第一端11的连接。多根第一吊带21与第一卸扣22的连接方式优选为穿过第一卸扣22并对折,用于增加第一吊带21的承载能力,使第一吊装部20可以更加稳定地吊装机舱。Specifically, the first end 11 of the suspension beam 10 is provided with a first suspension hole 13 , and one end of the third suspension belt 23 can be connected with the first suspension hole 13 to realize the connection with the first end 11 of the suspension beam 10 . Wherein, the structure of the first lifting hole 13 is similar to that of the above-mentioned second lifting hole 41 , which will not be repeated here. The first shackle 22 is connected to the other end of the third sling 23 , and a plurality of first slings 21 are all connected to the first shackle 22 for realizing the connection with the first end 11 of the suspension beam 10 . The connection mode of multiple first slings 21 and the first shackle 22 is preferably passed through the first shackle 22 and folded in half, which is used to increase the bearing capacity of the first sling 21, so that the first hoisting part 20 can hoist the cabin more stably .

较优地,底座71上设置有三个吊耳72,分别设置在底座71的两个和顶端,相应地,第一吊带21的数量也设置为三个,用于分别连接三个吊耳72,通过吊装底座71来完成对机舱70的吊装。例如,其中两根第一吊带21分别穿过第一卸扣22连接在底座两侧的两个吊耳72上,另一根第一吊带21穿过第一卸扣22连接在底座71顶端的吊耳72上。Preferably, the base 71 is provided with three lifting lugs 72, which are respectively set on the two ends and the top end of the base 71. Correspondingly, the number of the first suspenders 21 is also set to three, which are used to respectively connect the three lifting lugs 72, The nacelle 70 is hoisted through the hoisting base 71 . For example, wherein two first slings 21 pass through the first shackle 22 and are respectively connected to the two lugs 72 on both sides of the base, and the other first sling 21 passes through the first shackle 22 and is connected to the top of the base 71. On the lifting lug 72.

较优地,该吊装设备还包括起吊部60,其设置在吊梁10上,用于连接起吊设备,在第一吊装部20和第二吊装部30分别与连接机舱70和发电机80连接之后,起吊设备可以通过吊钩与起吊部60连接将该吊装设备吊起,进而吊起机舱70与发电机80的组合体。起吊部60可以由设置在吊梁10上的销轴以及吊带组成,用于连接起吊设备上的吊钩。Preferably, the lifting device further includes a lifting part 60, which is arranged on the lifting beam 10 and is used to connect the lifting device. After the first lifting part 20 and the second lifting part 30 are respectively connected to the nacelle 70 and the generator 80 , the hoisting equipment can be hoisted by connecting the hoisting part 60 with a hook, and then hoisting the combination of the nacelle 70 and the generator 80 . The hoisting part 60 may be composed of a pin shaft and a sling arranged on the hoisting beam 10, and is used for connecting to a hoisting hook on the hoisting device.

较优地,该吊装设备还包括配重块50,其可拆卸地设置在吊梁10上的第一端11,用于在该吊装设备被吊起后平衡吊梁10。Preferably, the hoisting device further includes a counterweight 50, which is detachably disposed on the first end 11 of the suspension beam 10, and is used to balance the suspension beam 10 after the hoisting device is hoisted.

配重块50设置在吊梁10上的具体位置,可以根据机舱70和发电机80各自的重量决定。由于机舱70的重量小于发电机80的重量,该吊装设备将机舱70和发电机80的组合体吊起后,吊梁10的第二端12向下倾斜,通过将配重块50设置在吊梁10的第一端11,可以使吊梁10保持平衡,进而使该吊装设备可以稳定地对机舱70和发电机80的组合体进行吊装。The specific position where the counterweight 50 is arranged on the suspension beam 10 can be determined according to the respective weights of the nacelle 70 and the generator 80 . Since the weight of the nacelle 70 is less than the weight of the generator 80, after the hoisting device lifts the combination of the nacelle 70 and the generator 80, the second end 12 of the suspension beam 10 is inclined downward, and the counterweight 50 is placed on the The first end 11 of the beam 10 can keep the suspension beam 10 balanced, so that the hoisting device can stably hoist the combination of the nacelle 70 and the generator 80 .

此外,配重块50的可以从吊梁10上拆卸下来,使配重块50的块数得到调整,进而调整设置在吊梁10上的配重块50的重量,用于精确调整吊梁10的平衡度。In addition, the counterweight 50 can be disassembled from the suspension beam 10, so that the number of counterweights 50 can be adjusted, and then the weight of the counterweight 50 arranged on the suspension beam 10 can be adjusted to accurately adjust the suspension beam 10. of balance.

本实施例的吊装设备结构设计简单,其中各部件可以由现有技术中的起吊装置组成,成本较低。例如,卸扣(包括第一卸扣22、第二卸扣32)可以由现有技术中的D型卸扣组成。再例如,吊带(包括第一吊带21、第二吊带33、第三吊带23)具有承载能力高和重量轻的优点,减小该吊装设备的整体重量,使该吊装设备可以方便搬运,其可以由现有技术中的异型吊带组成。此外,本方案中的吊带还可以由其他装置代替,例如吊链或吊绳。The hoisting device in this embodiment has a simple structural design, and each component can be composed of hoisting devices in the prior art, and the cost is relatively low. For example, the shackles (including the first shackle 22 and the second shackle 32 ) can be composed of D-shaped shackles in the prior art. For another example, the sling (comprising the first sling 21, the second sling 33, and the third sling 23) has the advantages of high load-carrying capacity and light weight, which reduces the overall weight of the hoisting device, so that the hoisting device can be easily carried, which can Consists of special-shaped slings in the prior art. In addition, the sling in this solution can also be replaced by other devices, such as sling chains or slings.

可选地,为了方便对吊梁10进行维护和保养工作,增加其使用寿命,该吊装设备还包括吊梁支架,用于在该吊装设备完成吊装作业后放置吊梁10,避免直接将吊梁10放置在地上、甲板上或其他易污染吊梁10的位置,造成吊梁10的使用寿命缩短。Optionally, in order to facilitate the maintenance and maintenance work on the hanging beam 10 and increase its service life, the hoisting equipment also includes a hanging beam bracket, which is used to place the hanging beam 10 after the hoisting equipment completes the hoisting operation, so as to avoid directly placing the hanging beam 10 10 is placed on the ground, on the deck or other positions that are easy to pollute the suspension beam 10, causing the service life of the suspension beam 10 to be shortened.

如上所述的吊装设备,通过设置在吊梁10两端的第一吊装部20和第二吊装部30,方便快捷地对风力发电机组的机舱和发电机进行组合吊装,并利用与发电机的法兰面相适配的连接板31实现与发电机的连接,有效解决了发电机在吊装过程中易发生形变的问题。The above-mentioned hoisting equipment, through the first hoisting part 20 and the second hoisting part 30 arranged at both ends of the hoisting beam 10, can conveniently and quickly carry out combined hoisting of the nacelle and the generator of the wind power generating set, and use the method of connecting with the generator to The connecting plate 31 matched with the blue surface realizes the connection with the generator, which effectively solves the problem that the generator is prone to deformation during hoisting.

在此基础上,本发明的实施例还提供一种风力发电机组的吊装方法,该方法使用如前所述的风力发电机的吊装设备,对机舱和发电机进行组合吊装,该吊装方法包括:On this basis, an embodiment of the present invention also provides a method for hoisting a wind power generator, the method uses the hoisting equipment for a wind power generator as described above to carry out combined hoisting of the nacelle and the generator, and the hoisting method includes:

组合步骤:将机舱70和发电机80进行组合组装。Assembling step: assembling the nacelle 70 and the generator 80 .

将机舱70和发电机80组合之后,对机舱70与发电机80的组合体进行吊装可以提升吊装效率。After the nacelle 70 and the generator 80 are combined, hoisting the combination of the nacelle 70 and the generator 80 can improve hoisting efficiency.

连接步骤:将第一吊装部20的多根第一吊带21与底座71上的多个吊耳72连接;将第二吊装部30的连接板31与发电机80的法兰面连接。Connecting steps: connect the multiple first straps 21 of the first lifting part 20 to the multiple lifting lugs 72 on the base 71 ; connect the connecting plate 31 of the second lifting part 30 to the flange surface of the generator 80 .

