CN105243486A - Construction scene simulation display method and apparatus - Google Patents

Construction scene simulation display method and apparatus Download PDF

Info

Publication number
CN105243486A
CN105243486A CN201510642781.9A CN201510642781A CN105243486A CN 105243486 A CN105243486 A CN 105243486A CN 201510642781 A CN201510642781 A CN 201510642781A CN 105243486 A CN105243486 A CN 105243486A
Authority
CN
China
Prior art keywords
construction
time point
task
construction task
default
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510642781.9A
Other languages
Chinese (zh)
Inventor
方文
江春华
陈显龙
罗新伟
陈晓龙
杨志鹏
陈少坤
李坤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Forever Technology Co Ltd
Original Assignee
Beijing Forever Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Forever Technology Co Ltd filed Critical Beijing Forever Technology Co Ltd
Priority to CN201510642781.9A priority Critical patent/CN105243486A/en
Publication of CN105243486A publication Critical patent/CN105243486A/en
Pending legal-status Critical Current

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present application provides an embodiment of a construction scene simulation display method. If a user wants to view the construction situation of a construction project at a certain time node, a display instruction can be triggered, so that a display time point of the instruction is acquired by the embodiment; in a pre-stored construction task, a construction task between a preset construction start time point and the display time point is searched; and in a model base, a building model of the construction task is searched, so that the found building model is placed in a display interface and a simulation scene graph of construction is acquired, wherein the simulation scene graph is used for a user to know the construction schedule situation of the construction project at a certain time node. This display manner is more vivid and more specific. In addition, the present application further provides an embodiment of a construction scene simulation display apparatus, which is used for ensuring application and implementation of the method embodiment in practice.

Description

The simulation shows method of construction scene and device
Technical field
The application relates to image shows technical field, more specifically, is simulation shows method and the device of construction scene.
Background technology
Construction projects, is in order to the actual demand of producing of living, and builds the process of certain architectural object.Such as, in order to need for electricity, build a power plant.Normally, construction projects is a long process, and in this process, architectural object progressively completes construction.At different timing nodes, the performance of architectural object is different, and monitor staff needs the building situation of checking certain timing node, specifically to understand construction speed.
At present, the construction situation of different construction stage is recorded in construction form, and monitor staff needs to check construction form, understands the completion situation of architectural object.
Summary of the invention
In view of this, this application provides a kind of simulation shows method of scene of constructing, in order to visual pattern ground exhibition building condition of construction.In addition, present invention also provides a kind of simulation shows device of scene of constructing, in order to ensure the application in practice of described method and realization.
For realizing described object, the technical scheme that the application provides is as follows:
The first aspect of the application provides a kind of simulation shows method of scene of constructing, and comprising:
In response to the displaying instruction that user triggers, obtain the displaying time point in described displaying instruction;
In multiple default construction task, determine to preset the target construction task started between engineering time point to described displaying time point;
In the model bank pre-set, determine each self-corresponding BUILDINGS MODELS of each described target construction task; Wherein, described BUILDINGS MODELS for using 3-D view, simulated target construction task build architectural object;
In default displaying interface, according to each described BUILDINGS MODELS position placement regulation separately, put construction model described in each, obtain construction simulation scene.
The second aspect of the application provides a kind of simulation shows device of scene of constructing, and comprising:
Show time point acquisition module, for the displaying instruction triggered in response to user, obtain the displaying time point in described displaying instruction;
Construction task determination module, in multiple default construction task, determines to preset the target construction task started between engineering time point to described displaying time point;
BUILDINGS MODELS determination module, in the model bank pre-set, determines each self-corresponding BUILDINGS MODELS of each described target construction task; Wherein, described BUILDINGS MODELS for using 3-D view, simulated target construction task build architectural object;
BUILDINGS MODELS display module, in default displaying interface, according to each described BUILDINGS MODELS position placement regulation separately, puts construction model described in each, obtains construction simulation scene.
As known from the above, the application has following beneficial effect:
This application provides a kind of simulation shows embodiment of the method for scene of constructing, if user wants to check that construction project is when the condition of construction of certain timing node, displaying instruction can be triggered, the present embodiment just obtains the displaying time point in instruction, in the construction task prestored, search the construction task preset and start engineering time point and show between time point, and in model bank, search the BUILDINGS MODELS of construction task, and then the BUILDINGS MODELS found is placed in displaying interface, obtain the simulated scenario figure of construction, simulated scenario figure understands the construction speed situation of construction project at certain timing node for user, this kind of exhibition method visual pattern more.
Accompanying drawing explanation
In order to be illustrated more clearly in the embodiment of the present application or technical scheme of the prior art, be briefly described to the accompanying drawing used required in embodiment or description of the prior art below, apparently, accompanying drawing in the following describes is only the embodiment of the application, for those of ordinary skill in the art, under the prerequisite not paying creative work, other accompanying drawing can also be obtained according to the accompanying drawing provided.
The process flow diagram of the simulation shows embodiment of the method 1 of the construction scene that Fig. 1 provides for the application;
The process flow diagram of the simulation shows embodiment of the method 2 of the construction scene that Fig. 2 provides for the application;
The structural representation of the simulation shows device embodiment 1 of the construction scene that Fig. 3 provides for the application;
The structural representation of the simulation shows device embodiment 2 of the construction scene that Fig. 4 provides for the application.
Embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present application, be clearly and completely described the technical scheme in the embodiment of the present application, obviously, described embodiment is only some embodiments of the present application, instead of whole embodiments.Based on the embodiment in the application, those of ordinary skill in the art are not making the every other embodiment obtained under creative work prerequisite, all belong to the scope of the application's protection.
See Fig. 1, it illustrates the flow process of the simulation shows embodiment of the method 1 of the construction scene that the application provides.As shown in Figure 1, the present embodiment can specifically comprise step S101 ~ step S104.
Step S101: the displaying instruction triggered in response to user, obtains the displaying time point shown in instruction.
Wherein, the construction of engineering project is a long-term process, and conveniently engineering staff understands construction speed, the time point that the present embodiment can be selected according to user, for user shows the simulated scenario figure of corresponding construction speed.
Particularly, if when user wants the scene graph checking certain timing node, displaying operation can being triggered, showing icon as clicked.Certainly, before displaying, user needs input to show time point, and input mode can be multiple, such as, manual keyboard point input time, or, conveniently user input, can in inputting interface displaying time node option, user selects corresponding timing node.
Such as, the timing node option shown in interface comprises: first week, second week, the 3rd week etc.If when user wants the scene graph checking certain timing node, can select this timing node option, the timing node that user selects by the present embodiment is as displaying time point.Certainly, user inputs and shows that the mode of time point is not limited thereto.
Step S102: in multiple default construction task, determines to preset the target construction task started between engineering time point to displaying time point.
It is appreciated that construction project is generally a comparatively long-term process, in order to guarantee to finish on schedule, generally a complete construction project can be divided into multiple construction task.Such as, power plant construction comprises land development, and land development, for building factory building, can be divided into and move mountain, level land, undermines, build multiple construction tasks such as enclosure wall.
The present embodiment is before enforcement, and can prestore multiple construction task (mode storing construction task can be the mark or the title that store construction task), each construction task has each self-corresponding time point.It should be noted that, application scenarios is different, and the type of the time point that construction task is corresponding is also different.。
Particularly, in actual applications, construction task can be any one in following two kinds: the construction task of plan and actual construction task.Wherein, the construction task of plan has Estimated Time Of Completion point, is applied in user and wants to check in the scene of preplanned construction speed; Actual construction task has actual finish time point, is applied in user and wants to check in the scene of actual construction speed.Below can be described in detail to the application scenarios of different construction task, not repeat herein.
Above-mentioned steps S101 can get displaying time point, construction project has default beginning engineering time point, therefore, and time point that can be corresponding according to construction task, in the multiple construction tasks stored, search default sart point in time and show the construction task between time point.For convenience of description, the construction task found is called target construction task.
Such as, the default beginning engineering time point of construction project is on May 5th, 2015, and the displaying time point of user's input is on September 14th, 2015, therefore, can search time point construction task during this period.
As described above, the present embodiment can be user's displaying time node option, and user can select certain timing node option as displaying time point.Wherein, for the timing node option of user's display can be periodic formation, now, show that time point can be then the last day in the cycle that user selects.
Such as, the default beginning engineering time point of the present embodiment is on May 1st, 2015, the timing node option shown in interface is: first week, multiple cycle options such as second week, user selects this cycle options of second week, then show that time point is the last day of the second week from 1 day May in 2015.
After using above-mentioned any one mode to determine displaying time point, just according to default beginning engineering time point and time point can be shown, search target construction task.
Step S103: in the model bank pre-set, determines each self-corresponding BUILDINGS MODELS of each target construction task; Wherein, BUILDINGS MODELS for using 3-D view, simulated target construction task build architectural object.
Before enforcement, for each construction task arranges each self-corresponding BUILDINGS MODELS, BUILDINGS MODELS uses the three-dimensional model diagram drawn as CAD drawing instrument of drawing instrument, is used for the architectural object of construction after the completion of construction simulation task.Such as, construction task, for moving mountain, is removed by certain mountain, then can draw a mountain model, and the lines of this mountain model can be dotted line, are removed in process of construction to point out this massif of beholder.And for example, construction task for building enclosure wall, then can draw a Wall model.
The model drawn is kept in model bank, after finding target construction task, in this model bank, can search the BUILDINGS MODELS corresponding to each target construction task further.
Step S104: in default displaying interface, according to each BUILDINGS MODELS position placement regulation separately, puts each construction model, obtains construction simulation scene.
Wherein, after finding BUILDINGS MODELS, in default displaying interface, these model group are combined into construction simulation scene.Particularly, each BUILDINGS MODELS has respective placement regulation, such as, BUILDINGS MODELS has respective three-dimensional location coordinates value, in displaying interface, according to three-dimensional location coordinates value, put each BUILDINGS MODELS, be combined as a complete construction simulation scene to make BUILDINGS MODELS.
By this construction simulation scene of showing, check that user can understand the condition of construction of construction project at certain timing node.Such as, the construction simulation scene of combination comprises mountain model, foundation model, then represent at this displaying time point, and construction project completes and moves mountain task and the task that undermines.
From above technical scheme, this application provides a kind of simulation shows embodiment of the method for scene of constructing, if user wants to check that construction project is when the condition of construction of certain timing node, displaying instruction can be triggered, the present embodiment just obtains the displaying time point in instruction, in the construction task prestored, search the construction task preset and start engineering time point and show between time point, and in model bank, search the BUILDINGS MODELS of construction task, and then the BUILDINGS MODELS found is placed in displaying interface, obtain the simulated scenario figure of construction, simulated scenario figure understands the construction speed situation of construction project at certain timing node for user, this kind of exhibition method is more specifically vivid.
In actual applications, a kind of embody rule scene of above embodiment is, shows the expectation progress of construction project.In this application scenarios, construction task has Estimated Time Of Completion point, before construction, for each construction task arranges respective Estimated Time Of Completion point.Such as, the Estimated Time Of Completion point of this construction task that undermines is on May 25th, 2015.
Correspondingly, in above embodiment, the specific implementation of step S102 (in multiple default construction task, determining to estimate to start engineering time point to the target construction task of showing between time point) comprises steps A 1.
Steps A 1: in multiple default construction task, searches the construction task of point of default deadline between default beginning engineering time point to displaying time point, the construction task found is defined as target construction task.
In this kind of implementation, each construction task has Estimated Time Of Completion point, and when searching, deadline point, searches target construction task according to expectation.
Certainly, in practice of construction process, according to the actual performance of each construction task, for each construction task arranges respective actual finish time point.Particularly, construction task can comprise one or more construction procedure, and construction monitoring personnel after each construction procedure completes, just can mark this construction procedure.The mode of mark can be pictorial symbolization or word marking, and such as, this construction procedure graph of a correspondence, in mark interface, is revised as " √ " by "×" by construction monitoring personnel.
Therefore, the setting steps presetting the actual finish time point of construction task can specifically comprise:
Mark the operation of construction procedure in response to user, whether the construction procedure of judge mark is last construction procedure; If so, using the actual finish time point of time point corresponding for marking operation as construction task.
Wherein, construction monitoring personnel are when monitoring certain construction procedure and completing, can mark this construction procedure, therefore, whether this construction procedure of judge mark is last construction procedure of corresponding construction task, if the time point of then recording mark operation, is defined as the deadline time point of this construction task by this time point.
Such as, this construction task that undermines comprises three construction procedures, is respectively to dig pit, build, beat base.The time point that construction monitoring worker labels beats this construction procedure of base is on May 20th, 2015, then the actual finish time point of this construction task of determining to undermine is on May 20th, 2015.
Correspondingly, in above embodiment, the specific implementation of step S102 (in multiple default construction task, determining to estimate to start engineering time point to the target construction task of showing between time point) comprises step B1.
Step B1: in multiple default construction task, searches the construction task of actual finish time point between default beginning engineering time point to displaying time point, the construction task found is defined as target construction task.
In this kind of implementation, each construction task has actual finish time point, when searching, according to actual finish time point, searches target construction task.
In force, user only checks simulated scenario situation, also thinks the completion information understanding construction task further.Therefore, see Fig. 2, this application provides the flow process of the simulation shows embodiment of the method 2 of construction scene.As shown in Figure 2, the present embodiment can specifically comprise step S201 ~ step S205.It should be noted that, the step S201 in the present embodiment ~ step S204 see the explanation of above-mentioned steps S101 ~ step S104, can not repeat herein, is only described step S205 below.
Step S205: operate the selection of certain BUILDINGS MODELS in response to user, obtains the construction information of the BUILDINGS MODELS selected and shows.
Wherein, can the construction information that produces in work progress of certain (a bit) construction task pre-recorded, as the material, person in charge etc. of construction start time and closing time, use.Certainly, this little construction information only example illustrates, the application is not limited thereto.
User in construction simulation scene graph, can select certain BUILDINGS MODELS, such as, clicks selection, or mouse-over is selected.After user selects BUILDINGS MODELS, the present embodiment just obtains the construction information of this BUILDINGS MODELS, and is presented in interface, such as, is presented at the side of this BUILDINGS MODELS.
In actual applications, can there is following characteristics in the BUILDINGS MODELS comprised in model bank, namely has the different construction tasks of same characteristic features data, and corresponding BUILDINGS MODELS can be relation of inclusion.
Particularly, mark can be set for the construction task with same characteristic features data, and mark the relation of inclusion between each construction task.Thus, in multiple construction task, when finding the construction task with same characteristic features data, only last construction task can be defined as target construction task, thus only load BUILDINGS MODELS corresponding to this last construction task.
Such as, construction task 1 is build the wall that floorage is a, height is 1.5m, and construction task 2 is the wall of adding a cover 0.5m on the basis of 1.5m.Wherein, if the BUILDINGS MODELS of construction task 1 is floorage is a, the high body of wall for 1.5m, the BUILDINGS MODELS of construction task 2 is floorage is a, the high body of wall for 0.5m.Like this, during exhibition building model scene, need the Wall model of loading more, loading velocity is slower.
Therefore, in order to accelerate loading velocity, thus improve displaying efficiency, the BUILDINGS MODELS of construction task 2 can comprise the model of construction task 1, and namely the model of construction task 2 is floorage is a, the high body of wall for 2m.Like this, when determining target construction task, only determine that construction task 2 is as target construction task, thus only load the BUILDINGS MODELS of construction task 2, show speed.
Below the simulation shows device of the construction scene that the application provides is introduced, it should be noted that, about the explanation of construction scenario simulation exhibiting device see construction scenario simulation methods of exhibiting above, can not repeat below.
See Fig. 3, it illustrates the structure of the simulation shows device embodiment 1 of construction scene.As shown in Figure 3, the present embodiment can specifically comprise: show time point acquisition module 301, construction task determination module 302, BUILDINGS MODELS determination module 303 and BUILDINGS MODELS display module 304; Wherein:
Show time point acquisition module 301, for the displaying instruction triggered in response to user, obtain the displaying time point shown in instruction;
Construction task determination module 302, in multiple default construction task, determines to preset the target construction task started between engineering time point to displaying time point;
BUILDINGS MODELS determination module 303, in the model bank pre-set, determines each self-corresponding BUILDINGS MODELS of each target construction task; Wherein, BUILDINGS MODELS for using 3-D view, simulated target construction task build architectural object;
BUILDINGS MODELS display module 304, in default displaying interface, according to each BUILDINGS MODELS position placement regulation separately, puts each construction model, obtains construction simulation scene.
In actual applications, each default construction task has respective actual finish time point; Correspondingly, construction task determination module 302 can specifically comprise: first determines submodule; Wherein:
First determines submodule, in multiple default construction task, searches the construction task of actual finish time point between default beginning engineering time point to displaying time point, the construction task found is defined as target construction task.
Wherein, default construction task comprises at least one construction procedure; Correspondingly, this device also comprises:
Actual finish time generation module, for marking the operation of construction procedure in response to user, whether the construction procedure of judge mark is last construction procedure at least one construction procedure; If so, using the actual finish time point of time point corresponding for marking operation as construction task.
Or in actual applications, each default construction task has respective Estimated Time Of Completion point; Correspondingly, construction task determination module 302 can specifically comprise: second determines submodule; Wherein:
Second determines submodule, in multiple default construction task, searches the construction task of point of default deadline between default beginning engineering time point to displaying time point, the construction task found is defined as target construction task.
See Fig. 4, this application provides the structure of the simulation shows device embodiment 2 of construction scene.As shown in Figure 4, the present embodiment, on the basis of embodiment 1, can also comprise: construction information display module 305.
Construction information display module 305, for operating the selection of certain BUILDINGS MODELS in response to user, obtaining the construction information of the BUILDINGS MODELS selected and showing.
It should be noted that, each embodiment in this instructions all adopts the mode of going forward one by one to describe, and what each embodiment stressed is the difference with other embodiments, between each embodiment identical similar part mutually see.
Also it should be noted that, in this article, the such as relational terms of first and second grades and so on is only used for an entity or operation to separate with another entity or operational zone, and not necessarily requires or imply the relation that there is any this reality between these entities or operation or sequentially.And, term " comprises ", " comprising " or its any other variant are intended to contain comprising of nonexcludability, thus make to comprise the process of a series of key element, method, article or equipment and not only comprise those key elements, but also comprise other key elements clearly do not listed, or also comprise by the intrinsic key element of this process, method, article or equipment.When not more restrictions, the key element limited by statement " comprising ... ", and be not precluded within process, method, article or the equipment comprising above-mentioned key element and also there is other identical element.
To the above-mentioned explanation of the disclosed embodiments, professional and technical personnel in the field are realized or uses the application.To be apparent for those skilled in the art to the multiple amendment of these embodiments, General Principle as defined herein when not departing from the spirit or scope of the application, can realize in other embodiments.Therefore, the application can not be restricted to these embodiments shown in this article, but will meet the widest scope consistent with principle disclosed herein and features of novelty.

Claims (10)

1. a simulation shows method for scene of constructing, is characterized in that, comprising:
In response to the displaying instruction that user triggers, obtain the displaying time point in described displaying instruction;
In multiple default construction task, determine to preset the target construction task started between engineering time point to described displaying time point;
In the model bank pre-set, determine each self-corresponding BUILDINGS MODELS of each described target construction task; Wherein, described BUILDINGS MODELS for using 3-D view, simulated target construction task build architectural object;
In default displaying interface, according to each described BUILDINGS MODELS position placement regulation separately, put construction model described in each, obtain construction simulation scene.
2. the simulation shows method of construction scene according to claim 1, is characterized in that, each described default construction task has respective actual finish time point;
Correspondingly, described in multiple default construction task, determine to preset the target construction task started between engineering time point to described displaying time point, comprising:
In multiple default construction task, search the construction task of actual finish time point between default beginning engineering time point to described displaying time point, the construction task found is defined as target construction task.
3. the simulation shows method of construction scene according to claim 2, is characterized in that, default construction task comprises at least one construction procedure; Correspondingly, the generation step presetting the actual finish time point of construction task comprises:
Mark the operation of construction procedure in response to user, whether the described construction procedure of judge mark is last construction procedure at least one construction procedure described;
If so, using the actual finish time point of time point corresponding for marking operation as described construction task.
4. the simulation shows method of construction scene according to claim 1, is characterized in that, each described default construction task has respective Estimated Time Of Completion point;
Correspondingly, described in multiple default construction task, determine to estimate to start the target construction task between engineering time point to described displaying time point, comprising:
In multiple default construction task, search the construction task of point of default deadline between default beginning engineering time point to described displaying time point, the construction task found is defined as target construction task.
5. the simulation shows method of construction scene according to claim 1, is characterized in that, also comprise:
In response to user, the selection of BUILDINGS MODELS described in certain is operated, obtain the construction information of the described BUILDINGS MODELS selected and show.
6. a simulation shows device for scene of constructing, is characterized in that, comprising:
Show time point acquisition module, for the displaying instruction triggered in response to user, obtain the displaying time point in described displaying instruction;
Construction task determination module, in multiple default construction task, determines to preset the target construction task started between engineering time point to described displaying time point;
BUILDINGS MODELS determination module, in the model bank pre-set, determines each self-corresponding BUILDINGS MODELS of each described target construction task; Wherein, described BUILDINGS MODELS for using 3-D view, simulated target construction task build architectural object;
BUILDINGS MODELS display module, in default displaying interface, according to each described BUILDINGS MODELS position placement regulation separately, puts construction model described in each, obtains construction simulation scene.
7. the simulation shows device of construction scene according to claim 6, is characterized in that, each described default construction task has respective actual finish time point;
Correspondingly, described construction task determination module comprises:
First determines submodule, in multiple default construction task, searches the construction task of actual finish time point between default beginning engineering time point to described displaying time point, the construction task found is defined as target construction task.
8. the simulation shows device of construction scene according to claim 7, is characterized in that, default construction task comprises at least one construction procedure; Correspondingly, this device also comprises:
Actual finish time generation module, for marking the operation of construction procedure in response to user, whether the described construction procedure of judge mark is last construction procedure at least one construction procedure described; If so, using the actual finish time point of time point corresponding for marking operation as described construction task.
9. the simulation shows device of construction scene according to claim 6, is characterized in that, each described default construction task has respective Estimated Time Of Completion point;
Correspondingly, described construction task determination module comprises:
Second determines submodule, in multiple default construction task, searches the construction task of point of default deadline between default beginning engineering time point to described displaying time point, the construction task found is defined as target construction task.
10. the simulation shows device of construction scene according to claim 6, is characterized in that, also comprise: construction information display module;
Described construction information display module, for operating the selection of BUILDINGS MODELS described in certain in response to user, obtaining the construction information of the described BUILDINGS MODELS selected and showing.
CN201510642781.9A 2015-09-30 2015-09-30 Construction scene simulation display method and apparatus Pending CN105243486A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510642781.9A CN105243486A (en) 2015-09-30 2015-09-30 Construction scene simulation display method and apparatus

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510642781.9A CN105243486A (en) 2015-09-30 2015-09-30 Construction scene simulation display method and apparatus

Publications (1)

Publication Number Publication Date
CN105243486A true CN105243486A (en) 2016-01-13

Family

ID=55041123

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510642781.9A Pending CN105243486A (en) 2015-09-30 2015-09-30 Construction scene simulation display method and apparatus

Country Status (1)

Country Link
CN (1) CN105243486A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107797824A (en) * 2017-11-08 2018-03-13 北京恒华伟业科技股份有限公司 A kind of project progress methods of exhibiting and device
CN111145354A (en) * 2019-12-31 2020-05-12 北京恒华伟业科技股份有限公司 BIM data model identification method and device
CN115408550A (en) * 2022-11-01 2022-11-29 深圳市睿拓新科技有限公司 Data platform based visual project progress display method and equipment

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101009001A (en) * 2006-12-14 2007-08-01 中国核工业第二三建设公司 Method and system for implementing four-dimensional visualization of engineering model
CN104166892A (en) * 2014-06-19 2014-11-26 国家电网公司 Engineering management and control method and system based on three-dimensional design system

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101009001A (en) * 2006-12-14 2007-08-01 中国核工业第二三建设公司 Method and system for implementing four-dimensional visualization of engineering model
CN104166892A (en) * 2014-06-19 2014-11-26 国家电网公司 Engineering management and control method and system based on three-dimensional design system

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
金丹 等: "桥梁施工进度的三维可视化管理", 《计算机应用与软件》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107797824A (en) * 2017-11-08 2018-03-13 北京恒华伟业科技股份有限公司 A kind of project progress methods of exhibiting and device
CN111145354A (en) * 2019-12-31 2020-05-12 北京恒华伟业科技股份有限公司 BIM data model identification method and device
CN111145354B (en) * 2019-12-31 2024-02-13 北京恒华伟业科技股份有限公司 BIM data model identification method and device
CN115408550A (en) * 2022-11-01 2022-11-29 深圳市睿拓新科技有限公司 Data platform based visual project progress display method and equipment

Similar Documents

Publication Publication Date Title
Banfi et al. Extended reality and informative models for the architectural heritage: from scan-to-BIM process to virtual and augmented reality
CN111382214B (en) Comprehensive pipe rack operation and maintenance management system based on 3DGIS BIM
KR102017075B1 (en) the virtual reality simulation platform based BIM data and the virtual reality simulation method using the same
KR101603622B1 (en) System and method for utilizing authoring tool of bim integrated design
CN105243486A (en) Construction scene simulation display method and apparatus
KR20130016620A (en) 3d process management method for bim(building information modeling)
CN113239543A (en) Digital factory simulation system based on virtual reality technology
Logothetis et al. From OSS CAD to BIM for cultural heritage digital representation
CN104537043A (en) Oblique modeling data based two and three dimensional integration method and system
Balogh et al. CodeMetropolis-code visualisation in MineCraft
CN108520102A (en) A kind of facing based on BIM build fast method of construction
CN108228962B (en) BIM-based foundation pit peripheral wall inclinometry generating method
CN116304245A (en) Dam safety monitoring result visualization system and generation method thereof
CN107729616A (en) Fire protection pipeline design system, design method, electronic equipment and computer program product based on Sketchup
Fassi et al. Complex architecture in 3D: from survey to web
Alam et al. EvoSpaces: 3D Visualization of Software Architecture.
Tsai et al. Integration of BIM and GIS to query management on pipeline of building-a case study of dormitory
Lucarelli et al. BEP & mapping process for the restoration building site
CN107066717A (en) Based on three-dimensional virtual scene engineering machinery layout method and system
Marzouk et al. A hybrid model for selecting location of mobile cranes in bridge construction projects
Pauditšová et al. Modelling as a platform for landscape planning
Mahulea et al. Matlab tools for Petri-net-based approaches to flexible manufacturing systems
Fernández et al. Prevention of occupational risks in geotechnical drilling works through virtual reality training
Banfi Modelli dinamici interattivi per il patrimonio costruito
CN111191930A (en) Method for displaying combination among multiple mind maps, electronic device and storage medium

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20160113

RJ01 Rejection of invention patent application after publication