CN106841842A - The method of testing and device in the empty loop of secondary device - Google Patents
The method of testing and device in the empty loop of secondary device Download PDFInfo
- Publication number
- CN106841842A CN106841842A CN201611141361.3A CN201611141361A CN106841842A CN 106841842 A CN106841842 A CN 106841842A CN 201611141361 A CN201611141361 A CN 201611141361A CN 106841842 A CN106841842 A CN 106841842A
- Authority
- CN
- China
- Prior art keywords
- model
- loop
- communication
- software
- communication relations
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01R—MEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
- G01R31/00—Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
Abstract
The invention discloses the method for testing and device in a kind of empty loop of secondary device.Wherein, the method includes:Obtain the whole station configuration file of intelligent substation;Multiple two measurement equipments to be tested in acquisition intelligent substation and communication relations from configuration file, wherein, communication relations are used to describe the information transfer relation that multiple secondary devices are carried out by multiple void loops;The multiple void loop of multiple secondary devices is tested according to communication relations in software.The present invention solves relatively low to the testing efficiency in empty loop in intelligent substation technical problem in correlation technique.
Description
Technical field
The present invention relates to field of power, method of testing in particular to a kind of empty loop of secondary device and
Device.
Background technology
In intelligent substation, whole station configuration file SCD (substation configuration description)
It is the basis of secondary device communication, converting station debugging and one of the important process safeguarded are exactly for institute defined in SCD models
There is the verification in the empty loop of information transfer between secondary device.
Test currently for empty loop is main by the way of hand inspection, i.e., be directly viewable first SCD file or from
Whether wrong in derived empty terminal table in SCD, this stage can only check some more superficial problems;Then pass through
Tester carries out monomer debugging to device, and empty returning is verified finally by the overall transmission to relay protection and automated system
Road and the correctness of empty terminal.
Adopt and test in this way, it is difficult to cover all of loop;If additionally, in test process find configuration error,
System integrator is needed to remodify SCD, then all tests are re-started, and cause work to be wasted time and energy, and debugging efficiency is low,
And cannot ensure all correct.
With increasing for the local intelligent substation quantity of each Utilities Electric Co., the work debugged to intelligent substation and safeguarded
Amount is also increasing, and need of work is not adapted to using artificial verification mode.
For technical problem relatively low to the testing efficiency in empty loop in intelligent substation in correlation technique, not yet carry at present
Go out effective solution.
The content of the invention
The method of testing and device in a kind of empty loop of secondary device are the embodiment of the invention provides, at least to solve correlation
The technical problem relatively low to the testing efficiency in empty loop in intelligent substation in technology.
One side according to embodiments of the present invention, there is provided a kind of method of testing in the empty loop of secondary device, the party
Method includes:Obtain the whole station configuration file of intelligent substation;The multiple to be tested in acquisition intelligent substation from configuration file
Two measurement equipments and communication relations, wherein, communication relations are used to describe the information that multiple secondary devices are carried out by multiple void loops
Transmission relation;The multiple void loop of multiple secondary devices is tested according to communication relations in software.
Further, carrying out test to the multiple void loop of multiple secondary devices according to communication relations in software includes:
The software model of each secondary device is set up in software;Multiple software models of the multiple secondary devices of operation;Closed according to communication
System, is communicated between multiple software models in operation, is tested with the multiple void loop to multiple secondary devices.
Further, carrying out communication according to communication relations, between multiple software models in operation includes:According to communication
For the first model for giving out information and the second model for subscribing to message in the multiple software models of relation determination;In the first mould
Between type and the second model message communication is carried out using the empty loop determined according to communication relations.
Further, message is carried out using the empty loop determined according to communication relations between the first model and the second model
Communication includes:According to communication relations determine corresponding to the first model secondary device with correspond to the second model secondary device it
Between target void loop;Given out information on target void loop by the first model;By the second model on target void loop
Receive the message of the first model issue.
Further, after being given out information on target void loop by the first model, the method also includes:Second
In the case that model does not receive the message that the first model is issued by empty loop, determine that target void loop is broken down.
Further, after it is determined that target void loop is broken down, the method also includes:Generation log information, wherein,
The identification information in the empty loop broken down is recorded in log information.
A kind of other side according to embodiments of the present invention, there is provided the test device in the empty loop of secondary device, should
Device includes:First acquisition unit, the whole station configuration file for obtaining intelligent substation;Second acquisition unit, for from matching somebody with somebody
Put and multiple two measurement equipments and communication relations to be tested in intelligent substation are obtained in file, wherein, communication relations are used to describe
The information transfer relation that multiple secondary devices are carried out by multiple void loops;Test cell, for being closed according to communication in software
It is that the multiple void loop of multiple secondary devices is tested.
Further, test cell includes:Module is set up, the software mould for setting up each secondary device in software
Type;Operation module, the multiple software models for running multiple secondary devices;Test module, for according to communication relations, in fortune
Communicated between multiple software models in row, tested with the multiple void loop to multiple secondary devices.
Further, test module includes:Determination sub-module, for determining to be used in multiple software models according to communication relations
The second model in the first model for giving out information and for subscribing to message;Communication submodule, in the first model and second
Between model message communication is carried out using the empty loop determined according to communication relations.
Further, communication submodule is additionally operable to:According to communication relations determine corresponding to the first model secondary device with
Corresponding to the target void loop between the secondary device of the second model;Given out information on target void loop by the first model;
The message that first model is issued is received on target void loop by the second model.
In embodiments of the present invention, by obtaining the whole station configuration file of intelligent substation;Intelligence is obtained from configuration file
Multiple two measurement equipments to be tested and communication relations in energy transformer station, wherein, communication relations are led to for describing multiple secondary devices
Cross the information transfer relation that multiple void loops are carried out;In software according to communication relations to multiple secondary devices multiple void loops
Tested.So as to solve relatively low to the testing efficiency in empty loop in intelligent substation technical problem in correlation technique.
Brief description of the drawings
Accompanying drawing described herein is used for providing a further understanding of the present invention, constitutes the part of the application, this hair
Bright schematic description and description does not constitute inappropriate limitation of the present invention for explaining the present invention.In the accompanying drawings:
Fig. 1 is the flow chart of the method for testing in the empty loop of secondary device according to embodiments of the present invention;
Fig. 2 is the schematic diagram of the form of emulation message according to embodiments of the present invention;
Fig. 3 is the schematic diagram of GOOSE message frame structure according to embodiments of the present invention;
Fig. 4 is the schematic diagram of the test device in the empty loop of secondary device according to embodiments of the present invention.
Specific embodiment
In order that those skilled in the art more fully understand the present invention program, below in conjunction with the embodiment of the present invention
Accompanying drawing, is clearly and completely described to the technical scheme in the embodiment of the present invention, it is clear that described embodiment is only
The embodiment of a part of the invention, rather than whole embodiments.Based on the embodiment in the present invention, ordinary skill people
The every other embodiment that member is obtained under the premise of creative work is not made, should all belong to the model of present invention protection
Enclose.
It should be noted that term " first ", " in description and claims of this specification and above-mentioned accompanying drawing
Two " it is etc. for distinguishing similar object, without for describing specific order or precedence.It should be appreciated that so using
Data can exchange in the appropriate case, so as to embodiments of the invention described herein can with except illustrating herein or
Order beyond those of description is implemented.Additionally, term " comprising " and " having " and their any deformation, it is intended that cover
Lid is non-exclusive to be included, for example, the process, method, system, product or the equipment that contain series of steps or unit are not necessarily limited to
Those steps or unit clearly listed, but may include not list clearly or for these processes, method, product
Or other intrinsic steps of equipment or unit.
First, the part noun or term for occurring during being described to the embodiment of the present invention are applied to following solution
Release:
GOOSE(Generic Object-Oriented Substation Event):It is a kind of towards general object
Transformer substation case.It is mainly used in realizing information transmission between multiple intelligent electronic devices (IED), including transmission breaker tripping and closing,
The multi-signals (order) such as connection locking, with the high-transmission probability of success.
SV(Sampled Value):That is sampled value, it is based on publish/subscribe mechanism, exchanges the sampling that sampled data is concentrated
The correlation model object of value and service, and the mapping that these model objects and service are arrived between ISO/IEC 8802-3 frames.
SCD is introduced:
The letter such as messaging parameter of all intelligent electronic devices in station is contained in intelligent substation configuration file (SCD file)
Breath, by the parsing to SCD file, can obtain the information of network connection relation and the equipment room transmission of secondary device.
In the communication parts of SCD file, describe station level mms networks, process layer goose networks with
And the messaging parameter of the related secondary device of process layer sv networks, each network distinguishes each network according to voltage class in SCD
Equipment.By parsing the field, the access point ConnectedAP and its communicatedly of the associate device of every primary network station is can obtain
Location, the IP address of equipment station level interface or the MAC Address of process layer interface, APPID and vlan information.
In the IED parts of SCD file, all smart machines for participating in communication, such as protection device, observing and controlling in station are described
Device, combining unit, intelligent terminal etc..There are network access point, such as station level network access point under the server fields of IED
S1, process layer GOOSE network accessing points G1, process layer SV accessing points M1.It is fixed under the S1 accessing points in the LLNO of each logical device
The data set that justice device sends to clients such as monitoring or scheduling systems.Under the G1 accessing points in the LLN0 of each logical device,
Define the GOOSE data sets (if having) that device is externally issued;Under the M1 accessing points in the LLN0 of each logical device, dress is defined
Put the SV data sets (if having) of external issue.
For substantial amounts of empty loop defined in SCD file, this is required for testing its correctness one by one.Empty circuit transmission
Signal, its type is different, such as single-point information, two point information, temporal information, floating point information, character string information, passes through
Manual testing is easy to omit some important test points.Therefore, signal imitation transmission system is developed, it appears particularly important.
According to embodiments of the present invention, there is provided a kind of embodiment of the method for the method of testing in the empty loop of secondary device, need
It is noted that can be in the such as one group computer system of computer executable instructions the step of the flow of accompanying drawing is illustrated
Middle execution, and, although show logical order in flow charts, but in some cases, can be with different from herein
Order performs shown or described step.
Fig. 1 is the flow chart of the method for testing in the empty loop of secondary device according to embodiments of the present invention, as shown in figure 1,
The method comprises the following steps:
Step S101, obtains the whole station configuration file of intelligent substation.
Step S102, multiple two measurement equipments to be tested in acquisition intelligent substation and communication relations from configuration file,
Communication relations are used to describe the information transfer relation that multiple secondary devices are carried out by multiple void loops.
Step S103, tests the multiple void loop of multiple secondary devices according to communication relations in software.
By above-described embodiment, by the whole station configuration file for obtaining intelligent substation;Intelligence is obtained from configuration file
Multiple two measurement equipments to be tested and communication relations in transformer station, communication relations are used to describe multiple secondary devices by multiple empty
The information transfer relation that loop is carried out;The multiple void loop of multiple secondary devices is surveyed according to communication relations in software
Examination, can in time find problematic empty loop, so as to solve by being simulated communication according to the communication relations between secondary device
The technical problem relatively low to the testing efficiency in empty loop in intelligent substation in correlation technique of having determined, realizes the intelligent power transformation of raising
The technique effect of the testing efficiency in empty loop in standing.
In this application, it is proposed that a kind of method of testing in secondary equipment of intelligent converting station void loop, first to SCD models
File carries out deep analysis, the Content of Communication of the attribute of each secondary device and equipment room in acquisition station, is then simulated by software
Communication process between each secondary device, while each analog machine is realized (including virtual connections, empty returning its ordered information
Road) verification, actual signal transmission process is simulated by software, so as to realize the test to intelligent substation void loop.
The method provided using the present invention, is capable of achieving the automatic test to intelligent substation void loop, used as artificial tune
The auxiliary and supplement of examination, are greatly improved debugging efficiency, reduce human error, improve substation safety level.
In intelligent substation, important loop is realized by process-level network between secondary device, i.e., empty to return
Road.In debugging process, it is necessary to assure the correctness in empty loop.Test to empty loop at present is mainly commissioning staff using guarantor
The debugging acids such as shield tester carry out monomer debugging or overall actual transmission to equipment, and because secondary circuit quantity is more, contact is complicated,
Manual debugging is difficult to ensure that the correctness in all loops, when also needing to retest after configuration modification.And utilize the application to propose
Method can solve the problems, such as intelligent substation void loop debug when inefficiency, it is error-prone, need to test repeatedly.
In the above-described embodiments, the multiple void loop of multiple secondary devices is tested according to communication relations in software
Including:The software model of each secondary device is set up in software;Multiple software models of the multiple secondary devices of operation;According to logical
News relation, is communicated between multiple software models in operation, is surveyed with the multiple void loop to multiple secondary devices
Examination.
Alternatively, carrying out communication according to communication relations, between multiple software models in operation includes:Closed according to communication
For the first model for giving out information and the second model for subscribing to message in the multiple software models of system's determination;In the first model
And second carry out message communication between model using the empty loop determined according to communication relations.
In an optional embodiment, using the void determined according to communication relations between the first model and the second model
Loop carries out message communication to be included:Determine corresponding to the secondary device of the first model and corresponding to the second model according to communication relations
Secondary device between target void loop;Given out information on target void loop by the first model;Existed by the second model
The message of the first model issue is received on target void loop.
In another optional embodiment, after being given out information on target void loop by the first model, the party
Method also includes:In the case where the second model does not receive the message that the first model is issued by empty loop, determine that target is empty and return
Break down on road.
Alternatively, after it is determined that target void loop is broken down, the method also includes:Generation log information, wherein, day
The identification information in the empty loop broken down is recorded in will information.
Following effect can be reached using the above method of the application:Parsing intelligent substation whole station configuration file SCD, obtains
The title and its attribute of secondary device IED (Intelligent Electronic Device, i.e. intelligent electronic device) are taken, is obtained
The communication link between each IED is taken, the empty loop transmitted on each link is obtained;Software simulates the operation of each IED, and emulation is each
The communication behavior of IED, the correspondence issue configured according to SCD between IED and subscription information;Each simulation IED is realized to ordering
The correctness verifying function of information is read, verifies whether the information that sender sends is correct, so as to realize the test in empty loop.
The technical scheme of the application is described in detail in detail with reference to specific embodiment:
1 configuration file SCD analytic methods
Intelligent substation SCD configuration files include header, substation, communication, ied and
The parts of template five.Wherein header describes the information of FileVersion, author etc;Substation describes transformer station
The structure of primary system;Described in communication parts transformer station station level mms networks, process layer goose networks with
And the messaging parameter of the related secondary device of process layer sv networks, by parsing the contents of the section, can obtain every primary network station
The access point ConnectedAP and its mailing address of associate device, the IP address of equipment station level interface or process layer interface
MAC Address, APPID and vlan information.
In the IED parts of SCD file, all smart machines for participating in communication, such as protection device, observing and controlling in station are described
Device, combining unit, intelligent terminal etc..There are network access point, such as station level network access point under the server fields of IED
S1, process layer GOOSE network accessing points G1, process layer SV accessing points M1.It is fixed under the S1 accessing points in the LLNO of each logical device
The data set that justice device sends to clients such as monitoring or scheduling systems.Under the G1 accessing points in the LLN0 of each logical device,
Define the GOOSE data sets (if having) that device is externally issued;Under the M1 accessing points in the LLN0 of each logical device, dress is defined
Put the SV data sets (if having) of external issue.
By parsing each IED parts, every signal all the way in the data set and data set of the external issue of device is can obtain.
IED needs the external signal subscribed to, and is determined by Inputs fields in the LLN0 of each logical device under accessing points G1 or M1
Justice, including the SV/GOOSE lines of the equipment are input into, each line contains the empty terminal signals of logical device inside input
With the output signal information of external device (ED), empty terminal is one-to-one relationship with each external output signal.
By parsing the above, you can obtain transformer station's networks at different levels, which equipment, equipment room are included in every grade of network
Link relation, equipment issue and subscribe to information.
SCD file follows xml specifications, to obtain each element in SCD, can be increased income storehouse using such as TinyXML, is based on
DOM methods are parsed, or are parsed using the foundational development bag of the sisco companies of business.
After SCD is parsed, each IED attribute and its link with other associate devices, empty loop information collection are obtained,
As the foundation that software simulation IED runs.
2IED communication simulations
Here the correctness in empty loop being test equipment the emulation purpose of smart machine IED, therefore need not be related to
The functional characteristic of equipment, such as protection act logic, and it is primarily upon communications portion.
The emulation of IED follows IEC61850 Communication Protocol Models, and the communication standard slave unit model, abstract communication service connect
The aspect such as mouth, data structure and attribute, particular communication service mapping comes specification substation communication network and system.IED models are needed
Completely to embody production, encapsulation, transmission, the overall process of parsing of information.
IED emulation can be divided into combining unit, intelligent terminal, protection device, measure and control device, monitoring system according to device type
Deng;According to communication message type, SV emulation, GOOSE emulation and MMS emulation can be divided into.
For different type equipment, such as observing and controlling, protection are required for emulating GOOSE and MMS;Combining unit needs to emulate SV
And GOOSE.Therefore facility center management is not introduced here, and is divided into the part of SV, GOOSE, MMS tri- according to type of message and is situated between
Continue emulation mode.
2.1 SV are emulated
SV sampling value messages are generated according to certain rule by combining unit, and combining unit is electronic mutual inductor and guarantor
The key equipment of the secondary device interfaces such as shield, observing and controlling and record ripple, it receives and processes three-phase current and three-phase voltage signal simultaneously,
After by multiple signals synchronization, used to secondary device according to IEC61850-9-2 standard outputs.
The sample frequency of SV messages is 4000Hz in actual transformer station, i.e., 80 points of being sampled per cycle, message sends interval
It is 250us (250us ± 10us).Here because only needing to verify the correctness in empty loop, therefore between simulation frequency and time
Every without requirement.
SV messages use osi model in transmission over networks, but only use four layers in seven layers of OSI network model,
Application layer, expression layer, data link layer and physical layer, transport layer and Internet are sky.Application layer defines protocol Data Unit
PDU, by after expression layer coding, not using ICP/IP protocol, but map directly to data link layer and physical layer.It is this to reflect
The purpose for penetrating mode is to avoid communication stack from causing transmission delay, so as to ensure message transmissions, the rapidity for the treatment of.
SV simulation processes are:According to the MAC Address of SV, APPID, number of channels, the data object of passage, data in SCD
Type etc. is configured, and organizes 9-2 messages, and send to data/address bus according to certain intervals.The form for emulating message is as shown in Figure 2.
The explanation of critical field in message:
MAC Address:Multicast address;01-0C-CD-04 starts;Unique mark,
Ethernet type:SV is 0x88BA,
APPID:Two after unique mark, generally destination address,
svID:Important mark,
Synchronous mark:Put 1 explanation sampled value be it is synchronous,
Maintenance mark:The position 1 when throwing maintenance state,
Sampling channel time delay:The constant time lag of combining unit output is collected from transformer,
Number of active lanes:Defined by configuration file.
2.2 GOOSE are emulated
Use data set total in transformer station process with GOOSE that " publish/subscribe " mode carries out common data exchange
It is used for breaker tripping and closing order and the quick transmission of status information on route, it works in ethernet link layer, directly serving in should
With devices such as layer protection and observing and controlling.
In intelligent substation, GOOSE communicates between bay device and process layer intelligent cell correctness and reliability
Property it is all extremely important, it is desirable to GOOSE publish/subscribes configuration must be correct.Therefore, not only need to check two in SCD models
Whether secondary logical circuit line is consistent with designing institute drawing, in addition it is also necessary to carry out GOOSE communication tests, that is, simulate GOOSE and issue/order
Read, whether normal issue with the GOOSE for testing each equipment, whether simulation GOOSE issues test equipment function normal etc..Here adopt
The correctness that GOOSE is configured is verified with GOOSE simulation softwares.
GOOSE message emulation is needed according to the MAC Address of GOOSE in SCD, GoID, dataset, number of channels, passage
Data object, data type etc. are configured, and organize message, and send to data/address bus according to certain intervals.GOOSE message frame structure
As shown in Figure 3.
GOOSE message significant field is parsed:
MAC Address:Multicast address;01-0C-CD-01 starts;Unique mark,
Ethernet type:GOOSE is 0X88B8,
APPID:Important sign, it is typically identical with two after target MAC (Media Access Control) address,
GoCbRef:Goose control blocks quote path,
DataSet:Data set quotes path,
GoID:Important mark,
Test:Maintenance position;The mark for whether using,
SqNum:GOOSE conjugates the message number for sending so far for the last time,
StNum:GOOSE message displacement number of times altogether,
dataSet:Number, order, the data type of data set, wherein data item are all by the GOOSE data of configuration file
Collection definition.Four types of GOOSE parameters in data set,
Boolean type:0th, 1 two states, regular tap amount signal,
Bit string type, 01,10,00,11 4 kind of state, for represent switch, disconnecting link two-position signal;01 expression point;10 tables
Show conjunction;00 represents centre position;11 represent that position is invalid,
Time type, represents the utc times of data displacement,
Floating type, for transmitting the analog acquisition signal such as temperature.
2.3 MMS are emulated
MMS emulation mainly uses software to realize IEC61850 client functionalitys.IEC61850 clients refer to based on mark
Certainly adopted client/server communication pattern carries out the system and equipment of function access and information exchange with bay device, such as
Monitoring system, telemechanical and substation etc., client follow IEC61850-8-1, that is, be mapped to MMS standards, are carried out with bay device
Communication.Bay device is server end.
IEC61850 client functionalitys mainly include communication association, report treatment, remote control, definite value operation, record ripple calling etc..
MMS emulation is exactly to develop general 61850 client, is associated with equipment, performs total greeting, receives service end master
The operations such as report, file calling, definite value calling download, the remote control sent on dynamic, between true imitating substation station level equipment
Communication process.
3 empty loop verifications
Empty loop verification process is carried out in the subscriber of communicating pair.Subscriber such as SV messages is protection device or survey
Control device.Then protection device then starts protocol monitor and authentication module, the received sv reports of detection after SV messages are received
Whether text is object that oneself is subscribed to, and whether the specific field of message meets SCD definition.
Each simulation IED includes empty loop verification module.As long as receiving message, whether just message configuration is just checked
Really, whether frame format is correct etc..Some common message error types have following several:
(1) message format mistake, such as SV, GOOSE, MMS message format mistake;
(2) message is discontinuous, such as frame losing, repetition, time-out;
(3) data attribute change, such as quality factor change, synchronous mark change;
(4) SV samplings are abnormal, and such as frequency is unstable, and double A/D is inconsistent etc.:
(5) Changing Pattern of GOOSE StNum and SqNum, such as conjugates, restarts, state is empty becomes;
(6) configure inconsistent with SCD, such as data set, entry number, address, reference;
(7) ACSI service analyses, such as name resolving, data parsing, service process parsing, capture time, negative response.
By the detection of empty loop verification module, the process of simulation manual signal transmission, so as to realize empty loop-around test.
The method that the application is proposed can be applied in intelligent substation, according to the signal imitation transmission of this method exploitation
System, after system reads SCD configuration files, corresponding virtual IED is generated according to the IED quantity and communication function that are configured in SCD.
After test process starts, emulation testing is carried out to each IED one by one, by the verification of the communication message to the IED, check IED
Between empty loop it is whether correct.Using the simulation transmission system of empty loop test method of the invention, can effectively find that SCD matches somebody with somebody
The mistake in middle empty loop is put, with practical value.
The operation principle of signal imitation transmission system is as follows:(1) configuration file of redaction is read, each IED is parsed
Empty terminal.(2) automatic or manual mode selects the IED for needing to be tested, generally pairwise testing.(3) wherein one is simulated
Individual IED sends message, may be SV, GOOSE or MMS message, and another IED receives message, and judges whether it is that oneself is subscribed to
Information and type, provide alarm if mistake, point out the mistake of configuration file appropriate section.System can be while Multipexer SV
With GOOSE, the automated procedures of test are improved, improve operating efficiency, reduce the generation of human error.
It should be noted that for foregoing each method embodiment, in order to be briefly described, therefore it is all expressed as a series of
Combination of actions, but those skilled in the art should know, the present invention not by described by sequence of movement limited because
According to the present invention, some steps can sequentially or simultaneously be carried out using other.Secondly, those skilled in the art should also know
Know, embodiment described in this description belongs to preferred embodiment, involved action and module is not necessarily of the invention
It is necessary.
The embodiment of the present invention additionally provides a kind of test device in the empty loop of secondary device.It should be noted that this hair
The test device in the empty loop of the secondary device of bright embodiment can be used for performing the secondary device that the embodiment of the present invention is provided
Empty loop method of testing, the method for testing in the empty loop of the secondary device of the embodiment of the present invention can also be by of the invention real
The test device for applying the empty loop of the secondary device that example is provided is performed.
Fig. 4 is the schematic diagram of the test device in the empty loop of secondary device according to embodiments of the present invention.As shown in figure 4,
The device can include:First acquisition unit 41, second acquisition unit 42 and test cell 43.
First acquisition unit 41, the whole station configuration file for obtaining intelligent substation;
Second acquisition unit 42, for obtained from configuration file in intelligent substation multiple two measurement equipments to be tested and
Communication relations, wherein, communication relations are used to describe the information transfer relation that multiple secondary devices are carried out by multiple void loops;
Test cell 43, for being surveyed to the multiple void loop of multiple secondary devices according to communication relations in software
Examination.
By above-described embodiment, first acquisition unit obtains the whole station configuration file of intelligent substation;Second acquisition unit
Multiple two measurement equipments to be tested in acquisition intelligent substation and communication relations from configuration file, wherein, communication relations are used for
The information transfer relation that the multiple secondary devices of description are carried out by multiple void loops;Test cell is in software according to communication relations
Multiple void loop to multiple secondary devices is tested, can by being simulated communication according to the communication relations between secondary device
To find problematic empty loop in time, so as to solve in correlation technique to the testing efficiency in empty loop in intelligent substation compared with
Low technical problem, realizes the technique effect of the testing efficiency for improving empty loop in intelligent substation.
In the above-described embodiments, test cell includes:Module is set up, for setting up the soft of each secondary device in software
Part model;Operation module, the multiple software models for running multiple secondary devices;Test module, for according to communication relations,
Communicated between multiple software models in operation, tested with the multiple void loop to multiple secondary devices.
Alternatively, test module includes:Determination sub-module, for determining to be used in multiple software models according to communication relations
The first model for giving out information and the second model for subscribing to message;Communication submodule, in the first model and the second mould
Between type message communication is carried out using the empty loop determined according to communication relations.
In an optional embodiment, communication submodule is additionally operable to:Determine to correspond to the first model according to communication relations
Secondary device and corresponding between the secondary device of the second model target void loop;By the first model in target void loop
On give out information;The message that first model is issued is received on target void loop by the second model.
In this application, it is proposed that a kind of method of testing in secondary equipment of intelligent converting station void loop, first to SCD models
File carries out deep analysis, the Content of Communication of the attribute of each secondary device and equipment room in acquisition station, is then simulated by software
Communication process between each secondary device, while each analog machine is realized (including virtual connections, empty returning its ordered information
Road) verification, actual signal transmission process is simulated by software, so as to realize the test to intelligent substation void loop.
The device provided using the present invention, is capable of achieving the automatic test to intelligent substation void loop, used as artificial tune
The auxiliary and supplement of examination, are greatly improved debugging efficiency, reduce human error, improve substation safety level.
In intelligent substation, important loop is realized by process-level network between secondary device, i.e., empty to return
Road.In debugging process, it is necessary to assure the correctness in empty loop.Test to empty loop at present is mainly commissioning staff using guarantor
The debugging acids such as shield tester carry out monomer debugging or overall actual transmission to equipment, and because secondary circuit quantity is more, contact is complicated,
Manual debugging is difficult to ensure that the correctness in all loops, when also needing to retest after configuration modification.And utilize the application to propose
Method can solve the problems, such as intelligent substation void loop debug when inefficiency, it is error-prone, need to test repeatedly.
Modules provided in the present embodiment are identical with the application method that the corresponding step of embodiment of the method is provided, should
Can also be identical with scene.It is noted, of course, that the scheme that above-mentioned module is related to can be not limited in above-described embodiment
Content and scene, and above-mentioned module may operate in terminal or mobile terminal, can be realized by software or hardware.
The embodiments of the present invention are for illustration only, and the quality of embodiment is not represented.
In the above embodiment of the present invention, the description to each embodiment all emphasizes particularly on different fields, and does not have in certain embodiment
The part of detailed description, may refer to the associated description of other embodiment.
In several embodiments provided herein, it should be understood that disclosed technology contents, can be by other
Mode is realized.Wherein, device embodiment described above is only schematical, such as division of described unit, Ke Yiwei
A kind of division of logic function, can there is other dividing mode when actually realizing, such as multiple units or component can combine or
Person is desirably integrated into another system, or some features can be ignored, or does not perform.Another, shown or discussed is mutual
Between coupling or direct-coupling or communication connection can be the INDIRECT COUPLING or communication link of unit or module by some interfaces
Connect, can be electrical or other forms.
The unit that is illustrated as separating component can be or may not be it is physically separate, it is aobvious as unit
The part for showing can be or may not be physical location, you can with positioned at a place, or can also be distributed to multiple
On unit.Some or all of unit therein can be according to the actual needs selected to realize the purpose of this embodiment scheme.
In addition, during each functional unit in each embodiment of the invention can be integrated in a processing unit, it is also possible to
It is that unit is individually physically present, it is also possible to which two or more units are integrated in a unit.Above-mentioned integrated list
Unit can both be realized in the form of hardware, it would however also be possible to employ the form of SFU software functional unit is realized.
If the integrated unit is to realize in the form of SFU software functional unit and as independent production marketing or use
When, can store in a computer read/write memory medium.Based on such understanding, technical scheme is substantially
The part for being contributed to prior art in other words or all or part of the technical scheme can be in the form of software products
Embody, the computer software product is stored in a storage medium, including some instructions are used to so that a computer
Equipment (can be personal computer, server or network equipment etc.) perform each embodiment methods described of the invention whole or
Part steps.And foregoing storage medium includes:USB flash disk, read-only storage (ROM, Read-Only Memory), arbitrary access are deposited
Reservoir (RAM, Random Access Memory), mobile hard disk, magnetic disc or CD etc. are various can be with store program codes
Medium.
The above is only the preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art
For member, under the premise without departing from the principles of the invention, some improvements and modifications can also be made, these improvements and modifications also should
It is considered as protection scope of the present invention.
Claims (10)
1. the method for testing in the empty loop of a kind of secondary device, it is characterised in that including:
Obtain the whole station configuration file of intelligent substation;
Multiple two measurement equipments and communication relations to be tested in the intelligent substation are obtained from the configuration file, wherein,
The communication relations are used to describe the information transfer relation that multiple secondary devices are carried out by multiple void loops;
The multiple described empty loop of multiple secondary devices is tested according to the communication relations in software.
2. method according to claim 1, it is characterised in that in software according to the communication relations to multiple described two
The multiple described empty loop of secondary device carries out test to be included:
The software model of each secondary device is set up in software;
Run the multiple described software model of multiple secondary devices;
According to the communication relations, communicated between multiple described software model in operation, with described secondary to multiple
The multiple described empty loop of equipment is tested.
3. method according to claim 2, it is characterised in that according to the communication relations, multiple in operation is described
Communication is carried out between software model to be included:
Determine to disappear for the first model for giving out information in multiple software models and for subscribing to according to the communication relations
Second model of breath;
Carried out using the described empty loop determined according to the communication relations between first model and second model
Message communication.
4. method according to claim 3, it is characterised in that utilized between first model and second model
The described empty loop determined according to the communication relations carries out message communication to be included:
Determine corresponding to the secondary device of first model and corresponding to second model according to the communication relations
The secondary device between target void loop;
Given out information on target void loop by first model;
The message that first model is issued is received on target void loop by second model.
5. method according to claim 4, it is characterised in that by first model on target void loop
After giving out information, methods described also includes:
In the case where second model does not receive the message of the first model issue by the empty loop, institute is determined
Target void loop is stated to break down.
6. method according to claim 5, it is characterised in that after it is determined that target void loop is broken down, institute
Stating method also includes:
Generation log information, wherein, the identification information in the empty loop broken down is recorded in the log information.
7. the test device in the empty loop of a kind of secondary device, it is characterised in that including:
First acquisition unit, the whole station configuration file for obtaining intelligent substation;
Second acquisition unit, for obtaining multiple two measurement equipments to be tested in the intelligent substation from the configuration file
And communication relations, wherein, the communication relations are used to describe the information that multiple secondary devices are carried out by multiple void loops
Transmission relation;
Test cell, for entering to the multiple described empty loop of multiple secondary devices according to the communication relations in software
Row test.
8. device according to claim 7, it is characterised in that the test cell includes:
Module is set up, the software model for setting up each secondary device in software;
Operation module, the multiple described software model for running multiple secondary devices;
Test module, for according to the communication relations, being communicated between multiple described software model in operation, with right
The multiple described empty loop of multiple secondary devices is tested.
9. device according to claim 8, it is characterised in that the test module includes:
Determination sub-module, for determining the first mould in multiple software models for giving out information according to the communication relations
Type and the second model for subscribing to message;
Communication submodule, for utilizing what is determined according to the communication relations between first model and second model
The empty loop carries out message communication.
10. device according to claim 9, it is characterised in that the communication submodule is additionally operable to:
Determine corresponding to the secondary device of first model and corresponding to second model according to the communication relations
The secondary device between target void loop;
Given out information on target void loop by first model;
The message that first model is issued is received on target void loop by second model.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611141361.3A CN106841842A (en) | 2016-12-12 | 2016-12-12 | The method of testing and device in the empty loop of secondary device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611141361.3A CN106841842A (en) | 2016-12-12 | 2016-12-12 | The method of testing and device in the empty loop of secondary device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106841842A true CN106841842A (en) | 2017-06-13 |
Family
ID=59140191
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201611141361.3A Pending CN106841842A (en) | 2016-12-12 | 2016-12-12 | The method of testing and device in the empty loop of secondary device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106841842A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110175204A (en) * | 2019-05-17 | 2019-08-27 | 国网河北省电力有限公司沧州供电分公司 | Intelligent substation data management and decision system, method and terminal device |
CN113408100A (en) * | 2021-05-11 | 2021-09-17 | 国网浙江省电力有限公司绍兴供电公司 | Virtual loop mirror image simulation transmission method based on intelligent maintenance platform |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102879662A (en) * | 2011-09-15 | 2013-01-16 | 湖北省电力公司电力科学研究院 | Device and method for detecting secondary virtual loop of intelligent transformer substation |
CN103176084A (en) * | 2013-03-07 | 2013-06-26 | 江苏省电力公司电力科学研究院 | Intelligent substation simulation system in panoramic replace mode and integration testing method for intelligent substation simulation system |
CN105242164A (en) * | 2015-08-21 | 2016-01-13 | 国电南瑞科技股份有限公司 | Automatic detection system and method of secondary virtual loop of intelligent transformer station |
-
2016
- 2016-12-12 CN CN201611141361.3A patent/CN106841842A/en active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102879662A (en) * | 2011-09-15 | 2013-01-16 | 湖北省电力公司电力科学研究院 | Device and method for detecting secondary virtual loop of intelligent transformer substation |
CN103176084A (en) * | 2013-03-07 | 2013-06-26 | 江苏省电力公司电力科学研究院 | Intelligent substation simulation system in panoramic replace mode and integration testing method for intelligent substation simulation system |
CN105242164A (en) * | 2015-08-21 | 2016-01-13 | 国电南瑞科技股份有限公司 | Automatic detection system and method of secondary virtual loop of intelligent transformer station |
Non-Patent Citations (3)
Title |
---|
侯亮等: "智能变电站虚拟回路自动化校核技术的研究", 《电网与清洁能源》 * |
刘彬等: "数字化变电站虚回路智能检测软件开发与应用", 《广西电力》 * |
宁夏电力公司教育培训中心: "《智能变电站运行与维护》", 30 November 2012 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110175204A (en) * | 2019-05-17 | 2019-08-27 | 国网河北省电力有限公司沧州供电分公司 | Intelligent substation data management and decision system, method and terminal device |
CN113408100A (en) * | 2021-05-11 | 2021-09-17 | 国网浙江省电力有限公司绍兴供电公司 | Virtual loop mirror image simulation transmission method based on intelligent maintenance platform |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN111262346B (en) | Integrated automatic acceptance system and method for transformer substation | |
CN108414849B (en) | Intelligent substation automatic test system and method | |
CN105116248B (en) | Relay protection device of intelligent substation automated closed-loop test method | |
CN103414251B (en) | A kind of substation network communication analogue system based on IEC61850 | |
CN105426454B (en) | Intelligent electronic device and SCD file circuit consistency on messaging detection method | |
CN103200051B (en) | Intelligent substation message emulating is tested and is associated message analysis system and method | |
CN106556765B (en) | The test method and RTDS emulator of distributed distribution automation system | |
CN103076520A (en) | Dynamic analogue simulation detection platform and analogue simulation method for secondary system of intelligent substation | |
CN105093017B (en) | Intelligent substation GOOSE integrated testabilities device and its method of testing | |
CN108663581A (en) | A kind of secondary equipment of intelligent converting station test method | |
CN105207366B (en) | Distribution terminal plug and play model configuration tool and its implementation based on IEC61850 | |
CN108259264A (en) | Test method, the device and system of the network equipment | |
CN110991037A (en) | Intelligent substation test simulation system based on SCD | |
CN110766263A (en) | Automatic acceptance method for secondary equipment of transformer substation and terminal equipment | |
CN111884851B (en) | Simulation design method for process level equipment of intelligent substation | |
Tong et al. | Flexible hardware‐in‐the‐loop testbed for cyber physical power system simulation | |
CN110989547A (en) | Detection method and system for intelligent substation one-key sequence control system | |
CN108595390B (en) | Method for verifying parameter consistency of SCD and IED of intelligent substation | |
Falk | IEC 61850 demystified | |
CN106844432A (en) | Data processing method and device | |
CN103676669B (en) | The check method of a kind of telecontrol information and nucleus correcting system | |
CN107995050A (en) | Secondary system of intelligent substation process layer communication failure diagnostic system and method | |
CN106841842A (en) | The method of testing and device in the empty loop of secondary device | |
CN111935767B (en) | Network simulation system | |
CN104638761B (en) | Packet sensing and packet simulation verification based GOOSE (generic object oriented substation event) virtual terminal connection method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170613 |
|
RJ01 | Rejection of invention patent application after publication |