如图3所示,可以通过卸扣将多根第一吊带21与设置在底座71吊耳72连接,例如,将一根第一吊带21通过机舱罩上的小窗口伸入机舱,与一个底座71上的吊耳72连接;将两根第一吊带21通过机舱罩上的大窗口伸入机舱,分别与底座71上的两个吊耳72连接。连接板31与法兰面连接,可以通过螺栓、铆钉等部件将连接板31与发电机80的法兰面连接来实现。As shown in Figure 3, a plurality of first slings 21 can be connected to the lugs 72 arranged on the base 71 through a shackle, for example, a first sling 21 is stretched into the nacelle through a small window on the nacelle cover, and connected to a base The lifting lugs 72 on the 71 are connected; two first suspenders 21 are stretched into the nacelle through the large window on the nacelle cover, and are connected with the two lifting lugs 72 on the base 71 respectively. The connecting plate 31 is connected to the flange surface, which can be realized by connecting the connecting plate 31 to the flange surface of the generator 80 through bolts, rivets and other components.

吊装步骤:利用起吊设备吊起吊梁10将机舱70和发电机80组合吊装到风力发电机组的塔架上。Hoisting step: use the hoisting equipment to hoist the hoisting beam 10 to hoist the nacelle 70 and the generator 80 together on the tower of the wind power generating set.

在第一吊装部20和第二吊装部30分别与机舱70和发电机80连接之后,便可以通过起吊设备吊起吊梁10,以实现吊装机舱70和发电机80的组合体到塔架上,在使用高强螺栓将螺栓机舱70和发电机80的组合体固定之后,可以将该吊装设备拆卸下来。After the first hoisting part 20 and the second hoisting part 30 are respectively connected with the nacelle 70 and the generator 80, the lifting beam 10 can be hoisted by the hoisting equipment, so as to realize hoisting the combination of the nacelle 70 and the generator 80 on the tower, After the high-strength bolts are used to fix the combination of the bolt nacelle 70 and the generator 80, the hoisting device can be disassembled.

进一步地,第二吊装部30包括多个连接板31,在将连接板31与法兰面连接时,需要将多个连接板31均匀地连接到发电机80的法兰面上,并分别通过对应的第二吊带33与吊梁10连接,以方便第二吊装部30吊装发电机80。Further, the second hoisting part 30 includes a plurality of connecting plates 31. When connecting the connecting plates 31 to the flange surface, it is necessary to evenly connect the plurality of connecting plates 31 to the flange surface of the generator 80, and pass the The corresponding second sling 33 is connected to the suspension beam 10 to facilitate the second hoisting part 30 to hoist the generator 80 .

进一步地,底座71上设置有三个吊耳72,分别设置在底座71的两个和顶端,相应地,第一吊带21的数量也设置为三个,用于分别连接三个吊耳72,通过吊装底座71的形式来完成对机舱70的吊装。Further, the base 71 is provided with three lifting lugs 72, which are respectively set on the two ends and the top end of the base 71. Correspondingly, the number of the first suspenders 21 is also set to three, which are used to connect the three lifting lugs 72 respectively. The hoisting of the nacelle 70 is completed in the form of the hoisting base 71.

具体地,在将三个第一吊带21与三个吊耳72连接时,可以将其中两根第一吊带21分别穿过第一卸扣22连接在底座两侧的两个吊耳72上,另一根第一吊带21穿过第一卸扣22连接在底座71顶端的吊耳72上。其中,第一吊带21可以通过卸扣或吊环等方式与吊耳72稳定连接,保证对底座71进行稳定地吊装,进而实现对机舱70的稳定吊装。Specifically, when connecting the three first slings 21 to the three lifting lugs 72, two of the first slings 21 can be connected to the two lifting lugs 72 on both sides of the base through the first shackle 22 respectively, Another first sling 21 passes through the first shackle 22 and is connected to the lifting ear 72 on the top of the base 71 . Wherein, the first sling 21 can be stably connected to the lifting lug 72 through shackles or rings, etc., so as to ensure stable hoisting of the base 71 , thereby realizing stable hoisting of the nacelle 70 .

如上所述的吊装方法,通过对机舱70和发电机80进行组合吊装,可以方便快捷将机舱70和发电机80的组合体吊装到风力发电机组的塔架上,进而达到提升吊装效率的目的,以及使用与发电机80的法兰面相适配的连接板31来连接发电机80,使发电机80在吊装过程中不易损坏。In the hoisting method mentioned above, by combining and hoisting the nacelle 70 and the generator 80, the combination of the nacelle 70 and the generator 80 can be hoisted conveniently and quickly on the tower of the wind power generating set, thereby achieving the purpose of improving the hoisting efficiency. And use the connecting plate 31 adapted to the flange surface of the generator 80 to connect the generator 80, so that the generator 80 is not easily damaged during the hoisting process.

需要指出,根据实施的需要,可将本申请中描述的各个部件/步骤拆分为更多部件/步骤,也可将两个或多个部件/步骤或者部件/步骤的部分组合成新的部件/步骤,以实现本发明的目的。It should be pointed out that, according to the needs of implementation, each component/step described in this application can be split into more components/steps, and two or more components/steps or parts of components/steps can also be combined into new components /step, to realize the object of the present invention.

本发明的实施例的风力发电机组的吊装设备和吊装方法具有如下效果:The hoisting equipment and hoisting method of the wind power generating set of the embodiment of the present invention have the following effects:

通过设置在吊梁两端的第一吊装部和第二吊装部,方便快捷地对风力发电机组的机舱和发电机进行组合吊装,有效提升了吊装效率;Through the first hoisting part and the second hoisting part arranged at both ends of the hoisting beam, the combined hoisting of the nacelle and generator of the wind power generating set is convenient and quick, and the hoisting efficiency is effectively improved;

利用与发电机的法兰面相适配的连接板来连接发电机,有效解决了发电机在吊装过程中易发生形变的问题。The generator is connected with the connecting plate matching the flange surface of the generator, which effectively solves the problem that the generator is easily deformed during the hoisting process.

此外,该吊装设备还具有结构简单、成本较低、方便安装拆卸等优点。In addition, the hoisting device also has the advantages of simple structure, low cost, convenient installation and disassembly, and the like.

以上所述,仅为本发明的具体实施方式,但本发明的保护范围并不局限于此,任何熟悉本技术领域的技术人员在本发明揭露的技术范围内,可轻易想到变化或替换,都应涵盖在本发明的保护范围之内。因此,本发明的保护范围应以所述权利要求的保护范围为准。The above is only a specific embodiment of the present invention, but the scope of protection of the present invention is not limited thereto. Anyone skilled in the art can easily think of changes or substitutions within the technical scope disclosed in the present invention. Should be covered within the protection scope of the present invention. Therefore, the protection scope of the present invention should be determined by the protection scope of the claims.

Claims (12)

1. the hanging device of a wind power generating set, for lifting the fabricate block of electrical generator (80) and cabin (70), described cabin (70) is inner is provided with base (71), described base (71) is provided with hanger (72), it is characterized in that, described hanging device comprises hanging beam (10) and is separately positioned on the first lifting portion (20) and the second lifting portion (30) at described hanging beam (10) two ends, the lower end in described first lifting portion (20) is provided with many first suspender belts (21), described first suspender belt (21) is for being connected to the described hanger (72) of described base (71), the lower end in described second lifting portion (30) is provided with connecting panel (31), wherein, described connecting panel (31) is provided with the connecting bore (34) with the flange hole adaptation on the flange face of electrical generator (80).
2. hanging device according to claim 1, it is characterized in that, described second lifting portion (30) also comprises the second suspender belt (33), and the two ends of described second suspender belt (33) are connected with described hanging beam (10) and described connecting panel (31) respectively.
3. hanging device according to claim 2, it is characterized in that, described second suspender belt (33) is connected with described connecting panel (31) by the second shackle (32), described connecting panel (31) is provided with the through hole (35) for connecting the second shackle (32).
4. hanging device according to claim 3, is characterized in that, the quantity of described connecting panel (31) is at least two, and the quantity of described second suspender belt (33) is corresponding with the quantity of described connecting panel (31).
5. hanging device according to claim 4, it is characterized in that, described hanging device also comprises the crossbeam (40) of the second end (12) being arranged on described hanging beam (10) with described hanging beam (10) T-shapedly, and one end of described second suspender belt (33) is connected with described crossbeam (40).
6. hanging device according to claim 1, it is characterized in that, described first lifting portion (20) also comprises the first shackle (22) and the 3rd suspender belt (23), and the two ends of described 3rd suspender belt (23) are connected with the first end (11) of described hanging beam (10) and described first shackle (22) respectively.
7. hanging device according to claim 6, it is characterized in that, described base (71) is provided with three hangers (72), be separately positioned on both sides and the top of described base (71), the quantity of described first suspender belt (21) is three, wherein two first suspender belts (21) are each passed through the first shackle (22) and are connected on two hangers (72) of described base (71) both sides, and another root first suspender belt (21) is connected on the hanger (72) on described base (71) top through described first shackle (22).
8. hanging device according to any one of claim 1 to 7, is characterized in that, described hanging beam (10) is provided with the hanging part (60) for connecting lifting appliance.
9. hanging device according to any one of claim 1 to 7, it is characterized in that, described hanging device also comprises clump weight (50), and described clump weight (50) is removably disposed on the described first end (11) of described hanging beam (10).
10. a hanging method for wind power generating set, is characterized in that, described hanging method uses hanging device as claimed in any one of claims 1-9 wherein to carry out combined hanging to cabin and electrical generator, and described hanging method comprises:
Combination step: cabin (70) and electrical generator (80) are carried out combination assembling;
Connection Step: many first suspender belts (21) in the first lifting portion (20) are connected with the multiple hangers on base (71); The connecting panel (31) in the second lifting portion (30) is connected with the flange face of electrical generator (80);
Lifting step: utilize lifting appliance to sling hanging beam (10) by described cabin (70) and electrical generator (80) combined hanging on the pylon of described wind power generating set.
11. hanging methods according to claim 10, is characterized in that, describedly the step that the connecting panel (31) in the second lifting portion (30) is connected with the flange face of electrical generator (80) are comprised:
The flange face of multiple connecting panel (31) with described electrical generator (80) is connected, and connects corresponding described connecting panel (31) and described hanging beam (10) respectively by the second suspender belt (33) that quantity is corresponding with multiple connecting panel (31).
12. hanging methods according to claim 10, it is characterized in that, described base (71) is provided with three hangers (72), be separately positioned on both sides and the top of described base (71), the quantity of described first suspender belt (21) is three, describedly the step that many first suspender belts (21) in the first lifting portion (20) are connected with the multiple hangers on base (71) is comprised:
Two first suspender belts (21) are connected on two hangers (72) of described base (71) both sides, another root first suspender belt (21) is connected on the hanger (72) on described base (71) top.
CN201511022610.2A 2015-12-29 2015-12-29 Lifting device and method for wind turbine generator set Pending CN105540410A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201511022610.2A CN105540410A (en) 2015-12-29 2015-12-29 Lifting device and method for wind turbine generator set

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201511022610.2A CN105540410A (en) 2015-12-29 2015-12-29 Lifting device and method for wind turbine generator set

Publications (1)

Publication Number Publication Date
CN105540410A true CN105540410A (en) 2016-05-04

Family

ID=55820049

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201511022610.2A Pending CN105540410A (en) 2015-12-29 2015-12-29 Lifting device and method for wind turbine generator set

Country Status (1)

Country Link
CN (1) CN105540410A (en)

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106829722A (en) * 2017-04-05 2017-06-13 东方电气风电有限公司 Large-scale Wind Turbines variable propeller gearbox installation tool
CN107399665A (en) * 2017-08-18 2017-11-28 大唐桂冠盘州市四格风力发电有限公司 Fan blade is flat to hang and changes suspender
CN108190725A (en) * 2017-12-30 2018-06-22 北京金风科创风电设备有限公司 Hoisting device and nacelle hoisting method
CN108358064A (en) * 2018-01-24 2018-08-03 南京工业大学 Self-powered tower crane rotating lifting appliance device
CN108840221A (en) * 2018-08-28 2018-11-20 山西航天清华装备有限责任公司 Cylinder plays combined sling
CN108840289A (en) * 2018-07-28 2018-11-20 安徽华瑞电气有限公司 Boom hoisting is used in a kind of processing of flange cluster type electric heater
EP3404259A1 (en) * 2017-05-18 2018-11-21 Senvion GmbH Method, load carrying means and mounting system for assembling a wind turbine
CN109019292A (en) * 2018-08-20 2018-12-18 广州电力机车有限公司 A kind of hanging method of dumper power assembly
CN110697560A (en) * 2019-10-24 2020-01-17 三一重能有限公司 Fixed knot constructs and hoist
CN114148888A (en) * 2021-12-24 2022-03-08 中交第一航务工程局有限公司 Lifting hanging beam for mounting wind driven generator cabin and operation method
CN114945751A (en) * 2019-12-19 2022-08-26 维斯塔斯风力系统有限公司 Method for installing or removing a wind turbine component
CN115110592A (en) * 2022-07-22 2022-09-27 宁夏回族自治区电力设计院有限公司 Deviation correcting method for power transmission line tower in coal mine goaf
CN117486045A (en) * 2022-07-26 2024-02-02 华能阳江风力发电有限公司 A kind of wind turbine hoisting equipment
CN119195986A (en) * 2024-09-25 2024-12-27 奉新伟恒风力发电有限公司 Center of gravity correction device and method for overall installation of top-mounted wind turbine generator set
EP3786448B1 (en) * 2019-08-29 2025-04-23 General Electric Renovables España, S.L. Method of mounting a nacelle of a wind turbine and assembling set of parts of a wind turbine

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201268549Y (en) * 2008-06-06 2009-07-08 中国海洋石油总公司 Hoisting appliance for offshore wind power generation tower frame
DE202010003033U1 (en) * 2010-02-17 2010-05-27 Nordex Energy Gmbh Hoist for positioning a rotor blade of a wind energy plant
CN102275809A (en) * 2011-07-07 2011-12-14 中国十七冶集团有限公司 Special-purposed bidirectional regulation combined lifting appliance for lifting tower drum of wind driven generator
CN102491162A (en) * 2011-11-24 2012-06-13 北京金风科创风电设备有限公司 Hoisting equipment and hoisting methods
CN202465024U (en) * 2012-02-16 2012-10-03 中国十七冶集团有限公司 Balance hoisting appliance for wind generator nacelle hoisting
CN203064997U (en) * 2013-01-22 2013-07-17 扬州市神力吊具制造有限公司 Wind driven generator and cabin assembly sling
CN203128000U (en) * 2013-03-28 2013-08-14 北京金风科创风电设备有限公司 Hoisting device for direct-driven wind power generator set
CN104444762A (en) * 2014-11-03 2015-03-25 珠海南方广立风电设备有限公司 Wind power foundation ring overturning device and method for overturning foundation ring by using same

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201268549Y (en) * 2008-06-06 2009-07-08 中国海洋石油总公司 Hoisting appliance for offshore wind power generation tower frame
DE202010003033U1 (en) * 2010-02-17 2010-05-27 Nordex Energy Gmbh Hoist for positioning a rotor blade of a wind energy plant
CN102275809A (en) * 2011-07-07 2011-12-14 中国十七冶集团有限公司 Special-purposed bidirectional regulation combined lifting appliance for lifting tower drum of wind driven generator
CN102491162A (en) * 2011-11-24 2012-06-13 北京金风科创风电设备有限公司 Hoisting equipment and hoisting methods
CN202465024U (en) * 2012-02-16 2012-10-03 中国十七冶集团有限公司 Balance hoisting appliance for wind generator nacelle hoisting
CN203064997U (en) * 2013-01-22 2013-07-17 扬州市神力吊具制造有限公司 Wind driven generator and cabin assembly sling
CN203128000U (en) * 2013-03-28 2013-08-14 北京金风科创风电设备有限公司 Hoisting device for direct-driven wind power generator set
CN104444762A (en) * 2014-11-03 2015-03-25 珠海南方广立风电设备有限公司 Wind power foundation ring overturning device and method for overturning foundation ring by using same

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106829722A (en) * 2017-04-05 2017-06-13 东方电气风电有限公司 Large-scale Wind Turbines variable propeller gearbox installation tool
CN106829722B (en) * 2017-04-05 2018-06-29 东方电气风电有限公司 Large-scale Wind Turbines variable propeller gearbox installation tool
EP3404259A1 (en) * 2017-05-18 2018-11-21 Senvion GmbH Method, load carrying means and mounting system for assembling a wind turbine
CN107399665A (en) * 2017-08-18 2017-11-28 大唐桂冠盘州市四格风力发电有限公司 Fan blade is flat to hang and changes suspender
CN108190725A (en) * 2017-12-30 2018-06-22 北京金风科创风电设备有限公司 Hoisting device and nacelle hoisting method
CN108190725B (en) * 2017-12-30 2020-03-10 北京金风科创风电设备有限公司 Hoisting device and nacelle hoisting method
CN108358064A (en) * 2018-01-24 2018-08-03 南京工业大学 Self-powered tower crane rotating lifting appliance device
CN108840289A (en) * 2018-07-28 2018-11-20 安徽华瑞电气有限公司 Boom hoisting is used in a kind of processing of flange cluster type electric heater
CN109019292A (en) * 2018-08-20 2018-12-18 广州电力机车有限公司 A kind of hanging method of dumper power assembly
CN108840221A (en) * 2018-08-28 2018-11-20 山西航天清华装备有限责任公司 Cylinder plays combined sling
CN108840221B (en) * 2018-08-28 2023-09-29 山西航天清华装备有限责任公司 Cartridge-bullet combined lifting appliance
EP3786448B1 (en) * 2019-08-29 2025-04-23 General Electric Renovables España, S.L. Method of mounting a nacelle of a wind turbine and assembling set of parts of a wind turbine
CN110697560A (en) * 2019-10-24 2020-01-17 三一重能有限公司 Fixed knot constructs and hoist
CN114945751A (en) * 2019-12-19 2022-08-26 维斯塔斯风力系统有限公司 Method for installing or removing a wind turbine component
CN114148888A (en) * 2021-12-24 2022-03-08 中交第一航务工程局有限公司 Lifting hanging beam for mounting wind driven generator cabin and operation method
CN115110592A (en) * 2022-07-22 2022-09-27 宁夏回族自治区电力设计院有限公司 Deviation correcting method for power transmission line tower in coal mine goaf
CN117486045A (en) * 2022-07-26 2024-02-02 华能阳江风力发电有限公司 A kind of wind turbine hoisting equipment
CN119195986A (en) * 2024-09-25 2024-12-27 奉新伟恒风力发电有限公司 Center of gravity correction device and method for overall installation of top-mounted wind turbine generator set

Similar Documents

Publication Publication Date Title
CN106415005B (en) Method and system for dismounting and remounting wind turbine blade
CN102464273B (en) Offshore fan installing platform and fan integral installation rotary holding and lifting mechanism
CN203806941U (en) Hoisting overturning device of direct-drive wind power generator
CN102491162B (en) Hoisting equipment and hoisting method
CN202848861U (en) Impeller hoisting device for wind generating set
CN105905813B (en) A kind of wind-driven generator leaf suspender
CN103939299B (en) The split type mounting process of a kind of offshore wind turbine
CN203064997U (en) Wind driven generator and cabin assembly sling
CN203128000U (en) Hoisting device for direct-driven wind power generator set
CN201686394U (en) Hoisting Tooling for Pitch Gearbox of Megawatt Wind Turbine Generating Set
CN105129629B (en) Large component lifting system, disassembling method thereof and large component lifting method
CN113120741A (en) 3200T tower section of thick bamboo lifting device
CN106829722A (en) Large-scale Wind Turbines variable propeller gearbox installation tool
CN114080498A (en) Method for handling wind turbine components and associated lifting system
CN205838410U (en) Blower fan hoisting mechanism
CN202465024U (en) Balance hoisting appliance for wind generator nacelle hoisting
CN114148888A (en) Lifting hanging beam for mounting wind driven generator cabin and operation method
CN210029720U (en) Gas turbine upper and lower platform dismounting lifting appliance
CN219412790U (en) Wind driven generator blade replacement equipment based on multiple pulley blocks
CN216945817U (en) Lifting hanging beam for mounting wind driven generator cabin
CN202729568U (en) Novel wind generating set variable pitch bearing assembly device
CN217894864U (en) Modular lifting appliance, lifting system and wind driven generator
CN205241039U (en) Installation hoist of generator
CN104986681A (en) Power-variable device for single-power pulley block
JP7063977B1 (en) How to remove the blade, how to attach the blade and hanging jig

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20160504