CN105200869B - Method for quickly constructing embedded rail system from top to bottom - Google Patents

Method for quickly constructing embedded rail system from top to bottom Download PDF

Info

Publication number
CN105200869B
CN105200869B CN201510553112.4A CN201510553112A CN105200869B CN 105200869 B CN105200869 B CN 105200869B CN 201510553112 A CN201510553112 A CN 201510553112A CN 105200869 B CN105200869 B CN 105200869B
Authority
CN
China
Prior art keywords
rail
construction
prefabricated components
fixed
macromolecule
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510553112.4A
Other languages
Chinese (zh)
Other versions
CN105200869A (en
Inventor
焦洪林
杨刚
费学梅
罗炯
何云伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chengdu Xinzhu Transportation Technology Co ltd
Original Assignee
Chengdu Xinzhu Road and Bridge Machinery Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chengdu Xinzhu Road and Bridge Machinery Co Ltd filed Critical Chengdu Xinzhu Road and Bridge Machinery Co Ltd
Priority to CN201510553112.4A priority Critical patent/CN105200869B/en
Publication of CN105200869A publication Critical patent/CN105200869A/en
Application granted granted Critical
Publication of CN105200869B publication Critical patent/CN105200869B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Road Paving Structures (AREA)
  • Machines For Laying And Maintaining Railways (AREA)

Abstract

The invention discloses a method for quickly constructing an embedded rail system from top to bottom. The method comprises construction steps as follows: surveying and setting-out are performed on a line center control line and an elevation control line of a base, steel rails, and high-polymer prefabricated components are transported to a construction site for storage; reinforcing meshes are machined, connected and longitudinally laid on the base in the direction of the rails; the steel rails transported to the construction site are welded and connected, and welding joints are ground to be flat; the high-polymer prefabricated components are bonded to two sides of the steel rails; steel rail assemblies are laid and fine adjusted; a concrete track bed is cast in-situ; maintenance and form stripping are performed. In conclusion, with the adoption of the technical scheme, the construction method comprises the simple and convenient steps and reasonable and novel procedures; construction in first, second and third steps can be performed simultaneously, construction in fourth and fifth steps can also be performed simultaneously, and the construction efficiency is improved; small land is occupied, the noise is low, and the period is short; a fixing tool can effectively adjust and keep the geometry of the steel rails, and the running safety and comfort of a train can be guaranteed.

Description

A kind of embedded tracks system rapid constructing method from top to bottom
Technical field
The present invention relates to a kind of rail system construction method, more particularly, to a kind of embedded tracks system from top to bottom fast Fast construction method, belongs to technical field of rail traffic.
Background technology
With the increase of urban traffic pressure, urban track traffic is due to having that freight volume is big, speed is fast, safety, on schedule, ring The features such as guarantor, energy-conservation, greatly develop in each city.But, the long construction period of urban track traffic, floor space is big, dust Noise seriously waits construction problem, and to urban transportation, resident living brings extreme influence.
In advanced urban rail transit technology field, embedded tracks system is as a kind of new non-fragment orbit system System it should have that construction is quick, construction cost is low, floor space is little, environmental protection attractive in appearance the features such as.
Content of the invention
The goal of the invention of the present invention is: for above-mentioned problem, provides a kind of embedded tracks system by up to Under rapid constructing method, first adjust the track geometry of track, then pour into a mould cast-in-place concrete railway roadbed, construction procedure is simple, quick, , noise little to traffic impact is low, and environmental protection is different from conventional fastener construction.
The technical solution used in the present invention is such that
A kind of embedded tracks system rapid constructing method from top to bottom, including following construction procedure:
Step one: preparation of construction
Using the surveying setting-out method of conventional ballastless track bed substrate, at the construction field (site) the wire center of substrate is controlled Line and elevation control line measure unwrapping wire, lay basis reference as rail assemblies;And rail, macromolecule prefabricated components are transported Deliver to job site storage;
Step 2: laying bar-mat reinforcement
Processing, connection bar-mat reinforcement simultaneously its direction along ng a path are longitudinally laid in substrate;
Step 3: rail welding
The rail being transported to job site is welded even and welding point polishes flat;
Step 4: rail two-side adhesive macromolecule prefabricated components
After floating for Rail Surface rust, dust are cleaned out, special gluing in rail, macromolecule prefabricated components bonding plane brushing Agent, macromolecule prefabricated components are bonded to steel rail web both sides.For ensureing initial adhesive effect, bonding after with binding strap by height Molecule prefabricated components are fixed on rail, during cast-in-place concrete railway roadbed to be cast, then remove binding strap;
Step 5: steel rail laying assembly accurate adjustment
On the basis of wire center control line, rail is simultaneously fixed to ensure by adjustment location of rail with fixing tool temporarily The track geometry of circuit meets design requirement and will not be disturbed during subsequent construction;
Step 6: cast-in-place concrete railway roadbed
In road surface both sides, template seals mould, and concrete should be tried one's best uniformly continuous placing, and during placing, with filling out with shaking Puddling is real;
Step 7: maintenance and form removal
Concrete can take band mould wrap up, water, spray watering measure carry out moisturizing, humidity maintenance.In concrete strength Reach and during 10mpa, get final product form removal.
Preferably, also including step 8: the laying of track surrounding landscape
Laid to carrying out Colophonium, masonry or greening around track according to urban landscape requirement.
Preferably, in step 5, described fixing tool includes a transverse slat, two support bars and two pieces of fixed blocks, Two described support bars are arranged on transverse slat two ends and are temporarily fixed at track both sides, an every support bar piece sleeve pipe of socket, two pieces Described fixed block is respectively placed on an one steel rail and fixed block bottom is provided with the projection matching with the groove inside rail, fixed block It is fixed on below transverse slat by bolt and nut.The purpose of setting sleeve pipe, is after cast-in-place concrete railway roadbed completes for convenience, will Transverse slat, fixed block take out recycling, and sleeve pipe is then directly stayed in railway roadbed.
Preferably, described macromolecule prefabricated components side is fixed with steel rail web side bonds, opposite side designs steel plate Or dowel, realize effectively anchoring with cast-in-place concrete railway roadbed.
In sum, due to employing technique scheme, the invention has the beneficial effects as follows:
1st, operating procedure is simple, quick, and operation is reasonable, novel;
2nd, multiple steps can be constructed simultaneously, such as step one, two, three it is possible to construct simultaneously, step 4, five can also Construct simultaneously, improve efficiency of construction;
3rd, take up an area less, noise is little, cycle is short;
4th, play adjustment, the fixing tool of fixation can effectively adjust and keep the track geometry of rail, to ensure The safety of train operation, comfortableness, stability.
Brief description
Fig. 1 is the cross-sectional structure schematic diagram of track involved by construction method of the present invention.
Fig. 2 is the vertical structure schematic diagram of track involved by construction method of the present invention.
Fig. 3 is the construction process figure of construction method of the present invention.
In figure labelling: 1 is fixing tool, 2 is rail, and 3 is macromolecule prefabricated components, and 4 is concrete road bed, and 5 is reinforcing bar Net, 6 is sleeve pipe.
Specific embodiment
Below in conjunction with the accompanying drawings, the present invention is described in detail.
Embodiment:
, in implementation process, involved structure is as shown in Figure 1, 2 for construction method of the present invention.
A kind of embedded tracks system rapid constructing method from top to bottom, including construction procedure as shown in Figure 3:
Step one: preparation of construction
Using the surveying setting-out method of conventional ballastless track bed substrate, at the construction field (site) the wire center of substrate is controlled Line and elevation control line measure unwrapping wire, lay basis reference as rail assemblies;And by rail 2, macromolecule prefabricated components 3 It is transported to job site storage;
Step 2: laying bar-mat reinforcement 5
Processing, connection bar-mat reinforcement 5 simultaneously its direction along ng a path are longitudinally laid in substrate.
Step 3: rail 2 welds
Rail 2 company of weldering of job site will be transported to and welding point polishes flat.
Step 4: rail 2 two-side adhesive macromolecule prefabricated components 3
After floating for rail 2 surface rust, dust are cleaned out, special in rail 2, macromolecule prefabricated components 3 bonding plane brushing Adhesive, macromolecule prefabricated components 3 are bonded to rail 2 web of the rail both sides.For ensure initial adhesive effect, bonding after use colligation Macromolecule prefabricated components 3 are fixed on rail 2 band, during cast-in-place concrete railway roadbed 4 to be cast, then remove binding strap.
Described macromolecule prefabricated components 3 side is fixed with rail 2 web of the rail side bonds, and opposite side designs steel plate or dowel, Realize effectively anchoring with cast-in-place concrete railway roadbed 4.
Step 5: steel rail laying assembly accurate adjustment
On the basis of wire center control line, adjustment rail 2 position and with fixing tool 1 by rail 2 fix temporarily with Ensure that the track geometry of circuit meets design requirement and will not be disturbed during subsequent construction.
In step 5, described fixing tool 1 includes a transverse slat, two support bars and two pieces of fixed blocks, described in two Support bar is arranged on transverse slat two ends and is temporarily fixed at track both sides, and every support bar is socketed a sleeve pipe, two pieces of described fixations Block is respectively placed on an one steel rail 2 and fixed block bottom is provided with the projection matching with the groove inside rail 2, and fixed block passes through spiral shell Bolt nut is fixed on below transverse slat.
Step 6: cast-in-place concrete railway roadbed
In road surface both sides, template seals mould, and concrete should be tried one's best uniformly continuous placing, and during placing, with filling out with shaking Puddling is real.
Step 7: maintenance and form removal
Concrete can take band mould wrap up, water, spray watering measure carry out moisturizing, humidity maintenance.In concrete strength Reach and during 10mpa, get final product form removal.
Also include step 8: track surrounding landscape laying
Laid to carrying out Colophonium, masonry or greening around track according to urban landscape requirement.

Claims (4)

1. a kind of embedded tracks system rapid constructing method from top to bottom is it is characterised in that include following construction procedure:
Step one: preparation of construction
Using the surveying setting-out method of conventional ballastless track bed substrate, at the construction field (site) the wire center control line to substrate and Elevation control line measures unwrapping wire, lays basis reference as rail assemblies;And rail, macromolecule prefabricated components are transported to Job site is stored;
Step 2: laying bar-mat reinforcement
Processing, connection bar-mat reinforcement simultaneously its direction along ng a path are longitudinally laid in substrate;
Step 3: rail welding
The rail being transported to job site is welded even and welding point polishes flat;
Step 4: rail two-side adhesive macromolecule prefabricated components
After floating for Rail Surface rust, dust are cleaned out, in rail, macromolecule prefabricated components bonding plane brushing special-purpose adhesive, Macromolecule prefabricated components are bonded to steel rail web both sides, for ensureing initial adhesive effect, bonding after with binding strap by high score Sub- prefabricated components are fixed on rail, during cast-in-place concrete railway roadbed to be cast, then remove binding strap;
Step 5: steel rail laying assembly accurate adjustment
On the basis of wire center control line, adjustment location of rail is simultaneously fixed rail to ensure circuit with fixing tool temporarily Track geometry meet design requirement and will not be disturbed during subsequent construction;
Step 6: cast-in-place concrete railway roadbed
In road surface both sides, template seals mould, and concrete should be tried one's best uniformly continuous placing, and during placing, close with vibrating with filling out Real;
Step 7: maintenance and form removal
Concrete can take band mould wrap up, water, spray watering measure carry out moisturizing, humidity maintenance, reach in concrete strength Form removal is got final product during 10mpa.
2. a kind of embedded tracks system according to claim 1 rapid constructing method from top to bottom it is characterised in that:
Also include step 8: track surrounding landscape laying
Laid to carrying out Colophonium, masonry or greening around track according to urban landscape requirement.
3. a kind of embedded tracks system according to claim 1 rapid constructing method from top to bottom it is characterised in that: In step 5, described fixing tool includes a transverse slat, two support bars and two pieces of fixed blocks, two described support bar settings At transverse slat two ends and be temporarily fixed at track both sides, every support bar is socketed a sleeve pipe, and two pieces of described fixed blocks are respectively placed in On one one steel rail and fixed block bottom is provided with the projection matching with the groove inside rail, fixed block is fixed on by bolt and nut Below transverse slat.
4. a kind of embedded tracks system according to claim 1 rapid constructing method from top to bottom it is characterised in that: Described macromolecule prefabricated components side is fixed with steel rail web side bonds, and opposite side designs steel plate or dowel, with cast-in-place coagulation Dirt road bed is realized effectively anchoring.
CN201510553112.4A 2015-09-02 2015-09-02 Method for quickly constructing embedded rail system from top to bottom Active CN105200869B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510553112.4A CN105200869B (en) 2015-09-02 2015-09-02 Method for quickly constructing embedded rail system from top to bottom

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510553112.4A CN105200869B (en) 2015-09-02 2015-09-02 Method for quickly constructing embedded rail system from top to bottom

Publications (2)

Publication Number Publication Date
CN105200869A CN105200869A (en) 2015-12-30
CN105200869B true CN105200869B (en) 2017-01-18

Family

ID=54948804

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510553112.4A Active CN105200869B (en) 2015-09-02 2015-09-02 Method for quickly constructing embedded rail system from top to bottom

Country Status (1)

Country Link
CN (1) CN105200869B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112064424B (en) * 2020-08-07 2022-05-17 上海远通路桥工程有限公司 Quick construction method for road section track at level crossing
CN112761034B (en) * 2020-12-24 2022-08-09 成都市新筑路桥机械股份有限公司 Fluid material pouring trolley

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2008003843A2 (en) * 2006-07-07 2008-01-10 Lohr Industrie Self-cleaning assembly employing a gap filler for a guidance or runway rail on the ground
CN101812819A (en) * 2010-04-28 2010-08-25 中铁二十局集团有限公司 Whole construction process for double block type ballastless track
CN103362036A (en) * 2013-07-24 2013-10-23 成都市新筑路桥机械股份有限公司 Quick construction method of embedded rail system
CN103452014A (en) * 2013-09-17 2013-12-18 浙江天铁实业股份有限公司 Tramcar vibration-absorbing and noise-damping structure

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101557024B1 (en) * 2013-03-06 2015-10-02 강남훈 Three-dimensional solid shape of the Embedded Rail concrete block manufacturing method and Embedded Rail Track System constructing methods using Embedded Rail concrete blocks manufactured by this method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2008003843A2 (en) * 2006-07-07 2008-01-10 Lohr Industrie Self-cleaning assembly employing a gap filler for a guidance or runway rail on the ground
CN101812819A (en) * 2010-04-28 2010-08-25 中铁二十局集团有限公司 Whole construction process for double block type ballastless track
CN103362036A (en) * 2013-07-24 2013-10-23 成都市新筑路桥机械股份有限公司 Quick construction method of embedded rail system
CN103452014A (en) * 2013-09-17 2013-12-18 浙江天铁实业股份有限公司 Tramcar vibration-absorbing and noise-damping structure

Also Published As

Publication number Publication date
CN105200869A (en) 2015-12-30

Similar Documents

Publication Publication Date Title
CN101215812B (en) Construction method for passenger transport dedicated line bolster embedded large-size ballastless track
CN108286210B (en) A kind of rapid constructing method of embedded railway points system
BR112013016308A2 (en) method for producing a slab railway
CN102653931B (en) Elastic supporting vibration isolation member ballast bed
CN101418535A (en) Construction method of monolithic road-bed in rail tunnel
CN204940141U (en) The reinforcement system of existing line in Framed underpass bridge process
CN105200869B (en) Method for quickly constructing embedded rail system from top to bottom
CN204343108U (en) A kind of split type continuous support ballast bed system
CN103374865B (en) Construction method for longitudinally connecting and laying ballastless track slabs
CN101691726A (en) Construction technology of double-block type ballastless track
CN103088727B (en) Deflection-resisting rail spacing device
CN107313313B (en) The framed bent construction method of prefabricated urethane cures railway roadbed
CN208604416U (en) A kind of continuous supporting track structure of assemblyization
JP2002227101A (en) Sleeper-integrated concrete ballast structure for railway line
CN105350409B (en) Urban track traffic bolster formula steel spring floating slab road bed railroad switch construction method
CN204715134U (en) Flush type track
CN101967782A (en) Construction method of ladder-shaped track in urban track traffic
JP4620044B2 (en) Rail structure for rail vehicles, especially railways
WO2024041054A1 (en) Prefabricated track structure for built-in pump house section in rail transportation and construction method
CN202099699U (en) Elastic supporting vibration isolation component ballast bed
CN2758310Y (en) Biblock type rail bearing
CN1837473A (en) Concrete-pouring method for double-block type ballastless track
KR100759923B1 (en) Low height and longspan girder for a railway
CN206233043U (en) Rail and railroad track
CN105421160A (en) Concrete foundation bed top face line type control method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20190904

Address after: 225000 Room 103, 4 Blocks, Wankejin Street, East Stumiao Road, Yangzhou City, Jiangsu Province

Patentee after: Jiangsu Huadong culture and technology Financing Leasing Co.,Ltd.

Address before: 611430 Xinjin Industrial Park, Sichuan, Chengdu

Patentee before: CHENGDU XINZHU ROAD & BRIDGE MACHINERY Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20191223

Address after: 101300, room 711, building 2, building 1, Golden Road, Beijing, Shunyi District (Tianzhu comprehensive bonded area, -031)

Patentee after: Beijing culture science and technology finance leasing Limited by Share Ltd.

Address before: 225000 Room 103, 4 Blocks, Wankejin Street, East Stumiao Road, Yangzhou City, Jiangsu Province

Patentee before: Jiangsu Huadong culture and technology Financing Leasing Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20221212

Address after: 611430 Xinjin Industrial Park, Xinjin District, Chengdu, Sichuan

Patentee after: CHENGDU XINZHU ROAD & BRIDGE MACHINERY Co.,Ltd.

Address before: 101300 room 711, 2 building, 1 Jin Hang Zhong Road, Shunyi District, Beijing (Tianzhu comprehensive bonded zone -031)

Patentee before: Beijing culture science and technology finance leasing Limited by Share Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20240116

Address after: 611400 No. 799, hope road, Wujin street, Xinjin District, Chengdu, Sichuan (Industrial Park)

Patentee after: Chengdu Xinzhu Transportation Technology Co.,Ltd.

Address before: 611430 Xinjin Industrial Park, Xinjin District, Chengdu, Sichuan

Patentee before: CHENGDU XINZHU ROAD & BRIDGE MACHINERY Co.,Ltd.