CN105256724A - 无人机牵引先导索过江施工方法 - Google Patents

无人机牵引先导索过江施工方法 Download PDF

Info

Publication number
CN105256724A
CN105256724A CN201510624756.8A CN201510624756A CN105256724A CN 105256724 A CN105256724 A CN 105256724A CN 201510624756 A CN201510624756 A CN 201510624756A CN 105256724 A CN105256724 A CN 105256724A
Authority
CN
China
Prior art keywords
guide cable
unmanned plane
tower top
pilot rope
bridge
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510624756.8A
Other languages
English (en)
Other versions
CN105256724B (zh
Inventor
先正权
梁进达
赵强
艾国清
梁彬彬
蒋能世
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Second Highway Engineering Co Ltd
CCCC SHEC Second Engineering Co Ltd
CCCC Highway Long Bridge Construction National Engineering Research Center Co Ltd
Original Assignee
CCCC SHEC Second Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC SHEC Second Engineering Co Ltd filed Critical CCCC SHEC Second Engineering Co Ltd
Priority to CN201510624756.8A priority Critical patent/CN105256724B/zh
Publication of CN105256724A publication Critical patent/CN105256724A/zh
Application granted granted Critical
Publication of CN105256724B publication Critical patent/CN105256724B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

本发明提供了一种无人机牵引先导索过江施工方法,包括以下步骤实现:起始点的桥梁一端塔顶上,放置好先导索索盘和无人机;从索盘上牵出先导索和无人机连接,同时在先导索上绑定配重块;无人机牵引先导索飞往终点的桥梁另一端塔顶;作业人员在塔顶拽拉接住先导索,无人机解除与先导索的连接,人工将先导索在塔顶锚固点上锚固。该发明设计、开发了完整的动态飞行模式,施工工期短,成本低,实现了真正意义上的不封航(路),避免了受地形、水文、交通限制,也降低了施工风险,便于推广应用。

Description

无人机牵引先导索过江施工方法
技术领域
本发明涉及桥梁技术领域,具体涉及一种无人机牵引先导索过江施工方法。
背景技术
在架设悬索桥牵引系统中,当直接架设牵引系统的牵引索存在困难时,首先要架设比牵引索细、轻的先导索,再利用先导索形成牵引系统。
在山高坡陡、植被丰富,水流急的山区桥梁和江海水深、水文复杂、通航船多等情况的桥梁,跨道路跨线的桥梁中,先导索施工采用常规的人工地面拽拉法或空中牵引法(火箭抛绳法、直升飞机、遥控飞艇),造价高,施工难度大,封航封路时间长,且存在安全隐患。
发明内容
本发明的目的是克服现有技术中存在的问题,提供一种不中断交通,不受地形和水文限制,且作业时间短、风险小、安全高效的牵引先导索过江的架设方法。
本发明的技术方案是提供了一种无人机牵引先导索过江施工方法,包括以下步骤实现:
1)在起始点的桥梁一端塔顶上,放置好先导索索盘和无人机;
2)从索盘上牵出先导索和无人机连接,同时在先导索上绑定配重块;
3)无人机牵引先导索飞往终点的桥梁另一端塔顶;
4)作业人员在塔顶拽拉接住先导索,无人机解除与先导索的连接,人工将先导索在塔顶锚固点上锚固。
上述步骤1)和步骤3)中,作为起始点和终点的桥梁一端,包括塔顶、地面。
上述的无人机为配置惯性导航系统的遥控飞行器。
上述的遥控飞行器为四旋翼飞行器或六旋翼飞行器。
上述的先导索为高强尼龙绳。
上述的高强尼龙绳,其直径选用2mm~4mm。
上述的配重块为装砂子的塑料瓶、装水的塑料瓶、由钢铁材料制成的重块或由混凝土块制成的重块中的一种。
本发明的有益效果:
(1)本发明的这种无人机牵引先导索过江施工方法设计、开发了完整的动态飞行模式,便于推广应用,在采用本发明的技术方案后,不仅缩短了施工工期,而且实现了真正意义上的不封航(路),避免了受地形、水文、交通限制,也降低了施工风险。
(2)本发明的这种无人机牵引先导索过江施工方法通过在两岸塔顶门架顶设置平台,有利于放置放索装置和指挥操作无人机作业以及先导索到达对岸塔顶收绳。
(3)本发明的这种无人机牵引先导索过江施工方法通过采用无人机节省了人力,大大的节约了成本,而且无人机体积小,重量轻,操控简单,安全可靠,方便适用。
(4)本发明的这种无人机牵引先导索过江施工方法通过采用轻质的高强尼龙绳作为先导索,减小了无人机负荷,可适用于小型的无人机,增大了无人机的选择范围。
(5)本发明的这种无人机牵引先导索过江施工方法可采用塑料瓶作为配重块,废物利用,节省成本。
以下将结合附图对本发明做进一步详细说明。
附图说明
图1(1)、(2)、(3)是本发明无人机牵引先导索过江施工方法的作业工程流程示意图。
附图标记说明:1、无人机;2、先导索;3、配重块;4、索盘;5、起始点;6、终点;7、锚固点。
具体实施方式
下面结合附图与具体实施方式对本发明作进一步详细描述:
实施例1:
为了克服现有技术中存在的问题,提供一种不中断交通,不受地形和水文限制,且作业时间短、风险小、安全高效的牵引先导索过江的架设方法。
本实施例提供了一种如图1所示的无人机牵引先导索过江施工方法,包括以下步骤实现:
1)在起始点5的桥梁一端塔顶上,放置好先导索索盘4和无人机1;
2)从索盘4上牵出先导索2和无人机1连接,同时在先导索2上绑定配重块3;
3)无人机1牵引先导索2飞往终点6的桥梁另一端塔顶;
4)作业人员在塔顶拽拉接住先导索2,无人机1解除与先导索2的连接,人工将先导索2在塔顶锚固点7上锚固。
本实施例通过这种无人机牵引先导索过江施工方法设计、开发了完整的动态飞行模式,便于推广应用,在采用本发明的技术方案后,不仅缩短了施工工期,而且实现了真正意义上的不封航(路),避免了受地形、水文、交通限制,也降低了施工风险。
实施例2:
本实施例提供了一种如图1所示的无人机牵引先导索过江施工方法,包括以下步骤实现:
1)在起始点5的桥梁一端塔顶上,放置好先导索索盘4和无人机1;
2)从索盘4上牵出先导索2和无人机1连接,同时在先导索2上绑定配重块3;
3)无人机1牵引先导索2飞往终点6的桥梁另一端塔顶;
4)作业人员在塔顶拽拉接住先导索2,无人机1解除与先导索2的连接,人工将先导索2在塔顶锚固点7上锚固。
而其中作为优选的实施方式,所述步骤1)和步骤3)中,作为起始点(5)和终点(6)的桥梁一端,包括塔顶、地面。本实施例提供的这种无人机牵引先导索过江施工方法通过在两岸塔顶门架顶设置平台,有利于放置放索装置和指挥操作无人机作业以及先导索到达对岸塔顶收绳。
实施例3:
本实施例提供了一种如图1所示的无人机牵引先导索过江施工方法,包括以下步骤实现:
1)在起始点5的桥梁一端塔顶上,放置好先导索索盘4和无人机1;
2)从索盘4上牵出先导索2和无人机1连接,同时在先导索2上绑定配重块3;
3)无人机1牵引先导索2飞往终点6的桥梁另一端塔顶;
4)作业人员在塔顶拽拉接住先导索2,无人机1解除与先导索2的连接,人工将先导索2在塔顶锚固点7上锚固。
而其中作为优选的实施方式,所述的无人机1为配置惯性导航系统的遥控飞行器。所述的遥控飞行器为四旋翼飞行器或六旋翼飞行器。本实施例提供的这种无人机牵引先导索过江施工方法通过采用无人机节省了人力,大大的节约了成本,而且无人机体积小,重量轻,操控简单,安全可靠,方便适用。
实施例4:
本实施例提供了一种如图1所示的无人机牵引先导索过江施工方法,包括以下步骤实现:
1)在起始点5的桥梁一端塔顶上,放置好先导索索盘4和无人机1;
2)从索盘4上牵出先导索2和无人机1连接,同时在先导索2上绑定配重块3;
3)无人机1牵引先导索2飞往终点6的桥梁另一端塔顶;
4)作业人员在塔顶拽拉接住先导索2,无人机1解除与先导索2的连接,人工将先导索2在塔顶锚固点7上锚固。
而其中作为优选的实施方式,所述的先导索2为高强尼龙绳。所述的高强尼龙绳,其直径选用2mm~4mm。本实施例提供的这种无人机牵引先导索过江施工方法通过采用轻质的高强尼龙绳作为先导索,减小了无人机负荷,可适用于小型的无人机,增大了无人机的选择范围。
实施例5:
本实施例提供了一种如图1所示的无人机牵引先导索过江施工方法,包括以下步骤实现:
1)在起始点5的桥梁一端塔顶上,放置好先导索索盘4和无人机1;
2)从索盘4上牵出先导索2和无人机1连接,同时在先导索2上绑定配重块3;
3)无人机1牵引先导索2飞往终点6的桥梁另一端塔顶;
4)作业人员在塔顶拽拉接住先导索2,无人机1解除与先导索2的连接,人工将先导索2在塔顶锚固点7上锚固。
而其中作为优选的实施方式,所述的配重块3为装砂子的塑料瓶、装水的塑料瓶、由钢铁材料制成的重块或由混凝土块制成的重块中的一种。本实施例提供的这种无人机牵引先导索过江施工方法可采用塑料瓶作为配重块,废物利用,节省成本。
实施例6:
本实施例提供了一种用于悬索桥的牵引系统中架设先导索的方法,其实施架设先导索的方法前的准备如下:
1)可选用FXQ---2无人机,其最大载重5.5kg,留空时间12~28分钟,最大飞行距离单控2000米以上、接力遥控4000米以上;
2)先导索的选用:根据无人机的牵引能力,尽量选用高强、轻质、直径小的尼龙绳,本实施例选用直径为2mm的韩国丝作为先导索。所述的高强尼龙绳破断拉力为50kgf;
3)配重块的选用,选用0.25kg的装砂子的塑料瓶子;
4)实例气象条件选择
本实施例中,在视野度,即可视距离超过2km,云高超过200m,风向及风速度为逆风:9m/s,顺风:6m/s的情况下实施。
其具体实施步骤如下:
1)在起始点5的桥梁一端塔顶上,放置好先导索索盘4和无人机1;
2)从索盘4上牵出先导索2和无人机1连接,同时在先导索2上绑定配重块3。如图1(1)所示;
3)无人机1牵引先导索2飞往终点6的桥梁另一端塔顶。如图1(2)所示;
4)作业人员在塔顶拽拉接住先导索2,无人机1解除与先导索2的连接,人工将先导索2在塔顶锚固点7上锚固。如图1(3)所示。
这样就完成先导索架设过程。
以上例举仅仅是对本发明的举例说明,并不构成对本发明的保护范围的限制,凡是与本发明相同或相似的设计均属于本发明的保护范围之内。

Claims (7)

1.无人机牵引先导索过江施工方法,其特征在于,包括以下步骤实现:
1)在起始点(5)的桥梁一端塔顶上,放置好先导索索盘(4)和无人机(1);
2)从索盘(4)上牵出先导索(2)和无人机(1)连接,同时在先导索(2)上绑定配重块(3);
3)无人机(1)牵引先导索(2)飞往终点(6)的桥梁另一端塔顶;
4)作业人员在塔顶拽拉接住先导索(2),无人机(1)解除与先导索(2)的连接,人工将先导索(2)在塔顶锚固点(7)上锚固。
2.根据权利要求1所述的一种无人机牵引先导索过江施工方法,其特征在于,所述步骤1)和步骤3)中,作为起始点(5)和终点(6)的桥梁一端,包括塔顶、地面。
3.根据权利要求1所述的一种无人机牵引先导索过江施工方法,其特征在于,所述的无人机(1)为配置惯性导航系统的遥控飞行器。
4.根据权利要求1或3所述的一种无人机牵引先导索过江施工方法,其特征在于,所述的遥控飞行器为四旋翼飞行器或六旋翼飞行器。
5.根据权利要求1所述的无人机牵引先导索过江施工方法,其特征在于,所述的先导索(2)为高强尼龙绳。
6.根据权利要求1或5所述的无人机牵引先导索过江施工方法,其特征在于,所述的高强尼龙绳,其直径选用2mm~4mm。
7.根据权利要求1所述的无人机牵引先导索过江施工方法,其特征在于,所述的配重块(3)为装砂子的塑料瓶、装水的塑料瓶、由钢铁材料制成的重块或由混凝土块制成的重块中的一种。
CN201510624756.8A 2015-09-28 2015-09-28 无人机牵引先导索过江施工方法 Active CN105256724B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510624756.8A CN105256724B (zh) 2015-09-28 2015-09-28 无人机牵引先导索过江施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510624756.8A CN105256724B (zh) 2015-09-28 2015-09-28 无人机牵引先导索过江施工方法

Publications (2)

Publication Number Publication Date
CN105256724A true CN105256724A (zh) 2016-01-20
CN105256724B CN105256724B (zh) 2017-10-20

Family

ID=55096640

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510624756.8A Active CN105256724B (zh) 2015-09-28 2015-09-28 无人机牵引先导索过江施工方法

Country Status (1)

Country Link
CN (1) CN105256724B (zh)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105866910A (zh) * 2016-06-29 2016-08-17 安徽电信工程有限责任公司 一种用于跨河光缆铺设的方法
CN105866912A (zh) * 2016-06-29 2016-08-17 安徽电信工程有限责任公司 一种种植园中光纤铺设的方法
CN105891989A (zh) * 2016-06-29 2016-08-24 安徽电信工程有限责任公司 一种光纤铺设方法
CN105891988A (zh) * 2016-06-29 2016-08-24 安徽电信工程有限责任公司 一种种植园中光纤铺设的方法
CN105905551A (zh) * 2016-07-05 2016-08-31 安徽电信工程有限责任公司 一种运输光缆的装置
CN106094149A (zh) * 2016-06-29 2016-11-09 安徽电信工程有限责任公司 一种山林中光纤铺设的装置及方法
CN106125244A (zh) * 2016-06-29 2016-11-16 安徽电信工程有限责任公司 一种跨河光纤铺设的装置及方法
CN106115525A (zh) * 2016-06-29 2016-11-16 安徽电信工程有限责任公司 一种光缆运输装置
CN111622111A (zh) * 2020-05-04 2020-09-04 中交第四公路工程局有限公司 超深河谷缆索吊机主索架设用先导索施工方法
CN115094760A (zh) * 2022-06-20 2022-09-23 中国十九冶集团有限公司 斜拉桥的斜拉索挂索装置及挂索方法

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08144218A (ja) * 1994-11-17 1996-06-04 Honsyu Shikoku Renrakukiyou Kodan ヘリコプタを用いてパイロットロープを張力管理しながら空中架線する方法
CN1936189A (zh) * 2006-10-13 2007-03-28 浙江省舟山连岛工程建设指挥部 一种用于悬索桥牵引系统中架设先导索的方法
CN101096839A (zh) * 2007-05-11 2008-01-02 大庆石油管理局 施工工作索的高空发送方法
CN201447665U (zh) * 2009-09-08 2010-05-05 中交第二公路工程局有限公司 一种大跨度悬索桥施工中的先导索水面牵引的放索装置
CN102720141A (zh) * 2012-07-13 2012-10-10 广东省长大公路工程有限公司 先导索过江与牵引体系一体化的施工方法
CN102787561A (zh) * 2012-08-30 2012-11-21 中交二公局第五工程有限公司 飞艇牵引先导索技术的施工方法

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08144218A (ja) * 1994-11-17 1996-06-04 Honsyu Shikoku Renrakukiyou Kodan ヘリコプタを用いてパイロットロープを張力管理しながら空中架線する方法
CN1936189A (zh) * 2006-10-13 2007-03-28 浙江省舟山连岛工程建设指挥部 一种用于悬索桥牵引系统中架设先导索的方法
CN101096839A (zh) * 2007-05-11 2008-01-02 大庆石油管理局 施工工作索的高空发送方法
CN201447665U (zh) * 2009-09-08 2010-05-05 中交第二公路工程局有限公司 一种大跨度悬索桥施工中的先导索水面牵引的放索装置
CN102720141A (zh) * 2012-07-13 2012-10-10 广东省长大公路工程有限公司 先导索过江与牵引体系一体化的施工方法
CN102787561A (zh) * 2012-08-30 2012-11-21 中交二公局第五工程有限公司 飞艇牵引先导索技术的施工方法

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
李磊等: ""浅论无人机应用领域及前景"", 《地理空间信息》 *

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105866910A (zh) * 2016-06-29 2016-08-17 安徽电信工程有限责任公司 一种用于跨河光缆铺设的方法
CN105866912A (zh) * 2016-06-29 2016-08-17 安徽电信工程有限责任公司 一种种植园中光纤铺设的方法
CN105891989A (zh) * 2016-06-29 2016-08-24 安徽电信工程有限责任公司 一种光纤铺设方法
CN105891988A (zh) * 2016-06-29 2016-08-24 安徽电信工程有限责任公司 一种种植园中光纤铺设的方法
CN106094149A (zh) * 2016-06-29 2016-11-09 安徽电信工程有限责任公司 一种山林中光纤铺设的装置及方法
CN106125244A (zh) * 2016-06-29 2016-11-16 安徽电信工程有限责任公司 一种跨河光纤铺设的装置及方法
CN106115525A (zh) * 2016-06-29 2016-11-16 安徽电信工程有限责任公司 一种光缆运输装置
CN105905551A (zh) * 2016-07-05 2016-08-31 安徽电信工程有限责任公司 一种运输光缆的装置
CN111622111A (zh) * 2020-05-04 2020-09-04 中交第四公路工程局有限公司 超深河谷缆索吊机主索架设用先导索施工方法
CN115094760A (zh) * 2022-06-20 2022-09-23 中国十九冶集团有限公司 斜拉桥的斜拉索挂索装置及挂索方法

Also Published As

Publication number Publication date
CN105256724B (zh) 2017-10-20

Similar Documents

Publication Publication Date Title
CN105256724A (zh) 无人机牵引先导索过江施工方法
CN204415730U (zh) 一种移动留空式无人飞行器基站
CN104890851B (zh) 一种临近空间气球系统安全发放方法
CN102092471B (zh) 系留热气飞艇浮空平台
Li et al. Design and implementation of UAV intelligent aerial photography system
CN104516354A (zh) 一种无人直升机电力巡线智能返航路径控制方法
CN103863546A (zh) 一种新型大尺寸高空气球释放方式
CN101707334A (zh) 无人直升机电力展放引导绳的展放方法及系统
CN104536459A (zh) 一种小型多轴无人机展放牵引绳的施工方法
CN105564663A (zh) 飞机悬挂式全自动起降系统及起降方法
CN108163179B (zh) 一种临近空间浮空器发放方法及发放装置
CN1936189B (zh) 一种用于悬索桥牵引系统中架设先导索的方法
CN102787561B (zh) 飞艇牵引先导索技术的施工方法
CN102720141A (zh) 先导索过江与牵引体系一体化的施工方法
CN102781755A (zh) 具有机翼的轨道交通工具
CN102704714B (zh) 张弦充气膜杂交结构悬浮式空中机场
CN103195662A (zh) 翼环及具有翼环的机构暨方法
CN201528159U (zh) 无人直升机电力展放引导绳的展放系统
CN106335622A (zh) 一种机动式观光系留气球
CN106284002A (zh) 一种基于城市公路网的空中快道
Moormann DHL parcelcopter research flight campaign 2014 for emergency delivery of medication
CN106274506A (zh) 一种城市空中公共交通系统
CN206664937U (zh) 一种无人机自动脱钩抛物器
CN202987501U (zh) 一种自动收放的滑翔伞
CN102277833A (zh) 一种先导索安装方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20210916

Address after: 710119 No.29, No.1 Enterprise Park, West Avenue, high tech Zone, Xi'an City, Shaanxi Province

Patentee after: CCCC-SHEC SECOND ENGINEERING Co.,Ltd.

Patentee after: CCCC SECOND HIGHWAY ENGINEERING Co.,Ltd.

Patentee after: CCCC HIGHWAY BRIDGES NATIONAL ENGINEERING RESEARCH CENTER Co.,Ltd.

Address before: 710119 No.29, No.1 Enterprise Park, West Avenue, high tech Zone, Xi'an City, Shaanxi Province

Patentee before: CCCC-SHEC SECOND ENGINEERING Co.,Ltd.