CN105205703A CN201510751011.8A CN201510751011A CN105205703A CN 105205703 A CN105205703 A CN 105205703A CN 201510751011 A CN201510751011 A CN 201510751011A CN 105205703 A CN105205703 A CN 105205703A
Authority
CN
China
Prior art keywords
electricity
information
power
management plan
power management
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510751011.8A
Other languages
Chinese (zh)
Inventor
陈政
宋艺航
张翔
傅蔷
蒙文川
冷媛
欧鹏
王庆红
邢胜男
杨龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BEIJING JINGSHI WANFANG INFORMATION TECHNOLOGY Co Ltd
CSG Electric Power Research Institute
Power Grid Technology Research Center of China Southern Power Grid Co Ltd
Research Institute of Southern Power Grid Co Ltd
Original Assignee
BEIJING JINGSHI WANFANG INFORMATION TECHNOLOGY Co Ltd
Power Grid Technology Research Center of China Southern Power Grid Co Ltd
Research Institute of Southern Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING JINGSHI WANFANG INFORMATION TECHNOLOGY Co Ltd, Power Grid Technology Research Center of China Southern Power Grid Co Ltd, Research Institute of Southern Power Grid Co Ltd filed Critical BEIJING JINGSHI WANFANG INFORMATION TECHNOLOGY Co Ltd
Priority to CN201510751011.8A priority Critical patent/CN105205703A/en
Publication of CN105205703A publication Critical patent/CN105205703A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S50/00Market activities related to the operation of systems integrating technologies related to power network operation or related to communication or information technologies
    • Y04S50/14Marketing, i.e. market research and analysis, surveying, promotions, advertising, buyer profiling, customer management or rewards

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The invention provides a business analysis-based grid electricity operation programme determining method and system. The business analysis-based grid electricity operation programme determining method comprises the following steps: acquiring a current electricity operation programme, and establishing a grid business performance analysis and forecasting model corresponding to the current electricity operation programme, wherein the model comprises an input parameter and a target parameter; acquiring external influence factor information and internal management and decision making information from an electricity business system, wherein the external influence factor information comprises electricity requirement information, electricity supply information and electricity price information, the internal management and decision making information comprises in-progress construction work information, fixed asset information, depreciation information and power supply capacity, and the input parameter comprises the external influence factor information and the internal management and decision making information; inputting the input parameter into the grid business performance analysis and forecasting model, and analyzing according to the grid business performance analysis and forecasting model to determine an output value corresponding to the target parameter; adjusting the current electricity operation programme according to the output value of the target parameter. Through the technical scheme, the current electricity operation programme can be adjusted to determine the appropriate electricity operation programme, so that a grid business performance requirement can be met.

Description

Based on grid power Management plan defining method and the system of business diagnosis
Technical field
The present invention relates to electric power network technique field, particularly a kind of grid power Management plan defining method based on business diagnosis and system.
Background technology
In electric power network technique, the formulation of numerous type of electrical power Management plan can be related to, in general, for some details, can formulate multiple different power operation scheme, and the power operation scheme that selection one is optimum from this multiple power operation scheme is applied in network system.When selecting this multiple power operation scheme, usually can analyze based on the failure rate etc. of this multiple different power operation scheme, and the power operation scheme therefrom selecting failure rate minimum carries out practice, to ensure the reliability of electrical network.But for the situation that reliability is secure, how to make electrical network service feature reach optimum and do not consider.
Summary of the invention
Based on this, the object of the embodiment of the present invention is to provide a kind of grid power Management plan defining method based on business diagnosis and a kind of grid power Management plan certainty annuity based on business diagnosis, it can reasonably adjust power operation scheme, thus determine suitable grid power Management plan, improve electrical network service feature.
For achieving the above object, the embodiment of the present invention by the following technical solutions:
Based on a grid power Management plan defining method for business diagnosis, comprise step:
Obtain current power Management plan, set up the electrical network service feature analyses and prediction model corresponding with described current power Management plan, described electrical network service feature analyses and prediction model comprises input parameter, target component;
External influence factors information, internal operation decision information is obtained from power business system, described external influence factors information comprises electricity needs information, electric power supply information, electricity price information, described internal operation decision information is included in builds engineering information, capital assets information, depreciation information, power supply capacity, and described input parameter comprises described external influence factors information, internal operation decision information;
Described input parameter is inputted described electrical network service feature analyses and prediction model, analyze according to described electrical network service feature analyses and prediction model, determine the output valve of corresponding target component;
Described target component output valve meet impose a condition time, using current power Management plan as the power operation scheme determined, described target component output valve meet impose a condition time, described current power Management plan is adjusted according to the output valve of described target component, and using the power operation scheme after adjustment as current power Management plan.
Based on a grid power Management plan certainty annuity for business diagnosis, comprise step:
Model building module, for obtaining current power Management plan, set up the electrical network service feature analyses and prediction model corresponding with described current power Management plan, described electrical network service feature analyses and prediction model comprises input parameter, target component;
Data obtaining module, for obtaining external influence factors information, internal operation decision information from power business system, described external influence factors information comprises electricity needs information, electric power supply information, electricity price information, described internal operation decision information is included in builds engineering information, capital assets information, depreciation information, power supply capacity, and described input parameter comprises described external influence factors information, internal operation decision information;
Analysis module, for described input parameter being inputted described electrical network service feature analyses and prediction model, analyzes according to described electrical network service feature analyses and prediction model, determines the output valve of corresponding target component;
Scheme is determined and adjusting module, when imposing a condition for meeting in the output valve of described target component, using current power Management plan as the power operation scheme determined, described target component output valve meet impose a condition time, described current power Management plan is adjusted according to the output valve of described target component, and using the power operation scheme after adjustment as current power Management plan.
According to the scheme of the embodiment of the present invention as above, it is based on set up power operation scheme, set up the electrical network service feature analyses and prediction model corresponding with this power operation scheme, input parameter in this electrical network service feature analyses and prediction model obtains from power business system, by carrying out power business analysis based on these input parameters obtained from power business system, can determine whether the output valve of the target component finally obtained meets business objective, thus accordingly power operation scheme is adjusted, impose a condition until the magnitude value of target component meets, thus determine suitable power operation scheme, to meet electrical network service feature.
Accompanying drawing explanation
Fig. 1 is the schematic flow sheet of the grid power Management plan defining method based on business diagnosis in an embodiment;
Fig. 2 is the structural representation of the grid power Management plan certainty annuity based on business diagnosis in an embodiment.
Embodiment
For making object of the present invention, technical scheme and advantage clearly understand, below in conjunction with drawings and Examples, the present invention is described in further detail.Should be appreciated that embodiment described herein only in order to explain the present invention, do not limit protection scope of the present invention.
The schematic flow sheet of the grid power Management plan defining method based on business diagnosis in an embodiment has been shown in Fig. 1.As shown in Figure 1, the method in the present embodiment comprises step:
Step S101: obtain current power Management plan, set up the electrical network service feature analyses and prediction model corresponding with described current power Management plan, described electrical network service feature analyses and prediction model comprises input parameter, target component;
Step S102: obtain external influence factors information, internal operation decision information from power business system, described external influence factors information comprises electricity needs information, electric power supply information, electricity price information, described internal operation decision information is included in builds engineering information, capital assets information, depreciation information, power supply capacity, and described input parameter comprises described external influence factors information, internal operation decision information;
Step S103: described input parameter is inputted described electrical network service feature analyses and prediction model, analyzes according to described electrical network service feature analyses and prediction model, determines the output valve of corresponding target component;
Step S104: described target component output valve meet impose a condition time, using current power Management plan as the power operation scheme determined, described target component output valve meet impose a condition time, described current power Management plan is adjusted according to the output valve of described target component, and using the power operation scheme after adjustment as current power Management plan.
According to the scheme of the embodiment of the present invention as above, it is based on set up power operation scheme, set up the electrical network service feature analyses and prediction model corresponding with this power operation scheme, input parameter in this electrical network service feature analyses and prediction model obtains from power business system, by carrying out power business analysis based on these input parameters obtained from power business system, can determine whether the output valve of the target component finally obtained meets business objective, thus accordingly power operation scheme is adjusted, impose a condition until the output valve of target component meets, thus determine suitable power operation scheme, to meet electrical network service feature.
Wherein, in a concrete example, above-mentioned electricity needs information can comprise electricity sales amount, and described electricity price information comprises sale of electricity unit price.Described electricity sales amount can comprise electricity sales amount in large industrial power supply amount, general industry power consumption, resident living power utility amount, non-resident electric consumption on lighting amount, commercial power amount, agricultural production power consumption, bulk sale power consumption, system, the outer electricity sales amount of system and other power consumptions.
In addition, above-mentioned electric power supply information can comprise purchase of electricity, and above-mentioned electricity price information comprises power purchase unit price.Described purchase of electricity comprises water power purchase of electricity, coal purchases by telephone electricity, electricity purchased by telephone by oil, coal gas purchases by telephone electricity, nuclear power purchase of electricity, regenerative resource purchase of electricity, outer purchase of electricity, other energy purchase of electricity.
In another specific example, described depreciation information comprises ratio of depreciation information and initial asset value information, wherein, ratio of depreciation information comprises transmission line of electricity assets composite depreciation rate, converting equipment assets composite depreciation rate, distribution line and asset of equipments composite depreciation rate, other assets composite depreciation rate, and described initial asset value information comprises average transmit power circuit initial asset value, average converting equipment initial asset value, average distribution line and asset of equipments initial value.
Above-mentioned target component, based on the difference of electrical network type of service to be analyzed, can be set as dissimilar parameter, can meet dissimilar perhaps demand to make set up power operation scheme.Such as, in a concrete example, above-mentioned target component can be profit value, can meet corresponding profit requirement to make set up power operation scheme.
Based on the method for the embodiment of the present invention as above, the processing procedure of the method in a specific embodiment can be as described below:
First, obtain current power Management plan, set up the electrical network service feature analyses and prediction model corresponding with described current power Management plan, wherein, this electrical network service feature analyses and prediction model comprises input parameter, target component, it will be appreciated by those skilled in the art that, the specific implementation setting up electrical network service feature analyses and prediction model can adopt any possible mode to carry out, as long as the corresponding interrelational form of the correlation parameter in power operation scheme and this target component can be embodied, based on the difference of selected target component, the electrical network service feature analyses and prediction model set up can difference to some extent.
Subsequently, external influence factors information, internal operation decision information is obtained from power business system.Wherein, this external influence factors information comprises electricity needs information, electric power supply information, electricity price information, this electricity needs information specifically can comprise electricity sales amount, electricity sales amount specifically can comprise large industrial power supply amount, general industry power consumption, resident living power utility amount, non-resident electric consumption on lighting amount, commercial power amount, agricultural production power consumption, bulk sale power consumption, electricity sales amount in system, the outer electricity sales amount of system, and other power consumptions, this Electrical information provision can comprise purchase of electricity, purchase of electricity specifically can comprise water power purchase of electricity, coal purchases by telephone electricity, electricity purchased by telephone by oil, coal gas purchases by telephone electricity, nuclear power purchase of electricity, regenerative resource purchase of electricity, outer purchase of electricity, other energy purchase of electricity.And electricity price information can comprise sale of electricity unit price.Internal operation decision information is specifically included in builds engineering information, capital assets information, depreciation information, power supply capacity, and described input parameter comprises described external influence factors information, internal operation decision information.
Then, the information of the input parameter of above-mentioned acquisition is input in the electrical network service feature analyses and prediction model of above-mentioned foundation, analyzes according to described electrical network service feature analyses and prediction model, determine the output valve of corresponding target component; Judge whether the output valve of corresponding target component meets to impose a condition.
If meet impose a condition, then using current power Management plan as the power operation scheme determined.
Impose a condition if do not met, then adjust described current power Management plan according to the output valve of described target component, and using the power operation scheme after adjustment as current power Management plan.The output valve of concrete based target parameter adjusts the mode of described current power Management plan, any possible mode can be adopted to carry out, such as, if the output valve of target component is less than the expection output valve of target component, the value of the corresponding parameter in Management plan of can suitably increasing electric power, or corresponding electric power supply mode is adjusted, such as will be adjusted to electric power supply mode another (such as nuclear power electric power supply) etc. for certain particular user from a kind of electric power presentation mode (such as oily electric electric power supply).Certainly, it will be understood by those skilled in the art that the difference of the type based on the parameter in power operation scheme, corresponding processing mode also difference to some extent.
After adjusting in power operation scheme, said process can be returned, again the information of the input parameter of acquisition is input to electrical network service feature analyses and prediction model, after determining the output of corresponding target component, according to target output valve adjustment current power Management plan again.
Can said process be repeated, until the output valve of target component meets the demands, then the power operation scheme after finally adjustment is applied in network system as final power operation scheme.
Based on the thought identical with said method, the embodiment of the present invention also provides a kind of grid power Management plan certainty annuity based on business diagnosis, and the structural representation of the grid power Management plan certainty annuity based on business diagnosis in an embodiment has been shown in Fig. 2.
As shown in Figure 2, the system in the embodiment of the present invention comprises:
Model building module 201, for obtaining current power Management plan, set up the electrical network service feature analyses and prediction model corresponding with described current power Management plan, described electrical network service feature analyses and prediction model comprises input parameter, target component;
Data obtaining module 202, for obtaining external influence factors information, internal operation decision information from power business system, described external influence factors information comprises electricity needs information, electric power supply information, electricity price information, described internal operation decision information is included in builds engineering information, capital assets information, depreciation information, power supply capacity, and described input parameter comprises described external influence factors information, internal operation decision information;
Analysis module 203, for described input parameter being inputted described electrical network service feature analyses and prediction model, analyzes according to described electrical network service feature analyses and prediction model, determines the output valve of corresponding target component;
Project setting module 204, when imposing a condition for meeting in the output valve of described target component, using current power Management plan as the power operation scheme determined, described target component output valve meet impose a condition time, described current power Management plan is adjusted according to the output valve of described target component, and using the power operation scheme after adjustment as current power Management plan.
According to the scheme of the embodiment of the present invention as above, it is based on set up power operation scheme, set up the electrical network service feature analyses and prediction model corresponding with this power operation scheme, input parameter in this electrical network service feature analyses and prediction model obtains from power business system, by carrying out power business analysis based on these input parameters obtained from power business system, can determine whether the output valve of the target component finally obtained meets business objective, thus accordingly power operation scheme is adjusted, determine suitable power operation scheme, to meet electrical network service feature.
Wherein, in a concrete example, above-mentioned electricity needs information can comprise electricity sales amount, and described electricity price information comprises sale of electricity unit price.Described electricity sales amount can comprise electricity sales amount in large industrial power supply amount, general industry power consumption, resident living power utility amount, non-resident electric consumption on lighting amount, commercial power amount, agricultural production power consumption, bulk sale power consumption, system, the outer electricity sales amount of system and other power consumptions.
In addition, above-mentioned electric power supply information can comprise purchase of electricity, and above-mentioned electricity price information comprises power purchase unit price.Described purchase of electricity comprises water power purchase of electricity, coal purchases by telephone electricity, electricity purchased by telephone by oil, coal gas purchases by telephone electricity, nuclear power purchase of electricity, regenerative resource purchase of electricity, outer purchase of electricity, other energy purchase of electricity.
In another specific example, described depreciation information comprises ratio of depreciation information and initial asset value information, wherein, ratio of depreciation information comprises transmission line of electricity assets composite depreciation rate, converting equipment assets composite depreciation rate, distribution line and asset of equipments composite depreciation rate, other assets composite depreciation rate, and described initial asset value information comprises average transmit power circuit initial asset value, average converting equipment initial asset value, average distribution line and asset of equipments initial value.
Above-mentioned target component, based on the difference of electrical network type of service to be analyzed, can be set as dissimilar parameter, can meet dissimilar perhaps demand to make set up power operation scheme.Such as, in a concrete example, above-mentioned target component can be profit value, can meet corresponding profit requirement to make set up power operation scheme.
The embodiment of the present invention based on the other technologies feature in the grid power Management plan certainty annuity of business diagnosis, can with above-mentioned identical based in the grid power Management plan defining method of business diagnosis, repeat no longer in detail at this.
Each technical characteristic of the above embodiment can combine arbitrarily, for making description succinct, the all possible combination of each technical characteristic in above-described embodiment is not all described, but, as long as the combination of these technical characteristics does not exist contradiction, be all considered to be the scope that this instructions is recorded.
The above embodiment only have expressed several embodiment of the present invention, and it describes comparatively concrete and detailed, but can not therefore be construed as limiting the scope of the patent.It should be pointed out that for the person of ordinary skill of the art, without departing from the inventive concept of the premise, can also make some distortion and improvement, these all belong to protection scope of the present invention.Therefore, the protection domain of patent of the present invention should be as the criterion with claims.

Claims (10)

1., based on a grid power Management plan defining method for business diagnosis, it is characterized in that, comprise step:
Obtain current power Management plan, set up the electrical network service feature analyses and prediction model corresponding with described current power Management plan, described electrical network service feature analyses and prediction model comprises input parameter, target component;
External influence factors information, internal operation decision information is obtained from power business system, described external influence factors information comprises electricity needs information, electric power supply information, electricity price information, described internal operation decision information is included in builds engineering information, capital assets information, depreciation information, power supply capacity, and described input parameter comprises described external influence factors information, internal operation decision information;
Described input parameter is inputted described electrical network service feature analyses and prediction model, analyze according to described electrical network service feature analyses and prediction model, determine the output valve of corresponding target component;
Described target component output valve meet impose a condition time, using current power Management plan as the power operation scheme determined, described target component output valve meet impose a condition time, described current power Management plan is adjusted according to the output valve of described target component, and using the power operation scheme after adjustment as current power Management plan.
2. the grid power Management plan defining method based on business diagnosis according to claim 1, it is characterized in that, described electricity needs information comprises electricity sales amount, described electricity sales amount comprises electricity sales amount in large industrial power supply amount, general industry power consumption, resident living power utility amount, non-resident electric consumption on lighting amount, commercial power amount, agricultural production power consumption, bulk sale power consumption, system, the outer electricity sales amount of system and other power consumptions, and described electricity price information comprises sale of electricity unit price.
3. the grid power Management plan defining method based on business diagnosis according to claim 1, it is characterized in that, described electric power supply information comprises purchase of electricity, described purchase of electricity comprises water power purchase of electricity, coal purchases by telephone electricity, electricity purchased by telephone by oil, coal gas purchases by telephone electricity, nuclear power purchase of electricity, regenerative resource purchase of electricity, outer purchase of electricity, other energy purchase of electricity, and described electricity price information comprises power purchase unit price.
4. the grid power Management plan defining method based on business diagnosis according to claim 1, it is characterized in that, described depreciation information comprises ratio of depreciation information and initial asset value information, described ratio of depreciation information comprises transmission line of electricity assets composite depreciation rate, converting equipment assets composite depreciation rate, distribution line and asset of equipments composite depreciation rate, other assets composite depreciation rate, and described initial asset value information comprises average transmit power circuit initial asset value, average converting equipment initial asset value, average distribution line and asset of equipments initial value.
5. the grid power Management plan defining method based on business diagnosis according to Claims 1-4 any one, it is characterized in that, described target component is profit value.
6., based on a grid power Management plan certainty annuity for business diagnosis, it is characterized in that, comprising:
Model building module, for obtaining current power Management plan, set up the electrical network service feature analyses and prediction model corresponding with described current power Management plan, described electrical network service feature analyses and prediction model comprises input parameter, target component;
Data obtaining module, for obtaining external influence factors information, internal operation decision information from power business system, described external influence factors information comprises electricity needs information, electric power supply information, electricity price information, described internal operation decision information is included in builds engineering information, capital assets information, depreciation information, power supply capacity, and described input parameter comprises described external influence factors information, internal operation decision information;
Analysis module, for described input parameter being inputted described electrical network service feature analyses and prediction model, analyzes according to described electrical network service feature analyses and prediction model, determines the output valve of corresponding target component;
Scheme is determined and adjusting module, when imposing a condition for meeting in the output valve of described target component, using current power Management plan as the power operation scheme determined, described target component output valve meet impose a condition time, described current power Management plan is adjusted according to the output valve of described target component, and using the power operation scheme after adjustment as current power Management plan.
7. the grid power Management plan certainty annuity based on business diagnosis according to claim 6, it is characterized in that, described electricity needs information comprises electricity sales amount, described electricity sales amount comprises electricity sales amount in large industrial power supply amount, general industry power consumption, resident living power utility amount, non-resident electric consumption on lighting amount, commercial power amount, agricultural production power consumption, bulk sale power consumption, system, the outer electricity sales amount of system and other power consumptions, and described electricity price information comprises sale of electricity unit price.
8. the grid power Management plan certainty annuity based on business diagnosis according to claim 6, it is characterized in that, described electric power supply information comprises purchase of electricity, described purchase of electricity comprises water power purchase of electricity, coal purchases by telephone electricity, electricity purchased by telephone by oil, coal gas purchases by telephone electricity, nuclear power purchase of electricity, regenerative resource purchase of electricity, outer purchase of electricity, other energy purchase of electricity, and described electricity price information comprises power purchase unit price.
9. the grid power Management plan certainty annuity based on business diagnosis according to claim 6, it is characterized in that, described depreciation information comprises ratio of depreciation information and initial asset value information, described ratio of depreciation information comprises transmission line of electricity assets composite depreciation rate, converting equipment assets composite depreciation rate, distribution line and asset of equipments composite depreciation rate, other assets composite depreciation rate, and described initial asset value information comprises average transmit power circuit initial asset value, average converting equipment initial asset value, average distribution line and asset of equipments initial value.
10. the grid power Management plan certainty annuity based on business diagnosis according to claim 6 to 9 any one, it is characterized in that, described target component is profit value.
CN201510751011.8A 2015-11-05 2015-11-05 Business analysis-based grid electricity operation programme determining method and system Pending CN105205703A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510751011.8A CN105205703A (en) 2015-11-05 2015-11-05 Business analysis-based grid electricity operation programme determining method and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510751011.8A CN105205703A (en) 2015-11-05 2015-11-05 Business analysis-based grid electricity operation programme determining method and system

Publications (1)

Publication Number Publication Date
CN105205703A true CN105205703A (en) 2015-12-30

Family

ID=54953368

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510751011.8A Pending CN105205703A (en) 2015-11-05 2015-11-05 Business analysis-based grid electricity operation programme determining method and system

Country Status (1)

Country Link
CN (1) CN105205703A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106096837A (en) * 2016-06-13 2016-11-09 中国南方电网有限责任公司电网技术研究中心 Power energy allocation method and system based on electric grid investment scale
CN106097140A (en) * 2016-06-13 2016-11-09 中国南方电网有限责任公司电网技术研究中心 Electricity sales amount distribution method and system

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102799952A (en) * 2012-07-13 2012-11-28 中国电力科学研究院 Optimization method of renewable energy source distribution type power generation operation mode
CN102855544A (en) * 2012-08-22 2013-01-02 中国电力科学研究院 Comprehensive evaluation method for distributed power generating project
CN104392334A (en) * 2014-12-12 2015-03-04 冶金自动化研究设计院 Joint optimized scheduling method for multiple types of generating sets of self-supply power plant of iron and steel enterprise
CN104952003A (en) * 2015-07-15 2015-09-30 国网河南省电力公司漯河供电公司 Load management device and management method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102799952A (en) * 2012-07-13 2012-11-28 中国电力科学研究院 Optimization method of renewable energy source distribution type power generation operation mode
CN102855544A (en) * 2012-08-22 2013-01-02 中国电力科学研究院 Comprehensive evaluation method for distributed power generating project
CN104392334A (en) * 2014-12-12 2015-03-04 冶金自动化研究设计院 Joint optimized scheduling method for multiple types of generating sets of self-supply power plant of iron and steel enterprise
CN104952003A (en) * 2015-07-15 2015-09-30 国网河南省电力公司漯河供电公司 Load management device and management method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106096837A (en) * 2016-06-13 2016-11-09 中国南方电网有限责任公司电网技术研究中心 Power energy allocation method and system based on electric grid investment scale
CN106097140A (en) * 2016-06-13 2016-11-09 中国南方电网有限责任公司电网技术研究中心 Electricity sales amount distribution method and system
CN106096837B (en) * 2016-06-13 2018-02-13 中国南方电网有限责任公司电网技术研究中心 Power energy allocation method and system based on electric grid investment scale

Similar Documents

Publication Publication Date Title
Alizadeh et al. Multistage multiresolution robust unit commitment with nondeterministic flexible ramp considering load and wind variabilities
Soroudi et al. Information gap decision theory approach to deal with wind power uncertainty in unit commitment
Zhang et al. Probabilistic wind energy modeling in electric generation system reliability assessment
KR101719428B1 (en) System and method for managing power demand
Chen et al. Electric demand response management for distributed large-scale internet data centers
US8265798B2 (en) System and method of curtailing energy production within congestive grid operating environments
Zhang et al. Two-stage robust security constrained unit commitment considering the spatiotemporal correlation of uncertainty prediction error
Safdarian et al. Domestic EWH and HVAC management in smart grids: Potential benefits and realization
Dehghani et al. Multi-stage resilience management of smart power distribution systems: A stochastic robust optimization model
CN115619288B (en) Method and system for evaluating utilization of distributed comprehensive energy
CN101901430A (en) Power grid risk management and control method and device
KR101572643B1 (en) THE APPARATUS AND METHOD OF NEMO's ELECTRICITY DEMAND RESOURCE MODELING SIMULATION WITH BUSINESS PLATFORM FOR NATIONAL VIRTUAL POWER PLANT
Pourahmadi et al. Economically optimal uncertainty set characterization for power system operational flexibility
Nataf et al. An economic comparison of battery energy storage to conventional energy efficiency technologies in Colorado manufacturing facilities
CN112633762A (en) Building energy efficiency obtaining method and equipment
Butturi et al. A model for renewable energy symbiosis networks in eco-industrial parks
CN105160559A (en) Interactive intelligent power utilization control method and system
CN105205703A (en) Business analysis-based grid electricity operation programme determining method and system
Zuloaga et al. Metrics for use in quantifying power system resilience with water-energy nexus considerations: Mathematical formulation and case study
KR101764758B1 (en) System and method of anaylzing water-energy-food nexus
CN104573858A (en) Prediction, regulation and control method for electric network loads
KR20210011652A (en) System and method for managing power demand using economic dispatch
CN105243513A (en) Optimal configuration method of county power grid funds from bottom to top
CN104036366A (en) Method for evaluating power grid development supporting degree through electric power telecommunication network
CN103345659B (en) Power distribution network Adds User and optimizes access information processing method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20151230

RJ01 Rejection of invention patent application after publication