CN105507498B - A kind of rear anchoring process of tension steel construction - Google Patents

A kind of rear anchoring process of tension steel construction Download PDF

Info

Publication number
CN105507498B
CN105507498B CN201510867260.3A CN201510867260A CN105507498B CN 105507498 B CN105507498 B CN 105507498B CN 201510867260 A CN201510867260 A CN 201510867260A CN 105507498 B CN105507498 B CN 105507498B
Authority
CN
China
Prior art keywords
hole
anchoring process
steel construction
rear anchoring
tension steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510867260.3A
Other languages
Chinese (zh)
Other versions
CN105507498A (en
Inventor
高宗瑞
宋春玲
顾强强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Aviation Planning and Design Institute Group Co Ltd
Original Assignee
China Aviation Planning and Design Institute Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Aviation Planning and Design Institute Group Co Ltd filed Critical China Aviation Planning and Design Institute Group Co Ltd
Priority to CN201510867260.3A priority Critical patent/CN105507498B/en
Publication of CN105507498A publication Critical patent/CN105507498A/en
Application granted granted Critical
Publication of CN105507498B publication Critical patent/CN105507498B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/08Members specially adapted to be used in prestressed constructions
    • E04C5/12Anchoring devices

Abstract

The present invention is a kind of rear anchoring process of tension steel construction, and this method is the rear anchoring process based on concrete substrate, belongs to the product structure technology of building engineering field.The present invention solves the technical problem anchored on concrete base layer after big load tension steel member, while has multiple defence line, reaches the effect of high-reliability.The pouring material poured after used must have microdilatancy effect, such as mix the concrete of micro-expanding agent or conventional back-grouting material.

Description

A kind of rear anchoring process of tension steel construction
Technical field:
The present invention is a kind of rear anchoring process of tension steel construction, and this method is the rear anchoring side based on concrete substrate Method, belong to the product structure technology of building engineering field.
Background technology:
The anchorage node practice has two kinds after tension steel construction on conventional concrete substrate:One kind is that production is anchored after using Product (such as chemically-planted steel bar, chemistry plant crab-bolt, mechanical anchor), will be fixed on concrete, this mode is by product mechanics after steel member The limitation of performance, bearing capacity are restricted, and can not be applicable when tension load value is larger;One kind is the hole-opening on concrete, and Poured after steel member is used into back-grouting material in embedment hole, bearing capacity is higher in theory for this mode, but actual field construction bar Part differs, and actual bearing capacity ratio theory is much lower, due to only setting up defences together, once construction quality is bad to directly result in section The destruction of point.
The content of the invention
The technical problems to be solved by the invention:
The present invention is exactly to design and provide on a kind of concrete substrate for shortcoming present in above-mentioned prior art Anchorage node after tension steel construction, the purpose is to the technology for solving to anchor after big load tension steel member on concrete base layer to ask Topic, while there is multiple defence line, reach the effect of high-reliability.The pouring material poured after used must have microdilatancy effect, Such as mix the concrete of micro-expanding agent or conventional back-grouting material.
Technical scheme:
A kind of rear anchoring process of tension steel construction is provided, this method is the rear anchoring process based on concrete substrate, its It is characterised by that this method comprises the following steps:
Step 1: the end of peg 5 is welded to the surface of the anchoring section of steel member 4;
Step 2: the hole-opening 2 on concrete base layer 1, described hole 2 is the wedge shape that oral area is small, bottom is big;
Step 3: being uniformly provided with side hole 7 in the side wall of the described bottom of hole 2, side hole 7 is multiple;
Step 4: in the inner wall surface dabbing of described hole 2;
Step 5: the inner wall surface in described hole 2 plants bar dowel 8;
Step 6: shear key 6 is inserted into side hole 7, one shear key 6 of insertion in each side hole 7, and cause shear key 6 end is exposed at outside side hole 7;
Step 7: steel member 4 is inserted into the bottom of described hole 2, and the lower end of steel member 4 and the end of shear key 6 are welded It is connected together;
Step 8: pouring grouting material 3 into described hole 2, and conserve to required intensity;Described grouting material To mix the concrete of micro-expanding agent or back-grouting material.
Further, the peg 5 in step 1 is multiple.
Further, the hole 2 described in step 2 is more than 30 degree with horizontal plane angle;Hole-opening is using water drilling, pneumatic pick And/or the mode manually to hole.
Further, opened in step 3 by the way of side hole holed using pneumatic pick or manually;
Further, in step 4 using pneumatic pick or it is artificial by the way of dabbing;
Further, the bar planting by the way of chemical glue or cement mortar in step 5.
The beneficial effect of invention:
The first line of defence:The pulling force of steel member 4 is transferred to grouting material 3 by surface shear key 5, then is transferred to hole 2 The surface of dabbing, finally it is transferred to concrete base layer 1.
Second defence line:The pulling force of steel member 4 is transferred to grouting material 3 by peg 5, then is transferred to the surface of hole 2 Bar dowel 8, finally it is transferred to concrete base layer 1.
Three lines of defence:The pulling force of steel member 4 is transferred to grouting material 3 by shear key 6, then is transferred to hole 2, passes through The inclined-plane of hole 2 is pressurized and is transferred to concrete base layer 1.
Four lines of defense:The pulling force of steel member 4 is transferred to grouting material 3 by shear key 6, then by the wall of side cavities 7 by Pressure is transferred to concrete base layer 1.
Four lines of defense each can independently undertake the pulling force of steel member 4, and reliability is greatly improved compared with conventional practice, subtracts The small node failure caused by execution conditions reason.
Brief description of the drawings
Fig. 1 is vertical cross section figure
Fig. 2 is top view
Fig. 3 is vertical cross section figure
Wherein:1- concrete base layers, 2- holes, 3- grouting material 4- steel members, 5- pegs, 6- shear keies, 7- side cavities, 8- bar dowels.
Embodiment:
The construction procedure of anchorage node is as follows after this tension steel construction:
Step 1: the end of peg 5 is welded to the surface of the anchoring section of steel member 4;
Step 2: the hole-opening 2 on concrete base layer 1, described hole 2 is the wedge shape that oral area is small, bottom is big;
Step 3: being uniformly provided with side hole 7 in the side wall of the described bottom of hole 2, side hole 7 is multiple;
Step 4: in the inner wall surface dabbing of described hole 2;
Step 5: the inner wall surface in described hole 2 plants bar dowel 8;
Step 6: shear key 6 is inserted into side cavities 7, one shear key 6 of insertion in each side cavities 7, and cause anti- The end for cutting key 6 is exposed at outside side hole 7;
Step 7: steel member 4 is inserted into the bottom of described hole 2, and the lower end of steel member 4 and the end of shear key 6 are welded It is connected together;
Step 8: pouring grouting material 3 into described hole 2, and conserve to required intensity;Described grouting material To mix the concrete of micro-expanding agent or back-grouting material.
Further, the peg 5 in step 1 is multiple.
Further, the hole 2 described in step 2 is more than 30 degree with horizontal plane angle;Hole-opening is using water drilling, pneumatic pick And/or the mode manually to hole.
Further, opened in step 3 by the way of side hole holed using pneumatic pick or manually;
Further, in step 4 using pneumatic pick or it is artificial by the way of dabbing;
Further, the bar planting by the way of chemical glue or cement mortar in step 5.
Further, in step 2, described hole is non-perpendicular with horizontal plane.

Claims (7)

1. a kind of rear anchoring process of tension steel construction, this method are the rear anchoring process based on concrete substrate, its feature exists Comprise the following steps in this method:
Step 1: the end of peg (5) is welded to the surface of steel member (4) anchoring section;
Step 2: the hole-opening (2) on concrete base layer (1), described hole (2) is the wedge shape that oral area is small, bottom is big;
Step 3: being uniformly provided with side hole (7) in the side wall of described hole (2) bottom, side hole (7) are multiple;
Step 4: in the inner wall surface dabbing of described hole (2);
Step 5: the inner wall surface in described hole (2) plants bar dowel (8);
Step 6: shear key (6) is inserted into side hole (7), one shear key (6) of insertion in each side hole (7), and cause anti- The end for cutting key (6) is exposed at side hole (7) outside;
Step 7: steel member (4) is inserted into described hole (2) bottom, and by steel member (4) lower end and the end of shear key (6) Portion welds together;
Step 8: pouring grouting material (3) into described hole (2), and conserve to required intensity;Described grouting material To mix the concrete of micro-expanding agent or back-grouting material.
A kind of 2. rear anchoring process of tension steel construction according to claim 1, it is characterised in that:Peg in step 1 (5) to be multiple.
A kind of 3. rear anchoring process of tension steel construction according to claim 1, it is characterised in that:Described in step 2 Hole (2) is more than 30 degree with horizontal plane angle;Hole-opening is using water drilling, pneumatic pick and/or by the way of manually holing.
A kind of 4. rear anchoring process of tension steel construction according to claim 1, it is characterised in that:Side hole is opened in step 3 By the way of using pneumatic pick or manually holing.
A kind of 5. rear anchoring process of tension steel construction according to claim 1, it is characterised in that:Wind is used in step 4 Pick or artificial mode dabbing.
A kind of 6. rear anchoring process of tension steel construction according to claim 1, it is characterised in that:Using change in step 5 Learn the mode bar planting of glue or cement mortar.
A kind of 7. rear anchoring process of tension steel construction according to claim 1, it is characterised in that:It is described in step 2 Hole and horizontal plane be non-perpendicular.
CN201510867260.3A 2015-12-01 2015-12-01 A kind of rear anchoring process of tension steel construction Active CN105507498B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510867260.3A CN105507498B (en) 2015-12-01 2015-12-01 A kind of rear anchoring process of tension steel construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510867260.3A CN105507498B (en) 2015-12-01 2015-12-01 A kind of rear anchoring process of tension steel construction

Publications (2)

Publication Number Publication Date
CN105507498A CN105507498A (en) 2016-04-20
CN105507498B true CN105507498B (en) 2017-11-28

Family

ID=55715771

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510867260.3A Active CN105507498B (en) 2015-12-01 2015-12-01 A kind of rear anchoring process of tension steel construction

Country Status (1)

Country Link
CN (1) CN105507498B (en)

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
BE663446A (en) * 1964-05-21
GB1216923A (en) * 1968-04-24 1970-12-23 Ccl Systems Ltd Improvements in or relating to anchorage assemblies for the prestressing of concrete structures
CN2455799Y (en) * 2000-12-28 2001-10-24 肖纹篯 Rear-installed wall anchor tightener
CN101525911B (en) * 2009-04-07 2011-04-27 同济大学 Sleeve dissipative element with shear key
CN103967289B (en) * 2014-04-23 2016-01-13 江苏建研建设工程质量安全鉴定有限公司 A kind ofly be applicable to the bar planting method and the bar planting structure that improve anchoring bearing capacity after plain concrete
CN203977892U (en) * 2014-06-26 2014-12-03 内蒙古电力勘测设计院有限责任公司 The casing reinforcement structure of power transformation steel pipe support
CN104929149A (en) * 2015-07-08 2015-09-23 黄冀卓 Stiffened embedded type column foot for reducing steel column embedment depth and construction technology thereof

Also Published As

Publication number Publication date
CN105507498A (en) 2016-04-20

Similar Documents

Publication Publication Date Title
US20050238441A1 (en) Novel surface structures and methods thereof
US6910832B2 (en) Surface structures and methods thereof
CN202925555U (en) Supporting and protecting structure for inclined struts of foundation pit
CN201512810U (en) Retaining wall
CN205188954U (en) Novel reinforced concrete prefabrication side stake pile extension structure
CN104594360A (en) Composite double-row pile foundation pit supporting structure
CN105507498B (en) A kind of rear anchoring process of tension steel construction
CN1332296A (en) Construction process of retaining wall with inner anchoring wall
CN108842790A (en) A kind of embankment side slope framework anchor holding frame lattice assembled retaining structure and construction method
CN205917713U (en) Truss -like steel pipe slip casting pile foundation
CN110453673B (en) Pier foundation reinforcement structure and method
CN105040855B (en) Prefabricated shear wall welded end plate and horizontal section steel combined connection apparatus
CN106480880B (en) Recoverable soil nailing and the construction method for using recoverable soil nail
CN218027637U (en) Self-anchoring structure of implanted steel pipe pile
CN205776152U (en) Prestressed anchor waveform sheet pile retaining structure
CN106087980B (en) reinforced concrete pile
CN109235431B (en) Moso bamboo anchor rod and construction method thereof
CN208121551U (en) A kind of assembled device of prefabricated pier shaft and prefabricated bent cap
CN108894235B (en) Frame anchor rod assembly type supporting structure without retaining plate and construction method
CN110185040B (en) Supporting waterproof structure of height-limited site and construction method thereof
CN205653896U (en) Light is built infilled wall post by laying bricks or stones and is joined steel sheet
CN109024973B (en) Connecting structure for prefabricated shear wall and construction method thereof
CN211621551U (en) Wedging type anti-pulling precast pile
CN218206712U (en) Prefabricated repair structure of repairing operation tunnel disease fast
CN215758995U (en) High-pressure jet grouting bottom-expanding prefabricated combined pile

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant