- CN105481277B CN105481277B CN201610100615.0A CN201610100615A CN105481277B CN 105481277 B CN105481277 B CN 105481277B CN 201610100615 A CN201610100615 A CN 201610100615A CN 105481277 B CN105481277 B CN 105481277B
- Authority
- CN
- China
- Prior art keywords
- workshop
- enclosure wall
- roof
- gypsum
- pretreatment system
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- C—CHEMISTRY; METALLURGY
- C04—CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
- C04B—LIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
- C04B11/00—Calcium sulfate cements
- C04B11/26—Calcium sulfate cements strating from chemical gypsum; starting from phosphogypsum or from waste, e.g. purification products of smoke
Landscapes
- Chemical & Material Sciences (AREA)
- Engineering & Computer Science (AREA)
- Ceramic Engineering (AREA)
- Materials Engineering (AREA)
- Structural Engineering (AREA)
- Organic Chemistry (AREA)
- Building Environments (AREA)
- Curing Cements, Concrete, And Artificial Stone (AREA)
Abstract
A kind of workshop of the pretreatment system of industrial gypsum belongs to building field, including enclosure wall, roof, feed inlet, equipment installation and operating platform, load-carrying members, ground, door;The enclosure wall is arranged around workshop, is made of clear material, and has the blow vent that can be opened and closed on enclosure wall;The roof is arranged on the top of enclosure wall, is made of clear material;The feed inlet is arranged on enclosure wall, and positioned at equipment installation and operating platform top;The both ends middle and upper part inboard wall in workshop is arranged in the equipment installation and operating platform;The load-carrying members are nested among enclosure wall and roof;The ground is arranged in enclosure wall inner circumferential in the following, the door is arranged on enclosure wall;Has the function of the characteristics of capable of realizing that industrial gypsum is converted into the workshop of the pretreatment system of building gypsum, saving traditional energy.
Description
Technical field
The invention belongs to building field, more particularly to the one of a kind of processing method converting industrial gypsum to building gypsum
The workshop of the pretreatment system of kind industrial gypsum.
Background technology
Signified industrial gypsum in the present invention refers to ardealite mostly, and ardealite is a kind of phosphatic byproduct of production,
It is a kind of insoluble difficulty faced in detergents and cosmetic and related chemistry industrial production, each producer spends a large amount of
Place and expense cause seriously to pollute, annoying the production warp of relevant enterprise for storing and handling ardealite to surrounding enviroment
Battalion;The byproduct that raising with coal-burning boiler to emission request, wherein sulfur removal technology generate is also gypsum;Gypsum is in Building wood
Application on material is that the gypsum that will contain there are two the crystallization water is sintered into the gypsum containing half of crystallization water, referred to as half water stone mostly
Cream;In the calcination process of dihydrate gypsum, gypsum is heated to 1300C-2300C so that contain free moisture and crystallization in gypsum
Elutriation goes out, and becomes semi-hydrated gypsum, to be applied to building field;Currently, mostly using stove external heat greatly, control in-furnace temperature exists
1650C or so, after a period of time, making dihydrate gypsum become semi-hydrated gypsum, when temperature is more than 2300C will be converted to anhydrous stone
The advantages that cream, gypsum are a kind of building trade commonly construction materials, have setting rate fast, light-weight, and adhesive strength is high;Often
Be commonly used for construction material is semi-hydrated gypsum, due to being dihydrate gypsum and containing remaining phosphate ion mostly in ardealite,
Fluoride etc. can not be converted into the gypsum that can be used for construction material using conventional gypsum calcining and processing method.It is inciting somebody to action
When ardealite is converted into building gypsum, since ardealite contains acid phosphate anion, dinectly bruning can cause to convert
Building gypsum afterwards is in acid without influencing the use in architectural engineering;And ardealite contains a large amount of natural moisture,
During ardealite is converted into building gypsum, dinectly bruning can cause the conglomeration of ardealite, and the ardealite surface after conglomeration is forged
It can be converted after burning, and a large amount of ardealite will not be calcined therefore will not participate in conversion inside conglomeration, to reduce ardealite
The conversion ratio converted to building gypsum.
Invention content
It is converted into the existing above problem during industrial gypsum for existing ardealite, the present invention proposes a kind of work
The pretreatment system of industry gypsum, it is characterised in that:Including workshop, device, distribution device, conveying device, loading attachment are neutralized;Institute
The roof or roof of the workshop stated and enclosure wall are made of clear material;The device that neutralizes is mounted on the upper of workshop one end
Portion;It is hanging that the distribution device is mounted on workshop middle and upper part;The distribution device has multiple;The conveying device installation
On the ground of workshop, it is located at other than the cloth range of distribution device;The loading attachment is mounted on the ground of workshop, is located at defeated
The side of device is sent, and can be moved along conveying device side;The neutralization device, conveying device, loading attachment are automatic
Control operation.
In order to realize a kind of workshop function of the pretreatment system of industrial gypsum, the present invention proposes a kind of the pre- of industrial gypsum
The workshop of processing system, it is characterised in that:Including enclosure wall, roof, feed inlet, equipment installation and operating platform, load-carrying members, ground
Face, door;The enclosure wall is arranged around workshop, is made of clear material, and has the blow vent that can be opened and closed on enclosure wall;It is described
Roof be arranged on the top of enclosure wall, be made of clear material;The feed inlet is arranged on enclosure wall, and is installed positioned at equipment
And operating platform top;The both ends middle and upper part inboard wall in workshop is arranged in the equipment installation and operating platform;Described
Load-carrying members are nested among enclosure wall and roof, can support the gravity of enclosure wall and roof and affiliated facility, and resist outer come from
The strength of right wind etc.;The ground is arranged in enclosure wall inner circumferential in the following, the door is arranged on enclosure wall;There are one the doors
More than.
Advantageous effect
The beneficial effects of the present invention are can realize that industrial gypsum is converted into the workshop of the pretreatment system of building gypsum
Function saves traditional energy.
Description of the drawings
Fig. 1 is the structural schematic diagram of the present invention
1. workshop, in 2. and device, 3. distribution devices, 4. conveying devices, 5. loading attachments.
Fig. 2 is the section structure diagram of workshop
11. enclosure wall, 12. roofs, 13. feed inlets, the installation of 14. equipment and operating platform, 15. load-carrying members, 16. ground,
17..
Specific implementation mode
Technical solution in order to further illustrate the present invention, in conjunction with attached drawing, the specific implementation that further illustrates the present invention
Mode;Such as Fig. 1, Fig. 2 using the roof 12 and enclosure wall 11 of workshop 1 is transparent material in this example, steel construction frame is used in this example
Frame is as load-carrying members 15, and glazing makes roof 12 and enclosure wall 11 on it, and 11 top of enclosure wall opens up charging at one end
Mouth 13, at both ends, the top of enclosure wall 11 is located at 13 lower end of feed inlet setting, 120 millimeters of thickness, and the perforation of 2000 mm length of width is enclosed
The width of wall 11 is installed as equipment and operating platform 14;Be on the 13 same enclosure wall 11 of feed inlet, be located at equipment installation and
Operating platform 14 opens up door 17 below, and ground 16 is made using the general method of the industry;It is used as workshop 1 above;In this example
Steam-electric power plant is installed on the roof 12 of workshop 1, steam-electric power plant can also be installed on enclosure wall 11, in enclosure wall 11
It is provided with electric heater unit and ventilation device, solar energy can be made full use of to be utilized at night with the cloudy day in this way and set with that can generate electricity very much
Standby electric energy storage continues to keep the temperature in workshop 1 and ventilation;Top of the device 2 mounted on 1 one end of workshop will be neutralized;By cloth
It is hanging to expect that device 3 is mounted on 1 middle and upper part of workshop;In this example workshop horizontal cross-section is evenly arranged in using two distribution devices 3;It will
Conveying device 4 is mounted on the ground of workshop, is located at other than the cloth range of distribution device 3;Loading attachment 5 is mounted on workshop
Ground, using the industry is general or the automatic collection of grain reserves industry universal and rehandling facilities are as loading dress in this example
5 are set, two loading attachments 5 is selected in this example, it is located at the two sides of conveying device 4, can be moved along 4 side of conveying device
It is dynamic;This completes the implementations of the present invention;In application, this example using quick lime as in phosphate anion in industrial gypsum
With and dry alkaline matter, industrial gypsum and quick lime are entered from the top feed inlet 13 of 1 one end of workshop and neutralize device 2,
Device 2 is neutralized by quick lime and industrial gypsum adequately proportionally mix and stir, general industrial gypsum nature shape
The moisture content of industrial gypsum, by the mixing with quick lime, can be lowered 6% or so by moisture content mostly 25% or so under state;
Under the action of quick lime, internal acid ion neutralizes mixed industrial gypsum with quick lime, and acid ion is removed
Or most of removal, ensure that the residual of acid ion meets the standard criterion of building gypsum;By neutralizing 2 mixed work of device
Industry gypsum is sent to distribution device 3, and mixed industrial gypsum is dispersed in workshop 1 by distribution device 3 due to installing in the air
Ground 16;It is made since the roof 12 of workshop 1 and enclosure wall 11 use transparent material, sunlight can be irradiated to inside workshop 1 so that
Industrial gypsum temperature in workshop 1 increases, and accelerates the evaporation of contained humidity in industrial gypsum, saves a large amount of traditional energy,
Because existing industrial gypsum subtracts in low-moisture method, industrial gypsum per ton often reduces by 1% moisture, needs a large amount of standard coals;
Industrial gypsum after reducing moisture is collected and is loaded into conveying device 4 by loading attachment 5;Due in this example
Using the loading attachment 5 automatically controlled, reducing labor intensity realizes automation;It is neutralized and solar energy workshop by quick lime
1 effect, industrial gypsum are pretreated the industrial gypsum for being known as meeting gypsum calcining requirement, and being sent to calcining by conveying device 4 sets
It is standby to be calcined, it is therefore prevented that generate conglomeration since industrial gypsum moisture content is high and be unfavorable for the defect calcined and converted, improve
Industrial gypsum is converted into the conversion ratio of building gypsum.
Claims (4)
1. a kind of workshop of the pretreatment system of industrial gypsum is suitable for a kind of pretreatment system of industrial gypsum, the work
The pretreatment system of industry gypsum includes workshop, neutralizes device, distribution device, conveying device, loading attachment;The room of the workshop
Top or roof and enclosure wall are made of clear material;The top for neutralizing device and being mounted on workshop one end;The cloth
It is hanging that device is mounted on workshop middle and upper part;The distribution device has multiple;The conveying device is mounted on the ground of workshop,
Other than the cloth range of distribution device;The loading attachment is mounted on the ground of workshop, is located at the side of conveying device,
And it can be moved along conveying device side;The neutralization device, conveying device, loading attachment are auto-controll operations;Its
It is characterized in that:Including enclosure wall, roof, feed inlet, equipment installation and operating platform, load-carrying members, ground, door;The enclosure wall
It is arranged around workshop, is made of clear material, there is the blow vent that can be opened and closed on enclosure wall;The roof is arranged in enclosure wall
Top, be made of clear material;The feed inlet is arranged on enclosure wall, and positioned at equipment installation and operating platform top;
The both ends middle and upper part inboard wall in workshop is arranged in the equipment installation and operating platform;The load-carrying members, which are nested in, encloses
Among wall and roof, the gravity of enclosure wall and roof and affiliated facility can be supported, and resists the strength of external natural wind;Described
Ground is arranged in enclosure wall inner circumferential in the following, the door is arranged on enclosure wall;The door is there are one more than.
2. a kind of workshop of the pretreatment system of industrial gypsum according to claim 1, it is characterised in that:The roof of workshop
On steam-electric power plant is installed.
3. a kind of workshop of the pretreatment system of industrial gypsum according to claim 1, it is characterised in that:It is installed on enclosure wall
Steam-electric power plant.
4. a kind of workshop of the pretreatment system of industrial gypsum according to claim 1, it is characterised in that:Setting in enclosure wall
There are electric heater unit and ventilation device.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610100615.0A CN105481277B (en) | 2016-02-24 | 2016-02-24 | A kind of workshop of the pretreatment system of industrial gypsum |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610100615.0A CN105481277B (en) | 2016-02-24 | 2016-02-24 | A kind of workshop of the pretreatment system of industrial gypsum |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105481277A CN105481277A (en) | 2016-04-13 |
CN105481277B true CN105481277B (en) | 2018-07-27 |
Family
ID=55668606
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610100615.0A Active CN105481277B (en) | 2016-02-24 | 2016-02-24 | A kind of workshop of the pretreatment system of industrial gypsum |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105481277B (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107265894A (en) * | 2017-08-01 | 2017-10-20 | 郑州三迪建筑科技有限公司 | A kind of ardealite pretreatment system |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN204132069U (en) * | 2014-09-19 | 2015-02-04 | 淮安市恩赐山庄垂钓有限公司 | A kind of strawberry cultivating factory building |
CN204590695U (en) * | 2015-04-01 | 2015-08-26 | 徐州东大钢结构建筑有限公司 | Be convenient to the steel-structure factory building of daylighting |
CN105220910A (en) * | 2014-06-26 | 2016-01-06 | 江苏神东木屋发展股份有限公司 | A kind of wooden structures factory building and manufacture method thereof and application |
CN205000691U (en) * | 2015-10-10 | 2016-01-27 | 浙江丰扬钢结构有限公司 | Novel steel construction factory building that takes precautions against earthquakes |
CN205473401U (en) * | 2016-02-24 | 2016-08-17 | 郑州三迪建筑科技有限公司 | Pretreatment systems's of industry gypsum factory building |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104534823A (en) * | 2014-12-05 | 2015-04-22 | 安徽尧龙竹木制品有限公司 | Bamboo material drying room device |
-
2016
- 2016-02-24 CN CN201610100615.0A patent/CN105481277B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105220910A (en) * | 2014-06-26 | 2016-01-06 | 江苏神东木屋发展股份有限公司 | A kind of wooden structures factory building and manufacture method thereof and application |
CN204132069U (en) * | 2014-09-19 | 2015-02-04 | 淮安市恩赐山庄垂钓有限公司 | A kind of strawberry cultivating factory building |
CN204590695U (en) * | 2015-04-01 | 2015-08-26 | 徐州东大钢结构建筑有限公司 | Be convenient to the steel-structure factory building of daylighting |
CN205000691U (en) * | 2015-10-10 | 2016-01-27 | 浙江丰扬钢结构有限公司 | Novel steel construction factory building that takes precautions against earthquakes |
CN205473401U (en) * | 2016-02-24 | 2016-08-17 | 郑州三迪建筑科技有限公司 | Pretreatment systems's of industry gypsum factory building |
Also Published As
Publication number | Publication date |
---|---|
CN105481277A (en) | 2016-04-13 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105645796B (en) | A kind of pretreatment system of industrial gypsum | |
CN102503272A (en) | Continuous production method for foam concrete | |
CN105481277B (en) | A kind of workshop of the pretreatment system of industrial gypsum | |
CN103623806B (en) | SCR (Selective Catalytic Reduction) honeycombed denitration catalyst production technology | |
CN108298940A (en) | A kind of titanium extraction tailings decorative panel for building and its production method | |
CN105863317A (en) | Energy-saving environmentally-friendly type distribution room based on quick construction technique | |
CN205635382U (en) | Pretreatment systems of industry gypsum | |
CN205473401U (en) | Pretreatment systems's of industry gypsum factory building | |
CN105601139B (en) | A kind of neutralization device of the pretreatment system of industrial gypsum | |
CN107265894A (en) | A kind of ardealite pretreatment system | |
CN205528466U (en) | Pretreatment systems's of industry gypsum distributing device | |
CN205473402U (en) | Pretreatment systems's of industry gypsum loading attachment | |
CN205669279U (en) | There is the NEW TYPE OF COMPOSITE GRC curtain wall system of prefabricated partition board | |
CN205369639U (en) | Automatic daylight roof of rotation type | |
CN105481276B (en) | A kind of distribution device of the pretreatment system of industrial gypsum | |
CN105601138B (en) | A kind of loading attachment of the pretreatment system of industrial gypsum | |
CN206986042U (en) | A kind of ardealite pretreatment system | |
CN104180621A (en) | Basic zinc carbonate drying device | |
CN102121322A (en) | Kelp airing sunlight room | |
CN206576016U (en) | A kind of ecological pig house | |
CN210910526U (en) | A curing means for heat preservation type light weight wallboard | |
CN206354082U (en) | A kind of straw wall self-heat conserving greenhouse | |
CN219027901U (en) | Improved baking frame for cement foaming plate | |
CN110549479B (en) | Maintenance method of energy-saving environment-friendly heat-preservation light wallboard | |
CN109169309A (en) | A kind of pig farm ecologic breeding special environment protection fermentation bed |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |