CN105507575B - A kind of hollow combined building shuttering - Google Patents

A kind of hollow combined building shuttering Download PDF

Info

Publication number
CN105507575B
CN105507575B CN201410495578.9A CN201410495578A CN105507575B CN 105507575 B CN105507575 B CN 105507575B CN 201410495578 A CN201410495578 A CN 201410495578A CN 105507575 B CN105507575 B CN 105507575B
Authority
CN
China
Prior art keywords
side plate
combined building
hollow combined
building shuttering
guide groove
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410495578.9A
Other languages
Chinese (zh)
Other versions
CN105507575A (en
Inventor
王斌坚
章国荣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nengcheng Group Co Ltd
Original Assignee
Nengcheng Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nengcheng Group Co Ltd filed Critical Nengcheng Group Co Ltd
Priority to CN201410495578.9A priority Critical patent/CN105507575B/en
Publication of CN105507575A publication Critical patent/CN105507575A/en
Application granted granted Critical
Publication of CN105507575B publication Critical patent/CN105507575B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Moulds, Cores, Or Mandrels (AREA)

Abstract

A kind of hollow combined building shuttering, including stencil body, have the first side plate, the second side plate and be arranged on some first gussets that are that connection function is played between first side plate and second side plate and extending in a first direction;Between first side plate and second side plate of the stencil body, and between each first gusset, several rebar elements are fixedly mounted along the second direction perpendicular to the first direction, the width of the rebar element in a first direction is less than length in a second direction, and along the first direction arranged for interval.The hollow combined building shuttering processing technology of the present invention is simple, on the premise of the intensity of hollow template is enhanced, can further save raw material so that whole hollow combined building shuttering quality is lighter.

