CN105344477A - Anode tube bundling hanger of wet electrostatic precipitator - Google Patents

Anode tube bundling hanger of wet electrostatic precipitator Download PDF

Info

Publication number
CN105344477A
CN105344477A CN201510857695.XA CN201510857695A CN105344477A CN 105344477 A CN105344477 A CN 105344477A CN 201510857695 A CN201510857695 A CN 201510857695A CN 105344477 A CN105344477 A CN 105344477A
Authority
CN
China
Prior art keywords
fixed mount
anode tube
hanger
connecting rod
fixed frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510857695.XA
Other languages
Chinese (zh)
Other versions
CN105344477B (en
Inventor
张恩泽
强宏理
沈国斌
胡文进
向俊平
朱海峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MHPS Dongfang Boiler Co Ltd
Original Assignee
MHPS Dongfang Boiler Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MHPS Dongfang Boiler Co Ltd filed Critical MHPS Dongfang Boiler Co Ltd
Priority to CN201510857695.XA priority Critical patent/CN105344477B/en
Publication of CN105344477A publication Critical patent/CN105344477A/en
Application granted granted Critical
Publication of CN105344477B publication Critical patent/CN105344477B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B03SEPARATION OF SOLID MATERIALS USING LIQUIDS OR USING PNEUMATIC TABLES OR JIGS; MAGNETIC OR ELECTROSTATIC SEPARATION OF SOLID MATERIALS FROM SOLID MATERIALS OR FLUIDS; SEPARATION BY HIGH-VOLTAGE ELECTRIC FIELDS
    • B03CMAGNETIC OR ELECTROSTATIC SEPARATION OF SOLID MATERIALS FROM SOLID MATERIALS OR FLUIDS; SEPARATION BY HIGH-VOLTAGE ELECTRIC FIELDS
    • B03C3/00Separating dispersed particles from gases or vapour, e.g. air, by electrostatic effect
    • B03C3/02Plant or installations having external electricity supply
    • B03C3/16Plant or installations having external electricity supply wet type
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B03SEPARATION OF SOLID MATERIALS USING LIQUIDS OR USING PNEUMATIC TABLES OR JIGS; MAGNETIC OR ELECTROSTATIC SEPARATION OF SOLID MATERIALS FROM SOLID MATERIALS OR FLUIDS; SEPARATION BY HIGH-VOLTAGE ELECTRIC FIELDS
    • B03CMAGNETIC OR ELECTROSTATIC SEPARATION OF SOLID MATERIALS FROM SOLID MATERIALS OR FLUIDS; SEPARATION BY HIGH-VOLTAGE ELECTRIC FIELDS
    • B03C3/00Separating dispersed particles from gases or vapour, e.g. air, by electrostatic effect
    • B03C3/34Constructional details or accessories or operation thereof
    • B03C3/86Electrode-carrying means

Abstract

The invention relates to an anode tube bundling hanger of a wet electrostatic precipitator. The anode tube bundling hanger comprises a front fixed frame and a back fixed frame having corresponding through holes, connecting rods penetrating through the corresponding through holes and having threads on two ends, circular plates coating the middle parts of the connecting rods, cylinders coating the two ends of the connecting rods, two end positioning pieces butted against the circular plates and the cylinders, a front lifting lug fixedly connected with the front fixed frame, and a back lifting lug fixedly connected with the back fixed frame, wherein the connecting rods are fixedly screwed with nuts through the threads at two ends. As the connecting rods penetrating through anode tube bundling holes are connected with the front fixed frame and the back fixed frame and are fixedly combined with anode tube bundles as a whole, and the lifting lugs are arranged on the front fixed frame and the back fixed frame, the technical problem of difficult lifting operation due to incapability of arranging lifting points at plastic anode tube body parts is solved; and the anode tube bundling hanger of the wet electrostatic precipitator can satisfy the anode tube bundle lifting operation demands.

Description

Wet cottrell anode tube does up suspension bracket
Technical field
the present invention relates to a kind of upending frame, especially relating to a kind of upending frame for lifting the tube bank of wet cottrell plastic material anode.
Background technology
wet cottrell structure is various, and anode tube bank is its important building block.Be in high-tension electricity and acidic flue gas due to during anode tube bank work, therefore adopt the anode of plastic tube restrain with the corrosion of its acid resistance and high voltage electrical isolation functional and be used widely, adopt the tube bank of the anode of plastic tube to form (as shown in Figure 1) primarily of perforate plastic plate and the plastic tube that is arranged in perforate plastic plate.Due to plastic material poor rigidity, yielding, directly Heave Here can not be set in the body part of anode tube bank, so bring difficulty to the lifting operation of anode tube bank, especially anode tube bank also needs to carry out that upset is holded up when installing in building site and waits operation, therefore a kind ofly can meet again anode and restrains the upending frame lifting needs without the need to arranging Heave Here in anode tube bank body part and become active demand.
Summary of the invention
the present invention mainly solves and causes anode to restrain to be difficult to carry out the technical problem of lifting operation, to provide a kind of wet cottrell anode tube that can meet anode tube bank lifting action need without the need to arranging Heave Here in anode tube bank body part to do up suspension bracket because anode tube bank body part cannot arrange Heave Here existing for prior art.
the present invention is directed to that above-mentioned technical problem mainly solved by following technical proposals: the present invention includes have mutually corresponding some through holes one before fixed mount after fixed mount and, identical with number of openings through through hole and at the threaded connecting rod of outboard end of front fixed mount and rear fixed mount, some plectanes be sheathed in the middle part of connecting rod, be sheathed on the cylinder of the medial end of close front fixed mount and rear fixed mount on connecting rod, be resisted against the keeper that plectane is fixedly connected with connecting rod with the two ends of cylinder, with be fixedly connected with outside front fixed mount before hanger, the rear hanger be fixedly connected with the outside of rear fixed mount, connecting rod is spirally connected fixing by the screw thread of its end and nut, plectane is identical with outside diameter of cylinder.
as preferably, front baffle and afterframe have 4 through holes respectively.
as preferably, front fixed mount is rectangular frame, and front hanger is two and is symmetrically distributed in the middle part of front fixed mount both sides, and rear fixed mount is I-shaped, and rear hanger is positioned at the middle part a little more than rear fixed mount center, and plectane is uniformly distributed at the middle part of connecting rod.
as preferably, plectane and cylinder adopt plastic material.
therefore, the present invention is rational in infrastructure, easy to use, has following feature:
the present invention is directed to plastic material anode tube bank poor rigidity, yielding, the technical problem of Heave Here cannot be directly set in body part, be connected with rear fixed mount with front fixed mount by the connecting rod being each passed through anode tube bank plastic tube, and front fixed mount and rear fixed mount be fixed on anode tube bank two ends and anode by the nut of tightening connecting rod two ends and restrain secure bond and be integrated, before front fixed mount and rear fixed mount are arranged, hanger and rear hanger are as Heave Here, thus solve the problem that anode tube bank body part cannot arrange Heave Here; Simultaneously, sheathed plectane and cylinder on connecting rod, by the laminating of plectane and cylinder and tube wall, avoid connecting rod and overturn bending distortion in perpendicular process in anode tube bank, thus can realize carrying out that upset is holded up etc. and lift operating to the tube bank of plastic material anode.
Accompanying drawing explanation
accompanying drawing 1 is the structural representation of wet cottrell anode tube bank;
accompanying drawing 2 is structural representations of the present invention;
accompanying drawing 3 is that the present invention and anode are restrained to lift and assembled schematic diagram;
accompanying drawing 4 is that the present invention and anode restrain the left view lifting and assemble;
accompanying drawing 5 is that the A-A of accompanying drawing 3 is to cross section view.
Detailed description of the invention
below by embodiment, and by reference to the accompanying drawings, technical scheme of the present invention is described in further detail.
embodiment 1: as shown in Figure 2, the present invention includes the front fixed mount 1 that has the rectangle of four through holes 10, the one I-shaped rear fixed mount 5 offering four through holes 10 corresponding with front fixed mount 1, be each passed through four connecting rods 3 of four corresponding through holes 10 of front fixed mount 1 and rear fixed mount 5, connecting rod 3 is threaded to be spirally connected with nut through the two ends of front fixed mount 1 and rear fixed mount 5 and is fixed on the outside of front fixed mount 1 and rear fixed mount 5.
middle part sheathed six plastics plectanes 4 equably of connecting rod 3, the each sheathed plastic cylinder 7 of medial end of close front fixed mount 1 and rear fixed mount 5 on connecting rod 3, keeper 8 adopts metallic plate to be resisted against the two ends of plastics plectane 4 and plastic cylinder 7 respectively and connecting rod 3 is welded and fixed, and plastics plectane 4 is identical with plastic cylinder 7 external diameter.
the middle part of front fixed mount 1 both sides of rectangle is welded and fixed two symmetrical front hangers 2, hanger 6 after being welded and fixed a little more than the medium position at center outside I-shaped rear fixed mount 5.
as accompanying drawing 2, accompanying drawing 3, shown in accompanying drawing 4 and accompanying drawing 5, the present invention is before anode tube bank lifts, first external diameter in the present invention and anode are restrained plastics plectane 4 that plastic tube internal diameter mates and plastic cylinder 7 is set on connecting rod 3, and the length of plastic tube is restrained according to anode, plastic cylinder 7 is positioned on connecting rod 3 and corresponds to position concordant with the mouth of pipe in the mouth of pipe at plastic tube two ends, six plastics plectanes 4 are distributed between two plastic cylinders 7, being welded and fixed keeper 8 makes plastics plectane 4 and the position of plastic cylinder 7 on connecting rod 3 fix, then plastic cylinder 7 is in the mouth of pipe of plastic tube two ends respectively and concordant with the mouth of pipe in plastic tube connecting rod 3 being penetrated respectively anode tube bank, plastics plectane 4 and plastic cylinder 7 are fitted substantially with plastic pipe inner wall, front fixed mount 1 and rear fixed mount 5 are installed, front fixed mount 1 is corresponding consistent with the position of four connecting rods 3 with the position of opening on rear fixed mount 5, connecting rod 3 is inserted in after being aimed at connecting rod 3 by through hole 10 on front fixed mount 1 and rear fixed mount 5, front fixed mount 1 and rear fixed mount 5 is made to abut in anode tube bank two ends, after tightening the nut at every root connecting rod 3 two ends, anode tube bank is combined as a whole securely with the present invention, anode tube bank can be lifted by crane by front hanger 2 and rear hanger 6.
when anode tube bank lifts, because plastic cylinder 7 and the gripper shoe 9 being installed on anode and restrain two ends are all positioned at the position of the plastic tube two ends mouth of pipe, anode tube bank weight can be born by gripper shoe 9 when level is lifted by crane; When anode tube bank needs to have overturn perpendicular, first the anode level of restraining is sling, then coordinated by two cranes, front hanger 2 promotes, rear hanger 6 down straightens and is totally released, and can complete perpendicular, and before being played by tower crane afterwards, anode tube bank is fallen into mounting shaft by hanger 2.
certainly, above-mentioned drawings and Examples only in order to for explain and illustrate the present invention, can not as improper restriction of the present invention.As front fixed mount of the present invention and rear fixed mount except rectangle and I-shaped except can also be that other shapes are as square or circular; the number of openings of front fixed mount and rear fixed mount and the quantity of corresponding connecting rod can change according to the needs of lifted anode tube bank; plectane of the present invention and cylinder also can be the other materials that hardness is suitable with plastics except adopting plastic material, and the technical scheme that all those skilled in the art make equivalence or equivalent adjustment and change according to the present invention and obtain all falls into protection scope of the present invention.

Claims (5)

1. a wet cottrell anode tube does up suspension bracket, it is characterized in that: comprise have mutually corresponding some through holes (10) one before fixed mount (1) and fixed mount (5) afterwards, identical with described through hole (10) quantity through described through hole (10) and at the threaded connecting rod of outboard end (3) of described front fixed mount (1) and described rear fixed mount (5), some plectanes (4) being sheathed on described connecting rod (3) middle part, be set in the cylinder (7) of the medial end of the upper close described front fixed mount (1) of described connecting rod (3) and described rear fixed mount (5), be resisted against the keeper (8) that described plectane (4) is fixedly connected with described connecting rod (3) with the two ends of described cylinder (7), the front hanger (2) be fixedly connected with described front fixed mount (1) outside, the rear hanger (6) be fixedly connected with the outside of described rear fixed mount (5), described connecting rod (3) is spirally connected fixing by the screw thread of its end and nut, described plectane (4) is identical with described cylinder (7) external diameter.
2. a kind of wet cottrell anode tube according to claim 1 does up suspension bracket, it is characterized in that: described front baffle (1) and described afterframe (5) have 4 described through holes (10) respectively.
3. a kind of wet cottrell anode tube according to claim 1 and 2 does up suspension bracket, it is characterized in that: described front fixed mount (1) is rectangular frame, described front hanger (6) is two and is symmetrically distributed in the middle part of described front fixed mount (1) both sides, described rear fixed mount (5) is for I-shaped, described rear hanger (6) is positioned at the middle part a little more than described rear fixed mount (5) center, and described plectane (4) is uniformly distributed at the middle part of described connecting rod (3).
4. a kind of wet cottrell anode tube according to claim 1 and 2 does up suspension bracket, it is characterized in that: described plectane (4) and described cylinder (7) adopt plastic material.
5. a kind of wet cottrell anode tube according to claim 3 does up suspension bracket, it is characterized in that: described plectane (4) and described cylinder (7) adopt plastic material.
CN201510857695.XA 2015-11-30 2015-11-30 Wet cottrell anode tube does up suspension bracket Active CN105344477B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510857695.XA CN105344477B (en) 2015-11-30 2015-11-30 Wet cottrell anode tube does up suspension bracket

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510857695.XA CN105344477B (en) 2015-11-30 2015-11-30 Wet cottrell anode tube does up suspension bracket

Publications (2)

Publication Number Publication Date
CN105344477A true CN105344477A (en) 2016-02-24
CN105344477B CN105344477B (en) 2017-12-29

Family

ID=55320618

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510857695.XA Active CN105344477B (en) 2015-11-30 2015-11-30 Wet cottrell anode tube does up suspension bracket

Country Status (1)

Country Link
CN (1) CN105344477B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107433434A (en) * 2017-09-05 2017-12-05 上海超惠通风环保设备有限公司 The assembled mould of high accuracy and assembling method of wet-type high-voltage electrostatic precipitation anode tube group

Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002274774A (en) * 2001-03-21 2002-09-25 Notsu Unso Kk Pipe suspending device
CN201406271Y (en) * 2009-05-08 2010-02-17 常州海杰冶金机械制造有限公司 Auxiliary tool for hoisting of large-sized cylindrical piece
CN101885448A (en) * 2010-07-06 2010-11-17 中冶宝钢技术服务有限公司 Electric precipitator positive plate lifting tool and process
CN201999621U (en) * 2010-11-22 2011-10-05 中国十七冶集团有限公司 Tape elevating protective device for bucket elevator
CN102515019A (en) * 2011-12-31 2012-06-27 河北拓安管业有限公司 Fixing device for steel pipes with lap joint flanges and method for coating plastics on steel pipes by aid of fixing device
CN202296828U (en) * 2011-10-26 2012-07-04 中建工业设备安装有限公司 Vertical hoisting tool of shaft pipeline
CN202462258U (en) * 2012-01-16 2012-10-03 安徽鸿翔建材有限公司 Deformation control assembly for large-diameter pipe orifice
CN203021162U (en) * 2012-06-12 2013-06-26 天津二十冶建设有限公司 Hoisting tool of round steel pipe
CN203795932U (en) * 2014-02-28 2014-08-27 中冶天工上海十三冶建设有限公司 Spray tower cylinder support device
CN203959639U (en) * 2014-04-30 2014-11-26 江苏德创制管有限公司 A kind of steel pipe hoisting fixture
CN104340857A (en) * 2013-08-09 2015-02-11 黄石市志云机电科技研究所 Cross beam type round pipe lifting appliance
CN204544466U (en) * 2014-12-24 2015-08-12 中国二十冶集团有限公司 Electrostatic precipitator positive plate auxiliary lifting appliance
CN205288698U (en) * 2015-11-30 2016-06-08 东方菱日锅炉有限公司 Gallows has been restrained to wet electrostatic precipitator positive pole

Patent Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002274774A (en) * 2001-03-21 2002-09-25 Notsu Unso Kk Pipe suspending device
CN201406271Y (en) * 2009-05-08 2010-02-17 常州海杰冶金机械制造有限公司 Auxiliary tool for hoisting of large-sized cylindrical piece
CN101885448A (en) * 2010-07-06 2010-11-17 中冶宝钢技术服务有限公司 Electric precipitator positive plate lifting tool and process
CN201999621U (en) * 2010-11-22 2011-10-05 中国十七冶集团有限公司 Tape elevating protective device for bucket elevator
CN202296828U (en) * 2011-10-26 2012-07-04 中建工业设备安装有限公司 Vertical hoisting tool of shaft pipeline
CN102515019A (en) * 2011-12-31 2012-06-27 河北拓安管业有限公司 Fixing device for steel pipes with lap joint flanges and method for coating plastics on steel pipes by aid of fixing device
CN202462258U (en) * 2012-01-16 2012-10-03 安徽鸿翔建材有限公司 Deformation control assembly for large-diameter pipe orifice
CN203021162U (en) * 2012-06-12 2013-06-26 天津二十冶建设有限公司 Hoisting tool of round steel pipe
CN104340857A (en) * 2013-08-09 2015-02-11 黄石市志云机电科技研究所 Cross beam type round pipe lifting appliance
CN203795932U (en) * 2014-02-28 2014-08-27 中冶天工上海十三冶建设有限公司 Spray tower cylinder support device
CN203959639U (en) * 2014-04-30 2014-11-26 江苏德创制管有限公司 A kind of steel pipe hoisting fixture
CN204544466U (en) * 2014-12-24 2015-08-12 中国二十冶集团有限公司 Electrostatic precipitator positive plate auxiliary lifting appliance
CN205288698U (en) * 2015-11-30 2016-06-08 东方菱日锅炉有限公司 Gallows has been restrained to wet electrostatic precipitator positive pole

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107433434A (en) * 2017-09-05 2017-12-05 上海超惠通风环保设备有限公司 The assembled mould of high accuracy and assembling method of wet-type high-voltage electrostatic precipitation anode tube group

Also Published As

Publication number Publication date
CN105344477B (en) 2017-12-29

Similar Documents

Publication Publication Date Title
CN203474220U (en) Spreader system for overturning and hoisting large diameter overweight sealing head
CN205288698U (en) Gallows has been restrained to wet electrostatic precipitator positive pole
CN207251109U (en) A kind of step type cable bridge frame
CN209130471U (en) A kind of antidetonation suspension and support
CN105344477A (en) Anode tube bundling hanger of wet electrostatic precipitator
CN108086485A (en) A kind of steel construction large-sized bolt gusset plate installation closing device and installation method
CN206595678U (en) A kind of Pre-Cutter-Type Anti-Vibration Hammer with deep bead
CN206806164U (en) 10kv outdoor transformers install suspension rod
CN208024047U (en) A kind of steel pipe tower structure of scalable installation
CN201211458Y (en) Supporting device of sulphuric acid absorbing column filler
CN202090663U (en) Same-tower and dual-loop straight line steel pipe tower
CN104192441A (en) Assembly capable of fixing multiple steel pipes
CN202577688U (en) Articulated cross beam-free metal plate curtain wall
CN208834896U (en) A kind of body overturning tooling of transformer
CN206159657U (en) Fixed pipe clamp structure of convenience side's nest of tubes dress
CN203596587U (en) Preformed vibration damper
CN103259234A (en) Electric transmission line rigid jumper asymmetric V-shaped insulator chain setting structure
CN207531518U (en) Ornamental and afforestation trees support device
CN205828133U (en) A kind of transformer low voltage paper tinsel winding solidification hold mode device
CN206412734U (en) A kind of Multi-frequency vibration damper
CN206205155U (en) A kind of Super High tower crane attachment embedded fixing component
CN220351467U (en) Lifting appliance for flue gas purification adsorption tower
CN211920632U (en) Special hoisting tool for suspension insulator string of transformer substation
CN209797429U (en) Assembled module roll-over stand capable of being repeatedly used
CN216147077U (en) Mosquito eradication lamp high-voltage net

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant