CN105226830A CN201510728989.2A CN201510728989A CN105226830A CN 105226830 A CN105226830 A CN 105226830A CN 201510728989 A CN201510728989 A CN 201510728989A CN 105226830 A CN105226830 A CN 105226830A
Authority
CN
China
Prior art keywords
frame
transmitting time
file
goose
simulation test
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510728989.2A
Other languages
Chinese (zh)
Other versions
CN105226830B (en
Inventor
杨国涛
程先锐
郝雨
宗翔
刘涛
陈腾渊
罗东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Liuan Power Supply Co of State Grid Anhui Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Liuan Power Supply Co of State Grid Anhui Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Liuan Power Supply Co of State Grid Anhui Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201510728989.2A priority Critical patent/CN105226830B/en
Publication of CN105226830A publication Critical patent/CN105226830A/en
Application granted granted Critical
Publication of CN105226830B publication Critical patent/CN105226830B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E60/00Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The present invention relates to a kind of transformer station process layer for dynamic simulation test and wall communication data back method, compared with prior art solve the defect cannot accomplishing data readback in dynamic simulation test process.The present invention includes following steps: generate new file; Configuration file; Formation sequence; Calculate transmitting time; Calculating takies Link Time; Calculate actual transmitting time; Spanned file; Playback file.The dynamic simulation test recorder data that the present invention will preserve with electric power system standard C OMTRADE file, convert to comprise and meet DL/T? do you the SV frame of 860.92 standards, meet DL/T? the pcap file of 860.8 standard GOOSE frames, and by network tester playback above-mentioned pcap file, implementation procedure layer and wall emulation testing.

Description

A kind of transformer station process layer for dynamic simulation test and wall communication data back method
Technical field
The present invention relates to relay protection of power system technical field of measurement and test, specifically a kind of transformer station process layer for dynamic simulation test and wall communication data back method.
Background technology
Dynamic simulation test refer to scaled down with the experimental study carried out in the pure physical model system of real system equivalence and simulation test system, simulation test system comprises generator, transformer, power transmission line circuit, line switching, current-voltage transformer, intelligent secondary device and control system, and be directly connected with practical power systems is grid-connected, the model system set up is simulated various operating condition and the fault of practical power systems.By current transformer, voltage transformer and MU acquisition system current and voltage signals, can be used for intelligent substation intelligence secondary device (IED) function and performance verify and examine.The requirement of dynamic simulation test to testing equipment and test site is higher, and the test period is long, drop into manpower and funds are comparatively large, and the domestic laboratory possessing dynamic simulation test ability is less at present, resource scarcity.Each to record a large amount of test data of ripple mode record in dynamic simulation test process, have recorded the voltage in process of the test, electric current, switching value information.If the recorder data of dynamic simulation test can be made full use of with wave shape playback form, namely realize the playback of data, then can realize the research and development inspection to secondary device and checking effect.Particularly between process layer and wall, developing a data readback method in dynamic simulation test has become the technical problem being badly in need of solving.
Summary of the invention
The object of the invention is to solve the defect cannot accomplishing data readback in prior art in dynamic simulation test process, providing a kind of transformer station process layer for dynamic simulation test and wall communication data back method to solve the problems referred to above.
To achieve these goals, technical scheme of the present invention is as follows:
For transformer station process layer and the wall communication data back method of dynamic simulation test, comprise the following steps:
Generate new file, according to the requirement of secondary equipment of intelligent converting station to sample rate, adopt interpolation algorithm the sample frequency of the analog quantity in original COMTRADE file to be converted to the sample frequency of secondary equipment of intelligent converting station needs, generate new COMTRADE convert file;
Configuration file, the analog quantity channel in COMTRADE convert file associates with SV passage by the configuration according to inputting SV controll block in secondary equipment of intelligent converting station; COMTRADE convert file breaker in middle amount passage associates with GOOSE passage by the configuration according to the input GOOSE controll block of secondary equipment of intelligent converting station;
Formation sequence, to each input SV controll block of secondary equipment of intelligent converting station, generates the SV frame sequence meeting DL/T860.92 standard, and calculates the desirable transmitting time of each SV frame;
Calculate transmitting time, to each GOOSE controll block of secondary equipment of intelligent converting station, according to switching value passage and the incidence relation of GOOSE passage, the change of switching value, according to GOOSE transmit mechanism, generate GOOSE frame sequence, and calculate the desirable transmitting time of each GOOSE frame;
Calculating takies Link Time, to each SV frame or GOOSE frame, calculates it and takies Link Time;
Calculate actual transmitting time, the SV frame that will input each light network interface of secondary equipment of intelligent converting station, GOOSE frame all sort, and calculate its actual transmitting time;
Spanned file, according to ordering SV frame, GOOSE frame and actual transmitting time thereof, generates pcap file;
Playback file, utilizes network tester to carry out playback to pcap file.
The actual transmitting time of described calculating comprises the following steps:
Variable t is set, makes t=0;
SV frame, GOOSE frame are all labeled as unsorted;
The frame finding desirable transmitting time minimum in unsorted SV frame, GOOSE frame, by this frame flag for sort; If there are two frames that desirable transmitting time is identical, then an optional frame flag is for sort, and by its desirable transmitting time assignment to variable t;
Relatively other unsorted SV frames, the desirable transmitting time of GOOSE frame and the size of t, if the desirable transmitting time of this frame is less than t, then the actual transmitting time arranging this frame is t, and the currency making the value of t equal t adds that this frame takies Link Time;
If the desirable transmitting time of this frame is more than or equal to t, then the actual transmitting time arranging this frame is the desirable transmitting time of this frame, and the actual transmitting time making the value of t equal this frame adds that this frame takies Link Time.
beneficial effect
A kind of transformer station process layer for dynamic simulation test of the present invention and wall communication data back method, the dynamic simulation test recorder data compared with prior art will preserved with electric power system standard C OMTRADE file, convert to and comprise the SV frame meeting DL/T860.92 standard, the pcap file meeting DL/T860.8 standard GOOSE frame, and by network tester playback above-mentioned pcap file, implementation procedure layer and wall emulation testing.The present invention only needs network tester, and not by the restriction of place to use test resource, utilize existing dynamic simulation test data to realize dynamic simulation test verification the verifying results, can complete the emulation testing of IED, experimentation cost greatly reduces.
The recorder data of dynamic simulation test makes full use of with wave shape playback form by the present invention, does not need complexity, huge dynamic simulation test environment can complete the emulation testing of IED; The dynamic simulation test data transaction stored with COMTRADE file is become general pcap file, only needs network tester, not by the restriction of place to use test resource, experimentation cost greatly reduces; Solve by the problem of the concurrent data in COMTRADE file to the conversion of the serial data in pcap file.
Accompanying drawing explanation
Fig. 1 is sequential flowchart of the present invention.
Embodiment
For making to have a better understanding and awareness architectural feature of the present invention and effect of reaching, coordinating detailed description in order to preferred embodiment and accompanying drawing, being described as follows:
As shown in Figure 1, a kind of transformer station process layer for dynamic simulation test of the present invention and wall communication data back method, comprise the following steps:
The first step, generates new file.According to the requirement of secondary equipment of intelligent converting station to sample rate, adopt interpolation algorithm the sample frequency of the analog quantity in original COMTRADE file to be converted to the sample frequency of secondary equipment of intelligent converting station needs, generate new COMTRADE convert file.New COMTRADE convert file is similarly COMTRADE file, for providing of basic data information in data readback process.
Second step, configuration file.Analog quantity channel in COMTRADE convert file associates with SV passage by the configuration according to inputting SV controll block in secondary equipment of intelligent converting station.COMTRADE convert file breaker in middle amount passage associates with GOOSE passage by the configuration according to the input GOOSE controll block of secondary equipment of intelligent converting station.
GOOSE(GenericObject-OrientedSubstationEvent) be a kind of transformer substation case towards general object, be mainly used in realizing the information transmission between multiple secondary equipment of intelligent converting station (IED), comprise the multi-signal (order) such as transmission breaker tripping and closing, connection locking, there is the high-transmission probability of success.SV (SampledValue) i.e. sampled value, it exchanges correlation model object and the service of the sampled value that sampled data is concentrated based on publish/subscribe mechanism, and the mapping between these model objects and service to ISO/IEC8802-3 frame.
3rd step, formation sequence.To each input SV controll block of secondary equipment of intelligent converting station, generate the SV frame sequence meeting DL/T860.92 standard, and calculate the desirable transmitting time of each SV frame, the desirable transmitting time of SV frame is for coordinating the calculating of actual transmitting time.
4th step, calculates transmitting time.To each GOOSE controll block of secondary equipment of intelligent converting station, according to switching value passage and the incidence relation of GOOSE passage, the change of switching value, according to GOOSE transmit mechanism, generate GOOSE frame sequence, and calculate the desirable transmitting time of each GOOSE frame, equally, the desirable transmitting time of calculating GOOSE frame is also the calculating for coordinating actual transmitting time.
5th step, calculates and takies Link Time, to each SV frame or GOOSE frame, calculate it and take Link Time, and calculating the object taking Link Time is also calculating in order to coordinate actual transmitting time.
6th step, calculates actual transmitting time, and the SV frame that will input each light network interface of secondary equipment of intelligent converting station, GOOSE frame all sort, and calculate its actual transmitting time.It specifically comprises the following steps:
(1) variable t is set, makes t=0.
(2) SV frame, GOOSE frame are all labeled as unsorted state.
(3) frame finding desirable transmitting time minimum in unsorted SV frame, GOOSE frame, by this frame flag for sort; If there are two frames that desirable transmitting time is identical, then an optional frame flag is for sort, and by its desirable transmitting time assignment to variable t.
(4) compare other all unsorted SV frames, the desirable transmitting time of GOOSE frame and sizes of t, if the desirable transmitting time of this frame is less than t, then the actual transmitting time arranging this frame is t, and the currency making the value of t equal t adds that this frame takies Link Time.
If the desirable transmitting time of this frame is more than or equal to t, then the actual transmitting time arranging this frame is the desirable transmitting time of this frame, and the actual transmitting time making the value of t equal this frame adds that this frame takies Link Time.
Above calculating comparison process is all carried out to all unsorted SV frames, GOOSE frame, until complete sequence to all SV frames, GOOSE frame.
7th step, spanned file.According to ordering SV frame, GOOSE frame and actual transmitting time thereof, generate pcap file, this pcap file then comprise meet DL/T860.92 standard SV frame, meet DL/T860.8 standard GOOSE frame.
8th step, playback file.Utilize network tester to carry out playback to pcap file, use the pcap file playback function of network tester, playback is carried out to the pcap file generated, with the playback of implementation procedure layer and wall data (fault).
More than show and describe general principle of the present invention, principal character and advantage of the present invention.The technical staff of the industry should understand; the present invention is not restricted to the described embodiments; the just principle of the present invention described in above-described embodiment and specification; the present invention also has various changes and modifications without departing from the spirit and scope of the present invention, and these changes and improvements all fall in claimed scope of the present invention.The protection range of application claims is defined by appending claims and equivalent thereof.

Claims (2)

1., for transformer station process layer and the wall communication data back method of dynamic simulation test, it is characterized in that, comprise the following steps:
11) new file is generated, according to the requirement of secondary equipment of intelligent converting station to sample rate, adopt interpolation algorithm the sample frequency of the analog quantity in original COMTRADE file to be converted to the sample frequency of secondary equipment of intelligent converting station needs, generate new COMTRADE convert file;
12) configuration file, the analog quantity channel in COMTRADE convert file associates with SV passage by the configuration according to inputting SV controll block in secondary equipment of intelligent converting station; COMTRADE convert file breaker in middle amount passage associates with GOOSE passage by the configuration according to the input GOOSE controll block of secondary equipment of intelligent converting station;
13) formation sequence, to each input SV controll block of secondary equipment of intelligent converting station, generates the SV frame sequence meeting DL/T860.92 standard, and calculates the desirable transmitting time of each SV frame;
14) transmitting time is calculated, to each GOOSE controll block of secondary equipment of intelligent converting station, according to switching value passage and the incidence relation of GOOSE passage, the change of switching value, according to GOOSE transmit mechanism, generate GOOSE frame sequence, and calculate the desirable transmitting time of each GOOSE frame;
15) calculating takies Link Time, to each SV frame or GOOSE frame, calculates it and takies Link Time;
16) calculate actual transmitting time, the SV frame that will input each light network interface of secondary equipment of intelligent converting station, GOOSE frame all sort, and calculate its actual transmitting time;
17) spanned file, according to ordering SV frame, GOOSE frame and actual transmitting time thereof, generates pcap file;
18) playback file, utilizes network tester to carry out playback to pcap file.
2. a kind of transformer station process layer for dynamic simulation test according to claim 1 and wall communication data back method, it is characterized in that, the actual transmitting time of described calculating comprises the following steps:
21) variable t is set, makes t=0;
22) SV frame, GOOSE frame are all labeled as unsorted;
23) frame finding desirable transmitting time minimum in unsorted SV frame, GOOSE frame, by this frame flag for sort; If there are two frames that desirable transmitting time is identical, then an optional frame flag is for sort, and by its desirable transmitting time assignment to variable t;
24) compare other unsorted SV frames, the desirable transmitting time of GOOSE frame and the size of t, if the desirable transmitting time of this frame is less than t, then the actual transmitting time arranging this frame is t, and the currency making the value of t equal t adds that this frame takies Link Time;
If the desirable transmitting time of this frame is more than or equal to t, then the actual transmitting time arranging this frame is the desirable transmitting time of this frame, and the actual transmitting time making the value of t equal this frame adds that this frame takies Link Time.
CN201510728989.2A 2015-10-31 2015-10-31 A kind of transformer station process layer for dynamic simulation test and wall communication data back method Active CN105226830B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510728989.2A CN105226830B (en) 2015-10-31 2015-10-31 A kind of transformer station process layer for dynamic simulation test and wall communication data back method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510728989.2A CN105226830B (en) 2015-10-31 2015-10-31 A kind of transformer station process layer for dynamic simulation test and wall communication data back method

Publications (2)

Publication Number Publication Date
CN105226830A true CN105226830A (en) 2016-01-06
CN105226830B CN105226830B (en) 2018-01-26

Family

ID=54995616

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510728989.2A Active CN105226830B (en) 2015-10-31 2015-10-31 A kind of transformer station process layer for dynamic simulation test and wall communication data back method

Country Status (1)

Country Link
CN (1) CN105226830B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106855592A (en) * 2015-12-08 2017-06-16 中国电力科学研究院 A kind of dynamic simulation test records ripple message back method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102565585A (en) * 2012-01-10 2012-07-11 上海电力学院 Method for building intelligent substation relay protection cooperation simulation testing system
CN103019141A (en) * 2012-12-28 2013-04-03 成都天进科技有限公司 Control module, control method and electric power dynamic recording device and implementation method thereof
CN104539473A (en) * 2014-12-03 2015-04-22 广东电网有限责任公司茂名供电局 Whole-group verification method and system for network virtual secondary loop of intelligent substation

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102565585A (en) * 2012-01-10 2012-07-11 上海电力学院 Method for building intelligent substation relay protection cooperation simulation testing system
CN103019141A (en) * 2012-12-28 2013-04-03 成都天进科技有限公司 Control module, control method and electric power dynamic recording device and implementation method thereof
CN104539473A (en) * 2014-12-03 2015-04-22 广东电网有限责任公司茂名供电局 Whole-group verification method and system for network virtual secondary loop of intelligent substation

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
FAN W等: "Intelligent Data Analysis for Power Systems", 《IEEE POWER AND ENERGY SOCIETY GENERAL MEETING PESGM》 *
RANSOM D L等: "Using GOOSE Messages in a Main-Tie-Main Scheme", 《IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS》 *
徐岩等: "基于故障录波与保护信息融合的变电站故障分析系统开发", 《电力自动化设备》 *
郑煜: "基于IEC61850智能变电站数据分析关键技术研究", 《中国优秀硕士学位论文全文数据库 工程科技Ⅱ辑》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106855592A (en) * 2015-12-08 2017-06-16 中国电力科学研究院 A kind of dynamic simulation test records ripple message back method
CN106855592B (en) * 2015-12-08 2020-03-13 中国电力科学研究院 Dynamic simulation test wave recording message playback method

Also Published As

Publication number Publication date
CN105226830B (en) 2018-01-26

Similar Documents

Publication Publication Date Title
CN104734364B (en) The method and system of relay protection device of intelligent substation SV, GOOSE input test
CN108173263A (en) A kind of power distribution network topology error identification algorithm based on AMI measurement informations
CN102520288B (en) Primary-rising based current differential protection synchronization performance testing system and testing method
WO2014108002A1 (en) Detection method and system of intelligent relay protection device
CN108683180B (en) Three-phase low-voltage power distribution network topology reconstruction method
JP2018081299A (en) Dynamic dispatcher training simulator
Aslan An alternative approach to fault location on power distribution feeders with embedded remote-end power generation using artificial neural networks
CN105159273A (en) System testing method of power grid distributed stability control devices
CN110161326A (en) A kind of more network live nuclear-phase methods and system at a distance
CN103954925A (en) Fault recorder dynamic testing method based on RTDS real-time simulation
Silos-Sanchez et al. Novel fault location algorithm for meshed distribution networks with DERs
CN103869192A (en) Smart power grid line loss detection method and system
CN105093017A (en) Integrated GOOSE tester of intelligent transformer station and test method of tester
CN103676669B (en) The check method of a kind of telecontrol information and nucleus correcting system
Hacker et al. A framework to evaluate multi-use flexibility concepts simultaneously in a co-simulation environment and a cyber-physical laboratory.
CN105226830A (en) A kind of transformer station process layer for dynamic simulation test and wall communication data back method
CN103645392A (en) Method for realizing device test protection through recording and playback
CN116561941A (en) SCD virtual loop template model and modeling and application method thereof
Sahoo Recent trends and advances in power quality
CN104461627A (en) Importing method of intelligent substation testing equipment SV and GOOSE configuration parameters
CN113177717B (en) Quick evaluation method for toughness of power transmission system based on influence increment sensitivity
CN105044517A (en) Intelligent transformer station protection vector diagnosis method based on trend characteristic value
CN104408665A (en) Event-oriented disturbance data processing system based on SCD model
CN106841842A (en) The method of testing and device in the empty loop of secondary device
Ponci et al. Instrumentation and measurement testing in the real-time lab for automation of complex power systems

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CB03 Change of inventor or designer information

Inventor after: Yang Guotao

Inventor after: Li Bao

Inventor after: Cheng Xianrui

Inventor after: Hao Yu

Inventor after: Zong Xiang

Inventor after: Liu Tao

Inventor after: Chen Tengyuan

Inventor after: Luo Dong

Inventor after: Xu Bin

Inventor after: Ding Qian

Inventor before: Yang Guotao

Inventor before: Cheng Xianrui