Description

A kind of hollow combined building shuttering
Technical field
The present invention relates to building field, relates in particular to a kind of to the hollow of hollow building template progress intensity reinforcement Combined building shuttering.
Background technology
The working building template of cast-in-place concrete structure, it is to ensure concrete structure according to design requirement casting concrete A kind of temporary pattern structure of shaping.The temporary pattern structure is often to be spliced by multiple building templates by certain connecting method Form.Recently as the development of technology, hollow building template arises at the historic moment.The hollow building template of prior art generally passes through Extrusion way is molded, and stress of the hollow building template of extrusion molding in non-extruded direction is weaker, therefore generally hollow Strengthened in building template by reinforcing rib structure.
A kind of hollow plastic building template as disclosed in Chinese patent literature CN203066453U, template hollow portion, which is provided with, to be added Strengthening tendons group, reinforcement group include several spaced first reinforcing rib structures and the second reinforcing rib structure, the first reinforcement Structure includes the two vertical reinforcements perpendicular to template two sides and the positive bevel reinforcement between two vertical reinforcements, the Two reinforcing rib structures include the two vertical reinforcements perpendicular to template two sides and the reverse slope between two vertical reinforcements Reinforcement, several Crop Areas are also distributed between reinforcement group.The patent document sets reinforcement group in hollow template, relatively For solid building template, raw material can be effectively reduced in the case where ensureing the mechanical strength of hollow building template Dosage, alleviate the weight of template, be easy to manufacture, but for metal form, because the property of material determines, by The poor fluidity of matter is melted in it, it is directly produced the template of this high density gusset by expressing technique and technical be stranded be present Difficulty, and the effect of the too low then gusset of density is by unobvious.In addition, the structure of this extrusion molding, in the template produced time Cloth reinforcement, and it is not optimal structure for the template of metal material, on the one hand its weight it is larger, using rise It is inconvenient to come, and material compares waste.On the other hand, change of the structure of reinforcement for template stress is spread all over, particularly It is not optimal to improve bending strength.
The content of the invention
Therefore, the technical problems to be solved by the invention are that the structure of the hollow building template of prior art is ensureing to have Intensity on the premise of, the problem of hollow building template of this kind of structure is not also most material saving, and quality is most light, and then provide On the premise of a kind of intensity for ensureing application, raw material, the lighter hollow combined building shuttering of quality can be further saved.
In order to solve the above technical problems, a kind of hollow combined building shuttering of the present invention, including stencil body, have first Side plate, the second side plate and be arranged on risen between first side plate and second side plate connection function and along first party To some first gussets of extension;
Between first side plate and second side plate of the stencil body, and each first gusset it Between, it is fixedly mounted several rebar elements along the second direction perpendicular to the first direction, the rebar element is the Width on one direction is less than length in a second direction, and along the first direction arranged for interval.
In the hollow combined building shuttering of the present invention, first side plate and second side plate and described the is arranged on Side plate and two first gussets of the second side plate both side edges surround a template inner chamber;The inwall of the inner chamber and described Edge corresponding to rebar element is provided with enters the guiding knot that the inner chamber is oriented to for the rebar element in a first direction Structure.
In the hollow combined building shuttering of the present invention, it is secondary that the guide frame is arranged to linear motion.
In the hollow combined building shuttering of the present invention, the secondary fit form for guide groove guide rail of linear motion.
In the hollow combined building shuttering of the present invention, the guide groove corresponds to the rectangle including being arranged on the inner chamber The first guide groove at the corner of housing, first guide groove are molded over four that these positions are set and extended along the first direction Fin on;The guide rail includes being arranged at the corner of the rectangular outer frame, four articles along described the of shaping in these positions First guide rail of one direction extension, first guide rail are adapted to be embedded in first guide groove.
In the hollow combined building shuttering of the present invention, the cross section of the fin is in from the top of the fin along parallel In the protuberance that the intracavity sidewall where the fin stretches out, the fin and the protuberance and the residing inner chamber Side wall together surrounds first groove;First guide rail is by the rectangular outer frame in the length perpendicular to the section of first direction The part that edge protrudes parallel to first side plate or second side plate is formed.
In the hollow combined building shuttering of the present invention, the rectangular outer frame is perpendicular to the long side in the section of first direction Middle part forms the second guide groove by being recessed, and the corresponding position of the intracavity sidewall, which is provided with, to be adapted in embedded second guide groove Second guide rail.
In the hollow combined building shuttering of the present invention, the rebar element includes rectangular outer frame, and is arranged on institute State the rib in rectangular outer frame;The gusset is connected and composed perpendicular to first party with first side plate and second side plate To section there is the hog frame of triangular element.
In the hollow combined building shuttering of the present invention, the rebar element is fixedly mounted on described by welding manner On stencil body.
In the hollow combined building shuttering of the present invention, institute is provided with the rebar element at corresponding pad State the solder-bump of the first side plate or second side plate protrusion.
In the hollow combined building shuttering of the present invention, light in each welding and set at least provided with two mutual intervals Put the solder-bump.
In the hollow combined building shuttering of the present invention, the pad is arranged on the muscle on the rebar element The corresponding housing outer edge locations of bar end.
In the hollow combined building shuttering of the present invention, the rebar element at least with first side plate and described the Two side plates are interference fitted.
The present invention hollow combined building shuttering in, first side plate, second side plate, first gusset with And the material of the rebar element is aluminium, or the material of first side plate, second side plate and first gusset is Aluminium, the material of the rebar element is rigid plastics.
In the hollow combined building shuttering of the present invention, in the space between the template inner chamber and the rebar element Expanded material is also marked with advance.
The above-mentioned technical proposal of the present invention has advantages below compared with prior art:
1st, in the present invention, by the way that compartment of terrain is provided with several rebar elements, phase in the first direction in stencil body The use for the material such as aluminium for making reinforcement can not only be reduced for prior art, reduces production cost, and reinforcement list Member can be processed individually with stencil body so that processing technology is simple, and this is in the mould with the metal material extrusion molding such as aluminium It is particularly evident, it is often more important that using material reduction while, intensity does not reduce, because the rebar element at interval Arrangement, can form " well " word girder construction, template is reached optimal stressed effect, so as to improve the carrying energy of hollow template Power.Also pre- note expanded material can not only prevent mud from entering in the space between template inner chamber and rebar element in addition, and And the ability enhancing that template can also be made integrally to withstand forces.
2nd, in the present invention, the use of the guide frame between inner chamber and rebar element, it is easy to multiple rebar elements Distribution in the inner chamber of stencil body, and when guide frame uses the form of guide groove guide rail, it is simple in construction, beneficial to template sheet The machine-shaping of body and rebar element.
3rd, in the present invention, using the connected mode of welding, not only technique is simple, and connects reliable, rebar element First side plate or second side plate protrusion are provided with corresponding to upper at pad and is extended along the first direction Solder-bump, it can be advantageous to rebar element being welded on stencil body.
Brief description of the drawings
In order that present disclosure is more likely to be clearly understood, specific embodiment and combination below according to the present invention Accompanying drawing, the present invention is further detailed explanation, wherein
Fig. 1 is the cross-sectional view of the hollow combined building shuttering of the present invention;
Fig. 2 is the cross-sectional view of the stencil body of the hollow combined building shuttering of the present invention;
Fig. 3 is the sectional view of the rebar element of the hollow combined building shuttering of the present invention.
Reference is expressed as in figure:The side plates of 1- first, the side plates of 2- second, the gussets of 3- first, 4- rebar elements, 5- One guide groove, the guide rails of 6- first, the guide grooves of 7- second, the guide rails of 8- second, 9- rectangular outer frames 9,10- ribs, 11- solder-bumps.
Embodiment
As Figure 1-3, a kind of hollow combined building shuttering of the present embodiment, including stencil body, there is the first side plate 1st, the second side plate 2 and be arranged on risen between first side plate 1 and second side plate 2 connection function and along first party To some first gussets 3 of extension;
Between first side plate 1 and second side plate 2 of the stencil body, and in each first gusset 3 Between, several rebar elements 4, the rebar element 4 is fixedly mounted along the second direction perpendicular to the first direction Width in a first direction is less than length in a second direction, and along the first direction arranged for interval.
Such scheme is core scheme of the invention, by the way that compartment of terrain is provided with several in the first direction in stencil body Rebar element 4, the use for the material for making reinforcement can not only be reduced relative to prior art, reduce production cost, and And processing technology is simple, it is often more important that the arrangement of the rebar element at interval, can form " well " word girder construction, reach template To optimal stressed effect, the bearing capacity of hollow template is improved.In addition, the template inner chamber and the rebar element 4 it Between space in be also marked with expanded material in advance, can not only prevent mud from entering, but also can make what template was integrally withstood forces Ability strengthens.
As shown in Fig. 2 first side plate 1 of hollow stencil body and second side plate 2 and being arranged on described first Side plate 1 and two first gussets 3 of the both side edges of the second side plate 2 surround a template inner chamber;For the ease of by multiple reinforcements Muscle unit 4 is smoothly fitly arranged on the interior intracavitary, corresponding to the inwall of the inner chamber and the rebar element 4 on edge Provided with the guide frame for entering inner chamber guiding in a first direction for the rebar element 4.The structure of the guide frame Form can have it is a variety of, in the present embodiment, the guide frame be preferably move along a straight line it is secondary.The linear motion pair is led for guide groove The fit form of rail.
The form that guide groove guide rail is set between the inner chamber and rebar element 4 have it is a variety of, be described below it is a kind of preferably Set-up mode:The guide groove includes being arranged on the inner chamber corresponding to the first guide groove 5 at the corner of the rectangular outer frame, institute The first guide groove 5 is stated to be molded on four fins along first direction extension of these positions setting;The guide rail includes setting Put at the corner of the rectangular outer frame, four the first guide rails 6 extended along the first direction of shaping, institute in these positions The first guide rail 6 is stated to be adapted in embedded first guide groove 5.Inserted by the first guide rail 6 and along the slip side of the first guide groove 5 Formula, multiple rebar elements can be enable to slide to corresponding set location from one end of the inner chamber, meanwhile, also can pair plus Strengthening tendons unit 4 carries out spacing.
The cross section of the fin is in from the top of the fin along parallel to the intracavity sidewall where the fin The protuberance of stretching, the fin together surround first groove with the protuberance and the residing intracavity sidewall;Institute State the first guide rail 6 by the rectangular outer frame perpendicular to the long edge in the section of first direction parallel to first side plate 1 or The part that second side plate 2 protrudes is formed.
In order to further in the lumen spacing of rebar element 4, the particularly length of rebar element 4 in a second direction When degree is longer, the rectangular outer frame forms the second guide groove 7, institute perpendicular to the middle part of the long side in the section of first direction by being recessed The corresponding position for stating intracavity sidewall is provided with the second guide rail 8 being adapted in embedded second guide groove 7.
The rebar element 4 includes rectangular outer frame 9, and the rib 10 being arranged in the rectangular outer frame 9;It is preferred that institute Stating rib 10 and being connected and composed with first side plate 1 and second side plate 2 has triangle in the section perpendicular to first direction The hog frame of shape unit, the hog frame bonding strength of this spline structure is more preferable, more stable.
The rebar element 4 is at least interference fitted with first side plate 1 and second side plate 2.The reinforcement Unit 4 by swelling after thermal expansion shrinkage mode can be fixedly mounted on the interior intracavitary, but in order to ensure bonding strength, can It is fixedly mounted on by welding manner on the stencil body.
Described the is provided with corresponding pad as shown in figure 3, for the ease of welding, on the rebar element 4 The solder-bump 11 of side plate 1 or second side plate 2 protrusion.Light in each welding and be spaced between each other at least provided with two The solder-bump 11 is set.The number of the solder-bump 11 can be arranged as required to.In order to ensure bonding strength, the weldering Contact is arranged on the corresponding housing outer edge locations of the end of the rib 10 on the rebar element 4.
It can be selected on the material of stencil body and rebar element according to being actually needed, in the present embodiment, First side plate 1, second side plate 2, the material of first gusset 3 and the rebar element 4 are aluminium.Template sheet Body structure is made with rebar element structure of aluminum material, and not only intensity is good, and template can be applied repeatedly, and by this The structural quality for covering template pouring molding is high.
In other embodiments, the material of first side plate 1, second side plate 2 and first gusset 3 is aluminium, The material of the rebar element 4 is rigid plastics, so can also meet the requirement of intensity, while saves the application of aluminum, Further save cost.
Obviously, above-described embodiment is only intended to clearly illustrate example, and is not the restriction to embodiment.It is right For those of ordinary skill in the art, can also make on the basis of the above description it is other it is various forms of change or Change.There is no necessity and possibility to exhaust all the enbodiments.And the obvious change thus extended out or Among changing still in the protection domain of the invention.

Claims (14)

1. a kind of hollow combined building shuttering, including
Stencil body, have the first side plate (1), the second side plate (2) and be arranged on first side plate (1) and described second Some first gussets (3) that are that connection function is played between side plate (2) and extending in a first direction;
It is characterized in that:
Between first side plate (1) of the stencil body and second side plate (2), and each first gusset it Between, several rebar elements (4), the rebar element is fixedly mounted along the second direction perpendicular to the first direction (4) width in a first direction is less than length in a second direction, and along the first direction arranged for interval;Described first Side plate (1) and second side plate (2) and two institutes for being arranged on first side plate (1) and the second side plate (2) both side edges State the first gusset (3) and surround a template inner chamber;Edge corresponding to the inwall of the inner chamber and the rebar element (4) is provided with Enter the guide frame that the inner chamber is oriented in a first direction for the rebar element (4).
2. hollow combined building shuttering according to claim 1, it is characterised in that:The guide frame is arranged to straight line fortune Dynamic pair.
3. hollow combined building shuttering according to claim 2, it is characterised in that:The linear motion pair is guide groove guide rail Fit form.
4. hollow combined building shuttering according to claim 3, it is characterised in that:The guide groove includes being arranged in described The first guide groove (5) that chamber corresponds at the corner of rectangular outer frame, first guide groove (5) are molded over four of these positions setting Along along the fin of first direction extension;The guide rail includes being arranged at the corner of the rectangular outer frame, in these positions The first guide rail (6) that four of shaping extend along the first direction, first guide rail (6) are adapted to embedded first guide groove (5) in.
5. hollow combined building shuttering according to claim 4, it is characterised in that:The cross section of the fin is in from described The protuberance that the top edge of fin is stretched out parallel to the intracavity sidewall where the fin, the fin and the protuberance And the residing intracavity sidewall together surrounds first guide groove;First guide rail (6) is by the rectangular outer frame vertical Formed in the long edge in the section of first direction parallel to the prominent part of first side plate (1) or second side plate (2).
6. hollow combined building shuttering according to claim 4, it is characterised in that:The rectangular outer frame is perpendicular to first party To the middle part of long side in section form the second guide groove (7) by being recessed, the corresponding position of the intracavity sidewall, which is provided with, to be adapted to The second guide rail (8) in embedded second guide groove (7).
7. according to the hollow combined building shuttering described in claim 1-6 any one, it is characterised in that:The rebar element (4) rectangular outer frame (9), and the rib (10) being arranged in the rectangular outer frame (9) are included;The rib (10) and described the Side plate (1) and second side plate (2) are connected and composed in the reinforcement perpendicular to the section of first direction with triangular element Frame.
8. hollow combined building shuttering according to claim 7, it is characterised in that:The rebar element (4) passes through weldering The mode of connecing is fixedly mounted on the stencil body.
9. hollow combined building shuttering according to claim 8, it is characterised in that:It is corresponding on the rebar element (4) Pad at be provided with first side plate (1) or second side plate (2) protrusion solder-bump (11).
10. hollow combined building shuttering according to claim 9, it is characterised in that:It is each welding light at least provided with Two are arranged at intervals the solder-bump (11) between each other.
11. hollow combined building shuttering according to claim 10, it is characterised in that:The pad is arranged on described add The corresponding rectangular outer frame outer edge locations of the rib (10) end on strengthening tendons unit (4).
12. the hollow combined building shuttering according to any one of claim 1-6, it is characterised in that:The reinforcement list First (4) are at least interference fitted with first side plate (1) and second side plate (2).
13. the hollow combined building shuttering according to any one of claim 1-6, it is characterised in that:First side plate (1), the material of second side plate (2), first gusset (3) and the rebar element (4) is aluminium, or described first The material of side plate (1), second side plate (2) and first gusset (3) is aluminium, and the material of the rebar element (4) is Rigid plastics.
14. the hollow combined building shuttering according to any one of claim 1-6, it is characterised in that:The template inner chamber Expanded material is also marked with advance in space between the rebar element (4).
CN201410495578.9A 2014-09-25 2014-09-25 A kind of hollow combined building shuttering Active CN105507575B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410495578.9A CN105507575B (en) 2014-09-25 2014-09-25 A kind of hollow combined building shuttering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410495578.9A CN105507575B (en) 2014-09-25 2014-09-25 A kind of hollow combined building shuttering

Publications (2)

Publication Number Publication Date
CN105507575A CN105507575A (en) 2016-04-20
CN105507575B true CN105507575B (en) 2018-01-12

Family

ID=55715847

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410495578.9A Active CN105507575B (en) 2014-09-25 2014-09-25 A kind of hollow combined building shuttering

Country Status (1)

Country Link
CN (1) CN105507575B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103364474A (en) * 2013-06-26 2013-10-23 湖南致力工程科技有限公司 Potentiometric-titration-based method for detecting doping amount of modifying agent in modified asphalt
CN108612304B (en) * 2018-05-31 2020-08-25 重庆瑞鑫科五金制品有限公司 Toilet hanging mould system

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08144510A (en) * 1994-11-22 1996-06-04 Mitsubishi Plastics Ind Ltd Plastic form panel
JPH08207190A (en) * 1995-02-06 1996-08-13 Mitsubishi Plastics Ind Ltd Plastic composite panel
CN201040923Y (en) * 2007-05-23 2008-03-26 吴德忠 Building elevation plane combined type mold
JP5391380B2 (en) * 2010-05-12 2014-01-15 株式会社長大 Formwork material
CN204186066U (en) * 2014-09-25 2015-03-04 能诚集团有限公司 A kind of hollow combined building shuttering

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08144510A (en) * 1994-11-22 1996-06-04 Mitsubishi Plastics Ind Ltd Plastic form panel
JPH08207190A (en) * 1995-02-06 1996-08-13 Mitsubishi Plastics Ind Ltd Plastic composite panel
CN201040923Y (en) * 2007-05-23 2008-03-26 吴德忠 Building elevation plane combined type mold
JP5391380B2 (en) * 2010-05-12 2014-01-15 株式会社長大 Formwork material
CN204186066U (en) * 2014-09-25 2015-03-04 能诚集团有限公司 A kind of hollow combined building shuttering

Also Published As

Publication number Publication date
CN105507575A (en) 2016-04-20

Similar Documents

Publication Publication Date Title
MX2009013128A (en) Process for constructing the loadbearing structure of a motor vehicle body, and loadbearing structure so constructed.
CN105507575B (en) A kind of hollow combined building shuttering
CN203066236U (en) SCS concrete-filled steel tubular structure with through and long inside where PBL stiffening ribs are distributed
CN208263086U (en) It is a kind of for forming the mold of non-uniform pile
CN204186066U (en) A kind of hollow combined building shuttering
CN203007821U (en) SCS steel tube concrete pier with double stiffening structures added on upper end portion and lower end portion
CN203008236U (en) SCS (steel concrete structure) concrete-filled steel tube structure with vertical reinforcing structure in internal whole length
CN204151682U (en) T-shaped joist steel mould adjustable angle device
CN211762342U (en) Internal mold top plate of prefabricated smoke exhaust pipeline forming mold
CN202866274U (en) Flat surface and curved surface dual-use combined steel formwork for pouring of concrete
CN104797762A (en) Building and construction method thereof
CN203171794U (en) Special template for orthogonal diagonal prefabricated box beams at broadening positions of forks of expressways
CN110524686B (en) Die for forming variable-section piles
CN208899859U (en) A kind of assembled architecture cylinder pours mould
CN206128445U (en) Reserve solid post of prefabrication of plug hole
CN207314821U (en) A kind of new aluminum alloy pattern plate
CN206539017U (en) Small-sized waffle beam lattice detachable template system
CN204126095U (en) A kind of hollow building cover
CN206800175U (en) A kind of double font Bridge High-pier structure
CN205421770U (en) Exempt from to weld trapezoidal guardrail section bar of high strength class
CN204418665U (en) A kind of hetermorphiscal column steel form
CN218699882U (en) Reinforcing die for drainage ditch template
CN214169635U (en) Semi-hollow gypsum block
CN217762660U (en) Outer rib reinforced porous ribbed pipe
CN210032330U (en) Reinforced main beam

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant