CN105406603B - A kind of power grid regulation end anti-incorrect manipulation deadlock method - Google Patents

A kind of power grid regulation end anti-incorrect manipulation deadlock method Download PDF

Info

Publication number
CN105406603B
CN105406603B CN201511030344.8A CN201511030344A CN105406603B CN 105406603 B CN105406603 B CN 105406603B CN 201511030344 A CN201511030344 A CN 201511030344A CN 105406603 B CN105406603 B CN 105406603B
Authority
CN
China
Prior art keywords
telecommand
equipment
error
transformer station
unlocked
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201511030344.8A
Other languages
Chinese (zh)
Other versions
CN105406603A (en
Inventor
施正钗
韩峰
陈坚
周毅
吴利锋
臧怡宁
邱承杰
俞凯
徐伟敏
陆千毅
郑微
高强
叶展
陈晨
张雯燕
叶超
袁金腾
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Zhejiang Electric Power Co Ltd
Wenzhou Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Zhejiang Electric Power Co Ltd
Wenzhou Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Zhejiang Electric Power Co Ltd, Wenzhou Power Supply Co of State Grid Zhejiang Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201511030344.8A priority Critical patent/CN105406603B/en
Publication of CN105406603A publication Critical patent/CN105406603A/en
Application granted granted Critical
Publication of CN105406603B publication Critical patent/CN105406603B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • H02J13/0006
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E60/00Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/16Electric power substations

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)
  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)

Abstract

The embodiment of the invention discloses a kind of power grid regulation end anti-incorrect manipulation deadlock method, including:The whole network locking is carried out to the administrative equipment of Centralized Monitoring;Remote measurement and remote signalling data of the transformer station of collection power network to regulation and control end in real time;The working condition of transformer station is judged according to remote measurement and remote signalling data;According to the telecommand at regulation and control end and the working condition of transformer station, the corresponding administration equipment in the whole network locking is unlocked;Judge whether the unblock to corresponding administration equipment succeeds;If unlocking successfully, anti-error checking is carried out to telecommand, judges whether telecommand meets default anti-error verification condition;If meeting default anti-error verification condition, telecommand is performed.Only unlocked successfully in equipment, and to telecommand it is anti-error be verified after could perform telecommand, equipment corresponding to control works, and realizes power grid regulation end to unattended transformer substation switch remote operation and comprehensive anti-incorrect manipulation deadlock, improves substation safety supportability.

Description

A kind of power grid regulation end anti-incorrect manipulation deadlock method
Technical field
The present invention relates to field of power electronics, more particularly to a kind of power grid regulation end anti-incorrect manipulation deadlock method.
Background technology
With the development of science and technology, power industry is gradually made the transition towards the direction of intelligentized control method, to realize electricity Intelligent monitoring, management control and security protection of net etc..
At present, China is promoting electricity grid substation to switch normalization remote operation, realizes regulation and control center to unattended Centralized Monitoring transformer substation switch remote operation normalization, this just needs to set misoperation-proof locking device in transformer substation end.It is existing Misoperation-proof locking device include misoperation-proof locking device for transformer substation and scheduling full mesh topology error-proof device, wherein, power transformation Misoperation-proof locking device of standing plays anti-misoperation locking effect just for monotropic power station execute-in-place, and live breaker operator is not risen Anti-misoperation locking acts on, and can only play suggesting effect, line segregation does not associate offside substation equipment, and offside state can not correspond to Anti-misoperation locking is acted on, and these can only be checked on by dispatching responsible correctness;Scheduling full mesh topology error-proof device is mainly used in tune Spend anti-error effect of making out an invoice, it is impossible to applied to regulation and control remote operation.Under normal circumstances, the administrative equipment of Centralized Monitoring (is set except idle It is standby outer) it is in the whole network locking, operation is remotely controlled to equipment just to be needed to carry out multi-section operation, however, above-mentioned anti-error behaviour Anti-incorrect manipulation deadlock can only be carried out when monotropic power station execute-in-place or scheduling are made out an invoice by making blocking device, can not realize whole remote control Comprehensive anti-incorrect manipulation deadlock of flow.
Thus, comprehensive anti-incorrect manipulation deadlock when power grid regulation end is remotely controlled equipment how is realized, is art technology The current technical issues that need to address of personnel.
The content of the invention
It is an object of the invention to provide a kind of power grid regulation end anti-incorrect manipulation deadlock method, it is possible to achieve power grid regulation end is entered Comprehensive anti-incorrect manipulation deadlock during row remote control equipment.
In order to solve the above technical problems, the invention provides following technical scheme:
A kind of power grid regulation end anti-incorrect manipulation deadlock method, including:
The whole network locking is carried out to the administrative equipment of Centralized Monitoring;
Remote measurement and remote signalling data of the transformer station of collection power network to regulation and control end in real time;
The working condition of the transformer station is judged according to the remote measurement and remote signalling data;
According to the telecommand at regulation and control end and the working condition of the transformer station, to the respective tube in the whole network locking Linchpin equipment is unlocked;
Judge whether the unblock to the corresponding administration equipment succeeds;
If to the corresponding unblock success for administering equipment, anti-error checking is carried out to the telecommand, described in judgement Whether telecommand meets default anti-error verification condition;
If the telecommand meets default anti-error verification condition, the telecommand is performed.
Preferably, the working condition according to the telecommand and the transformer station that regulate and control end, to being closed in the whole network Corresponding administration equipment in lock be unlocked including:
The telecommand at the regulation and control end is received, locked mode is solved according to corresponding to the selection of the working condition of the transformer station Formula, the corresponding administration equipment being in the whole network locking is unlocked, wherein, the latching mode includes:
Program operation mode, under being in normal operating conditions in the transformer station, operation order is issued, and according to operation Single equipment corresponding to ticket unblock;
Accident treatment pattern, under being in accident condition in the transformer station, by whole station accident resultant signal, interval accident Resultant signal, all kinds of protection automatic safety devices action outlet information and section institute residing for switch changed position information unblock accident transformer station The remote control for having equipment is weighed;
Provisional application pattern, for when interim exception or defect occur for the power network, unlocking and setting in preset time period It is standby.
Preferably, the telecommand at the regulation and control end is received, is selected according to the working condition of the transformer station corresponding Latching mode, the corresponding administration equipment being in the whole network locking is unlocked including:
After the telecommand at the regulation and control end is received, judge whether possess operation order;
If possessing operation order, the corresponding administration equipment being in the whole network locking is unlocked;
If not possessing operation order, trouble-signal is judged whether;
If trouble-signal be present, the corresponding administration equipment being in the whole network locking is unlocked;
If trouble-signal is not present, judge whether to unlock temporarily;
If interim unblock, the corresponding administration equipment being in the whole network locking is unlocked;
If do not unlock temporarily, forbid being unlocked the corresponding administration equipment in the whole network locking.
Preferably, in the latching mode according to corresponding to the selection of the working condition of the transformer station, closed to described in the whole network Corresponding administration equipment in lock also includes after being unlocked:
After the unblock of select planning operator scheme, when in the state change of the equipment of unblock after, preset time period prolongs When after or in the case that single equipment does not perform according to corresponding to unlocking operation order, locked remote control operating rights again;
After selection accident treatment pattern unblock, confirmed after the completion of accident treatment, and recover straighforward operation power Locking;
After selection provisional application pattern unblock, after the completion of unlocker device or after the delay of preset time period again Locked remote control operating rights.
Preferably, it is described that anti-error checking is carried out to the telecommand, it is default to judge whether the telecommand meets Anti-error verification condition includes:
To the telecommand carry out validating topology, judge the telecommand whether meet predetermined registration operation condition and Whether dead electricity will not be caused;
If the telecommand does not meet the condition of predetermined registration operation and/or can cause dead electricity, alarm is carried out;
If the telecommand meets the condition of predetermined registration operation and will not cause dead electricity, tide is carried out to the telecommand Flow verification, whether power network is safe after judging remote control;
If power network is dangerous after remote control, alarm is carried out;
If power grid security after remote control, performs the telecommand.
Preferably, also include after judging that the telecommand meets default anti-error verification condition:
The telecommand is resolved into corresponding remote control preliminary command;
Anti-error return to school is carried out to the remote control preliminary command.
Preferably, it is described that anti-error return to school of the remote control preliminary command progress is also included:
Judge whether the telecommand meets the secondary anti-mis-logical of the anti-error logical sum of default sign board, wherein, it is described The anti-mis-logical of sign board includes the anti-mis-logical of maintenance board, the anti-mis-logical of isolation board, the anti-mis-logical of guarantor's electricity board, described secondary anti-error to patrol Collecting, which includes the anti-error logical sum route protection throwing of the anti-mis-logical of air pressure, circuit breaking, moves back anti-mis-logical.
Preferably, carrying out anti-error return to school to the remote control preliminary command also includes:
Mutual exclusion locking is carried out to the reactive apparatus in the administrative equipment of Centralized Monitoring.
Compared with prior art, above-mentioned technical proposal has advantages below:
A kind of power grid regulation end anti-incorrect manipulation deadlock method that the embodiment of the present invention is provided, including:To Centralized Monitoring Administrative equipment carries out the whole network locking;Remote measurement and remote signalling data of the transformer station of collection power network to regulation and control end in real time;According to described distant Survey the working condition that the transformer station is judged with remote signalling data;According to the work of the telecommand at regulation and control end and the transformer station State, the corresponding administration equipment in the whole network locking is unlocked;Judge whether is unblock to the corresponding administration equipment Success;If to the corresponding unblock success for administering equipment, anti-error checking is carried out to the telecommand, judges the remote control Whether instruction meets default anti-error verification condition;If the telecommand meets default anti-error verification condition, institute is performed State telecommand.Existing remote measurement, the remote signalling data at regulation and control end are collected using transformer station, establishes remote measurement and remote signalling data change With the association of telecommand, telecommand is carried out according to actual conditions it is anti-error, in addition, telecommand is to remote control equipment, then Need by the equipment of locking be unlocked with anti-error checking, only unlocked successfully in equipment, and to the anti-error checking of telecommand By that could perform telecommand afterwards, equipment corresponding to control works, and realizes power grid regulation end to unattended power transformation Stand and switch remote operation, while realize comprehensive anti-incorrect manipulation deadlock when being remotely controlled equipment, improve the unmanned value of transformer station It is horizontal to keep power grid security supportability and electric service under pattern.
Brief description of the drawings
In order to illustrate more clearly about the embodiment of the present invention or technical scheme of the prior art, below will be to embodiment or existing There is the required accompanying drawing used in technology description to be briefly described, it should be apparent that, drawings in the following description are the present invention Some embodiments, for those of ordinary skill in the art, on the premise of not paying creative work, can also basis These accompanying drawings obtain other accompanying drawings.
The power grid regulation end anti-incorrect manipulation deadlock method flow diagram that Fig. 1 is provided for a kind of embodiment of the present invention;
To place in the power grid regulation end anti-incorrect manipulation deadlock method that Fig. 2 is provided for another embodiment of the present invention The method flow diagram that corresponding administration equipment in the whole network locking is unlocked;
To distant in the power grid regulation end anti-incorrect manipulation deadlock method that Fig. 3 is provided for another embodiment of the invention Control instruction carries out the method flow diagram of anti-error checking.
Embodiment
The core of the present invention is to provide a kind of power grid regulation end anti-incorrect manipulation deadlock method, can realize power grid regulation end pair Unattended transformer substation switch remote operation and comprehensive anti-incorrect manipulation deadlock when being remotely controlled equipment, improve transformer station without Power grid security supportability and electric service are horizontal under people's pattern on duty.
In order that the above objects, features and advantages of the present invention can become apparent it is understandable, below in conjunction with the accompanying drawings to this hair Bright embodiment is described in detail.
Detail is elaborated in the following description in order to fully understand the present invention.But the present invention can with it is a variety of not Other manner described here is same as to implement, those skilled in the art can do class in the case of without prejudice to intension of the present invention Like popularization.Therefore the present invention is not limited by following public embodiment.
It refer to Fig. 1, the power grid regulation end anti-incorrect manipulation deadlock side that Fig. 1 is provided for a kind of embodiment of the present invention Method flow chart.
In a kind of embodiment of the present invention, there is provided a kind of power grid regulation end anti-incorrect manipulation deadlock method, bag Include:
S11:The whole network locking is carried out to the administrative equipment of Centralized Monitoring.
In order to prevent from end anti-misoperation, administrative equipment the whole network locking.Wherein, so-called the whole network locking refers to locking Straighforward operation is weighed, that is, forbids the direct controlling equipment work of the telecommand for regulating and controlling end.So-called regulation and control end anti-misoperation refers to Prevent from causing major accident because regulating and controlling personnel distant place maloperation scene high voltage electric equipment, cause casualties and damaged with equipment It is bad, large-area power-cuts, cause power network unstable, cause serious economic loss, generally take technological means to prevent maloperation, it is right In high voltage electric equipment, to prevent from dividing, closing breaker by mistake;On-load point, close disconnecting switch;Band cable address (conjunction) ground wire (ground connection Switch);Band ground wire power transmission;Mistakenly entering charged chamber etc., generally take some blocking devices be installed in regulation and control end monitoring system or To realize anti-error function on high voltage electric equipment.In addition, in the present embodiment, the whole network is carried out to the administrative equipment of Centralized Monitoring and closed Lock is mainly for active equipment.
S12:Remote measurement and remote signalling data of the transformer station of collection power network to regulation and control end in real time.
Existing remote measurement and the remote signalling data at regulation and control end are collected using transformer station, is compiled according to anti-incorrect manipulation deadlock logic Journey, associating for remote measurement and remote signalling data change and remote operation instruction is established, to regulate and control personnel's remote operation and remotely judging, keep away Exempt from maloperation and data support is provided so that regulation and control personnel and anti-misoperation system judge this according to the virtual condition of live transformer station When telecommand it is whether suitable.
S13:The working condition of transformer station is judged according to remote measurement and remote signalling data.
The working condition of transformer station generally includes normal operating conditions, accident condition and interim exception or defect, according to distant Survey and remote signalling data can judge the instantaneous operating conditions of transformer station.
S14:According to the telecommand at regulation and control end and the working condition of transformer station, to the respective tube in the whole network locking Linchpin equipment is unlocked.
In the present embodiment, because transformer station is likely to be at different working conditions according to actual conditions, therefore, in reality In the operation of border, the equipment for wanting remote control is solved using corresponding latching mode according to the actual working condition of transformer station Lock.
Wherein, after the telecommand at regulation and control end is received, locked mode is solved according to corresponding to the selection of the working condition of transformer station Formula, the corresponding administration equipment in the whole network locking is unlocked, latching mode includes:Program operation mode, for becoming Power station is under normal operating conditions, issues operation order, and the single equipment according to corresponding to unlocking operation order;Accident treatment mould Formula, under being in accident condition in transformer station, by whole station accident resultant signal, interval accident resultant signal, all kinds of protections safety certainly The remote control power of section all devices residing for dynamic device action outlet information and switch changed position information unblock accident transformer station;Interim Shen Please pattern, for when interim exception or defect occur for power network, by interim single equipment unlocking function in preset time period Unlocker device in unlocker device, i.e. short time.
S15:Judge whether the unblock to corresponding administration equipment succeeds.
S16:If to the corresponding unblock success for administering equipment, anti-error checking is carried out to telecommand, judges telecommand Whether default anti-error verification condition is met.Failure is remotely controlled if unsuccessful.
S17:If telecommand meets default anti-error verification condition, telecommand is performed.Otherwise, remote control failure.
When telecommand has passed through anti-error verification condition, it is not maloperation to judge the telecommand, now, live power transformation Station equipment performs telecommand, realizes remote control manipulator's transformer substation switch remote operation unattended to scene.
In the present embodiment, if regulation and control personnel are wanted remotely by telecommand remote control equipment, need locking Equipment be unlocked with anti-error checking, only unlocked successfully in equipment, and to telecommand it is anti-error be verified after ability Telecommand is performed, equipment corresponding to control works, and realizes power grid regulation end and a unattended transformer substation switch distant place is grasped Make, while realize comprehensive anti-incorrect manipulation deadlock when being remotely controlled equipment, improve power network under the unattended pattern of transformer station Safety assurance ability and electric service are horizontal.
It refer to Fig. 2, the power grid regulation end anti-incorrect manipulation deadlock that Fig. 2 is provided for another embodiment of the present invention The flow chart being unlocked in method to the corresponding administration equipment in the whole network locking.
On the basis of above-mentioned embodiment, in one embodiment of the present invention, the telecommand at regulation and control end is received, according to Latching mode corresponding to the working condition selection of transformer station, bag is unlocked to the corresponding administration equipment in the whole network locking Include:
S21:Receive the telecommand at regulation and control end.
S22:Judge whether possess operation order.
So-called operation order is the written foundation that electric operation is carried out in power system, including dispatch command ticket and power transformation Operation order, its role is to prevent maloperation.To be operated in normal electric operation in strict accordance with operation order.
In the present embodiment, dispatching terminal is provided with anti-error system, and it possesses policer operation ticket function, possesses intelligence and intends ticket work( Can, including figure intends ticket function and dispatch command intends ticket function automatically.Monitor can quickly generate monitoring by graphical interfaces Operational order ticket, can also power network operation order corresponding to manual edit.It is specific as follows:
1. manual bill
The mode of manual bill is provided, regulation and control personnel can directly intend the editing area at ticket interface by input through keyboard, The mode that phrase is drawn a bill, typical ticket is drawn a bill is completed to instruct the formulation of ticket.
2. single step figure intends ticket function
By selection operation task type on the equipment pel of primary connection figure, operation task is drafted;Possess increase, insert Enter, move up, lower shifting function, in that context it may be convenient to carrying out step adjustment.
3. comprehensive state intends ticket function
The method of operation of single transformer station is changed, or situations such as each side state change of uniline, typical case can be passed through Ticket and using current power system operating mode as condition carry out intelligent inference, ultimately form operation task and each operating procedure.
4. dispatch command intends ticket function automatically
The association between dispatch command and policer operation ticket is realized, policer operation ticket is automatically generated by dispatch command, is monitored Member need to only be audited.
5. call history ticket function
Operating personnel can recall the operation order performed in the past, carry out appropriate modification, be formed currently available Operation order.
6. human-edited's function
To some special non routine operations, user can be with power network operation order corresponding to manual edit.Meanwhile system will be right The operation order of user's hand-coding carries out intelligently parsing and carries out security constraint analysis.
7. concrete operations and the technology correlation function of transfer order
No matter regulating and controlling the operation of center plan remote control using operation order as foundation, must realize that the technology of operation and transfer order is closed Connection.Beyond opereating specification, system can provide prompting and quiescing, prevent from not operating by transfer order.
If so, then perform step S23:Corresponding administration equipment in the whole network locking is unlocked.
When substation equipment is under normal operating conditions, policer operation ticket can be realized effectively is to telecommand The no judgement that can correctly unlock, to determine whether to be unlocked using program operation mode.
S24:If not possessing operation order, trouble-signal is judged whether.
If operation order is not present, it is probably that equipment is in accident condition, now, judges whether trouble-signal, with Determine a need for being unlocked using accident treatment pattern.
If trouble-signal be present, step S23 is performed, the corresponding administration equipment in the whole network locking is unlocked. It is unlocked using accident treatment pattern.
S25:If trouble-signal is not present, judge whether to unlock temporarily.
When being not received by trouble-signal again without operation order, judge whether to need to be solved using provisional application pattern Lock.
If interim unblock, performs step S23:Corresponding administration equipment in the whole network locking is unlocked.Adopt It is unlocked with provisional application pattern.
S26:If do not unlock temporarily, forbid being unlocked the corresponding administration equipment in the whole network locking.
In the present embodiment, telecommand is judged successively, judges whether the telecommand meets transformer station The processing mode of actual working state, if meeting, it is unlocked according to actual conditions.
In the present embodiment, latching mode corresponding to being selected according to the working condition of transformer station, to being closed in the whole network Corresponding administration equipment in lock also includes after being unlocked:
After the unblock of select planning operator scheme, when in the state change of the equipment of unblock after, preset time period prolongs When after or in the case that single equipment does not perform according to corresponding to unlocking operation order, locked remote control operating rights again;
After selection accident treatment pattern unblock, confirmed after the completion of accident treatment, and recover straighforward operation power Locking;
After selection provisional application pattern unblock, after the completion of unlocker device or after the delay of preset time period again Locked remote control operating rights.
It should be noted that in order to ensure safety operation in case of emergency, unblock in emergency circumstances is additionally provided with, i.e., Support in emergency circumstances, by rights management, to realize that single station, multistation always unlock operation in anti-error system.
In order to ensure each telecommand is all verified, to ensure the security of electric operation, each telecommand After the completion of being unlocked corresponding device by checking, all need to recover the locking of straighforward operation power again, to prevent at one After telecommand unblock corresponding device, the not unlocked checking of latter bar telecommand is controlled to the equipment, to be prevented Maloperation.
It refer to Fig. 3, the power grid regulation end anti-incorrect manipulation deadlock that Fig. 3 is provided for another embodiment of the invention The method flow diagram of anti-error checking is carried out in method to telecommand.
On the basis of any of the above-described embodiment, in one embodiment of the present invention, anti-error test is carried out to telecommand Card, judges whether telecommand meets default anti-error verification condition and include:
S31:To telecommand carry out validating topology, judge telecommand whether meet predetermined registration operation condition and whether Dead electricity will not be caused.
If telecommand does not meet the condition of predetermined registration operation and/or can cause dead electricity, step S32 is performed:Alarmed Prompting.
S33:If telecommand meets the condition of predetermined registration operation and will not cause dead electricity, trend is carried out to telecommand and tested Card, whether power network is safe after judging remote control.
If power network is dangerous after remote control, step S32 is performed:Carry out alarm.
S34:If power grid security after remote control, performs telecommand.
In the present embodiment, after equipment remote-control operating rights lock release, before performing guidance command, anti-error system pair It is remotely controlled result and carries out validating topology and trend checking, further ensure that telecommand meets the condition of remote operation, and can Ensure the safety of power network.
It should be noted that double two-shipper is needed during straighforward operation equipment, it is ensured that the monitoring of remote operation is in place.
Further, also include after judging that telecommand meets default anti-error verification condition:By telecommand solution Analyse as corresponding remote control preliminary command;Anti-error return to school is carried out to remote control preliminary command.
In order to prevent the equipment in administrative monitoring range from being missed remote control, maloperation, economic loss is caused, increases policer operation Blocking function, all straighforward operations have to pass through the anti-error verification of system.Receive the monitoring such as the ground wire sent in transformer station, net door The non-collecting device information of system or monitor's set information, and as the condition of anti-error analysis, avoid scheduling and field data not The maloperation symmetrically brought.System is worked out in operational order, the anti-error verifications of middle addition of concrete operations, constrains the row of straighforward operation To avoid remote control, maloperation by mistake.
Wherein, it is anti-error return to school it is specific as follows:
1. unanimous vote verifies
After the completion of ticket is intended, unanimous vote verification must be carried out before assigning operational order, to whether meet remote operation condition, Situations such as whether causing dead electricity is verified that the result of verification reminds out in a manner of alerting.To help monitoring personnel to carry out Anti-error analysis.
2. interim functional check
During for accident treatment pattern and provisional application pattern, monitor has no operation order, according to the equipment of required operation Single checking is carried out, the result of verification reminds out in a manner of alerting.
3. increase network topology variable
In topology is anti-error in addition to having state quantity of the equipment anti-error, also increases sign board and (maintenance board, isolation board, protect electric board Deng) logic it is anti-error and secondary (air pressure, circuit breaking, route protection throw move back) it is anti-error, anti-error logic checking is more comprehensive.
4. reactive apparatus mutual exclusion blocking function
The mutual exclusion locking of the capacitor and reactor in same transformer station can be achieved.When capacitor or reactor are put into, Another kind equipment is in romote controlled locking, prevents same transformer station's inner capacitor and reactor while is passed through situation.
In summary, in embodiments of the present invention, the process of administrative equipment is operated by telecommand at regulation and control end In, it is necessary to by by the equipment of locking be remotely controlled unblock, validating topology, trend checking and four big steps of straighforward operation, profit Existing remote measurement, the remote signalling data at regulation and control end are collected with transformer station, establishes remote measurement and remote signalling data change and telecommand Association, anti-error to telecommand progress according to actual conditions, telecommand then needs to enter the equipment of locking to remote control equipment Row unblock and anti-error checking, only unlocked successfully in equipment, and to telecommand it is anti-error be verified after could perform it is distant Control instruction, equipment corresponding to control work, and realize power grid regulation end to unattended transformer substation switch remote operation, simultaneously Comprehensive anti-incorrect manipulation deadlock when being remotely controlled equipment is realized, improves power grid security guarantee under the unattended pattern of transformer station Ability and electric service are horizontal.
In addition, anti-error checking effectively constrains straighforward operation, controlled plant only modulated end telecommand control, ensure Sole operation authority, regulation and control center receive remote measurement and the facility information such as remote signalling data and ground wire, ground connection, sign board, made It is more comprehensive that central information must be regulated and controled, improve the anti-error logic verify degree of accuracy.
A kind of power grid regulation end anti-incorrect manipulation deadlock method provided by the present invention is described in detail above.Herein Apply specific case to be set forth the principle and embodiment of the present invention, the explanation of above example is only intended to help Understand the present invention and its core concept.It should be pointed out that for those skilled in the art, this hair is not being departed from On the premise of bright principle, some improvement and modification can also be carried out to the present invention, these are improved and modification also falls into power of the present invention In the protection domain that profit requires.

Claims (7)

  1. A kind of 1. power grid regulation end anti-incorrect manipulation deadlock method, it is characterised in that including:
    The whole network locking is carried out to the administrative equipment of Centralized Monitoring;
    Remote measurement and remote signalling data of the transformer station of collection power network to regulation and control end in real time;
    The working condition of the transformer station is judged according to the remote measurement and remote signalling data;
    According to the telecommand at regulation and control end and the working condition of the transformer station, the corresponding administration in the whole network locking is set It is standby to be unlocked;
    Judge whether the unblock to the corresponding administration equipment succeeds;
    If to the corresponding unblock success for administering equipment, anti-error checking is carried out to the telecommand, judges the remote control Whether instruction meets default anti-error verification condition;
    If the telecommand meets default anti-error verification condition, the telecommand is performed;
    The working condition according to the telecommand and the transformer station that regulate and control end, to the respective tube in the whole network locking Linchpin equipment be unlocked including:
    Receive it is described regulation and control end the telecommand, according to the working condition of the transformer station selection corresponding to latching mode, The corresponding administration equipment being in the whole network locking is unlocked, wherein, the latching mode includes:
    Program operation mode, under being in normal operating conditions in the transformer station, operation order is issued, and according to operation order solution Single equipment corresponding to lock;
    Accident treatment pattern, under being in accident condition in the transformer station, always believed by whole station accident resultant signal, interval accident Number, section is all residing for all kinds of protection automatic safety devices action outlet information and switch changed position information unblock accident transformer station sets Standby remote control power;
    Provisional application pattern, for when interim exception or defect occur for the power network, the unlocker device in preset time period.
  2. 2. according to the method for claim 1, it is characterised in that the telecommand at the regulation and control end is received, according to institute Latching mode corresponding to the working condition selection of transformer station is stated, the corresponding administration equipment being in the whole network locking is solved Lock includes:
    After the telecommand at the regulation and control end is received, judge whether possess operation order;
    If possessing operation order, the corresponding administration equipment being in the whole network locking is unlocked;
    If not possessing operation order, trouble-signal is judged whether;
    If trouble-signal be present, the corresponding administration equipment being in the whole network locking is unlocked;
    If trouble-signal is not present, judge whether to unlock temporarily;
    If interim unblock, the corresponding administration equipment being in the whole network locking is unlocked;
    If do not unlock temporarily, forbid being unlocked the corresponding administration equipment in the whole network locking.
  3. 3. according to the method for claim 2, it is characterised in that according to corresponding to the selection of the working condition of the transformer station Latching mode, also include after being unlocked to the corresponding administration equipment being in the whole network locking:
    After the unblock of select planning operator scheme, after in the state change of the equipment of unblock, after the delay of preset time period Or according to corresponding to unlocking operation order in the case that single equipment does not perform, locked remote control operating rights again;
    After selection accident treatment pattern unblock, confirmed after the completion of accident treatment, and recover straighforward operation power locking;
    After selection provisional application pattern unblock, locking again after the completion of unlocker device or after the delay of preset time period Straighforward operation is weighed.
  4. 4. according to the method described in any one of claims 1 to 3, it is characterised in that described anti-error to telecommand progress Checking, judges whether the telecommand meets default anti-error verification condition and include:
    To the telecommand carry out validating topology, judge the telecommand whether meet predetermined registration operation condition and whether Dead electricity will not be caused;
    If the telecommand does not meet the condition of predetermined registration operation and/or can cause dead electricity, alarm is carried out;
    If the telecommand meets the condition of predetermined registration operation and will not cause dead electricity, trend is carried out to the telecommand and tested Card, whether power network is safe after judging remote control;
    If power network is dangerous after remote control, alarm is carried out;
    If power grid security after remote control, performs the telecommand.
  5. 5. according to the method for claim 4, it is characterised in that meet default anti-error checking in the judgement telecommand Also include after condition:
    The telecommand is resolved into corresponding remote control preliminary command;
    Anti-error return to school is carried out to the remote control preliminary command.
  6. 6. according to the method for claim 5, it is characterised in that described that anti-error return to school of the remote control preliminary command progress is also wrapped Include:
    Judge whether the telecommand meets the secondary anti-mis-logical of the anti-error logical sum of default sign board, wherein, the mark The anti-mis-logical of board includes the anti-mis-logical of maintenance board, the anti-mis-logical of isolation board, the anti-mis-logical of guarantor's electricity board, the secondary anti-mis-logical bag Include the anti-error logical sum route protection throwing of the anti-mis-logical of air pressure, circuit breaking and move back anti-mis-logical.
  7. 7. according to the method for claim 6, it is characterised in that described that anti-error return to school of the remote control preliminary command progress is also wrapped Include:
    Mutual exclusion locking is carried out to the reactive apparatus in the administrative equipment of Centralized Monitoring.
CN201511030344.8A 2015-12-31 2015-12-31 A kind of power grid regulation end anti-incorrect manipulation deadlock method Active CN105406603B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201511030344.8A CN105406603B (en) 2015-12-31 2015-12-31 A kind of power grid regulation end anti-incorrect manipulation deadlock method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201511030344.8A CN105406603B (en) 2015-12-31 2015-12-31 A kind of power grid regulation end anti-incorrect manipulation deadlock method

Publications (2)

Publication Number Publication Date
CN105406603A CN105406603A (en) 2016-03-16
CN105406603B true CN105406603B (en) 2018-04-06

Family

ID=55471924

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201511030344.8A Active CN105406603B (en) 2015-12-31 2015-12-31 A kind of power grid regulation end anti-incorrect manipulation deadlock method

Country Status (1)

Country Link
CN (1) CN105406603B (en)

Families Citing this family (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105894210B (en) * 2016-04-21 2019-12-03 国电南瑞科技股份有限公司 A kind of operation order trigger-type grid equipment remote operation anti-misoperation method
CN106527229A (en) * 2016-11-30 2017-03-22 国网江苏省电力公司淮安供电公司 Method for misoperation-preventing locking of transformer station secondary overhaul remote control operation
CN107026431B (en) * 2017-03-13 2019-01-08 全球能源互联网研究院有限公司 The fault detection method and device of region AC/DC interconnected system
CN106953324A (en) * 2017-05-27 2017-07-14 广东电网有限责任公司电力调度控制中心 One kind is based on the hot female process median generatrix disconnecting link control method and device of main station system
CN107844090A (en) * 2017-11-03 2018-03-27 许继集团有限公司 A kind of interlock method and device of the shutdown of substation data communication network
CN109978181B (en) * 2019-01-31 2023-04-07 国网浙江宁海县供电有限公司 Large-screen display system for monitoring power grid operation risk
CN110889959B (en) * 2019-11-28 2021-09-21 国网山东省电力公司蓬莱市供电公司 Beidou distribution network communication system and Beidou distribution network communication method
CN110991675A (en) * 2019-12-17 2020-04-10 珠海长园共创软件技术有限公司 Distribution network operation and maintenance monitoring method and system
CN111697696A (en) * 2020-06-05 2020-09-22 国网福建省电力有限公司 Substation anti-error system and method based on anti-error double-host mode operation
CN111969724B (en) * 2020-07-27 2022-08-05 国网福建省电力有限公司 Method and system for realizing remote control state of power equipment

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202997704U (en) * 2012-12-19 2013-06-12 珠海优特电力科技股份有限公司 Distribution network terminal having anti-misoperation function
CN104158294A (en) * 2014-08-27 2014-11-19 凯里供电局 Dispatching anti-misoperation control method

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202997704U (en) * 2012-12-19 2013-06-12 珠海优特电力科技股份有限公司 Distribution network terminal having anti-misoperation function
CN104158294A (en) * 2014-08-27 2014-11-19 凯里供电局 Dispatching anti-misoperation control method

Also Published As

Publication number Publication date
CN105406603A (en) 2016-03-16

Similar Documents

Publication Publication Date Title
CN105406603B (en) A kind of power grid regulation end anti-incorrect manipulation deadlock method
CN111293784B (en) Temporary power utilization system for construction site
CN202940643U (en) Comprehensive anti-misoperation system for power distribution network
CN109995138B (en) Misoperation-preventive locking management system and overhauling isolation locking management method for transformer substation
CN106712300A (en) Intelligent master station and sub-station multi-level anti-misoperation locking system
CN107508264B (en) A kind of site route protection does not have a power failure drive method
CN107591892B (en) Intelligent substation operation and maintenance method and system
CN202034678U (en) Error preventing system used for electrical power system
CN105634129A (en) Sequence control method for intelligent substation
CN108233536A (en) A kind of intelligent program remote handling system
CN201898375U (en) Intelligent, integrated and comprehensive mal-operation preventing system of distribution network
CN104821662A (en) Multidimensional intelligent anti-misoperation system and method
CN103501045A (en) Network command issuing method of electric power system dispatching commands
CN105894210B (en) A kind of operation order trigger-type grid equipment remote operation anti-misoperation method
CN106655168A (en) Method and device for building loop closing model of power distribution network
CN104750095B (en) Regulation and control center inspection pilot system and method
CN108494089A (en) A kind of fast and safely reliably ration the power supply draws road mass-produced remote control method
CN105470935A (en) Defect security isolation and auxiliary decision-making method for intelligent substation relay protection equipment
CN111583465A (en) Intelligent key working method for electric power switching operation
EP2371611A1 (en) Device and method for controlled exchange of energy between a power network and a meter
CN107359702A (en) Intelligent linkage Interlocking Methods based on IES700 systems
CN108964259A (en) A kind of power grid intelligence control system
CN108879441A (en) Substation inspection and grid switching operation system and its control method
CN105048293A (en) Method for monitoring secondary pressure plate compulsory locking device and state thereof
CN106451788A (en) Method for remotely controlling and operating dispatching automation systems by aid of remote-control safety strategy module

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant