CN105186338A - Construction method of employing insulation bucket arm vehicle insulating gloves with load to change pole top switch device - Google Patents
Construction method of employing insulation bucket arm vehicle insulating gloves with load to change pole top switch device Download PDFInfo
- Publication number
- CN105186338A CN105186338A CN201510471581.1A CN201510471581A CN105186338A CN 105186338 A CN105186338 A CN 105186338A CN 201510471581 A CN201510471581 A CN 201510471581A CN 105186338 A CN105186338 A CN 105186338A
- Authority
- CN
- China
- Prior art keywords
- switch
- insulated
- truck
- bucket arm
- pole
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000009413 insulation Methods 0.000 title claims abstract description 37
- 238000010276 construction Methods 0.000 title claims abstract description 36
- 230000005611 electricity Effects 0.000 claims abstract description 12
- 238000007689 inspection Methods 0.000 claims abstract description 10
- 238000002360 preparation method Methods 0.000 claims abstract description 9
- 238000009434 installation Methods 0.000 claims abstract description 8
- 238000005259 measurement Methods 0.000 claims abstract description 7
- 239000012071 phase Substances 0.000 claims description 28
- 239000008385 outer phase Substances 0.000 claims description 9
- 239000004568 cement Substances 0.000 claims description 8
- 239000008384 inner phase Substances 0.000 claims description 8
- 238000012360 testing method Methods 0.000 claims description 8
- 239000012212 insulator Substances 0.000 claims description 3
- 238000001514 detection method Methods 0.000 claims description 2
- 238000002955 isolation Methods 0.000 abstract description 8
- 238000012423 maintenance Methods 0.000 abstract description 2
- 238000000034 method Methods 0.000 description 19
- 239000002184 metal Substances 0.000 description 7
- WABPQHHGFIMREM-UHFFFAOYSA-N lead(0) Chemical compound [Pb] WABPQHHGFIMREM-UHFFFAOYSA-N 0.000 description 6
- 239000000463 material Substances 0.000 description 6
- 230000001681 protective effect Effects 0.000 description 3
- 238000012549 training Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000009933 burial Methods 0.000 description 1
- 238000004140 cleaning Methods 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000009863 impact test Methods 0.000 description 1
- 201000001371 inclusion conjunctivitis Diseases 0.000 description 1
- 239000012211 strain insulator Substances 0.000 description 1
- 239000013589 supplement Substances 0.000 description 1
- 206010044325 trachoma Diseases 0.000 description 1
- 238000012546 transfer Methods 0.000 description 1
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
- Y02A30/00—Adapting or protecting infrastructure or their operation
- Y02A30/14—Extreme weather resilient electric power supply systems, e.g. strengthening power lines or underground power cables
Landscapes
- Forklifts And Lifting Vehicles (AREA)
Abstract
本发明提供一种绝缘斗臂车绝缘手套带负荷更换柱上开关设备的施工方法,包括以下步骤:施工准备;验电测电并设置绝缘遮蔽;安装旁路引流线;断路器退出运行并拆除原有的引流线;拆除开关;检测并吊装新开关;搭接断路器两侧引线;新的断路器投入运行并拆除旁路引流线;拆除绝缘遮蔽;撤离杆塔。本发明在确保操作安全和用电安全的基础上,实现了10KV线路带负荷更换开关,在不停一个用户用电的情况下,实现隔离刀闸的更换,为电力工程线上维修领域提供了全新的工作模式,对供、用电企业都将带来巨大的经济效益。The invention provides a construction method for replacing switchgear on a pole with loads of insulating gloves on an insulated bucket arm truck, comprising the following steps: construction preparation; electrical inspection and electrical measurement and insulation shielding; installation of bypass drain wires; circuit breaker out of operation and removal The original drain line; remove the switch; detect and hoist the new switch; lap the lead wires on both sides of the circuit breaker; put the new circuit breaker into operation and remove the bypass drain line; remove the insulation shielding; evacuate the tower. On the basis of ensuring safe operation and safe use of electricity, the present invention realizes the replacement switch of a 10KV line with load, and realizes the replacement of the isolation knife switch without stopping the power consumption of one user, which provides a great advantage for the field of online maintenance of electric power engineering The new working mode will bring huge economic benefits to both power supply and power consumption enterprises.
Description
技术领域technical field
本发明涉及电力工程领域。The invention relates to the field of electric power engineering.
背景技术Background technique
运行的10KV线路中,柱上开关(隔离刀闸)对该开关后段的线路、负荷起着控制、保护作用,运行中常常会遇到有的开关机械部分发生故障不能操作、有的开关需要增加容量的情况,这就必须更换此柱上开关(隔离刀闸),目前通常采用下列方法更换:1、停电更换:采用这种方法更换,需要拉开开关上一级开关,造成部分甚至全线停电。2、切除开关后段线路上所有负荷,然后带电拆除开关上引线,再更换开关,更换期间开关后段线路上所有用户就不能用电。由于电力成为日常生活中必不可少的能源,部分甚至全线断电必然给用户造成很大的不便。In the running 10KV line, the switch on the column (isolation knife switch) plays a role in controlling and protecting the line and load in the rear section of the switch. During operation, it is often encountered that some mechanical parts of the switch fail to operate, and some switches require In the case of increasing capacity, it is necessary to replace the switch (isolation switch) on the column. At present, the following methods are usually used for replacement: 1. Replacement after power failure: In this method, it is necessary to pull the switch on the upper level of the switch, causing some or even the entire line to be replaced. power failure. 2. Cut off all the loads on the line at the rear of the switch, then remove the upper lead of the switch with electricity, and then replace the switch. During the replacement, all users on the line at the back of the switch will not be able to use electricity. Since electricity has become an indispensable source of energy in daily life, partial or even full-line power outages will inevitably cause great inconvenience to users.
发明内容Contents of the invention
本发明所要解决的技术问题是提供一种绝缘斗臂车绝缘手套带负荷更换柱上开关设备的施工方法,能够在不断电的情况下进行开关设备的更换,最大程度地保障线上用户的利益。The technical problem to be solved by the present invention is to provide a construction method for replacing the switchgear on the pole with the insulated gloves of the insulated bucket arm truck under load, which can replace the switchgear without power interruption, and protect the interests of online users to the greatest extent .
本发明解决技术问题所采用的技术方案是:The technical scheme that the present invention solves technical problem adopts is:
绝缘斗臂车绝缘手套带负荷更换柱上开关设备的施工方法,所述施工方法包括以下步骤:A construction method for replacing switchgear on a pole with loads of insulating gloves on an insulating bucket truck, the construction method includes the following steps:
1)施工准备:检查气象条件、周围环境、线路装置和安全措施,布置现场,安放绝缘斗臂车和绝缘工器具;1) Construction preparation: check the meteorological conditions, surrounding environment, line installation and safety measures, arrange the site, and place insulating bucket trucks and insulating tools;
2)验电测电并设置绝缘遮蔽;2) Electrical inspection and electrical measurement and insulation shielding;
3)操作开关使其锁闭,分别在开关的进线侧和出线侧安装旁路引流线;3) Operate the switch to lock it, and install bypass drainage lines on the incoming line side and outgoing line side of the switch respectively;
4)断路器退出运行,并拆除开关两侧的原有的引流线;4) The circuit breaker is out of operation, and the original drainage wires on both sides of the switch are removed;
5)拆除开关;5) Remove the switch;
6)检测并吊装新开关;6) Detect and hoist the new switch;
7)搭接带电柱上断路器两侧引线;7) Lap the lead wires on both sides of the circuit breaker on the live column;
8)新的断路器投入运行并拆除旁路引流线;8) The new circuit breaker is put into operation and the bypass drain line is removed;
9)拆除绝缘遮蔽;9) Remove insulation shielding;
10)撤离杆塔。10) Evacuate the tower.
在采用上述技术方案的同时,本发明还可以采用或者组合采用以下进一步的技术方案:While adopting the above-mentioned technical solution, the present invention can also adopt or adopt the following further technical solutions in combination:
步骤1)的施工准备包括:The construction preparation of step 1) includes:
1.1、检查气象条件、周围环境、线路装置和安全措施;1.1. Check the meteorological conditions, surrounding environment, wiring devices and safety measures;
1.2、布置现场:在工作现场设置安全护栏、作业标志和相关警示标志;1.2. Arranging the site: set up safety guardrails, operation signs and related warning signs at the work site;
1.3、对绝缘斗臂车及车上工作人员进行编号并安放绝缘斗臂车,绝缘斗臂车达到作业位置并避开附近电力线和障碍物,避免停放在沟道盖板上,绝缘斗臂车支腿顺序为先伸出水平支腿,再伸出垂直支腿,支撑到位后车辆前后左右呈水平,四轮离地,绝缘斗臂车停放在软土地面时使用垫板或枕木,垫板重叠不超过2块且互成45°角,停放位置为坡地时,停放坡度≯7°,车头超下坡方向停放,先支前支腿,后支后支腿,调整水平后车辆前后高度差≯3°,绝缘斗臂车临时接地体埋深≮0.6m;1.3. Number the insulated bucket truck and the staff on it and place the insulated bucket truck. The insulated bucket truck reaches the working position and avoids nearby power lines and obstacles. Avoid parking on the ditch cover. The insulated bucket truck The order of outriggers is to first extend the horizontal outriggers, and then extend the vertical outriggers. After the support is in place, the front, rear, left, and right sides of the vehicle are horizontal, and the four wheels are off the ground. Overlap no more than 2 blocks and form an angle of 45° with each other. When the parking position is on a slope, the parking slope is ≯7°. When the front of the car is parked in the downhill direction, the front outriggers are supported first, and the rear outriggers are supported at the rear. The height difference between the front and rear of the vehicle after adjustment ≯3°, the buried depth of the temporary grounding body of the insulated bucket arm truck is ≮0.6m;
1.4、对绝缘工器具进行检查,采用绝缘电阻测试仪对绝缘工器具进行表面绝缘电阻检测,阻值不低于700MΩ,检查完毕的绝缘工器具摆放在防潮垫上。1.4. Inspect the insulating tools and appliances. Use an insulation resistance tester to test the surface insulation resistance of the insulating tools and appliances. The resistance value is not less than 700MΩ. The inspected insulating tools and appliances are placed on the moisture-proof mat.
所述步骤2)具体包括以下步骤:Described step 2) specifically comprises the following steps:
2.1、验电:每台绝缘斗臂车内的1号作业人员用高压验电器对横担、顶相抱箍进行验电,确认绝缘子无泄漏电流;2.1. Electricity inspection: No. 1 operator in each insulated bucket arm vehicle uses a high-voltage electroscope to conduct an electric inspection on the cross arm and top phase hoop to confirm that the insulator has no leakage current;
2.2、测电:每台绝缘斗臂车内的1号作业人员用钳形电流表测量各相引流线的电流;2.2. Electricity measurement: No. 1 operator in each insulated bucket arm car uses a clamp ammeter to measure the current of each phase's drain wire;
2.3、设置绝缘遮蔽:将作业通道内不符合作业安全距离的带电部位和接地体用绝缘毯及绝缘软管进行绝缘遮蔽。2.3. Set up insulation shielding: use insulating blankets and insulating hoses to insulate and shield the live parts and grounding bodies in the working channel that do not meet the working safety distance.
所述步骤4)中拆除引流线的顺序为:先拆内边相、后拆外边相、再拆中间相引线。The order of removing the drain wires in step 4) is: first remove the inner phase, then remove the outer phase, and then remove the middle phase lead.
所述步骤5)具体包括以下步骤:Described step 5) specifically comprises the following steps:
5.1、1号绝缘斗臂车的2号作业人员操作小吊,使吊钩处在开关上方的适当位置;5.1, No. 2 operator of No. 1 insulated bucket arm truck operates the small crane, so that the hook is in an appropriate position above the switch;
5.2、将吊钩挂人吊开关的绳套,收小吊牵引绳,使牵引绳微受力;5.2. Hang the hook on the rope cover of the human crane switch, and close the traction rope of the small crane, so that the traction rope is slightly stressed;
5.3、2号绝缘斗臂车的2号作业人员拆除开关与开关之家的固定螺丝,或开关之家和水泥杆固定抱箍的对销螺帽;5.3. The No. 2 operator of the No. 2 insulated bucket arm truck removes the fixing screws of the switch and the switch house, or the counter-pin nut of the switch house and the cement pole fixing hoop;
5.4、1号绝缘斗臂车的2号作业人员操作小吊将开关吊至地面。5.4. Operator No. 2 of No. 1 insulated arm truck operates a small crane to hoist the switch to the ground.
所述步骤6)中的检测新开关包括以下步骤:The detection new switch in described step 6) comprises the following steps:
6.1、对新开关进行分合操作2-3次,确认开关灵活,指示无误;6.1. Open and close the new switch 2-3 times to confirm that the switch is flexible and the instructions are correct;
6.2、用2500V绝缘电阻表测量相间和相对地的绝缘电阻,确保二者均大于500兆欧。6.2. Use a 2500V insulation resistance meter to measure the insulation resistance between phases and phases to ensure that both are greater than 500 megohms.
所述步骤6)中的吊装新开关包括以下步骤:Said step 6) in the hoisting new switch comprises the following steps:
6.3、1号绝缘斗臂车的2号作业人员操作小吊,将开关吊至带安装位置;6.3. Operator No. 2 of No. 1 insulated bucket arm truck operates the small crane and lifts the switch to the belt installation position;
6.4、2号绝缘斗臂车的2号作业人员拧紧开关与开关之家的固定螺丝,或者开关支架和水泥杆固定抱箍的对销螺帽。6.4. The No. 2 operator of the No. 2 insulated bucket arm truck tightens the fixing screws of the switch and the switch house, or the counter-pin nuts of the switch bracket and the cement pole fixing hoop.
所述步骤7)具体包括以下步骤:Described step 7) specifically comprises the following steps:
7.1、地面作业人员安装好新柱上断路器两侧的引流线,罩好绝缘罩,拉开断路器;7.1. The ground operators install the drain wires on both sides of the circuit breaker on the new column, cover the insulation cover, and pull the circuit breaker;
7.2、两台绝缘斗臂车内的作业人员分别搭接柱上断路器的两侧引线;7.2. The operators in the two insulated bucket arm vehicles respectively lap the lead wires on both sides of the circuit breaker on the column;
7.3、合上柱上断路器,用电流表确认已分流;7.3. Close the circuit breaker on the column, and use the ammeter to confirm that the current has been shunted;
7.4、两台绝缘斗臂车内的作业人员分别拆除柱上断路器的两侧引线。7.4. The operators in the two insulated arm trucks removed the lead wires on both sides of the circuit breaker on the pole respectively.
所述步骤8)具体包括以下步骤:Described step 8) specifically comprises the following steps:
8.1、1号绝缘斗臂车内的1号作业人员操作开关使其处于合闸位置;8.1. The No. 1 operator in the No. 1 insulating arm car operates the switch to make it in the closing position;
8.2、用钳形电流表测量开关各相引流线电流是否正常,从而确认开关正常运行;8.2. Use a clamp ammeter to measure whether the current of each phase of the switch is normal, so as to confirm the normal operation of the switch;
8.3、确认无误后,拆除步骤3)中安装的旁路引流线。8.3. After confirming that it is correct, remove the bypass drainage line installed in step 3).
所述步骤8)中拆除引流线的顺序为:先中间相、后外边相、再内边相。The sequence of removing the drainage wires in step 8) is: first the middle phase, then the outer phase, and then the inner phase.
本发明的有益效果是:本发明采用两台绝缘斗臂车相互配合的施工形式,在确保操作安全和用电安全的基础上,实现了10KV线路带负荷更换开关,在不停一个用户用电的情况下,实现隔离刀闸的更换,为电力工程线上维修领域提供了全新的工作模式,对供、用电企业都将带来巨大的经济效益。The beneficial effects of the present invention are: the present invention adopts the construction form of two insulated bucket trucks cooperating with each other, and on the basis of ensuring safe operation and safe use of electricity, it realizes the replacement switch of the 10KV line with load, without stopping the power consumption of one user. Under the circumstances, realizing the replacement of the isolation switch provides a new working mode for the field of electric power engineering online maintenance, and will bring huge economic benefits to both the power supply and power consumption enterprises.
具体实施方式Detailed ways
本发明的施工方法要求至少6人的工作团队,其中至少有一名具有3年以上配电带电作业实际工作经验,熟悉设备状况,具有一定组织能力和事故处理能力,并经工作负责人的专门培训,考试合格的人员作为工作负责人(监护人),4名通过10kV配电线路带电作业专项培训,考试合格并持有上岗证的人员分别作为绝缘斗臂车内的作业人员,1名通过10kV配电线路专项培训,考试合格并持有上岗证的人员作为地面作业人员。The construction method of the present invention requires a working team of at least 6 people, at least one of whom has more than 3 years of practical work experience in power distribution and live work, is familiar with equipment conditions, has certain organizational capabilities and accident handling capabilities, and has been specially trained by the person in charge of the work , the person who passes the test is the person in charge (guardian), 4 people who have passed the special training for 10kV distribution line live work, and the people who have passed the test and hold the job certificate are respectively used as the operators in the insulated arm car, and 1 person who has passed the 10kV distribution line Special training for electric lines, personnel who have passed the examination and hold employment certificates shall serve as ground operators.
本发明的施工方法应至少配备以下工器具和材料:The construction method of the present invention should at least be equipped with following implements and materials:
表1、个人安全防护用具Table 1. Personal safety protective equipment
表2、常备器具Table 2. Standing equipment
表3、绝缘遮蔽工具Table 3. Insulation and shielding tools
表4、绝缘工具Table 4. Insulation tools
表5、其他工器具:常规的线路施工所需工器具,如扳手等。Table 5. Other tools: Tools required for conventional line construction, such as wrenches.
表6、材料:包括装置性材料和消耗性材料。Table 6. Materials: including device materials and consumable materials.
本发明的施工方法具体包括以下步骤:Construction method of the present invention specifically comprises the following steps:
步骤1、施工准备。Step 1. Construction preparation.
施工准备阶段主要是进行施工前的一系列准备活动,包括条件检查、装配配置以及人员配备等事项。The construction preparation stage is mainly a series of preparatory activities before construction, including condition inspection, assembly configuration and staffing.
在施工准备阶段,首先,由工作负责人核对工作线路的命名和水泥杆杆号,工作负责人检查施工周边环境是否符合作业要求(什么样的情况算是符合要求?),检查线路装置是否具备带电作业条件(具备带电作业条件是指什么条件?),检查气象条件,检查安全措施,必要时可以补充安全措施。In the construction preparation stage, first of all, the person in charge of the work checks the name of the working line and the number of the cement pole. Operating conditions (what are the conditions for having live working conditions?), check the weather conditions, check the safety measures, and supplement safety measures if necessary.
所检查的气象条件通常需要满足以下几点:1.天气应晴好,无雷、雨、雪、雾;2.气温:-5~35℃;3.风力:<5级;4.空气相对湿度<80%。The meteorological conditions to be inspected usually need to meet the following points: 1. The weather should be fine, without thunder, rain, snow, fog; 2. Temperature: -5 ~ 35 ℃; 3. Wind force: <5 levels; 4. Relative humidity of the air <80%.
上述条件检查齐备后,由工作负责人与调度联系,获得调度工作许可,确认线路重合闸已停用。After the above conditions are checked, the person in charge of the work will contact the dispatcher to obtain the dispatcher's work permit and confirm that the line recloser has been disabled.
然后,进行工作现场布置,包括在工作现场设置安全护栏、作业标志和相关警示标志。Then, arrange the work site, including setting up safety guardrails, operation signs and related warning signs on the work site.
接着,由绝缘斗臂车作业人员停放绝缘斗臂车,本施工方法需要用到两台绝缘斗臂车,分别编号为1号车和2号车,每台绝缘斗臂车配备两名作业人员,分别编号为1号作业人员和2号作业人员。Next, the insulated bucket truck operators park the insulated bucket truck. This construction method requires two insulated bucket trucks, numbered No. 1 and No. 2, and each insulated bucket truck is equipped with two operators. , respectively numbered as operator No. 1 and operator No. 2.
停放绝缘斗臂车的具体过程如下:The specific process of parking the insulated bucket truck is as follows:
一、作业人员分别将1号车和2号车停放到最佳位置,此过程中需要遵循以下几点:1.应便于绝缘斗臂车工作斗达到作业位置,避开附近电力线和障碍物;2.避免停放在沟道盖板上;3.软土地面应使用垫块或枕木,垫放时垫板重叠不超过2块,呈45°角;4.停放位置如为坡地,停放位置坡度≯7°,绝缘斗臂车车头应朝下坡方向停放。1. The operators park the No. 1 car and No. 2 car in the best position respectively. During this process, the following points need to be followed: 1. It should be convenient for the working bucket of the insulated bucket arm truck to reach the working position, avoiding nearby power lines and obstacles; 2. Avoid parking on the ditch cover; 3. Pads or sleepers should be used on soft ground. When padded, the pads overlap no more than 2 pieces, forming an angle of 45°; 4. If the parking position is on a slope, the slope of the parking position ≯7°, the front of the insulated bucket truck should be parked facing downhill.
二、作业人员操作1号车和2号车进行支腿,在此过程中需要遵循以下几点:1.支腿顺序应正确:应先伸出水平支腿,再伸出垂直支腿;2.在坡地停放,应先支前支腿,后支后支腿;3.支撑应到位,车辆前后、左右呈水平;四轮应离地;4.坡地停放调整水平后,车辆前后高度应≯3°。2. The operator operates No. 1 car and No. 2 car to carry out outriggers. During the process, the following points need to be followed: 1. The order of outriggers should be correct: the horizontal outriggers should be extended first, and then the vertical outriggers should be extended; 2. .When parking on a slope, the front outriggers should be supported first, and then the rear outriggers should be supported; 3. The support should be in place, and the front, rear, left and right sides of the vehicle should be level; the four wheels should be off the ground; 4. After parking on a slope and adjusting the level, the front and rear heights of the vehicle should be 3°.
三、作业人员将1号车和2号车可靠接地,临时接地体的埋深不少于0.6m。3. The operators ground the No. 1 car and the No. 2 car reliably, and the burial depth of the temporary grounding body is not less than 0.6m.
停好绝缘斗臂车后,检查绝缘工器具,具体过程如下:After parking the insulated bucket truck, check the insulating tools. The specific process is as follows:
一、将绝缘工器具摆放在防潮垫(毯)上,防潮垫(毯)应清洁、干燥,绝缘工器具不能与金属工具、材料混放。1. Put the insulating tools and appliances on the moisture-proof mat (blanket). The moisture-proof mat (blanket) should be clean and dry. The insulating tools and appliances should not be mixed with metal tools and materials.
二、对绝缘工器具进行外观检查:绝缘工具应不变形损坏,操作灵活,测量准确;个人安全防护用具和遮蔽、隔离用具应无针孔、砂眼、裂纹;并作冲击试验;检察人员必须佩带清洁、干燥的手套。2. Appearance inspection of insulation tools: insulation tools should not be deformed and damaged, flexible in operation, and accurate in measurement; personal safety protective equipment, shielding, and isolation equipment should be free of pinholes, trachoma, and cracks; impact tests should be carried out; inspectors must wear them Clean, dry gloves.
三、使用绝缘电阻测试仪对绝缘工器具进行表面绝缘电阻检测:阻值不得低于700MΩ。3. Use an insulation resistance tester to test the surface insulation resistance of insulating tools: the resistance value should not be lower than 700MΩ.
之后,绝缘斗臂车的作业人员对绝缘斗臂车进行检查,具体包括检查绝缘斗臂车表面状况:绝缘部分应清洁、无裂纹损伤。Afterwards, the operators of the insulating bucket truck inspect the insulating bucket truck, including checking the surface condition of the insulating bucket truck: the insulating part should be clean and free of crack damage.
检查完毕后,斗内作业人员根据电力系统安全作业要求穿戴相应的工作服和安全防护用具并携带工具进入绝缘斗臂车的工作斗,斗内作业人员系好绝缘安全带。After the inspection is completed, the workers in the bucket wear corresponding work clothes and safety protective equipment according to the safe operation requirements of the power system, and carry tools into the working bucket of the insulated bucket arm truck, and the operators in the bucket fasten the insulating safety belt.
至此,施工准备阶段完成,正式进入施工阶段。At this point, the construction preparation stage is completed and the construction stage is officially entered.
步骤2,验电测点并设置绝缘遮蔽。Step 2, electrical testing points and setting insulation shielding.
2.1验电。2.1 Electricity test.
两台绝缘斗臂车内的1号作业人员(斗内作业人员)用高压验电器对横担、顶相抱箍进行验电,确认绝缘子无泄漏电流。Worker No. 1 (operator inside the bucket) in the two insulated bucket arm vehicles used a high-voltage electroscope to conduct an electric test on the cross arm and top phase hoop to confirm that the insulator has no leakage current.
在此过程中需要遵循以下几点:1.转移工作斗时应注意绝缘斗臂车周围杆塔、线路等情况,绝缘臂的金属部位与带电体和地电位物体的距离大于1.0m;2.作业时,绝缘臂的伸出长度应大于等于1.0m;3.斗内1号作业人员验电时,应戴绝缘手套;验电器使用前应进行自检,并在带电体上试验。The following points need to be followed in this process: 1. When transferring the working bucket, pay attention to the poles, towers and lines around the insulated bucket arm truck. The distance between the metal part of the insulated arm and the charged body and ground potential object is greater than 1.0m; 2. Operation 3. The No. 1 operator in the bucket should wear insulating gloves when inspecting the electricity; the electroscope should be self-inspected before use and tested on the live body.
2.2测电。2.2 Electricity measurement.
1号作业人员用钳形电流表测量各相引流线电流。在此过程中需要遵循以下几点:1.应注意保持与带电部位的安全距离;2.正确使用钳形电流表。Worker No. 1 uses a clamp ammeter to measure the current of each phase drain line. In this process, the following points need to be followed: 1. Pay attention to keep a safe distance from the live parts; 2. Use the clamp ammeter correctly.
2.3设置绝缘遮蔽。2.3 Set up insulation shielding.
1号车和2号车分别负责待作业开关的进线侧和出线侧;斗内作业人员取得工作负责人同意后:1)用电流表测量负荷电流,确认其在引流线及旁路真空隔离开关额定载流范围内;2)将作业通道内不符合作业安全距离的带电部位和接地体用绝缘毯及绝缘软管等进行绝缘遮蔽。Car No. 1 and No. 2 are respectively responsible for the incoming line side and outgoing line side of the switch to be operated; after the operator in the bucket obtains the consent of the person in charge of the work: 1) Measure the load current with an ammeter to confirm that it is connected to the drain line and the bypass vacuum isolating switch 2) Use insulating blankets and insulating hoses to insulate and shield the live parts and grounding bodies in the working channel that do not meet the working safety distance.
在工作负责人的监护下,斗内电工转移绝缘斗至内边相合适工作位置,按照“由近至远、从下到上、先大后小”的原则对作业中可能触及的部位进行绝缘遮蔽隔离:1)绝缘遮蔽隔离的部位和顺序依次为:A,先内边相、后外边相、再中相,B,先开关引线、后主线。C,一相里的次序:电缆终端引线、避雷器引线、导线、耐张线夹、耐张绝缘子串;2)斗内电工动作应轻缓并保持足够安全距离(相对地0.4m,相间0.6m);3)绝缘遮蔽隔离措施应严密、牢固,绝缘遮蔽组合的重叠长度不得小于15cm。Under the supervision of the person in charge of the work, the electrician in the bucket moves the insulating bucket to a suitable working position inside, and insulates the parts that may be touched during the operation according to the principle of "from near to far, from bottom to top, first big and then small" Shielding and isolation: 1) The position and sequence of insulation, shielding and isolation are as follows: A, the inner phase first, then the outer phase, and then the middle phase; B, the switch leads first, and then the main line. C, the sequence in one phase: cable terminal leads, arrester leads, wires, strain clamps, strain insulator strings; 2) The electrician in the bucket should move gently and keep a safe distance (0.4m relative to the ground, 0.6m between phases) ); 3) The insulation, shielding and isolation measures should be tight and firm, and the overlapping length of the insulation and shielding combination should not be less than 15cm.
步骤3,操作开关使其闭锁,安装旁路引流线。Step 3, operate the switch to lock it, and install the bypass drain line.
3.1、1号车的2号作业人员(车内作业人员)操作1号车,使车到达合适位置,1号车的1号作业人员操作开关使开关闭锁;3.1. The No. 2 operator (in-car operator) of the No. 1 car operates the No. 1 car to make the car reach the proper position, and the No. 1 operator of the No. 1 car operates the switch to lock the switch;
在此过程中需要注意以下几点:1.注意保持与带电部位的安全距离;2.必须用绝缘操作杆操作;3.确认开关闭锁。In this process, the following points need to be paid attention to: 1. Pay attention to keep a safe distance from the live parts; 2. It must be operated with an insulating operating lever; 3. Confirm that the switch is locked.
3.2、1号车和2号车分别负责开关的进线侧和出线侧旁路引流线的安装,先安装中间相引流线,后安装外边相引流线,再安装内边相引流线;在此过程中需要注意以下几点:1.开关进线侧、和出线侧引流线的安装1号车和2号车的1号作业人员必须同相同时进行;2.接点处安装要紧密;3.每安装好引流线,必须用钳形电流表测量其电流,确认其正常运行。3.2, No. 1 car and No. 2 car are respectively responsible for the installation of the bypass drain line on the incoming line side and the outgoing line side of the switch. First install the middle phase drain line, then install the outer phase drain line, and then install the inner phase drain line; here The following points need to be paid attention to during the process: 1. The installation of the drain wires on the inlet side and the outlet side of the switch must be done at the same time by the No. 1 operator of No. 1 car and No. 2 car; 2. The installation at the contact point must be tight; 3. Every After the drain wire is installed, its current must be measured with a clamp ammeter to confirm its normal operation.
步骤4,旧开关退出运行,拆除开关两侧原有的引流线。Step 4, the old switch is out of operation, and the original drain wires on both sides of the switch are removed.
4.1、1号车2号作业人员操作1号车,使车到达合适位置,1号车1号作业人员操作开关使其处在断开位置,拆除断路器。此时开关这一路的线路为断开,步骤3中安装的旁路引流线起作用,原有的线路从旁路引流线连通,不影响电负荷的运行。4.1. Personnel No. 2 of Car No. 1 operates Car No. 1 to make the car reach the proper position. Personnel No. 1 of Car No. 1 operates the switch to make it in the off position and removes the circuit breaker. At this time, the line of the switch is disconnected, the bypass drain line installed in step 3 works, and the original line is connected through the bypass drain line, which does not affect the operation of the electric load.
4.2、1号车和2号车分别负责开关的进线侧和出线侧的引流线;作业人员取得工作负责人同意后:1)1号车和2号车2号作业人员操作绝缘斗臂车,使车到达合适位置,2)1号车和2号车1号作业人员将引线拆除;在此过程中需要注意以下几点:1.注意保持与带电部位的安全距离;2.转移工作斗时应注意绝缘斗臂车周围杆塔、线路等情况,绝缘臂的金属部位与带电体和地电位物体的距离大于1.0m;3.拆除引线后作业人员应牵住引线的随车下降,保持与未拆相引线安全距离;4.拆除引线的次序:先拆内边相、后拆外边相、再拆中间相引线。4.2, No. 1 car and No. 2 car are respectively responsible for the drain wires on the inlet side and outlet side of the switch; after the operator obtains the consent of the person in charge of the work: 1) No. 1 car and No. 2 car No. 2 operators operate the insulated bucket arm truck , so that the car reaches the appropriate position, 2) No. 1 car and No. 2 car No. 1 operator will remove the lead wire; in this process, the following points need to be paid attention to: 1. Pay attention to keep a safe distance from the live parts; 2. Transfer the working bucket Attention should be paid to the pole towers and lines around the insulated bucket arm truck. The distance between the metal part of the insulated arm and the charged body and ground potential object is greater than 1.0m; 4. The order of removing the leads: first remove the inner phase, then remove the outer phase, and then remove the middle phase lead.
步骤5,拆除原开关。Step 5, remove the original switch.
5.1、1号车的2号作业人员操作1号车,使车到达合适位置;5.1, No. 2 operator of No. 1 car operates No. 1 car to make the car reach the proper position;
5.2、1号车的2号作业人员操作小吊(绝缘斗臂车上的起吊装置),使吊钩处在开关上方合适位置;5.2. The No. 2 operator of the No. 1 car operates the small crane (the lifting device on the insulated bucket arm car), so that the hook is in a proper position above the switch;
5.3、1号车的1号作业人员将吊钩挂上人吊开关的绳套,收小吊牵引绳,使牵引绳微受力;5.3. The No. 1 operator of the No. 1 car hangs the hook on the rope cover of the human crane switch, retracts the traction rope of the small crane, and makes the traction rope slightly stressed;
5.3、2号车的2号作业人员操作2号车,使车到达合适位置;5.3. The No. 2 operator of the No. 2 car operates the No. 2 car to make the car reach the proper position;
5.4、2号车的1号作业人员拆除开关与开关支架的固定螺丝或开关支架和水泥杆固定抱箍的对销螺帽(对销螺帽是将开关支架与水泥杆固定抱箍对接固定的紧固部件);5.4, No. 1 operator of No. 2 car removes the fixing screws of the switch and the switch bracket or the counter-pin nut of the switch bracket and the fixing hoop of the cement rod (the counter-pin nut is to connect the switch bracket and the fixing hoop of the cement rod) fastening parts);
5.5、1号车2号作业人员操作小吊将开关吊至地面。5.5, No. 1 car No. 2 operators operate the small crane to hoist the switch to the ground.
在此过程中应当注意以下几点:1,应注意保持与带电部位的安全距离;2,转移工作斗时应注意绝缘斗臂车周围杆塔、线路等情况,绝缘臂的金属部位与带电体和地电位物体的距离大于1.0m;3,吊开关时应平稳,避免既升降又旋转防止开关与电杆发生碰撞。In this process, the following points should be paid attention to: 1. Pay attention to keep a safe distance from the live parts; 2. When transferring the working bucket, pay attention to the poles, towers and lines around the insulating arm truck, and the metal parts of the insulating arm are in contact with the live parts and The distance of the ground potential object is greater than 1.0m; 3. When hanging the switch, it should be stable, avoid lifting and rotating to prevent the switch from colliding with the pole.
步骤6、检测并吊装新开关。Step 6. Detect and hoist the new switch.
6.1、对新开关进行分、合操作2-3次,确认新开关应灵活,指示正确无误;6.1. Open and close the new switch 2-3 times to confirm that the new switch should be flexible and the instructions are correct;
6.2、用2500V绝缘电阻表测量相间和相对地绝缘电阻,均应大于500兆欧;6.2. Use a 2500V insulation resistance meter to measure the phase-to-phase and phase-to-ground insulation resistance, which should be greater than 500 megohms;
6.3、地面作业人员安装好新柱上断路器的两侧引线,罩好绝缘罩,拉开断路器;6.3. The ground operator installs the lead wires on both sides of the circuit breaker on the new column, covers the insulation cover, and pulls the circuit breaker;
6.4、1号车的2号作业人员操作1号车,使车到达合适位置;6.4, No. 2 operator of No. 1 car operates No. 1 car to make the car reach the proper position;
6.5、1号车的2号作业人员操作小吊,使吊钩处在开关上方合适位置;6.5. Operator No. 2 of No. 1 car operates the small crane so that the hook is in a proper position above the switch;
6.6、1号车的2号作业人员操作小吊将开关吊至待安装位置;6.6. Operator No. 2 of No. 1 car operates the small crane to hoist the switch to the position to be installed;
6.7、2号车的2号作业人员操作2号车,使车到达合适位置;6.7. The No. 2 operator of the No. 2 car operates the No. 2 car to make the car reach the proper position;
6.8、2号车的1号作业人员拧紧开关与开关支架的固定螺丝或开关支架和水泥杆固定抱箍的对销螺帽。6.8. The No. 1 operator of the No. 2 car tightens the fixing screws of the switch and the switch bracket or the counter-pin nut of the switch bracket and the cement pole fixing hoop.
在此过程中应当注意以下几点:1,应注意保持与带电部位的安全距离;2,转移工作斗时应注意绝缘斗臂车周围杆塔、线路等情况,绝缘臂的金属部位与带电体和地电位物体的距离大于1.0m;3,吊开关时应平稳,避免既升降又旋转防止开关与电杆发生碰撞。In this process, the following points should be paid attention to: 1. Pay attention to keep a safe distance from the live parts; 2. When transferring the working bucket, pay attention to the poles, towers and lines around the insulating arm truck, and the metal parts of the insulating arm are in contact with the live parts and The distance of the ground potential object is greater than 1.0m; 3. When hanging the switch, it should be stable, avoid lifting and rotating to prevent the switch from colliding with the pole.
步骤7,搭接柱上断路器两侧引线。Step 7, Lap the lead wires on both sides of the circuit breaker on the column.
7.1、1号车和2号的1号作业人员分别搭带电接柱上断路器两侧引线;7.1, No. 1 operator of No. 1 car and No. 2 take lead wires on both sides of the circuit breaker on the live connection post;
7.2、作业人员合上柱上断路器,用电流表确认已分流。7.2. The operator closes the circuit breaker on the pole and confirms that the current has been shunted with an ammeter.
在此过程中应当注意以下几点:1,应注意保持与带电部位的安全距离;2,转移工作斗时应注意绝缘斗臂车周围杆塔、线路等情况,绝缘臂的金属部位与带电体和地电位物体的距离大于1.0m。In this process, the following points should be paid attention to: 1. Pay attention to keep a safe distance from the live parts; 2. When transferring the working bucket, pay attention to the poles, towers and lines around the insulating arm truck, and the metal parts of the insulating arm are in contact with the live parts and The distance of the ground potential object is greater than 1.0m.
引线的施工工艺和质量应满足施工和验收规范的要求:The construction process and quality of lead wires shall meet the requirements of construction and acceptance specifications:
1)引线长度适宜,弧度均匀;1) The length of the lead wire is appropriate and the arc is uniform;
2)引线无散股、断股现象;2) There are no loose strands or broken strands in the lead wire;
3)引线与地电位构件的距离应不小于20cm,相间不小于30cm;3) The distance between the lead wire and the ground potential component should not be less than 20cm, and the phase interval should not be less than 30cm;
4)并沟线夹垫片整齐无歪斜现象,搭接紧密;4) The shims of parallel groove clamps are neat and without skewing, and the lap joints are tight;
5)每相引线的并沟线夹不少于2个,引线穿出线夹的长度约为2~3cm,并沟线夹之间应留出一个线夹的宽度。5) There are no less than 2 parallel groove clamps for each phase lead wire, and the length of the lead wire passing through the clamp is about 2-3cm, and the width of one clamp should be reserved between the parallel groove clamps.
步骤8,新开关投入运行并拆除旁路引流线。Step 8, put the new switch into operation and remove the bypass drain wire.
8.1、1号车的2号作业人员操作1号车,使车到达合适位置;8.1, No. 2 operator of No. 1 car operates No. 1 car to make the car reach the proper position;
8.2、1号车的1号作业人员操作开关使其处在合闸位置位置;8.2, No. 1 operator of No. 1 car operates the switch to make it in the closed position;
8.3、1号车的1号作业人员用钳形电流表测量开关各相引线路电流是否正常,确认开关已经正常运行;如果正常运行,进行下一步;8.3. The No. 1 operator of No. 1 car uses a clamp ammeter to measure whether the current of each phase lead line of the switch is normal, and confirms that the switch has been operating normally; if it is operating normally, proceed to the next step;
8.4、1号车和2号车的1号作业人员取得工作负责人同意后拆除步骤3中安装的旁路引流线。8.4, No. 1 operator of No. 1 car and No. 2 car removes the bypass drainage line installed in step 3 after obtaining the consent of the person in charge of the work.
在此过程中应注意以下几点:1.拆除的次序:先中间相、后外边相、再内边相;2.1号车和2号车的1号作业人员必须同相同时进行;3.应注意保持与带电部位的安全距离;4.转移工作斗时应注意绝缘斗臂车周围杆塔、线路等情况,绝缘臂的金属部位与带电体和地电位物体的距离大于1.0m。The following points should be paid attention to in this process: 1. The order of dismantling: first the middle phase, then the outer phase, and then the inner phase; 2. The No. 1 operator of the No. 1 car and the No. 2 car must be at the same time; 3. It should be noted that Keep a safe distance from the live parts; 4. When transferring the working bucket, pay attention to the towers and lines around the insulated arm truck. The distance between the metal part of the insulated arm and the charged body and ground potential object is greater than 1.0m.
步骤9,拆除绝缘遮蔽。Step 9, remove the insulation shielding.
更换作业完成后,1号车和2号车的作业人员取得工作负责人同意后拆除接地体和带电部位上的绝缘遮蔽用具。After the replacement operation is completed, the operators of No. 1 and No. 2 cars remove the insulation and shielding equipment on the grounding body and live parts after obtaining the consent of the person in charge of the work.
在此过程中应注意以下几点:1.注意保持与带电部位的安全距离;2.按照由上至下、由远至近、先接地体后带电体的原则进行;3.1号车和2号车的作业人员应同时同相进行;4.拆除的次序:先中间相、后外边相、再内边相。During this process, the following points should be paid attention to: 1. Pay attention to keep a safe distance from the live parts; 2. Follow the principle of from top to bottom, from far to near, first grounding body and then live body; 3. Car No. 1 and Car No. 2 4. The order of dismantling: first the middle phase, then the outer phase, and then the inner phase.
步骤10,撤离杆塔。Step 10, evacuate the tower.
斗内作业人员检查确认线路设备运行正常,无遗漏或缺陷后,撤离有电区域,返回地面,下降工作斗、收回绝缘臂时应注意绝缘斗臂车周围杆塔、线路等情况。The operators in the bucket check and confirm that the line equipment is in normal operation. After there are no omissions or defects, they should evacuate the live area and return to the ground.
至此,施工过程完成。之后,工作负责人组织班组成员清理工具和现场,绝缘斗臂车各部件复位,收回绝缘斗臂车支腿,整理工具、材料。将工器具清洁后放入专用的箱(袋)中。清理现场。在坡地停放时,应先收后支腿,后收前支腿;支腿收回顺序应先收回垂直支腿,再收回水平支腿。工作完成后,向调度汇报工作结束。At this point, the construction process is complete. Afterwards, the person in charge organized the team members to clean up the tools and the site, reset the parts of the insulated bucket truck, retract the outriggers of the insulated bucket truck, and sort out the tools and materials. Put the tools and utensils into a special box (bag) after cleaning. Clean up the scene. When parking on a slope, the rear outriggers should be retracted first, and then the front outriggers should be retracted; the sequence of retracting the outriggers should first retract the vertical outriggers, and then retract the horizontal outriggers. After the work is completed, report the end of the work to the dispatcher.
Claims (10)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510471581.1A CN105186338A (en) | 2015-08-04 | 2015-08-04 | Construction method of employing insulation bucket arm vehicle insulating gloves with load to change pole top switch device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510471581.1A CN105186338A (en) | 2015-08-04 | 2015-08-04 | Construction method of employing insulation bucket arm vehicle insulating gloves with load to change pole top switch device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN105186338A true CN105186338A (en) | 2015-12-23 |
Family
ID=54908269
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510471581.1A Pending CN105186338A (en) | 2015-08-04 | 2015-08-04 | Construction method of employing insulation bucket arm vehicle insulating gloves with load to change pole top switch device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105186338A (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105703248A (en) * | 2016-03-31 | 2016-06-22 | 国网山东省电力公司青岛供电公司 | Column switch insulated shielding structure |
CN106356758A (en) * | 2016-09-07 | 2017-01-25 | 国网浙江淳安县供电公司 | Operating method for replacing pole-mounted switch live on indirect bypass of 10 KV line insulating pole |
CN109994961A (en) * | 2019-01-15 | 2019-07-09 | 国网辽宁省电力有限公司鞍山供电公司 | Vertically arranged 10kV overhead line with load replacement column switch device and method |
CN110327049A (en) * | 2018-08-22 | 2019-10-15 | 宁波送变电建设有限公司永耀科技分公司 | It is a kind of electric shock bracelet monitoring electric power first-aid scene application |
CN112604199A (en) * | 2020-12-07 | 2021-04-06 | 浙江大有实业有限公司带电作业分公司 | Fixing device for work bucket with buffer device and insulating bucket arm vehicle |
CN113328374A (en) * | 2021-04-19 | 2021-08-31 | 国网浙江淳安县供电有限公司 | Earth potential all-terrain on-load operation method |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH06339206A (en) * | 1993-05-27 | 1994-12-06 | Matsushita Electric Ind Co Ltd | Cubicle type high-voltage receiving facility |
-
2015
- 2015-08-04 CN CN201510471581.1A patent/CN105186338A/en active Pending
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH06339206A (en) * | 1993-05-27 | 1994-12-06 | Matsushita Electric Ind Co Ltd | Cubicle type high-voltage receiving facility |
Non-Patent Citations (1)
Title |
---|
刘云涛等: "带负荷更换10kv配电线路附属设备作业方法的研究与实施", 《中国电力企业管理》 * |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105703248A (en) * | 2016-03-31 | 2016-06-22 | 国网山东省电力公司青岛供电公司 | Column switch insulated shielding structure |
CN106356758A (en) * | 2016-09-07 | 2017-01-25 | 国网浙江淳安县供电公司 | Operating method for replacing pole-mounted switch live on indirect bypass of 10 KV line insulating pole |
CN106356758B (en) * | 2016-09-07 | 2018-04-10 | 国网浙江淳安县供电公司 | 10KV line insulations bar bypasses charged for replacement on-pole switch operational method indirectly |
CN110327049A (en) * | 2018-08-22 | 2019-10-15 | 宁波送变电建设有限公司永耀科技分公司 | It is a kind of electric shock bracelet monitoring electric power first-aid scene application |
CN110327049B (en) * | 2018-08-22 | 2021-11-30 | 宁波送变电建设有限公司永耀科技分公司 | Application of electric shock bracelet in monitoring electric power rush-repair site |
CN109994961A (en) * | 2019-01-15 | 2019-07-09 | 国网辽宁省电力有限公司鞍山供电公司 | Vertically arranged 10kV overhead line with load replacement column switch device and method |
CN109994961B (en) * | 2019-01-15 | 2023-10-20 | 国网辽宁省电力有限公司鞍山供电公司 | Device and method for replacing pole-mounted switch of vertically arranged 10kV overhead line with load |
CN112604199A (en) * | 2020-12-07 | 2021-04-06 | 浙江大有实业有限公司带电作业分公司 | Fixing device for work bucket with buffer device and insulating bucket arm vehicle |
CN113328374A (en) * | 2021-04-19 | 2021-08-31 | 国网浙江淳安县供电有限公司 | Earth potential all-terrain on-load operation method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105186338A (en) | Construction method of employing insulation bucket arm vehicle insulating gloves with load to change pole top switch device | |
CN109217151A (en) | Electric substation's installation engineering method | |
WO2016023141A1 (en) | Process for live replacement of tension hard-tube bus-bar jumper insulator of +/- 800kv ultra-high-voltage dc transmission line | |
CN102931609B (en) | On-load changes the operational method of 10kV fuse switch | |
CN102110520A (en) | Construction process for installing and debugging large transformer | |
CN102128983B (en) | Method for measuring phase of power transmission and distribution line | |
CN102664358B (en) | Live replacement method for static contact of 220 kV flexible busbar | |
CN101894701A (en) | 220KV vertical opening type isolating switch shunting device and method thereof | |
CN104505763B (en) | UHVDC Transmission Lines charged for replacement duplex V string composite insulator operational methods | |
CN103746315A (en) | Quick hot-line by-pass jumper overlapping operation method for 10kV insulated power distribution line | |
CN103746314A (en) | Quick hot-line by-pass jumper removing operation method for 10kV insulated power distribution line | |
CN103001142A (en) | Operation method for on-load replacing of 10kV pole-mounted disconnector | |
CN110120643A (en) | A kind of ground potential distribution power circuit uninterrupted operation method | |
CN103474909B (en) | Drainage thread supports the method for expansion live-line replacing multiloop strain insulator string | |
CN106356758B (en) | 10KV line insulations bar bypasses charged for replacement on-pole switch operational method indirectly | |
CN107482535A (en) | The Method of Installing Segment Switch on Straight Rod of 10KV Line with Load Breaking | |
CN201717173U (en) | 220KV vertically-opened disconnecting switch shunt device | |
CN202611568U (en) | Insulation trestle ladder | |
CN105301439B (en) | A kind of method for rapidly positioning of overhead transmission line earth fault | |
CN104617513B (en) | The UHVDC Transmission Lines treatment connection gold utensil powered operational method of heating | |
CN106410674A (en) | Hot-line work method for 10-kV distribution line and equipment | |
CN104037648A (en) | Operating method of 35kV-overhead-line insulating-glove-method electrified disconnection and connection of zero-load-line lead wire | |
CN104071036B (en) | Urban rail transit contact rail traction system | |
CN104538888B (en) | A kind of distribution line straight line pole cross-arm charged for replacement method | |
CN203707670U (en) | Tool for lively processing bolt of by-pass jumper clamp |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20151223 |