CN105184688A - Remote real-time cost control management for power network - Google Patents

Remote real-time cost control management for power network Download PDF

Info

Publication number
CN105184688A
CN105184688A CN201510733576.3A CN201510733576A CN105184688A CN 105184688 A CN105184688 A CN 105184688A CN 201510733576 A CN201510733576 A CN 201510733576A CN 105184688 A CN105184688 A CN 105184688A
Authority
CN
China
Prior art keywords
data
user
unit
measuring parameter
electricity consumption
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510733576.3A
Other languages
Chinese (zh)
Inventor
郭俊宏
蔡静鹏
张�浩
范荻
王旭冉
黄毅臣
杨威
刘永辉
李博
岳云力
王宣元
李珊
梁大鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BEIJING BOWANG HUAKE TECHNOLOGY Co Ltd
State Grid Corp of China SGCC
State Grid Jibei Electric Power Co Ltd
Economic and Technological Research Institute of State Grid Jibei Electric Power Co Ltd
Original Assignee
BEIJING BOWANG HUAKE TECHNOLOGY Co Ltd
State Grid Jibei Electric Power Co Ltd
Economic and Technological Research Institute of State Grid Jibei Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING BOWANG HUAKE TECHNOLOGY Co Ltd, State Grid Jibei Electric Power Co Ltd, Economic and Technological Research Institute of State Grid Jibei Electric Power Co Ltd filed Critical BEIJING BOWANG HUAKE TECHNOLOGY Co Ltd
Priority to CN201510733576.3A priority Critical patent/CN105184688A/en
Publication of CN105184688A publication Critical patent/CN105184688A/en
Pending legal-status Critical Current

Links

Abstract

The invention provides a remote real-time cost control management for a power network. The remote real-time cost control management for the power network comprises a monitoring device, a teletransmission device, a cost control device and a user terminal, wherein the teletransmission device is in communication interconnection with the monitoring device, the cost control device and the user terminal respectively; and the teletransmission device obtains metering parameters, related to the electricity usage condition, in the cost control device through communicating with the cost control device. Management and analysis on the metering parameters are facilitated; various electricity consumption trends can be analyzed; a useful reference is provided for power supply enterprises; meanwhile, a user module is arranged, so that a convenient interface is provided for customer query and payment; the management level is improved; and users can conveniently query and know the electricity consumption data through the user terminal.

Description

A kind of remote electric network takes control and management system in real time
Technical field
The present invention relates to electrical network management of power use field, be specifically related to a kind of remote electric network and take control and management system in real time.
Background technology
The long-range real-time expense of electrical network controls the client-related data and the prepaid expense of client that refer to based on electrical network business application system, according to the electrical representation logarithmic data of electricity consumption data acquisition system (DAS) real time propelling movement, the automatic measurement & calculation client electricity consumption residue electricity charge amount of money, completes the process of early warning, tripping operation and instructions such as sending a telegram in reply of closing a floodgate with the warning amount of money arranged, the reference values such as the thresholding amount of money of overdrawing after comparing.
Along with the development of science and technology, the especially development of technology of Internet of things and Internet technology, the practicality of traditional electrical network expense Ore-controlling Role reduces gradually, is applied in the expense control device of electrical network, have real-time high, use efficient and convenient, save the advantages such as manpower.
But at present, expense control device lays particular emphasis on demand charge measuring and calculating and long-range power failure or telegram in reply and controls, lack the monitoring to the process data of expense control in real time and analysis, effectively cannot carry out management and monitoring to the real-time expense control business procedure of user, cannot intellectual analysis user early warning and have a power failure strategy, more can not analyse in depth expense control in real time and apply the income brought, bring many constant to the strengthened research of expense control in real time.
Summary of the invention
The present invention in order to solve above-mentioned mention existing expense control device function singleness, use circumscribed shortcoming, a kind of management system for the long-range real-time expense control of electrical network is provided, cooperatively interact with existing expense control device, connect each other, various statistical study to the business of expense control are in real time provided, and refinement analysis is carried out to time period, the space segment taking control business in real time, optimize customer interface, grasp user power utilization trend, for power grid construction, client's development, serve the effect of Added Management, the benefit of administration of power networks enterprise can be improved to a great extent.
Concrete, the invention provides a kind of management system for the long-range real-time expense control of electrical network, it comprises supervising device, remote transmission device, take control device and user terminal, described remote transmission device is respectively with described supervising device with take that to control device communication interconnected, described user terminal carries out data communication by network and described supervising device, described supervising device comprises the control module of mutual communication, data capture unit, data storage cell, query unit, electricity consumption assessment unit, analytic unit and line module, described control module can call operation instruction, described data capture unit is by obtaining measuring parameter with described remote transmission device communication, and measuring parameter is stored in data storage cell, the operational order that described query unit is called according to control module, inquires about the measuring parameter return data that store in the data store, described analytic unit provides the measuring parameter of multiple user according to the operational order that control module calls, and carries out statistical study to described measuring parameter, described line module obtains the measuring parameter in storage unit, obtains described measuring parameter for user terminal, described electricity consumption assessment unit obtains electricity consumption trend data according to user's described measuring parameter within Preset Time.
Preferably, the operational order that described analytic unit can call according to control module, provides the measuring parameter of at least one user in Preset Time.
Preferably, described data storage cell comprises data and stores Read Controller and redundant arrays of inexpensive disks, described data store Read Controller and store according to the operational order that control module calls or data in reading disk redundant array, described redundant arrays of inexpensive disks is provided with redundant memory modules, stores data for automated back-up, inspection, check and correction and corrigendum.
Preferably, described line module comprises user data management unit, user data display unit and User Alarms unit, described user data management unit is used for the data of leading subscriber, user accesses account and password, described user data display unit is for showing electricity consumption data and the payment data of user, and described User Alarms unit is used for reporting to the police when the actual payment volume of user is not enough.
Preferably, described query unit is provided with data-query interfaces.
Preferably, described electricity consumption assessment unit obtains the electricity consumption trend data of sole user according to the user data obtained in Preset Time.
Preferably, described User Alarms unit inside is provided with payment volume threshold value, and when the actual payment volume of user is less than or equal to payment volume threshold value, described User Alarms unit sends to described user terminal and reports to the police.
Preferably, described user terminal is intelligent communication device.
The invention provides a kind of provide a kind of for electrical network long-range real-time expense control management system, it is provided with remote transmission device, device communication can be controlled with original expense, obtain the original electricity consumption data of user, by multiple chart display mode and client flexibly, time period selection mode, various visual angles are provided, multi-faceted data presentation mode, be convenient to keeper's inquiry and analyze, also be provided with electricity consumption assessment unit and analyze various electricity consumption trend, for the development of power supply enterprise is offered help, the line module simultaneously comprised, for customer inquiries, the interface that payment is provided convenience, improve management level.
User can the Customer Service Center of access monitoring device by user terminal such as mobile phone or other smart machines, thus the electricity consumption data of oneself can be known at any time, Customer Service Center can also provide warning simultaneously, when subscriber payment volume is not enough, alarming short message is sent in time to client, prevent accident power-off, cause the unnecessary loss of user.
Accompanying drawing explanation
Fig. 1 is structural representation of the present invention;
Fig. 2 is the structural schematic block diagram of supervising device of the present invention;
Fig. 3 is the structural schematic block diagram of data storage cell of the present invention;
Fig. 4 is the structural schematic block diagram of line module of the present invention; And
Fig. 5 is workflow schematic diagram of the present invention.
Embodiment
Below in conjunction with accompanying drawing and embodiment, structure of the present invention and workflow are further explained:
As shown in Figure 1, the invention provides a kind of management system for the long-range real-time expense control of electrical network, it comprises supervising device 1, remote transmission device 2, expense control device 3 and user terminal 4, and remote transmission device 2 is respectively with supervising device 1 and take that to control device 3 communication interconnected.User terminal 4 and supervising device 1 carry out communication data exchange by wireless network.In specific implementation process, user terminal is mobile phone, PAD or other intelligent communication equipment.
Expense control device 3 can obtain and preserve measuring parameter.Remote transmission device 2 by with take control device 3 communication obtain take control device 3 the measuring parameter that obtains and preserve.Supervising device 1 from remote transmission device 2 obtain measuring parameter go forward side by side row relax store, user can obtain the corresponding measuring parameter of oneself by user terminal.
As shown in Figure 2, supervising device 1 comprises the control module 11 of mutual communication, data capture unit 12, data storage cell 13, query unit 14, electricity consumption assessment unit 15, analytic unit 16 and line module 17.
Control module 11 can call operation instruction, and measuring parameter by obtaining measuring parameter with remote transmission device 2 communication, and is stored in data storage cell 13 by data capture unit 12; The instruction that query unit 14 is called according to control module 11, inquires about the measuring parameter be stored in data storage cell 13, and according to specified format return data.
As shown in Figure 3, data storage cell 13 comprises data and stores Read Controller 131 and redundant arrays of inexpensive disks 132, data store the data in the instruction storage or reading disk redundant array 132 that Read Controller 131 calls according to control module, described redundant arrays of inexpensive disks provides redundant memory modules, stores data for automated back-up, inspection, error correction.
Query unit 14 provides the data-query interfaces of standard, inquires about in sql like language mode, and with forms mode return data, for checking.
Analytic unit 16 provides the measuring parameter of multiple users of demand according to the instruction that control module 11 calls, and carries out statistical study to measuring parameter.The instruction that analytic unit 16 can call according to control module, provides the measuring parameter of special time period, specific user colony, and adopts conventional tables, many curve maps and pie chart to carry out statistical study to measuring parameter.Analytic unit 16 provides multiple time inquiring mode according to user instruction.
Analytic unit 16 can be inquired about for the same day, yesterday, this week, last week, this month, last month, current season, preceding quarter, this year, last year and User Defined time.Except basic form display mode, go back offer curves figure, sole user's special time period curve map, the same time step curve figure of multi-user etc., are convenient to checking and analysis of power supply department.Analytic unit also provides pie chart display mode, provides user group to analyze, the pie chart such as user's income analysis.
Line module 17 obtains measuring parameter in storage unit, provides access interface by internet, accesses account inquiry electricity consumption data for user terminal user; Electricity consumption assessment unit 15, according to user's one section of electricity consumption trend data in the past, analyzes the electricity consumption trend drawn in a period of time from now on.
User terminal 4 can pass through internet terminal calling party module 17, obtains measuring parameter.
As shown in Figure 4, line module 17 comprises user data management unit 171, user data display unit 172 and User Alarms unit 173, user data management unit 171 accesses account and password for the data of leading subscriber and user, user must use legal user name and password ability calling party module, user data display unit 172 shows electricity consumption data and the payment data of user, described User Alarms unit is when subscriber payment volume is not enough, prior notice electricity consumption user pays the fees, and prevents accident power-off.
Preferably, the present invention also provides a kind of management method based on the above-mentioned management system for the long-range real-time expense control of electrical network, and as shown in Figure 5, it comprises the following steps:
S1, remote transmission device 2 obtain to take and control by controlling device 3 communication with expense the measuring parameter that device obtained and preserved;
S2, control module 11 can call operation instructions, and measuring parameter by obtaining measuring parameter with described remote transmission device communication, and is stored in data storage cell 13 by data capture unit 12,
The instruction that S3, query unit 14 are called according to control module, inquiry stores measuring parameter in the data store and returns;
S4, analytic unit 15 provide the measuring parameter of multiple user according to the operational order that control module 11 calls, and carry out statistical study to described measuring parameter;
S5, electricity consumption assessment unit 16, according to the electricity consumption trend data in user's schedule time, analyze the electricity consumption trend data drawing and specify in a period of time;
S6, line module 17 obtain measuring parameter in storage unit, provide access interface by internet, access account inquiry electricity consumption data for user terminal 4 user; And
S7, user terminal 4, by internet access line module 17, obtain measuring parameter, and when subscriber payment volume is not enough, line module 17 sends to user terminal 4 and reports to the police.
The invention provides a kind of management system for the long-range real-time expense control of electrical network, it is provided with remote transmission device, device communication can be controlled with original expense, obtain the original electricity consumption data of user, by multiple chart display mode and client flexibly, time period selection mode, various visual angles are provided, multi-faceted data presentation mode, be convenient to inquiry and analyze, also be provided with electricity consumption assessment unit, analyze various electricity consumption trend, for the development of power supply enterprise is offered help, the line module simultaneously comprised, for customer inquiries, the interface that payment is provided convenience, improve service level.Meanwhile, can prevent the generation of the situations such as seasonal peak of power consumption, time period peak of power consumption, user's accident power-off in time, actively grasp the development trend of user, transformation and upgrade electrical network simultaneously, development and the new user of developing, with adapt to development demand.
User can the Customer Service Center of access monitoring device by user terminal such as mobile phone or other smart machines, thus the electricity consumption data of oneself can be known at any time, Customer Service Center can also provide warning simultaneously, when subscriber payment volume is not enough, alarming short message is sent in time to client, prevent accident power-off, cause the unnecessary loss of user.
Last it is noted that above-described each embodiment is only for illustration of technical scheme of the present invention, be not intended to limit; Although with reference to previous embodiment to invention has been detailed description, those of ordinary skill in the art is to be understood that: it still can be modified to the technical scheme described in previous embodiment, or to wherein partly or entirely technical characteristic carry out equivalent replacement; And these amendments or replacement, do not make the essence of appropriate technical solution depart from the scope of various embodiments of the present invention technical scheme.

Claims (8)

1. one kind for electrical network long-range real-time take control management system, it is characterized in that: it comprises supervising device, remote transmission device, expense control device and user terminal, described remote transmission device is respectively with described supervising device with take that to control device communication interconnected, described user terminal carries out data communication by network and described supervising device
Described supervising device comprises the control module of mutual communication, data capture unit, data storage cell, query unit, electricity consumption assessment unit, analytic unit and line module, described control module can call operation instruction, measuring parameter by obtaining measuring parameter with described remote transmission device communication, and is stored in data storage cell by described data capture unit; The operational order that described query unit is called according to control module, inquires about the measuring parameter return data that store in the data store; Described analytic unit provides the measuring parameter of multiple user according to the operational order that control module calls, and carries out statistical study to described measuring parameter; Described line module obtains the measuring parameter in storage unit, obtains described measuring parameter for user terminal; Described electricity consumption assessment unit obtains electricity consumption trend data according to user's described measuring parameter within Preset Time.
2. according to claim 1 for the long-range real-time management system of taking control of electrical network, it is characterized in that: the operational order that described analytic unit can call according to control module, the measuring parameter of at least one user in Preset Time is provided.
3. according to claim 1 for the long-range real-time management system of taking control of electrical network, it is characterized in that: described data storage cell comprises data and stores Read Controller and redundant arrays of inexpensive disks, described data store Read Controller and store according to the operational order that control module calls or data in reading disk redundant array, described redundant arrays of inexpensive disks is provided with redundant memory modules, stores data for automated back-up, inspection, check and correction and corrigendum.
4. according to claim 1 for the long-range real-time management system of taking control of electrical network, it is characterized in that: described line module comprises user data management unit, user data display unit and User Alarms unit, described user data management unit is used for the data of leading subscriber, user accesses account and password, described user data display unit is for showing electricity consumption data and the payment data of user, and described User Alarms unit is used for reporting to the police when the actual payment volume of user is not enough.
5. according to claim 1 for the long-range real-time management system of taking control of electrical network, it is characterized in that: described query unit is provided with data-query interfaces.
6. according to claim 1 for the long-range real-time management system of taking control of electrical network, it is characterized in that: described electricity consumption assessment unit obtains the electricity consumption trend data of sole user according to the user data obtained in Preset Time.
7. according to claim 4 for the long-range real-time management system of taking control of electrical network, it is characterized in that: described User Alarms unit inside is provided with payment volume threshold value, when the actual payment volume of user is less than or equal to payment volume threshold value, described User Alarms unit sends to described user terminal and reports to the police.
8. according to claim 7 for the long-range real-time management system of taking control of electrical network, it is characterized in that: described user terminal is intelligent communication device.
CN201510733576.3A 2015-11-03 2015-11-03 Remote real-time cost control management for power network Pending CN105184688A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510733576.3A CN105184688A (en) 2015-11-03 2015-11-03 Remote real-time cost control management for power network

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510733576.3A CN105184688A (en) 2015-11-03 2015-11-03 Remote real-time cost control management for power network

Publications (1)

Publication Number Publication Date
CN105184688A true CN105184688A (en) 2015-12-23

Family

ID=54906744

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510733576.3A Pending CN105184688A (en) 2015-11-03 2015-11-03 Remote real-time cost control management for power network

Country Status (1)

Country Link
CN (1) CN105184688A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109166245A (en) * 2018-08-17 2019-01-08 云丁智能科技(北京)有限公司 The method and device of the electricity charge amount of money is calculated based on step price
CN109255603A (en) * 2018-11-21 2019-01-22 日立楼宇技术(广州)有限公司 A kind of elevator charging method, device, equipment and storage medium
CN116991149A (en) * 2023-09-28 2023-11-03 山西磊源电器有限责任公司 Method and device for checking fee-controlled product, electronic equipment and storage medium

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102521921A (en) * 2011-12-15 2012-06-27 中国电力科学研究院 Charge control device, prepayment electricity selling system, electricity selling system and method thereof
CN104063756A (en) * 2014-05-23 2014-09-24 国网辽宁省电力有限公司本溪供电公司 Electric power utilization information remote control system
CN204155365U (en) * 2014-10-29 2015-02-11 新奥科技发展有限公司 The recharging and paying system of smart card
CN104601396A (en) * 2014-12-04 2015-05-06 国家电网公司 Power grid data monitoring method and device

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102521921A (en) * 2011-12-15 2012-06-27 中国电力科学研究院 Charge control device, prepayment electricity selling system, electricity selling system and method thereof
CN104063756A (en) * 2014-05-23 2014-09-24 国网辽宁省电力有限公司本溪供电公司 Electric power utilization information remote control system
CN204155365U (en) * 2014-10-29 2015-02-11 新奥科技发展有限公司 The recharging and paying system of smart card
CN104601396A (en) * 2014-12-04 2015-05-06 国家电网公司 Power grid data monitoring method and device

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109166245A (en) * 2018-08-17 2019-01-08 云丁智能科技(北京)有限公司 The method and device of the electricity charge amount of money is calculated based on step price
CN109255603A (en) * 2018-11-21 2019-01-22 日立楼宇技术(广州)有限公司 A kind of elevator charging method, device, equipment and storage medium
CN116991149A (en) * 2023-09-28 2023-11-03 山西磊源电器有限责任公司 Method and device for checking fee-controlled product, electronic equipment and storage medium
CN116991149B (en) * 2023-09-28 2023-12-08 山西磊源电器有限责任公司 Method and device for checking fee-controlled product, electronic equipment and storage medium

Similar Documents

Publication Publication Date Title
Yang et al. Optimal sharing and fair cost allocation of community energy storage
CN112487046B (en) Power consumption information analysis method, device, system, computer equipment and storage medium
CN107784481A (en) Task timeliness method for early warning and device
Erden et al. Adaptive V2G peak shaving and smart charging control for grid integration of PEVs
CN106357414B (en) Information interacting method and system for base station electric generation management
CN111563764B (en) Electricity price calculation method and device, shared electricity utilization system and storage medium
CN105184688A (en) Remote real-time cost control management for power network
CN108449393A (en) Combustion gas data transmission method and Internet of things system
CN115619439A (en) Power load operation management system, device and method
CN114462722A (en) New energy power generation light-weight high-precision cloud prediction system, method and device
CN110636107A (en) Power grid data interaction system based on 5g communication and interaction method thereof
CN112015813B (en) Data sharing method, system and device for power distribution network and computer equipment
CN201426043Y (en) Load control and management system based on GPRS network
CN112541616A (en) Power utilization adjusting method and system based on demand side response
CN108614173B (en) Low-voltage side comprehensive energy consumption analysis method and low-voltage side comprehensive energy consumption analysis system
KR20180075273A (en) Microgrid electric power management method and system thereof
CN108921733B (en) Property information processing system based on cloud storage
CN113052417A (en) Resource allocation method and device
CN115358590A (en) Adjustable load resource aggregation service platform
CN111244938A (en) Source network load storage coordination control method, device and system applied to power grid
CN103019190B (en) A kind of intelligent energy monitoring analysis method
CN114683908B (en) Method, system, electronic equipment and medium for evaluating power exchange capacity of power exchange station
CN114066200A (en) Enterprise user energy efficiency analysis system
CN115524469A (en) Novel Internet of things monitoring platform system for air soil water quality
CN209357108U (en) A kind of industrial park comprehensive energy interaction systems

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20160128

Address after: 100160 Beijing, Fengtai District, South Fourth Ring Road West, No. eleven, building 202, room 41, room 188

Applicant after: ECONOMIC RESEARCH INSTITUTE OF STATE GRID JIBEI ELECTRIC POWER COMPANY LIMITED

Applicant after: State Grid Jibei Electric Power Company Limited

Applicant after: Beijing Bowang Huake Technology Co., Ltd.

Applicant after: State Grid Corporation of China

Address before: 100160 Beijing, Fengtai District, South Fourth Ring Road West, No. eleven, building 202, room 41, room 188

Applicant before: ECONOMIC RESEARCH INSTITUTE OF STATE GRID JIBEI ELECTRIC POWER COMPANY LIMITED

Applicant before: State Grid Jibei Electric Power Company Limited

Applicant before: Beijing Bowang Huake Technology Co., Ltd.

RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20151223