CN105184680B CN201510611693.2A CN201510611693A CN105184680B CN 105184680 B CN105184680 B CN 105184680B CN 201510611693 A CN201510611693 A CN 201510611693A CN 105184680 B CN105184680 B CN 105184680B
Authority
CN
China
Prior art keywords
power grid
grid infrastructure
gis
local server
mobile message
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510611693.2A
Other languages
Chinese (zh)
Other versions
CN105184680A (en
Inventor
陈亮
殷博
林永峰
张国强
唐萍
石伟
单宝麟
谢伟光
王炳辉
纪明
苏靖宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TIANJIN PUXUN POWER INFORMATION TECHNOLOGY Co Ltd
State Grid Corp of China SGCC
State Grid Tianjin Electric Power Co Ltd
Original Assignee
TIANJIN PUXUN POWER INFORMATION TECHNOLOGY Co Ltd
State Grid Corp of China SGCC
State Grid Tianjin Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TIANJIN PUXUN POWER INFORMATION TECHNOLOGY Co Ltd, State Grid Corp of China SGCC, State Grid Tianjin Electric Power Co Ltd filed Critical TIANJIN PUXUN POWER INFORMATION TECHNOLOGY Co Ltd
Priority to CN201510611693.2A priority Critical patent/CN105184680B/en
Publication of CN105184680A publication Critical patent/CN105184680A/en
Application granted granted Critical
Publication of CN105184680B publication Critical patent/CN105184680B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)
  • Mobile Radio Communication Systems (AREA)

Abstract

The mobile message for the power grid infrastructure based on GIS that the present invention relates to a kind of acquires and synchronous updating system, technical characterstic: the synchronized update including first identifier code, the aerial photography device of current information for acquiring power grid infrastructure, the historical information for storing the power grid infrastructure in presumptive area and the local server handled in power grid infrastructure for identifying power grid infrastructure device is arranged in and for receiving local server transmission requests and verifies the host computer of local server identity by unique verification code.Using take pictures and lock the three-dimensional arrangement and quantitative relation of the infrastructure of the power grid in the region to the power grid infrastructure in specified region in the present invention, data understand reliably, analysis and synchronized update convenient for local server and host computer, guarantee the stabilization of data system.

Description

The mobile message of power grid infrastructure based on GIS acquires and synchronous updating system
Technical field
The invention belongs to the long-range detection technique field of power grid infrastructure, especially a kind of power grid basis based on GIS is set The mobile message acquisition applied and synchronous updating system.
Background technique
Distribution GIS (Geographic Information System) is using geospatial database as base Plinth, under the support of computer software and hardware, with the theory of system engineering and information science, scientific management and comprehensive analysis have The geodata of spatial connotation, to provide the technological system of the information needed such as management, decision.Briefly, GIS is integrated treatment It with a kind of technological system of analysis geographical spatial data, using database as data storage and is made based on surveying and drawing measurement Data source analyzes instant technology by the global space of platform of computer programming.GIS-Geographic Information System, which is used as, to be obtained, deposits Important tool, technology and the subject of storage, analysis and management geographical spatial data, get the attention in recent years and rapidly send out Exhibition.Especially and the combination of network system forms more mature power grid GIS data platform, which is flown in recent years Speed development, for usually and disaster occur when power grid infrastructure rationally arrange net and power grid repairing, maintenance provided with detection Perfect geographical three-dimensional information, greatly improves work efficiency.
Currently, being directed to the power grid infrastructure construction stage, only pass through acceptance survey in completion link as a result, verifying and setting The power grid basis instrument three-dimensional layout data built along topography could be uploaded to electricity later by the consistency of meter, construction drawing Net GIS data platform, and GIS platform data acquisition modes at this stage by traditional mapping means and conventional recording mode come It realizes.Since the habit of collector is different, quality is different, while lacking effective field data verifying means, causes to acquire Situations such as content does not meet specification, mistake is adopted, leakage is adopted, attribute information mistake occurs often, and acquisition data precision is unable to control, the later period Rework aspect is frequent.Carry out GIS data according to present mode and update acquisition, needs data synchronous maintenance after collection in worksite to electric In net GIS platform, centre will pass through data mart modeling processing, self-test, check, audit and propose the processes such as report, and at data mart modeling In the reason stage, heavy workload, manual intervention degree is high, not can guarantee the accuracy and timeliness of data, data inputting seriously lags behind Data collection task, pending data are possible to live unusual fluctuation again after being put in storage, lead to the data and field device situation of typing It is inconsistent.
Summary of the invention
It is an object of the invention to overcome the deficiencies of the prior art and provide a kind of design is reasonable, high-efficient and quick and precisely The power grid infrastructure based on GIS mobile message acquisition and synchronous updating system.
The present invention solves its technical problem and adopts the following technical solutions to achieve:
The mobile message acquisition of a kind of power grid infrastructure based on GIS and synchronous updating system includes:
First identifier code: it is arranged in power grid infrastructure for identifying power grid infrastructure device;
Aerial photography device: for acquiring the current information of power grid infrastructure;
Local server: for storing the historical information of the power grid infrastructure in presumptive area, aerial photography device acquisition is received Current information, and historical information and current information are compared, if comparison result is difference, are referred to aerial photography device sending It enables all first identity codees scanned in the specified region of the current information, while current information is covered into historical information, and to Host computer issues synchronized update request;If comparison result be it is identical, current information is deleted, wherein historical information and work as Preceding information is respectively that aerial photography device is applied to be covered with electricity in specified region along what chronological order was successively shot in establishing shot point Two 360 degree of distant view photographs of net infrastructure, and taking in multiple 360 degree of distant view photographs of same establishing shot point shooting Scape latitude and longitude coordinates, 24 hours system in find a view the time and find a view height it is constant always;
Host computer: for receiving the synchronized update request of local server transmission, local clothes are verified by unique verification code The identity of business device, after the authentication success of local server, log-on data wireless transmission, by current information and current information Historical information in first identifier code covering host computer in specified region, completes synchronized update.
Moreover, system further include:
GPS positioning system and scanning device: it is arranged in the aerial photography device, the GPS positioning system is for realizing positioning Function, the scanning device is for scanning first identifier code.
Moreover, system further include:
Picture recognition module: being mounted in local server, for comparing power grid basis in historical information and current information Whether the influence of the position of facility, quantity and presentation is identical.
Moreover, the total quantity of the power grid infrastructure presented in 360 degree of distant view photographs of establishing shot point shooting is not More than 15.
Moreover, the total quantity of power grid infrastructure is no more than 50 in the specified region;Power grid in the specified region The total quantity of infrastructure is divided into multiple subregions, at least one establishing shot point, a fixation are arranged in subregion It is mutually staggered between the power grid infrastructure presented in 360 degree of distant view photographs of shooting point shooting.
Moreover, the specified region is equipped with second identification code, which includes the institute of specified regional center position In longitude and latitude and corresponding province title;The subregion is equipped with third identification code, which includes second identification code With the serial number for the establishing shot point arranged in the subregion from north orientation south.
Moreover, by the second identification code and third identification code pair when the local server and host computer synchronize update The historical information of corresponding establishing shot point should be found and specify the third identification code in region with the historical information.
Moreover, the power grid infrastructure presented in 360 degree of distant view photographs of the historical information and current information is according to certainly The sequence of from left to right is successively stored in local server and host computer with the first identifier code of power grid infrastructure one-to-one correspondence It is interior.
Moreover, the first identifier code includes two dimensional code and RFID electronic label.
Moreover, shooting height of the aerial photography device in plains region is lower than 30 meters;The aerial photography device is in the shooting in mountain area Height is higher than 100 meters.
The advantages and positive effects of the present invention are:
1, the present invention is for synchronizing update to the three-dimensional localization data of infrastructure in power grid, by by taken at regular intervals The current information of power grid infrastructure be compared with historical information, by changed current information synchronized update to being based on To cover historical information in the power grid infrastructure information of GIS, artificial participation is reduced, reduces error probability, guarantees that data update Efficiency and data accuracy.
2, the burst electricity that fast and accurately infrastructure construction of power grid, repacking and disaster can occur by the present invention Systematically delta data is updated on power grid GIS data platform net, by by the current letter of the power grid infrastructure of taken at regular intervals Breath is compared with historical information, by changed infrastructure information synchronized update to the power grid infrastructure based on GIS In information, for usually and disaster occur when power grid infrastructure rationally arrange net and power grid repairing, maintenance provided with detection Perfect geographical three-dimensional information, greatly improves work efficiency.
3, the aerial photography device that the present invention is arranged can acquire the photo of the power grid infrastructure in specified region in real time, for locking The three-dimensional arrangement and quantitative relation of power grid infrastructure in the fixed region, and combine local server automatically to the letter of locking Breath is analysed and compared, and detects changed data;Local server is also configured to for locking GIS data and photo The region in power grid infrastructure combination formed power grid infrastructure three-dimensional distribution map;First identifier code, the second mark The calibration for knowing code and third identification code ensure that and can be mutually distinguishable in power grid GIS data platform between power grid infrastructure It opens, data understand that reliably, the analysis convenient for local server and host computer is transferred;Host computer also by local server more New request carries out authentication, does not receive the GIS data that extraneous illegal identity server distorts power grid, guarantees data system Stablize.
Detailed description of the invention
Fig. 1 is data interaction structural schematic diagram of the invention;
Fig. 2 is the third identification code layout of each power grid infrastructure in the subregion specified in region in an embodiment Schematic diagram.
Specific embodiment
The embodiment of the present invention is further described below in conjunction with attached drawing:
The mobile message acquisition of the power grid infrastructure based on GIS a kind of and synchronous updating system, as shown in Figure 1, comprising:
First identifier code: it is arranged in power grid infrastructure for identifying power grid infrastructure device;
Aerial photography device: for acquiring the current information of power grid infrastructure, it can be also used for scanning first identifier code;
Local server: for storing the historical information of the power grid infrastructure in presumptive area, local server is also used In the current information of reception aerial photography device acquisition, and historical information and current information are compared, if comparison result is difference, All first identity codees in the specified region of the instruction scan current information then are issued to aerial photography device, while current information being covered Lid historical information, and synchronized update request is issued to host computer;If comparison result be it is identical, current information is deleted, In, historical information and current information are respectively the covering for applying aerial photography device successively to shoot in establishing shot point along chronological order Have two 360 degree of distant view photographs of power grid infrastructure in specified region, and the shooting of same establishing shot point multiple 360 Spend distant view photograph latitude and longitude coordinates of finding a view, 24 hours system in find a view the time and find a view height it is constant always, such as: every When two days noon 12, latitude and longitude coordinates are 30.35 east longitude 114.17 of north latitude, and the establishing shot that height is 30 meters from the ground Point carries out shooting panoramic photo piece, and the position of this shooting point is constant, and true by carrying out information exchange with communications satellite It is correct to protect shooting point selection.
Host computer: for receiving the synchronized update request of local server transmission, this is verified by unique verification code first The identity of ground server, after the authentication success of local server, log-on data wireless transmission, by current information and currently Historical information in first identifier code covering host computer in the specified region of information, completes synchronized update.
In the above scheme, aerial photography device is set as acquiring the photo of the power grid infrastructure in specified region in real time, is used for The three-dimensional arrangement and quantitative relation of the power grid infrastructure in the region are locked, and combines local server automatically to locking Information is analysed and compared, and detects that changed data, changed data refer to the number of infrastructure in photo The variation of amount, the arrangement angle of arrangement mode.Aerial photography device is also configured to the first identifier code in surface sweeping infrastructure, will shine The arrangement mode of changed infrastructure and first identifier code carry out one-to-one correspondence acquisition in piece, for cooperating local service Device carries out data and resurveys and update.Local server is also configured in the region for locking GIS data with photo Power grid infrastructure combination formed power grid infrastructure three-dimensional distribution map.First identifier code, second identification code and third The calibration of identification code ensure that and can be mutually distinguishable open in power grid GIS data platform between power grid infrastructure that data understand Reliably, the analysis convenient for local server and host computer is transferred.Host computer also requests to carry out by the update to local server Authentication does not receive the GIS data that extraneous illegal identity server distorts power grid, guarantees the stabilization of data system.
In the present embodiment, the total quantity of power grid infrastructure in region is specified to be no more than 50.Power grid infrastructure can Think high-voltage line protective frame, electric pole, transformer or wind wheel for wind power generation or even power plant etc., meanwhile, limit testing number Amount cannot be excessive, guarantees to be easier to when the accuracy of data acquisition and later period emergency situations are handled to the power grid base to break down Plinth setting is positioned, and investigation range is reduced.
As shown in Fig. 2, the total quantity of power grid infrastructure in specified region is marked off multiple subregions, in subregion At least one establishing shot point, the power grid infrastructure presented in 360 degree of distant view photographs of establishing shot point shooting are set Between mutually stagger.The setting of establishing shot point will guarantee not omitting any one power grid infrastructure, therefore, on visual angle not Can be superimposed, for example, in Fig. 2 " in 360 degree of distant view photographs of shooting, infrastructure 2-1,2-2,2-3,2-4,2-5 and 2-6, Image is presented.
In the present embodiment, the power grid infrastructure presented in 360 degree of distant view photographs of establishing shot point shooting Total quantity is no more than 15.
In the present embodiment, the specified region is equipped with second identification code, which includes specified 1 center of region The place longitude and latitude of position and corresponding province title, the subregion 2 or 3 are equipped with third identification code, the third mark Code includes second identification code and the establishing shot point 2 arranged in the subregion from north orientation south " serial number, such as in figure, The number in infrastructure from north orientation south in subregion 2 is 2-1,2-2,2-3,2-4,2-5 and 2-6, then adds said sequence Into third identification code to show position difference.In the above scheme, combining geographic location and longitude and latitude are by specified region and son Region is identified, and carries out accurate recognition and processing to data convenient for local server and host computer, and by authentication with And three layer identification code just finally by information synchronize update processing, avoid data from arbitrarily being distorted, guarantee data security.
In the present embodiment, the power grid basis presented in 360 degree of distant view photographs of the historical information and current information is set Apply according to sequence from left to right, successively with the first identifier code of power grid infrastructure one-to-one correspondence be stored in local server and In host computer.Compared by image, by the power grid infrastructure presented in 360 degree of distant view photographs of current information in turn with history The photo of information carries out image recognition, carries out accurate judgement to the variation of the quantity, the arrangement angle of arrangement mode of infrastructure, Human error is avoided, error rate is reduced.
In the present embodiment, by the second identification code and third when the local server and host computer synchronize update Identification code corresponds to the historical information for finding establishing shot point and specifies the third identification code in region with the historical information.
In the present embodiment, further includes:
Picture recognition module, be used to compare the position of power grid infrastructure in historical information and current information, quantity and Whether the influence of presentation is identical;GPS positioning system and scanning device are arranged in the aerial photography device, and the scanning device is used In scanning first identifier code.
The first identifier code includes two dimensional code and RFID electronic label.Wherein, RFID electronic label guarantees that aerial photography device can It is convenient and efficient without establishing mechanical or optical contact with the first identifier code of mobile collection power grid infrastructure.
In the present embodiment, in plains region, the shooting height of the aerial photography device is lower than 30 meters;It is described to take photo by plane in mountain area The shooting height of device is higher than 100 meters.
Number of devices and treatment scale described herein are for simplifying explanation of the invention.To the present invention is based on GIS Power grid infrastructure mobile message acquisition and the application of synchronous updating system, modifications and variations to those skilled in the art For be obvious.
It is emphasized that embodiment of the present invention be it is illustrative, without being restrictive, therefore packet of the present invention Include and be not limited to embodiment described in specific embodiment, it is all by those skilled in the art according to the technique and scheme of the present invention The other embodiments obtained, also belong to the scope of protection of the invention.

Claims (10)

1. mobile message acquisition and the synchronous updating system of a kind of power grid infrastructure based on GIS, characterized by comprising:
First identifier code: it is arranged in power grid infrastructure for identifying power grid infrastructure device;
Aerial photography device: for acquiring the current information of power grid infrastructure, and for scanning first identifier code;
Local server: for storing the historical information of the power grid infrastructure in presumptive area, working as aerial photography device acquisition is received Preceding information, and historical information and current information are compared, if comparison result is difference, instruction is issued to aerial photography device and is swept It retouches all first identifier codes in the specified region of the current information, while current information is covered into historical information, and to upper Machine issues synchronized update request;If comparison result be it is identical, current information is deleted, wherein historical information and current letter Breath is respectively to be covered with power grid base in specified region along what chronological order was successively shot in establishing shot point using aerial photography device Two 360 degree of distant view photographs of Infrastructure, and same establishing shot point shooting multiple 360 degree of distant view photographs find a view through Latitude coordinate, 24 hours system in find a view the time and find a view height it is constant always;
Host computer: for receiving the synchronized update request of local server transmission, local server is verified by unique verification code Identity, after the authentication of local server success, current information and current information are specified in log-on data wireless transmission Region in first identifier code covering host computer in historical information, complete synchronized update.
2. mobile message acquisition and the synchronous updating system of the power grid infrastructure according to claim 1 based on GIS, It is characterized in that: further include:
GPS positioning system and scanning device: being arranged in the aerial photography device, the GPS positioning system for realizing positioning function, The scanning device is for scanning first identifier code.
3. mobile message acquisition and the synchronous updating system of the power grid infrastructure according to claim 1 based on GIS, It is characterized in that: further include:
Picture recognition module: being mounted in local server, for comparing power grid infrastructure in historical information and current information Position, the image of quantity and presentation it is whether identical.
4. the mobile message of the power grid infrastructure according to any one of claims 1 to 3 based on GIS is acquired and is synchronized more New system, it is characterised in that: the sum of the power grid infrastructure presented in 360 degree of distant view photographs of establishing shot point shooting Amount is no more than 15.
5. the mobile message of the power grid infrastructure according to any one of claims 1 to 3 based on GIS is acquired and is synchronized more New system, it is characterised in that: the total quantity of power grid infrastructure is no more than 50 in the specified region;In the specified region The total quantity of power grid infrastructure is divided into multiple subregions, is arranged at least one establishing shot point in subregion, and one It is mutually staggered between the power grid infrastructure presented in 360 degree of distant view photographs of establishing shot point shooting.
6. mobile message acquisition and the synchronous updating system of the power grid infrastructure according to claim 5 based on GIS, Be characterized in that: the specified region is equipped with second identification code, which includes the place warp of specified regional center position Latitude and corresponding province title;The subregion be equipped with third identification code, the third identification code include second identification code and The serial number for the establishing shot point arranged in the subregion from north orientation south.
7. mobile message acquisition and the synchronous updating system of the power grid infrastructure according to claim 6 based on GIS, It is characterized in that: by the second identification code and third identification code is corresponding looks for when the local server synchronizes update with host computer The third identification code in region is specified to the historical information of corresponding establishing shot point and with the historical information.
8. the mobile message of the power grid infrastructure according to any one of claims 1 to 3 based on GIS is acquired and is synchronized more New system, it is characterised in that: the power grid infrastructure presented in 360 degree of distant view photographs of the historical information and current information is pressed According to sequence from left to right, local server and upper successively is stored in the first identifier code of power grid infrastructure one-to-one correspondence In machine.
9. the mobile message of the power grid infrastructure according to any one of claims 1 to 3 based on GIS is acquired and is synchronized more New system, it is characterised in that: the first identifier code includes two dimensional code and RFID electronic label.
10. mobile message acquisition and the synchronous updating system of the power grid infrastructure according to claim 1 based on GIS, It is characterized by: shooting height of the aerial photography device in plains region is lower than 30 meters;The aerial photography device is high in the shooting in mountain area Degree is higher than 100 meters.
CN201510611693.2A 2015-09-21 2015-09-21 The mobile message of power grid infrastructure based on GIS acquires and synchronous updating system Active CN105184680B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510611693.2A CN105184680B (en) 2015-09-21 2015-09-21 The mobile message of power grid infrastructure based on GIS acquires and synchronous updating system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510611693.2A CN105184680B (en) 2015-09-21 2015-09-21 The mobile message of power grid infrastructure based on GIS acquires and synchronous updating system

Publications (2)

Publication Number Publication Date
CN105184680A CN105184680A (en) 2015-12-23
CN105184680B true CN105184680B (en) 2018-12-04

Family

ID=54906736

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510611693.2A Active CN105184680B (en) 2015-09-21 2015-09-21 The mobile message of power grid infrastructure based on GIS acquires and synchronous updating system

Country Status (1)

Country Link
CN (1) CN105184680B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108764401A (en) * 2018-05-28 2018-11-06 孔令根 It is a kind of to be easy to debate the two-dimensional marker scheme to addressing
CN110019276B (en) * 2018-06-29 2024-01-30 珠海爱路达信息科技有限公司 Intelligent highway facility data acquisition and update method
CN109710696B (en) * 2018-12-28 2021-11-30 山东恒道信息技术有限公司 System and method for power equipment checking and transaction moving operation

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101046802A (en) * 2006-03-31 2007-10-03 马飞涛 Geographic picture searching method

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8144937B2 (en) * 2008-10-15 2012-03-27 The Boeing Company System and method for airport mapping database automatic change detection

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101046802A (en) * 2006-03-31 2007-10-03 马飞涛 Geographic picture searching method

Also Published As

Publication number Publication date
CN105184680A (en) 2015-12-23

Similar Documents

Publication Publication Date Title
KR102015388B1 (en) 3D point cloud DB construction and virtual reality space map providing system and method of providing orthophotosimposing point cloud DB using UAV, ground-based LiDAR scanner
CN110243354B (en) Dynamic monitoring method and system for urban illegal building
CN103424113B (en) Indoor positioning and navigating method of mobile terminal based on image recognition technology
CN111322994B (en) Large-scale cadastral survey method for intensive house area based on unmanned aerial vehicle oblique photography
CN102884400B (en) Messaging device, information processing system and program
CN108168554B (en) Rapid map planning method for unmanned aerial vehicle power line patrol system
Gerke et al. Orientation of oblique airborne image sets-experiences from the ISPRS/EUROSDR benchmark on multi-platform photogrammetry
KR20110066133A (en) Image annotation on portable devices
CN105184680B (en) The mobile message of power grid infrastructure based on GIS acquires and synchronous updating system
CN106940187B (en) Navigation method and system for mine ground rapid inspection
CN205942445U (en) Site selection planning of wireless base station panorama and reconnaissance system based on take photo by plane
CN105046447A (en) Information acquisition method, device and terminal of electric power facility
CN103745190A (en) Two-dimensional code-based performance and monitoring data presentation method
CN113656477A (en) Method for verifying and fusing multi-source heterogeneous data of homeland space
CN106227730A (en) Power grid GIS data acquisition and recording system and collect and record method
CN109636850A (en) Visible light localization method in faced chamber under intelligent lamp
CN115858714B (en) Unmanned aerial vehicle collected GIS data automatic modeling management system and method
CN113316160B (en) MR-based operation and maintenance method, system and storage medium for base station equipment
CN116164730A (en) Photovoltaic equipment positioning navigation method and related equipment
CN116129064A (en) Electronic map generation method, device, equipment and storage medium
CN110717061B (en) Transformer substation equipment positioning method and system based on camera and associated mapping
CN113239076A (en) Geographic information inquiry management platform based on three-dimensional image
US11320262B2 (en) Geolocation method and system for implementing same
CN113650783A (en) Fixed wing oblique photography cadastral mapping method, system and equipment
CN102831180A (en) Equipment and method for converting space references of land supervision data

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant