CN105422104A - 立井井筒加固维护方法 - Google Patents

立井井筒加固维护方法 Download PDF

Info

Publication number
CN105422104A
CN105422104A CN201510945194.7A CN201510945194A CN105422104A CN 105422104 A CN105422104 A CN 105422104A CN 201510945194 A CN201510945194 A CN 201510945194A CN 105422104 A CN105422104 A CN 105422104A
Authority
CN
China
Prior art keywords
stage
slurry hole
concrete
bolt
collapsing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510945194.7A
Other languages
English (en)
Other versions
CN105422104B (zh
Inventor
任世杰
王权仕
李庆汝
刘春龙
赵海荣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Datong Coal Mine Group Co Ltd
Original Assignee
Datong Coal Mine Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Datong Coal Mine Group Co Ltd filed Critical Datong Coal Mine Group Co Ltd
Priority to CN201510945194.7A priority Critical patent/CN105422104B/zh
Publication of CN105422104A publication Critical patent/CN105422104A/zh
Application granted granted Critical
Publication of CN105422104B publication Critical patent/CN105422104B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D5/00Lining shafts; Linings therefor
    • E21D5/04Lining shafts; Linings therefor with brick, concrete, stone, or similar building materials
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D5/00Lining shafts; Linings therefor
    • E21D5/12Accessories for making shaft linings, e.g. suspended cradles, shutterings
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D7/00Shaft equipment, e.g. timbering within the shaft

Abstract

本发明涉及立井井筒的维护方法,具体为立井井筒加固维护方法。立井井筒加固维护方法,包括施工平台搭建阶段、工程盒板固定阶段、混凝土浇灌阶段和防护罩构筑阶段,施工平台搭建阶段革新了罐笼并安装了防护栏,工程盒板固定阶段是在井筒崩浆坑凹处利用锚栓固定工程盒板;混凝土浇灌阶段即在各个崩浆坑凹处进行混凝土浇灌;防护罩构筑阶段是在崩浆坑凹外部形成保护罩,防止崩浆坑凹处凝固体坠落。立井井筒维护通过采取在井壁打预埋锚栓支盒板并在浇灌后构筑砼保护罩,浇灌后的砼墙体并未因气温降低而冷缩坠落,同时将井筒内风化的部分全部加固后,再无崩落的浆块,不会对乘罐人员构成安全隐患。

Description

立井井筒加固维护方法
技术领域
本发明涉及立井井筒的维护方法,具体为立井井筒加固维护方法。
背景技术
立井是煤矿的主提升井,一直担负着矿井进风及提升人与物料的任务。立井受季节干湿交替、温度冷热变化的影响,且在高风速的作用下,井壁混凝土砼墙体严重风化,出现崩浆、墙体脱落等现象。井壁墙体脱落、特别是在罐道牛腿部的墙体脱落后,不仅会伤害乘罐人员,而且还会影响罐笼的运行稳定,因此必须对立井井筒进行加固维护。为保证立井的提升安全,需对井筒墙体脱落区域用混凝土砼进行浇灌,防止其继续风化脱落。因立井一般为圆形井筒,在施工过程中面临以下问题:1)施工危险系数高:立井井壁从上到下多处脱落,加固工作为高空作业,工作平台仅在罐笼及其延伸平台处,空间狭小;2)施工难度大:在竖直的井壁作业,受重力作用影响,支盒板、浇灌作业难度非常大;3)施工环境差:立井加固有时在冬季,井筒内温度约在-5℃~2℃,风速约5.3m/s,通迅又不畅(对讲机),施工环境很差。在保证安全的前提下,如何高效、高质地完成立井井筒的加固工程,是亟待解决的问题。
发明内容
本发明为了解决能在保证安全的前提下,高效、高质地完成立井井筒加固的问题,提供了立井井筒加固维护方法。
本发明是采用如下的技术方案实现的:立井井筒加固维护方法,包括施工平台搭建阶段、工程盒板固定阶段、混凝土浇灌阶段和防护罩构筑阶段,
施工平台搭建阶段包括以下步骤:
在槽钢上依次打三组调节孔位,然后将槽钢通过螺丝杆与罐笼铁道连接,形成龙骨;
防护栏的底槽角钢分别扣在对应槽钢上,角钢和槽钢之间通过螺丝固定;
将木板平铺在龙骨上,并夹在角钢和槽钢之间,再用螺丝固定;
工程盒板固定阶段包括以下步骤:
在井筒崩浆坑凹处左、右两边各施工2列预埋锚栓,锚栓排距为0.3m、列距为30mm、锚栓杆外漏长度为20mm;
再在井筒崩浆坑凹处下部施工2排预埋锚栓,锚栓排距为30mm、列距为0.3m、锚栓杆外漏长度为20mm,则崩浆坑凹处的预埋锚栓轮廓为凹形,且预埋锚栓距崩浆坑凹外边不小于0.2m;
然后再在预埋锚栓轮廓内插入工程盒板;
混凝土浇灌阶段即在各个崩浆坑凹处进行混凝土浇灌;
防护罩构筑阶段包括以下步骤:
等崩浆坑凹处浇铸的混凝土凝固、工程盒板拆除后,在距离崩浆坑凹上边和下边0.15m处各施工2~3个锚栓;再用螺栓将宽40mm、厚4mm的扁铁上下、左右、交叉固定,在崩浆坑凹外部形成保护罩,防止崩浆坑凹处凝固体坠落。
浇灌混凝土必须先固定工程盒板,但立井井壁无支撑点,无法固定。为固定盒板,先在崩浆坑凹处左、右两边各施工2列预埋锚栓,再在坑凹处下部施工2排预埋锚栓,锚栓轮廓为凹形,然后将2m长、20cm宽、2cm厚的木板切割成长20cm、30cm、50cm、100cm等多种长度的盒板,根据需浇灌部位的弧度及形状拼接盒板,以保证加固效果;另外为防止因气温低水结冰冷缩,浇灌的混凝土与井壁脱落,伤到乘罐人员,在崩浆坑凹处凝固体外部形成保护罩,防止其坠落;浇铸时,人员需借助平台才能施工,为保证施工安全,本发明革新了施工平台并安装了防护栏,施工时根据现场情况的需要,利用槽钢上的调节孔位,调整伸缩平台长度,保证纵向延升距离,满足施工空间,保证施工安全。
立井井筒维护通过采取在井壁打预埋锚栓支盒板并在浇灌后构筑砼保护罩,浇灌后的砼墙体并未因气温降低而冷缩坠落,同时将井筒内风化的部分全部加固后,再无崩落的浆块,不会对乘罐人员构成安全隐患,本发明提供的立井井筒加固维护方法在今后加固井筒墙体有很好借鉴意义,应大力推广。
附图说明
图1为施工平台的结构示意图。
图2为保护罩的结构示意图。
图中:1-罐笼,2-槽钢,3-防护栏,4-罐笼铁道,5-扁铁。
具体实施方式
立井井筒加固维护方法,包括施工平台搭建阶段、工程盒板固定阶段、混凝土浇灌阶段和防护罩构筑阶段,
施工平台搭建阶段包括以下步骤:
选用四根槽钢2并在各个槽钢2上依次打三组调节孔位,然后将槽钢2分别通过螺丝杆与罐笼铁道4连接,形成龙骨;
选用四个防护栏4,并将各个防护栏4的底槽角钢分别扣在对应槽钢2上,角钢和槽钢2之间通过螺丝固定;
木板平铺在龙骨上,并夹在角钢和槽钢2之间,再用螺丝固定;
工程盒板固定阶段包括以下步骤:
在井筒崩浆坑凹处左、右两边各施工2列预埋锚栓,锚栓排距为0.3m、列距为30mm、锚栓杆外漏长度为20mm;
再在井筒崩浆坑凹处下部施工2排预埋锚栓,锚栓排距为30mm、列距为0.3m、锚栓杆外漏长度为20mm,则崩浆坑凹处的预埋锚栓轮廓为凹形,且预埋锚栓距崩浆坑凹外边不小于0.2m;
然后再在预埋锚栓轮廓内插入工程盒板;
混凝土浇灌阶段即在各个崩浆坑凹处进行混凝土浇灌;
防护罩构筑阶段包括以下步骤:
等崩浆坑凹处浇铸的混凝土凝固、工程盒板拆除后,在距离崩浆坑凹上边和下边0.15m处各施工2~3个锚栓;再用螺栓将宽40mm、厚4mm的扁铁5上下、左右、交叉固定,在崩浆坑凹外部形成保护罩,防止崩浆坑凹处凝固体坠落。

Claims (1)

1.立井井筒加固维护方法,其特征在于包括施工平台搭建阶段、工程盒板固定阶段、混凝土浇灌阶段和防护罩构筑阶段,
施工平台搭建阶段包括以下步骤:
在槽钢上依次打三组调节孔位,然后将槽钢(2)通过螺丝杆与罐笼铁道(4)连接,形成龙骨;
防护栏(3)的底槽角钢分别扣在对应槽钢上,角钢和槽钢(2)之间通过螺丝固定;
将木板平铺在龙骨上,并夹在角钢和槽钢(2)之间,再用螺丝固定;
工程盒板固定阶段包括以下步骤:
在井筒崩浆坑凹处左、右两边各施工2列预埋锚栓,锚栓排距为0.3m、列距为30mm、锚栓杆外漏长度为20mm;
再在井筒崩浆坑凹处下部施工2排预埋锚栓,锚栓排距为30mm、列距为0.3m、锚栓杆外漏长度为20mm,则崩浆坑凹处的预埋锚栓轮廓为凹形,且预埋锚栓距崩浆坑凹外边不小于0.2m;
然后再在预埋锚栓轮廓内插入工程盒板;
混凝土浇灌阶段即在各个崩浆坑凹处进行混凝土浇灌;
防护罩构筑阶段包括以下步骤:
等崩浆坑凹处浇铸的混凝土凝固、工程盒板拆除后,在距离崩浆坑凹上边和下边0.15m处各施工2~3个锚栓;再用螺栓将宽40mm、厚4mm的扁铁(5)上下、左右、交叉固定,在崩浆坑凹外部形成保护罩,防止崩浆坑凹处凝固体坠落。
CN201510945194.7A 2015-12-17 2015-12-17 立井井筒加固维护方法 Active CN105422104B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510945194.7A CN105422104B (zh) 2015-12-17 2015-12-17 立井井筒加固维护方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510945194.7A CN105422104B (zh) 2015-12-17 2015-12-17 立井井筒加固维护方法

Publications (2)

Publication Number Publication Date
CN105422104A true CN105422104A (zh) 2016-03-23
CN105422104B CN105422104B (zh) 2018-02-23

Family

ID=55500599

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510945194.7A Active CN105422104B (zh) 2015-12-17 2015-12-17 立井井筒加固维护方法

Country Status (1)

Country Link
CN (1) CN105422104B (zh)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06129189A (ja) * 1991-10-09 1994-05-10 Shimizu Corp セグメントを利用した立坑構築工法
CN101117888A (zh) * 2007-09-19 2008-02-06 北京科技大学 一种地下矿山主溜井的加固方法
CN101397909A (zh) * 2008-09-17 2009-04-01 中冶集团武勘岩土基础工程公司 坍塌超深竖井人工掘进修复新工法
CN103215922A (zh) * 2013-04-09 2013-07-24 长江勘测规划设计研究有限责任公司 高压力大流量集中渗漏灌浆堵漏方法
CN104533424A (zh) * 2014-11-17 2015-04-22 大同煤矿集团有限责任公司 冻结立井井筒裂纹加固方法
CN104533485A (zh) * 2015-01-21 2015-04-22 中煤第三建设(集团)有限责任公司 立井井筒井壁内锚杆快速安装方法
CN104612695A (zh) * 2015-01-29 2015-05-13 湖南科技大学 一种剧烈垮塌立井井壁修复加固方法
CN104912569A (zh) * 2015-06-05 2015-09-16 中国安全生产科学研究院 一种溜井治理的方法

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06129189A (ja) * 1991-10-09 1994-05-10 Shimizu Corp セグメントを利用した立坑構築工法
CN101117888A (zh) * 2007-09-19 2008-02-06 北京科技大学 一种地下矿山主溜井的加固方法
CN101397909A (zh) * 2008-09-17 2009-04-01 中冶集团武勘岩土基础工程公司 坍塌超深竖井人工掘进修复新工法
CN103215922A (zh) * 2013-04-09 2013-07-24 长江勘测规划设计研究有限责任公司 高压力大流量集中渗漏灌浆堵漏方法
CN104533424A (zh) * 2014-11-17 2015-04-22 大同煤矿集团有限责任公司 冻结立井井筒裂纹加固方法
CN104533485A (zh) * 2015-01-21 2015-04-22 中煤第三建设(集团)有限责任公司 立井井筒井壁内锚杆快速安装方法
CN104612695A (zh) * 2015-01-29 2015-05-13 湖南科技大学 一种剧烈垮塌立井井壁修复加固方法
CN104912569A (zh) * 2015-06-05 2015-09-16 中国安全生产科学研究院 一种溜井治理的方法

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
刘志海等: "《利用井筒罐笼修复立井井筒》", 《煤矿现代化》 *

Also Published As

Publication number Publication date
CN105422104B (zh) 2018-02-23

Similar Documents

Publication Publication Date Title
CN109403374A (zh) 用于明挖隧道整体式衬砌的工厂化施工方法
CN105370304B (zh) 高应力强扰动煤层沿空留巷多级加固方法
CN201250407Y (zh) 嵌入式型钢腰梁
CN202596743U (zh) 地下隧道无拉杆侧墙施工用模板台车
CN103352471B (zh) 集装箱式活动房装配式型钢混凝土单双柱基础及施工方法
CN103939114A (zh) 一种悬轨式台车衬砌施工方法
CN100516378C (zh) 采用横隔式预应力混凝土管桩对建筑基坑进行支护的方法
CN207829006U (zh) 定型可移动挡土墙模架
CN103174293A (zh) 空心楼板自稳式内模安装方法
CN114164764B (zh) 一种高填方桥梁承台结构施工方法
CN103343547B (zh) 集装箱式活动房装配式型钢混凝土四柱基础及施工方法
CN107663863B (zh) 一种多年冻土区桩基础及其施工工艺
CN102286932A (zh) 移动模架桥台后方拼装自行上桥施工方法
CN102767378B (zh) 排架施工隧道双柱式洞门方法
CN106567405A (zh) 一种地下厂房岩壁吊车梁超挖补强结构及其施工方法
CN105422104A (zh) 立井井筒加固维护方法
CN102605988B (zh) 烟囱内衬外砼同步施工方法
CN207943803U (zh) 高架桥下地下连续墙钢筋笼起吊装置
CN203498850U (zh) 超高层建筑筏板基础钢筋支架
CN102561551A (zh) 一种厚墙及其施工方法
CN203049588U (zh) 坑中坑筒模
CN212866952U (zh) 一种低层楼面混凝土浇筑用防护装置
CN211851153U (zh) 一种组合钢柱式gps观测墩
CN209670395U (zh) 一种适用于施工升降机地下室顶板的加固结构
CN209243590U (zh) 多底模头罩支撑架造槽机

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Ren Shijie

Inventor after: Fu Maoquan

Inventor after: Wang Quanshi

Inventor after: Li Qingru

Inventor after: Zhou Zhichao

Inventor after: Liu Chunlong

Inventor after: Zuo Xinmei

Inventor after: Zhao Hairong

Inventor before: Ren Shijie

Inventor before: Wang Quanshi

Inventor before: Li Qingru

Inventor before: Liu Chunlong

Inventor before: Zhao Hairong

GR01 Patent grant
GR01 Patent grant