CN105422144A - Waterproof material conveying mechanism for trolley - Google Patents

Waterproof material conveying mechanism for trolley Download PDF

Info

Publication number
CN105422144A
CN105422144A CN201510985928.4A CN201510985928A CN105422144A CN 105422144 A CN105422144 A CN 105422144A CN 201510985928 A CN201510985928 A CN 201510985928A CN 105422144 A CN105422144 A CN 105422144A
Authority
CN
China
Prior art keywords
waterproofing materials
reel
conveying mechanism
clamping plate
chassis
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510985928.4A
Other languages
Chinese (zh)
Other versions
CN105422144B (en
Inventor
杨明
曾朝明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Deyang Siyuan Heavy Industry Co Ltd
Original Assignee
Deyang Siyuan Heavy Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Deyang Siyuan Heavy Industry Co Ltd filed Critical Deyang Siyuan Heavy Industry Co Ltd
Priority to CN201510985928.4A priority Critical patent/CN105422144B/en
Publication of CN105422144A publication Critical patent/CN105422144A/en
Application granted granted Critical
Publication of CN105422144B publication Critical patent/CN105422144B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/40Devices or apparatus specially adapted for handling or placing units of linings or supporting units for tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Road Paving Structures (AREA)

Abstract

The invention discloses a waterproof material conveying mechanism for a trolley. The waterproof material conveying mechanism for the trolley comprises a support frame and a winding drum, wherein the support frame is arranged at the bottom of the trolley and is used for supporting waterproof materials; the winding drum is rotatably arranged on a walking trolley of the trolley and is used for winding the waterproof materials on the support frame. The waterproof material conveying mechanism for the trolley mainly solves the following technical problems: the waterproof materials can be rapidly wound on the walking trolley, so that the consumption of manpower and material resources is reduced; and the waterproof materials can be automatically unfolded to automatically form perpendicularity, so that the purpose of paving one coil of waterproof material for one time is achieved, and the construction efficiency is improved.

Description

For the waterproofing materials conveying mechanism of chassis
Technical field
The present invention relates to special mechanical equipment field, tunnel, relate in particular to a kind of waterproofing materials conveying mechanism for chassis.
Background technology
At present along with Chinese Railway, the communications such as highway keep developing fast, particularly at high-speed railway, the significant achievement that the constructing tunnel construction aspects such as highway obtain, facilitate the rapid raising of constructing tunnel design and processes technology, the scale of building of Tunnel Engineering of Mountainous Region structure is caused to be unprecedented, the trend of oriented the growing up development in tunnel, the people of changing over are often because circuit runs into mountain and just makes circuit show line get around, shorten length of tunnel as far as possible or do not repair the idea in tunnel, run into now the mountain ridge then take bent cut-off mode thus cause growing up of tunnel, this illustrates the development of tunnel construction technology and the advanced person of constructing tunnel equipment to a certain extent.
For this reason, the standard of building along with the communications such as railway, highway is also more and more stricter, and in the work progress in the communications such as railway, highway tunnel, waterproofing work is most important.At present, composite lining waterproof technique is widely applied in existing tunnel waterproofing engineering, its main construction course on the section in tunnel, successively lays the waterproofing materials such as geotextiles and splash guard at twice, to reach the object preventing the water in rock stratum to seepage in tunnel.In prior art, waterproofing materials laid by usual use chassis, the prior art being " 201410035985.1 " as China Patent No. discloses a kind of anchor bar of waterproof plate in tunnels laying chassis and laying method thereof on April 30th, 2014, its technical scheme is that described chassis comprises trolley running device, splash guard erecting device, lay stand, lay dolly, lay track, described trolley running device comprises motor, walking case, interior telescopic, walking guide rail, motor bolt is fixed on walking case upper surface, be connected with the transmission system in walking case, drive the transmission system in walking case, make it along the walking of walking guide rail, one end of interior telescopic is by pinned connection at walking case upper surface, and external surface and bolt are fixed on the external extension laid on stand and overlap and coordinate.But in actual application, this patent still also exists following defect: one, the waterproofing materials of drum is become first to adopt manual type to be transported to up and down on walking dolly, again by a large amount of manpower and materials and loader coordinating operation, waterproofing materials could be spread out laying and be attached to preliminary bracing surface, this a series of form of construction work is all difficult to meet the requirement of construction and accelerate the progress of construction, simultaneously because construction technology is loaded down with trivial details, in tunnel, construction environment is poor, temperature is higher, dust is larger, mechanization degree is low, increase the weight of the physical demands of operating personnel, increase labor intensity of operating staff, but also add construction coordination difficulty, constrain laying efficiency and the construction speed of waterproofing materials, construct under such circumstances and easily occur that waterproof material laying is of poor quality, welding quality cannot ensure, the probability that leaks increases, to there is weld length in the low and waterproofing materials of efficiency of construction inadequate in process of deployment, damaged, hang hidden danger of quality lack of standardization of Denging.Two, the type chassis is only applicable to the laying of 3 ~ 4m fabric width waterproofing materials at present mostly, be that mechanical assistance is manually launched, artificial jacking is in place, manually dilatoryly form sag, human factor is large on construction quality impact, be difficult to ensure to form sag requirement, do not solve splash guard sag formation process and splash guard jacking technique well, also without automatic control mode, limit promoting the use of of 6 ~ 7m fabric width waterproofing materials simultaneously.Three, the type chassis can only be used for laying waterproofing materials, can not be used for laying reinforcing bar, and need other professional equipment when laying reinforcing bar, its scope of application is poor.Four, the operation after chassis rising, without locking device, once meet accident, will cause severe safety accident.
Summary of the invention
The object of the invention is to solve the above-mentioned problems in the prior art, a kind of waterproofing materials conveying mechanism for chassis is provided, the present invention mainly solves following technical problem: one is to be wound up on walking dolly by waterproofing materials rapidly, decreases the use of manpower and materials; Two is can make waterproofing materials Automatic-expanding, automatically form sag, thus reaches the object that one-time laying completes a volume waterproofing materials, improves efficiency of construction.
For achieving the above object, the technical solution used in the present invention is as follows:
For a waterproofing materials conveying mechanism for chassis, it is characterized in that: comprise bracket and reel, described bracket is arranged on pallet bottom for supporting waterproofing materials, the waterproofing materials on the walking dolly that described spool turns is arranged on chassis on winding cradle.
Described conveying mechanism also comprises motor, and described motor is fixed on walking dolly, and described reel is arranged on walking dolly by electric machine rotation.
Described reel is provided with the holder of at least two groups for fixed clamp waterproofing materials, described holder comprises grip block, clamping plate and set bolt, described grip block is fixed on reel, the end of described clamping plate is movably connected on grip block, described set bolt is fixedly connected on grip block through after clamping plate, during work, set bolt and clip board engagement by waterproofing materials fixed clamp between reel and clamping plate.
Described reel offers mounting groove, and described grip block is fixed in mounting groove, and described grip block offers fixing threaded hole, and the middle part of described clamping plate offers through hole, and described set bolt is fixed in the fixing threaded hole of grip block through after the through hole on clamping plate.
Described clamping plate comprise the clamping face for plane and the non-clamping face for arcwall face, and the radius in this non-clamping face is identical with the radius of reel.
Described bracket comprises fixing bracket body, slip support body and multiple brace table, described fixing bracket body is fixed on pallet bottom, described slip support body is slidably connected on fixing bracket body, and described multiple brace tables are evenly fixed on slip support body, and described brace table is provided with arc groove.
Employing the invention has the advantages that:
One, in the present invention, the reel be arranged on walking dolly by bracket and rotation, can be wound up on walking dolly by waterproofing materials rapidly, not only reduce use and the hand labor intensity of manpower and materials, also help raising efficiency of construction.By coordinating of reel and walking dolly, waterproofing materials Automatic-expanding can be made, automatically form sag, thus reach the object that one-time laying completes a volume waterproofing materials, significantly improve efficiency of construction.Compared with prior art, after the present invention adopts the conveying mechanism of said structure, maximum can realize 6 ~ 7m fabric width waterproofing materials disposable winding, expansion and laying, it is higher to lay efficiency.
Two, in the present invention, the structure that reel is connected with motor, achieves the auto reeling of waterproofing materials, is not only conducive to improving efficiency of construction and reducing hand labor intensity, also helps the stability improving reel winding.
Three, in the present invention, fix waterproofing materials by least two group holders, ensure that the stability that waterproofing materials is fixing.And the structure that holder forms primarily of grip block, clamping plate and set bolt, then make reel have the advantage that structure is simple, fixed clamp speed is fast and fixed clamp is effective.
Four, in the present invention, the clamping face of clamping plate is set to plane, be conducive to the steadiness improving clamping, and the non-clamping face of clamping plate is set to the arcwall face identical with reel radius, the reel being provided with holder is then made still to belong to cylindrical structure in overall structure, so not only be conducive to fast winding, also can not cause damage to waterproofing materials.
Five, in the present invention, by coordinating of slip support body and fixing bracket body, can not only fast waterproofing materials be placed on the brace table of slip support body, can also the waterproofing materials placed be positioned, be conducive to carrying out fast of next rolling step.And by being arranged on the multiple brace tables on slip support body, then can prevent waterproofing materials sideslip when reel reels.
Accompanying drawing explanation
Fig. 1 is main TV structure schematic diagram of the present invention;
Fig. 2 is a kind of perspective view of the present invention;
Fig. 3 is another kind of structural representation of the present invention;
Fig. 4 is the structure for amplifying schematic diagram at I place in Fig. 3;
Fig. 5 is the structural representation of reel in the present invention;
Fig. 6 is A-A generalized section of Fig. 5;
Fig. 7 is the main TV structure schematic diagram of push rod in the present invention;
Fig. 8 is the backsight structural representation of push rod in the present invention;
Be labeled as in figure: 1, door frame, 2, walking dolly, 3, arc track, 4, reel, 5, grip block, 6, clamping plate, 7, set bolt, 8, clamping face, 9, non-clamping face, 10, fixing bracket body, 11, slip support body, 12, brace table, 13, push rod, 14, jacking cylinder, 15, vacuum cup, 16, limited impression, 17, crossover sub, 18, base, 19, guide pillar, 20, hoist cylinder, 21, locking cylinder, 22, locking pin, 23, waterproofing materials, 24, spring base.
Detailed description of the invention
Embodiment 1
A kind of waterproofing materials conveying mechanism for chassis, comprise bracket, reel 4 and motor, described bracket is arranged on pallet bottom for supporting waterproofing materials 23, described chassis is provided with two symmetrical walking dollies 2, the quantity of described motor is two, two motor symmetries are fixed on two walking dollies 2, and described reel 4 is arranged on the waterproofing materials 23 on two walking dollies 2 on winding cradle by two electric machine rotations.During winding waterproofing materials 23, the waterproofing materials 23 on two motor synchronous belt movable reel 4 auto reeling brackets.
In the present embodiment, described reel 4 is provided with the holder of at least two groups for fixed clamp waterproofing materials 23, described holder comprises grip block 5, clamping plate 6 and set bolt 7, and described grip block 5 is square block, and described clamping plate 6 comprise the clamping face 8 for plane and the non-clamping face 9 for arcwall face; The external surface of described reel 4 offers mounting groove, described grip block 5 is embedded in mounting groove by the mode be welded and fixed, the upper end of described clamping plate 6 is connected on grip block 5 by articulate, and described set bolt 7 is fixedly connected on grip block 5 through after clamping plate 6.Before winding waterproofing materials 23, need first the end winding support of waterproofing materials 23 to be clamped on reel 4, concrete fixed clamp step is: be first placed between clamping plate 6 and reel 4 by the end of waterproofing materials 23, then set bolt 7 is regulated to make clamping plate 6 with the junction of its upper end and grip block 5 for basic point moves to reel 4, until by waterproofing materials 23 held tight between reel 4 and the clamping face 8 of clamping plate 6.Wherein, because the clamping face 8 of clamping plate 6 is plane, in order to ensure the steadiness clamped, correspondingly, retaining part corresponding on reel 4 is also plane.In addition, due to reel 4 offering mounting groove, complete tubular construction can also be kept after holder has been installed to make reel 4, preferably the non-clamping face 9 of clamping plate 6 is set to its radius arcwall face identical with the radius of reel 4, the slot area face just filled up on reel 4 with this non-clamping face 9 is good.Like this, when clamping plate 6 are in clamped position, reel 4 keeps complete cylindrical structure in overall structure, is not only conducive to fast winding, also can not cause damage to waterproofing materials 23.
Further, described grip block 5 offers fixing threaded hole, the middle part of described clamping plate 6 offers through hole, described set bolt 7, through being fixed in the fixing threaded hole of grip block 5 after the through hole on clamping plate 6, namely can being realized the clamping of waterproofing materials 23 by the adjustment position of set bolt 7 in fixing threaded hole and be unclamped.Wherein, also saucer washer is provided with between the through hole of clamping plate 6 and set bolt 7.
Further, the quantity of described holder is five groups, and five groups of holders are evenly arranged on reel 4.
In the present embodiment, described bracket comprises fixing bracket body 10, slip support body 11 and multiple brace table 12, described fixing bracket body 10 comprises two spill guide rails and Duo Gen connector, and many connectors are fixedly connected on the bottom of chassis side by side, and two spill guide rail symmetries are fixed on many connectors.Described slip support body 11 comprises two parallel and slide rails be integrally fixed, and this slide rail is slidably arranged between two spill guide rails of fixing bracket body 10.Described multiple brace tables 12 are evenly fixed on two one slide rails of slip support body 11, and described brace table 12 is provided with arc groove.During work, waterproofing materials 23 is placed in arc groove.
In the present embodiment, described walking dolly 2 by electrical control electric machine rotation drive walking dolly 2 with the mode of sprocket wheel chain arcuately track 3 move, when arcuately track 3 moves walking dolly 2, the reversion of two Electric Machine Control reels 4 make waterproofing materials 23 arcuately track 3 launch.
Embodiment 2
A kind of chassis using above-mentioned waterproofing materials conveying mechanism, also comprise door frame 1, lifting body, mobile retaining mechanism and two walking dollies 2, described door frame 1 is provided with two symmetrical arc tracks 3, two walking dollies 2 are symmetricly set on arc track 3, and described conveying mechanism is arranged on the bottom of door frame 1; Described lifting body is many groups, and many group lifting bodies are fixed on door frame 1 for waterproofing materials 23 that jacking launches through walking dolly 2; Described mobile retaining mechanism be arranged on door frame 1 bottom for the moving horizontally of door frame 1, oscilaltion is moved and constructs time locking positioning.
In the present embodiment, described lifting body comprises push rod 13, jacking cylinder 14 and multiple vacuum cup 15, the quantity of described jacking cylinder 14 is two covers, two cover jacking cylinder 14 symmetries are fixed on door frame 1, described push rod 13 is square structure, its two ends are fixedly connected with two piston rods overlapping jacking cylinder 14 respectively, and described multiple vacuum cups 15 are evenly fixed on push rod 13 for adsorbing waterproofing materials 23.Further, described door frame 1 is also provided with vacuum adsorption machine, described vacuum adsorption machine is connected with the multiple vacuum cups 15 on push rod 13.During work, walking dolly 2 launches waterproofing materials 23 by reel 4, and often through one group of lifting body, waterproofing materials 23 is adsorbed onto on push rod 13 by the vacuum cup 15 that vacuum adsorption machine controls on this group lifting body, prevents waterproofing materials 23 landing.
Further, in order to prevent by waterproofing materials 23 when vacuum cup 15 the lose absorption affinity landing of jacking to tunnel inner wall, described push rod 13 is also evenly provided with multiple spring base 24, described spring base 24 is positioned on the same face of push rod 13 with vacuum cup 15, and the height of spring base 24 is higher than the height of vacuum cup 15.Like this, when vacuum cup 15 loses absorption affinity, spring base 24 is taken over vacuum cup 15 and automatically waterproofing materials 23 jacking is supported on tunnel inner wall.
In the present embodiment, described push rod 13 also evenly offers multiple limited impression 16 for limit steel bar, described limited impression 16 is positioned at the another side corresponding with vacuum cup 15.This structure makes push rod 13 can either be used for jacking waterproofing materials 23, can be used in jacking rod again, concrete jacking process is: after having laid waterproofing materials 23, control push rod 13 to overturn, again reinforcing bar is placed in the limited impression 16 on multiple push rod 13, prevent slip of bar, then get final product jacking rod by jacking cylinder 14.
Further, the piston rod of described jacking cylinder 14 is fixedly connected with crossover sub 17, the two ends of described push rod 13 are connected with two crossover subs 17 respectively by bearing, and push rod 13 and crossover sub 17 are provided with jack, and push rod 13 and crossover sub 17 are fixed by latch and jack.When reality uses, only need get by inserting the quick upset that latch can realize push rod 13.And then reach the rapid translating of jacking waterproofing materials 23 and reinforcing bar.
In the present embodiment, the quantity of described lifting body is five groups, five groups of lifting bodies are arranged on door frame 1 by 45 degree in the angle increased progressively, and concrete arrangement is: first group of lifting body and the 5th group of lifting body lateral symmetry layout respectively, and both jacking directions are contrary; 3rd group of lifting body is longitudinally arranged, the jacking direction of its jacking direction and first group of lifting body is perpendicular; Second group of lifting body is arranged in the middle of first group of lifting body and the 3rd group of lifting body, and the jacking direction of the jacking direction of its jacking direction and first group of lifting body and the 3rd group of lifting body in angle of 45 degrees; 4th group of lifting body is arranged in the middle of the 5th group of lifting body and the 3rd group of lifting body, and the jacking direction of the jacking direction of its jacking direction and the 5th group of lifting body and the 3rd group of lifting body in angle of 45 degrees.When jacking, five magnetic lifting body synchronizations of jacking up, with this makes it possible to accurate stable by waterproofing materials 23 and bar one-time jacking to assigned address.
In the present embodiment, described mobile retaining mechanism comprises base 18, guide pillar 19, hoist cylinder 20 and locking cylinder 21, the quantity of described base 18 is two covers, two cover bases 18 are symmetricly set on door frame 1 bottom, be connected with road wheel below described base 18, moving horizontally of whole chassis can be controlled by control lines travelling wheel.The quantity of described guide pillar 19 is four, and four guide pillars 19 are symmetricly set on two cover bases 18 respectively, and one end of described guide pillar 19 is fixed on base 18, and the other end is movably set in the guide pin bushing of door frame 1, and guide pillar 19 and guide pin bushing all offer locating hole.The quantity of described hoist cylinder 20 and locking cylinder 21 is four covers, and both are all fixed on door frame 1 bottom, and wherein, the piston rod of four cover hoist cylinders 20 is separately fixed on two cover bases 18, for controlling the oscilaltion of whole chassis; Four cover locking oil cylinders 21 are then fixed on the bottom of door frame 1, the piston rod of four cover locking oil cylinders 21 is all fixedly connected with locking pin 22, four locking pins 22 are symmetricly set on the locating hole place of four guide pillars 19, when needs locking door frame 1, four cover locking oil cylinder 21 Synchronization Control, four locking pins 22 insert the locating hole on guide pin bushing and the locating hole on guide pillar 19.By coordinating of locking cylinder 21 and locking pin 22, door frame 1 can be automatically locked when door frame 1 is elevated to and specifies construction location, prevent security incident, significantly improve working security.
In the present invention, described door frame 1 is also provided with platform and cat ladder, the construction up and down of convenient construction personnel.
In the present invention, the construction method comprising the chassis of above-mentioned conveying mechanism, lifting body and mobile retaining mechanism comprises the construction method of waterproofing materials 23 and the construction method of reinforcing bar, is respectively:
The construction method of waterproofing materials 23: preparation, the waterproofing materials 23 of rolling to be placed on brace table 12 and to be resetted by slip support body 11 by artificial pull-out slip support body 11, manual operation is clamped to the end winding support of waterproofing materials 23 on reel 4 by holder, rotated forward by motor and control reel 4 and to reel waterproofing materials 23, the rear control walking dolly 2 that reeled moves, and control motor reversal simultaneously, now reel 4 along with walking dolly 2 movement arcuately track 3 launch waterproofing materials 23, when the waterproofing materials 23 launched is after first group of lifting body, on the push rod 13 that startup vacuum adsorption machine makes vacuum cup 15 be adsorbed on by the waterproofing materials 23 of process on this first group of lifting body, by that analogy, until waterproofing materials 23 launches completely and is adsorbed on the push rod 13 of five groups of lifting bodies, then the waterproofing materials 23 of the clamping that is fixed is unclamped by set bolt 7 and clamping plate 6, again by base 18, hoist cylinder 20 adjusts horizontal level and the height of door frame 1, after having adjusted, by locking cylinder 21 locking pin 22 inserted in the locating hole on guide pillar 19 and guide pin bushing and whole door frame 1 is locked, after having locked, start jacking cylinder 14 synchronization of jacking up waterproofing materials 23 to the tunnel contour place in five groups of lifting bodies, then control vacuum adsorption machine to quit work, now vacuum cup 15 pairs of waterproofing materialss 23 lose absorption affinity, waterproofing materials 23 continues to be supported on tunnel inner wall under the effect of spring base 24, the platform of constructor on door frame 1 uses the welding gun of portable supersonic bonding machine, preparation waterproofing materials 23 is welded with the position that ultrasonic bonding pad overlaps, after having welded, jacking cylinder 14 and locking cylinder 21 are all reset to original position, wait for and constructing next time.
The construction method of reinforcing bar: preparation, control push rod 13 by latch to overturn, one side push rod 13 being provided with limited impression 16 is made to become work plane, then reinforcing bar to be placed in the push rod 13 in five groups of lifting bodies in limited impression 16 by the spacing of design code, after reinforcing bar has been placed, artificial assembling reinforcement, after colligation completes, again by base 18, hoist cylinder 20 adjusts horizontal level and the height of door frame 1, after having adjusted, by locking cylinder 21 locking pin 22 inserted in the locating hole on guide pillar 19 and guide pin bushing and whole door frame 1 is locked, after having locked, the jacking cylinder 14 synchronization of jacking up reinforcing bar started in five groups of lifting bodies is constructed to tunnel contour place, after having constructed, jacking cylinder 14 and locking cylinder 21 are all reset to original position, wait for and constructing next time.
The present invention is by the cooperation of door frame 1, conveying mechanism, lifting body, mobile retaining mechanism and two walking dollies 2, achieve the auto reeling of waterproofing materials 23, Automatic-expanding, automatic lifting, automatically regulate the function such as paving location, automatic stand, have and lay the higher and intelligence degree more advantages of higher of efficiency.

Claims (6)

1. the waterproofing materials conveying mechanism for chassis, it is characterized in that: comprise bracket and reel (4), described bracket is arranged on pallet bottom for supporting waterproofing materials (23), described reel (4) rotate be arranged on chassis walking dolly (2) on waterproofing materials (23) on winding cradle.
2., as claimed in claim 1 for the waterproofing materials conveying mechanism of chassis, it is characterized in that: described conveying mechanism also comprises motor, described motor is fixed on walking dolly (2), and described reel (4) is arranged on walking dolly (2) by electric machine rotation.
3. as claimed in claim 1 or 2 for the waterproofing materials conveying mechanism of chassis, it is characterized in that: described reel (4) is provided with the holder of at least two groups for fixed clamp waterproofing materials (23), described holder comprises grip block (5), clamping plate (6) and set bolt (7), described grip block (5) is fixed on reel (4), the end of described clamping plate (6) is movably connected on grip block (5), described set bolt (7) is through being fixedly connected on grip block (5) after clamping plate (6), during work, set bolt (7) coordinates waterproofing materials (23) fixed clamp between reel (4) and clamping plate (6) with clamping plate (6).
4. as claimed in claim 3 for the waterproofing materials conveying mechanism of chassis, it is characterized in that: (4) offer mounting groove with described reel, described grip block (5) is fixed in mounting groove, (5) offer fixing threaded hole to described grip block, the middle part of described clamping plate (6) offers through hole, and described set bolt (7) is fixed in the fixing threaded hole of grip block (5) through after the through hole on clamping plate (6).
5. as claimed in claim 3 for the waterproofing materials conveying mechanism of chassis, it is characterized in that: described clamping plate (6) comprise the clamping face (8) for plane and the non-clamping face (9) for arcwall face, and the radius in this non-clamping face (9) is identical with the radius of reel (4).
6. as claimed in claim 1 for the waterproofing materials conveying mechanism of chassis, it is characterized in that: described bracket comprises fixing bracket body (10), slip support body (11) and multiple brace table (12), described fixing bracket body (10) is fixed on pallet bottom, described slip support body (11) is slidably connected on fixing bracket body (10), described multiple brace tables (12) are evenly fixed on slip support body (11), and (12) are provided with arc groove to described brace table.
CN201510985928.4A 2015-12-25 2015-12-25 Waterproof material conveying mechanism for chassis Active CN105422144B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510985928.4A CN105422144B (en) 2015-12-25 2015-12-25 Waterproof material conveying mechanism for chassis

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510985928.4A CN105422144B (en) 2015-12-25 2015-12-25 Waterproof material conveying mechanism for chassis

Publications (2)

Publication Number Publication Date
CN105422144A true CN105422144A (en) 2016-03-23
CN105422144B CN105422144B (en) 2018-01-19

Family

ID=55500637

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510985928.4A Active CN105422144B (en) 2015-12-25 2015-12-25 Waterproof material conveying mechanism for chassis

Country Status (1)

Country Link
CN (1) CN105422144B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108716413A (en) * 2018-08-30 2018-10-30 中铁局集团有限公司 A kind of waterproof cloth is laid with and the construction method of lining cutting bar-mat reinforcement binding
CN108843353A (en) * 2018-07-18 2018-11-20 湖南进军隧道智能装备有限公司 A kind of excavation stand translation installing mechanism
CN110171108A (en) * 2019-06-25 2019-08-27 易伟青 A kind of injection mold

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1312041A1 (en) * 1985-12-24 1987-05-23 Центральное проектно-конструкторское бюро кузнечно-прессового машиностроения Drum for winding long material
JPH08170498A (en) * 1994-12-19 1996-07-02 Fujimori Kogyo Kk Waterproof sheet stretching device
CN102226402A (en) * 2011-04-08 2011-10-26 中铁三局集团有限公司 Auxiliary device and method used for laying tunnel waterproofing plates
CN103899337A (en) * 2014-04-09 2014-07-02 邓卫东 Wide tunnel waterproof board installation platform and installation method
CN105084127A (en) * 2015-08-27 2015-11-25 重庆雨帝建材有限公司 Waterproof roll lining
CN205243539U (en) * 2015-12-25 2016-05-18 德阳思远重工有限公司 A waterproof material conveying mechanism for platform truck

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1312041A1 (en) * 1985-12-24 1987-05-23 Центральное проектно-конструкторское бюро кузнечно-прессового машиностроения Drum for winding long material
JPH08170498A (en) * 1994-12-19 1996-07-02 Fujimori Kogyo Kk Waterproof sheet stretching device
CN102226402A (en) * 2011-04-08 2011-10-26 中铁三局集团有限公司 Auxiliary device and method used for laying tunnel waterproofing plates
CN103899337A (en) * 2014-04-09 2014-07-02 邓卫东 Wide tunnel waterproof board installation platform and installation method
CN105084127A (en) * 2015-08-27 2015-11-25 重庆雨帝建材有限公司 Waterproof roll lining
CN205243539U (en) * 2015-12-25 2016-05-18 德阳思远重工有限公司 A waterproof material conveying mechanism for platform truck

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108843353A (en) * 2018-07-18 2018-11-20 湖南进军隧道智能装备有限公司 A kind of excavation stand translation installing mechanism
CN108843353B (en) * 2018-07-18 2023-08-15 湖南进军隧道智能装备有限公司 Excavation grudging post translation installation mechanism
CN108716413A (en) * 2018-08-30 2018-10-30 中铁局集团有限公司 A kind of waterproof cloth is laid with and the construction method of lining cutting bar-mat reinforcement binding
CN110171108A (en) * 2019-06-25 2019-08-27 易伟青 A kind of injection mold
CN110171108B (en) * 2019-06-25 2021-06-25 佛山市力晟塑胶制品有限公司 Injection mold

Also Published As

Publication number Publication date
CN105422144B (en) 2018-01-19

Similar Documents

Publication Publication Date Title
CN105422143A (en) Intelligent trolley for tunnel construction
CN109236302B (en) Variable section excavation trolley in tunnel
CN105443148A (en) Jacking mechanism and trolley using same
CN205078283U (en) Tunnel geotechnique's cloth, waterproof board shop cloth machine
CN105736016A (en) Tunnel secondary lining steel bar framework construction equipment and application thereof
CN105422144A (en) Waterproof material conveying mechanism for trolley
CN111733948B (en) Pipeline laying device and construction method thereof
CN205243538U (en) Tunnel construction intelligence platform truck
CN112096281B (en) Drilling, pile splicing and pile planting all-in-one machine and construction method thereof
CN105298209A (en) Installing device for telegraph pole
WO2020155104A1 (en) Anchoring device and working method thereof
CN205243535U (en) A remove locking mechanism for platform truck
CN112610242A (en) Integrative platform truck of cloth is hung to big section reinforcing bar of railway tunnel
CN205277453U (en) Climbing mechanism and use this climbing mechanism's platform truck
CN202148920U (en) Conveying mechanism for tunnel construction
CN102359383A (en) Waterproof cloth laying trolley
CN205243539U (en) A waterproof material conveying mechanism for platform truck
JP4143442B2 (en) PC floor slab erection device and PC floor slab erection method using the device
CN202391434U (en) Water-proof cloth laying trolley
CN110700107A (en) Sliding type construction method for hoisting prefabricated anti-collision wall
CN216342142U (en) Pushing structure
CN111594076B (en) Nearly horizontal auger stem machine drill pipe sleeve installation device
CN211691358U (en) Constructional engineering steel construction support frame
CN209369833U (en) A kind of moveable tunneltron canopy operation platform
JP2023008536A (en) Mounting device for construction of tunnel and construction method using the same

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant