CN105507159B - A kind of temporary support device suitable for large-span prestressed bent cap system transform - Google Patents

A kind of temporary support device suitable for large-span prestressed bent cap system transform Download PDF

Info

Publication number
CN105507159B
CN105507159B CN201610083943.4A CN201610083943A CN105507159B CN 105507159 B CN105507159 B CN 105507159B CN 201610083943 A CN201610083943 A CN 201610083943A CN 105507159 B CN105507159 B CN 105507159B
Authority
CN
China
Prior art keywords
base
pin
bent cap
swivel base
prestressed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610083943.4A
Other languages
Chinese (zh)
Other versions
CN105507159A (en
Inventor
郭俊峰
刘勇
张文锋
王志强
石雯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Municipal Engineering Design and Research Institute Co Ltd
Original Assignee
Wuhan Municipal Engineering Design and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Municipal Engineering Design and Research Institute Co Ltd filed Critical Wuhan Municipal Engineering Design and Research Institute Co Ltd
Priority to CN201610083943.4A priority Critical patent/CN105507159B/en
Publication of CN105507159A publication Critical patent/CN105507159A/en
Application granted granted Critical
Publication of CN105507159B publication Critical patent/CN105507159B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/04Bearings; Hinges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

A kind of temporary support device suitable for large-span prestressed bent cap system transform of the present invention,Belong to science of bridge building field,The present invention includes top swivel base and bottom pin base,The top swivel base coordinates the top of the semiellipse cylinder pin for being placed on bottom pin base by the downward semi-circular turn trough of the centrally disposed notch of its swivel base,Constitute the rotatable one bearing in top,And semiellipse cylinder pin is fixed between Prestressed Slab Beams and performance of concrete column confined perpendicular to bent cap trend by the carrier setting bolt of the upper base plate and bottom pin base of top swivel base respectively,Bent cap can be along prestressed tensioning direction,Rotated relative to bottom pier stud by semiellipsoid pin of the semi-circular turn trough of top swivel base along bottom pin base,Solve the not revolvable problem of existing bearing,Ensure that the prestressed effective applying of bent cap,Greatly reduce loss of prestress,Make bent cap stress definitely,Improve large-span prestressed Coping Construction efficiency and security and stability.

Description

A kind of temporary support device suitable for large-span prestressed bent cap system transform
Technical field
A kind of temporary support device suitable for large-span prestressed bent cap system transform of the present invention, belongs to science of bridge building neck Domain.
Background technology
The queen post bent cap structure of prior art is because of its succinct moulding and maturation, easily construction technology is in highway And widely use in urban road bridges.Used as the important supporting member in bridge bottom, it subjects the perseverance of superstructure to bent cap Carry and girder passes to its mobile load effect, and these loads are passed to into bridge pier.But the structure for using at present is using lid The processing mode that beam is consolidated with bottom pier stud.When with the increase of the distance between twin columns, during using Prestressed Slab Beams, this process Mode unavoidably produces following detrimental effect:
(1) as bent cap is consolidated with pier stud, affected by pier stud, the loss of prestress of Prestressed Slab Beams span centre is larger, it is impossible to Play its due effect.
(2) as bent cap is consolidated with pier stud, prestressed stretch-draw can produce large effect to bottom pier stud, cause pier stud to cut Face increases, and causes the waste and moulding of material not good.
Particularly in urban elevated bridge construction, the overall Alignment Design of elevated bridge is all that global planning considers. Local special road section occurs limited condition unavoidably, such as considers to reduce earth clearance, the expense of underground utilities migration, while taking into account Existing road traffic function.For sections such as this intersections being limited in local condition, queen post bent cap structure design is proposed High requirement.Beyond pier stud must being placed on road width using large-span prestressed bent cap, span is even more than 30 meters, therefore by covering The adverse effect that beam and pier stud consolidation process mode are brought, it appears especially prominent, in addition have influence on Coping Construction safety and Stability.
Obviously, bent cap and pier stud consolidation structure in prior art, have not adapted to the requirement of urban elevated bridge construction, special It is not the requirement that can not meet large-span prestressed bent cap and pier stud connection construction, for this purpose, seeking to be applied to large span in construction The on-fixed temporary support device of Prestressed Slab Beams system transform becomes the weight of the traffic elevated bridge construction concern of Development of Urban Want problem.
The content of the invention
It is an object of the invention to provide a kind of temporary support device suitable for large-span prestressed bent cap system transform, leads to The temporary support device that on-fixed connection is set between top Prestressed Slab Beams and bottom performance of concrete column confined is crossed, and bent cap is made pre- Under the tensioning effect of stress, can rotate along prestressed tensioning direction, to solve, existing bearing is not revolvable important to ask Topic, it is ensured that the prestressed effective applying of bent cap, so as to improve the security and stability and efficiency of construction of large-span prestressed bent cap.
The purpose of the present invention is achieved by the following technical solution:It is of the invention a kind of suitable for large-span prestressed bent cap The temporary support device of system transform, including top swivel base and bottom pin base, the top swivel base is by upper base plate and swivel base Composition, swivel base center is provided with the downward semi-circular turn trough of notch;Bottom pin base is made up of semiellipsoid pin and lower seat board, Semiellipsoid pin is fixedly connected on the upper surface center of lower seat board, and lower seat board is equipped with carrier setting bolt, and top swivel base passes through which partly Round turn trough coordinates the top of the semiellipse cylinder pin for being placed on bottom pin base, constitutes the rotatable one in top Seat, and semiellipse cylinder pin is made perpendicular to lid by the carrier setting bolt of the upper base plate and bottom pin base of top swivel base respectively Beam trend is fixed between Prestressed Slab Beams and performance of concrete column confined.
The upper base plate of the top swivel base is poured and is mounted in pre-stressed concrete coping bottom surface.
The bottom of the carrier setting bolt installed in seat board under the bottom pin base pours and is fixed in performance of concrete column confined.
Semi-circular turn less than top swivel base of the top radius of curvature of the semiellipse cylinder pin of the bottom pin base The radius of groove, the radius of curvature of bottom are more than the radius of the semi-circular turn trough of top swivel base.
The carrier setting bolt installed in seat board under the bottom pin base carries reinforcement crotch.
The innovation of the present invention and obvious technical effects:
A kind of temporary support device suitable for large-span prestressed bent cap system transform of the present invention, by semiellipsoid pin Post is uniformly transmitted the performance of concrete column confined for giving bottom by the weight of bent cap, it is ensured that the contact with bottom pin of top swivel base Face, improves Bearing Seat Force approach, after the age of concrete of bent cap and concrete strength satisfaction requirement, starts tensioning bent cap pre- Stress, as swivel base is semicircle with the contact surface of pin, bent cap can be along prestressed tensioning direction, by top swivel base Semi-circular turn trough along bottom pin base semiellipsoid pin relative to bottom pier stud rotate, solving existing bearing can not The key problem of rotation, it is ensured that the prestressed effective applying of bent cap, greatly reduces loss of prestress, makes bent cap stress more Clearly, large-span prestressed bent cap security and stability and efficiency of construction are improved;Simultaneously as bent cap can revolve during prestressed stretch-draw Turn, the additional internal force produced by prestressed stretch-draw will not pass to bottom pier stud, so, it is not necessary to increase pier stud section chi It is very little, both favorably had and arranged in the space of pier stud, saved construction material again.Additionally, after the completion of temporary support mission of the present invention, only needing Cut off pre-buried carrier setting bolt, you can dismounting temporary support from bottom to top, then by concrete pier capital and Prestressed Slab Beams The corresponding reserved steel bar welding in bottom, and the concrete in this region of formwork erection cast in situs, complete system transform.Therefore, the present invention faces When stand apparatus innovative design, the construction of the large-span prestressed bent cap system to increasingly being lifted in urban elevated bridge construction Using its technique effect is particularly significant.
Description of the drawings
Fig. 1 is schematic front view of the present invention;
Fig. 2 is the turn trough schematic diagram of top swivel base of the present invention;
Fig. 3 is pin base schematic diagram in bottom of the present invention.
Specific embodiment
Further illustrate how the present invention is implemented in conjunction with accompanying drawing:
A kind of temporary support device suitable for large-span prestressed bent cap system transform of the present invention, including top swivel base and Bottom pin base, the top transposase 11 are made up of upper base plate 1-1 and transposase 11-2, and it is downward that-2 center of transposase 11 is provided with notch Semi-circular turn trough 1-3;Bottom pin base 2 is made up of semiellipsoid pin 2-1 and lower seat board 2-2, and semiellipsoid pin 2-1 is solid Surely the upper surface center of lower seat board 2-2 is connected to, lower seat board 2-2 is provided with carrier setting bolt 3, top transposase 11 by its bolt hole Coordinate the upper end of the semiellipse cylinder pin 2-1 for being placed on bottom pin base 2 by its semi-circular turn trough 1-3, in composition The rotatable one bearing in portion, and made by the carrier setting bolt 3 of the upper base plate 1-1 of top transposase 11 and bottom pin base 2 respectively Semiellipse cylinder pin 2-1 is fixed between Prestressed Slab Beams G and performance of concrete column confined D perpendicular to the trend of bent cap G, and bent cap can be with It is along prestressed tensioning direction, relative along the semiellipsoid pin of bottom pin base by the semi-circular turn trough of top swivel base Rotate in bottom pier stud, as shown in Figure 1.
The upper base plate 1-1 of the top transposase 11 is poured and is mounted in pre-stressed concrete coping bottom surface.
3 bottom of carrier setting bolt installed in seat board 2-2 under the bottom pin base 2 pours and is fixed in performance of concrete column confined It is interior.
Semicircle of the top radius of curvature of the semiellipse cylinder pin 2-1 of the bottom pin base 2 less than top transposase 11 The radius of type turn trough 1-3, radius of the bottom radius of curvature more than the semi-circular turn trough 1-3 of top transposase 11.
The carrier setting bolt 3 installed in seat board 2-2 under the bottom pin base 2 carries reinforcement crotch.
Application of the present invention in large-span prestressed Coping Construction:
When bottom performance of concrete column confined is poured, 3 lower end of carrier setting bolt with reinforcement crotch is embedded in into performance of concrete column confined In;After bottom performance of concrete column confined has been poured, carrier setting bolt 3 is just reliably fixed on the pier stud of bottom, then lower seat board 2-2 is led to Cross prepared screw-bolt hole to be fastenedly connected on carrier setting bolt 3;After the completion of fixing Deng seat board 2-2 under bottom pin base 2, by molten Weldering thoroughly is welded on semiellipse cylinder pin 2-1 on lower seat board 2-2;Then it is ellipse with half by the semi-circular turn trough 1-3 of transposase 11-2 Circle pin 2-1 coordinates, and transposase 11-2 is placed horizontally on pin 2-1, finally the upper of the top transposase 11 at bent cap bottom will be embedded in Seat board 1-1 is welded on the upper surface of transposase 11-2, keeps semiellipse cylinder pin 2-1 to be fixed in pre- answering perpendicular to the trend of bent cap G Between power bent cap G and performance of concrete column confined D, that is, complete to install.
After the completion of temporary support mission of the present invention, only pre-buried carrier setting bolt need to be cut off, you can dismounting from bottom to top is faced When bearing, then by the corresponding reserved steel bar welding of concrete pier capital and Prestressed Slab Beams bottom, and this area of formwork erection cast in situs The concrete in domain, completes system transform.

Claims (5)

1. a kind of temporary support device suitable for large-span prestressed bent cap system transform, it is characterised in that turn including top Seat and bottom pin base, the top swivel base is made up of upper base plate and swivel base, and swivel base center is provided with downward semi-circular of notch Turn trough;Bottom pin base is made up of semiellipsoid pin and lower seat board, and semiellipsoid pin is fixedly connected on the upper of lower seat board Centre of surface, lower seat board are equipped with carrier setting bolt, top swivel base coordinated by its semi-circular turn trough be placed on bottom pin base it The top of semiellipse cylinder pin, constitutes the rotatable one bearing in top, and respectively by the upper base plate of top swivel base with The carrier setting bolt of portion's pin base makes semiellipse cylinder pin be fixed in Prestressed Slab Beams and concrete pier perpendicular to bent cap trend Between post.
2. a kind of temporary support device suitable for large-span prestressed bent cap system transform according to claim 1, its It is characterised by, the upper base plate of top swivel base is poured and is mounted in pre-stressed concrete coping bottom surface.
3. a kind of temporary support device suitable for large-span prestressed bent cap system transform according to claim 1, its It is characterised by, the bottom of the carrier setting bolt installed in seat board under the pin base of bottom pours and is fixed in performance of concrete column confined.
4. a kind of temporary support device suitable for large-span prestressed bent cap system transform according to claim 1, its It is characterised by, the top radius of curvature of the semiellipse cylinder pin of bottom pin base is less than the semi-circular turn trough of top swivel base Radius, the radius of curvature of bottom are more than the radius of the semi-circular turn trough of top swivel base.
5. a kind of temporary support device suitable for large-span prestressed bent cap system transform according to claim 1, its It is characterised by, the carrier setting bolt installed in seat board under the pin base of bottom carries reinforcement crotch.
CN201610083943.4A 2016-02-06 2016-02-06 A kind of temporary support device suitable for large-span prestressed bent cap system transform Active CN105507159B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610083943.4A CN105507159B (en) 2016-02-06 2016-02-06 A kind of temporary support device suitable for large-span prestressed bent cap system transform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610083943.4A CN105507159B (en) 2016-02-06 2016-02-06 A kind of temporary support device suitable for large-span prestressed bent cap system transform

Publications (2)

Publication Number Publication Date
CN105507159A CN105507159A (en) 2016-04-20
CN105507159B true CN105507159B (en) 2017-03-29

Family

ID=55715437

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610083943.4A Active CN105507159B (en) 2016-02-06 2016-02-06 A kind of temporary support device suitable for large-span prestressed bent cap system transform

Country Status (1)

Country Link
CN (1) CN105507159B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105951585A (en) * 2016-06-20 2016-09-21 中山市公路钢结构制造有限公司 Support structure of integrated steel-framed bridge
CN111733714A (en) * 2020-06-01 2020-10-02 中铁第四勘察设计院集团有限公司 Beam column node structure of overhead station and interval bridge

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101613989A (en) * 2009-07-16 2009-12-30 南京工业大学 What be applied to assembling or prefabricated assembling beam bridge subtracts shock isolation method and structure
KR100948359B1 (en) * 2009-06-24 2010-03-22 우경건설 주식회사 The bridge upper structure lifting method for which bridge upper structure lifter which does the bridge shue function and this were used
CN102767134A (en) * 2012-07-24 2012-11-07 成都市新筑路桥机械股份有限公司 Large-angle assembly support
CN203065956U (en) * 2013-01-15 2013-07-17 广州市市政工程设计研究院 Transition structure between bent cap and pier stud
CN103205928A (en) * 2013-04-24 2013-07-17 张保忠 Anti-drawing curved surface rotatable support seat
CN204059207U (en) * 2014-09-23 2014-12-31 中国水利水电第四工程局有限公司 Bridge construction steel cylinder temporary support
CN205387670U (en) * 2016-02-06 2016-07-20 武汉市政工程设计研究院有限责任公司 Temporary support device suitable for conversion of large -span prestressing force bent cap system

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6572071B1 (en) * 2001-11-16 2003-06-03 Chung-Shien Tsai Shock eliminator

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100948359B1 (en) * 2009-06-24 2010-03-22 우경건설 주식회사 The bridge upper structure lifting method for which bridge upper structure lifter which does the bridge shue function and this were used
CN101613989A (en) * 2009-07-16 2009-12-30 南京工业大学 What be applied to assembling or prefabricated assembling beam bridge subtracts shock isolation method and structure
CN102767134A (en) * 2012-07-24 2012-11-07 成都市新筑路桥机械股份有限公司 Large-angle assembly support
CN203065956U (en) * 2013-01-15 2013-07-17 广州市市政工程设计研究院 Transition structure between bent cap and pier stud
CN103205928A (en) * 2013-04-24 2013-07-17 张保忠 Anti-drawing curved surface rotatable support seat
CN204059207U (en) * 2014-09-23 2014-12-31 中国水利水电第四工程局有限公司 Bridge construction steel cylinder temporary support
CN205387670U (en) * 2016-02-06 2016-07-20 武汉市政工程设计研究院有限责任公司 Temporary support device suitable for conversion of large -span prestressing force bent cap system

Also Published As

Publication number Publication date
CN105507159A (en) 2016-04-20

Similar Documents

Publication Publication Date Title
CN105908621A (en) Damage-controllable self-resetting section prefabricated assembled steel pipe concrete bridge pier and manufacturing method thereof
CN110387822B (en) Cast-in-situ bent cap assembly type steel pipe support and construction method thereof
CN108149585B (en) Splicing structure and splicing method for pier column sections of prefabricated spliced pier
CN103046476A (en) Railway long-span rotator T-shaped bridge construction method
CN113652966A (en) Construction method of full-prefabricated assembly type concrete beam type bridge structure system
CN105507159B (en) A kind of temporary support device suitable for large-span prestressed bent cap system transform
CN106012851A (en) Synchronous construction method of steel box girder and concrete pier studs
CN110004791A (en) A kind of prestressing without bondn assembled road and its construction method
CN106087711A (en) Antinode work beam-steel concrete top board-external prestressing combines T-shaped simply supported beam
CN107780337B (en) Cast-in-situ balance swivel door-shaped pier and construction method thereof
CN108374352A (en) A kind of the pier bottom rotation swivel construction method and system of wide-plate bridge pier
CN205387670U (en) Temporary support device suitable for conversion of large -span prestressing force bent cap system
CN208328660U (en) The U-shaped girder construction of the Two bors d's oeuveres of combined bridge
CN111335135A (en) Bridge device based on combination of concrete box girder and steel box girder and construction method
CN218596920U (en) Face empty assembled concrete bent cap cast-in-place construction support
CN203361027U (en) Bridge rotation construction spherical hinge capable of being used repeatedly
CN213682477U (en) Upper cover structure system applied to track operation line
CN104499436A (en) Anti-torque balancing pier for live load of swivel bridge
CN211571239U (en) Temporary covering structure for subway station construction
CN210621475U (en) Cast-in-situ bent cap assembled steel pipe support
CN107974930B (en) Segment-assembled balance swivel gate-shaped pier and construction method thereof
CN211735114U (en) A antidumping reinforced structure for rectangle single-column mound bridge
CN210482000U (en) Limiting device for jacking construction of large-span steel pipe concrete tied arch bridge
CN112095780A (en) Upper cover structure system applied to track operation line and implementation method thereof
CN106400646A (en) Temporary pavement splicing block and steel plate type box pavement

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant