CN105179807A - Moving device used for large steel pipe to penetrate through roadbed sleeve - Google Patents
Moving device used for large steel pipe to penetrate through roadbed sleeve Download PDFInfo
- Publication number
- CN105179807A CN105179807A CN201510691924.5A CN201510691924A CN105179807A CN 105179807 A CN105179807 A CN 105179807A CN 201510691924 A CN201510691924 A CN 201510691924A CN 105179807 A CN105179807 A CN 105179807A
- Authority
- CN
- China
- Prior art keywords
- steel pipe
- roadbed
- sleeve pipe
- transport vehicle
- sleeve
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L1/00—Laying or reclaiming pipes; Repairing or joining pipes on or under water
- F16L1/024—Laying or reclaiming pipes on land, e.g. above the ground
- F16L1/028—Laying or reclaiming pipes on land, e.g. above the ground in the ground
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Machines For Laying And Maintaining Railways (AREA)
Abstract
The invention discloses a moving device used for a large steel pipe to penetrate through a roadbed sleeve. The moving device comprises traction equipment and a transport cart used for bearing the steel pipe. The traction equipment is arranged on one side of a roadbed, the transport cart is arranged inside the sleeve on the other side of the roadbed in a sliding mode and connected with the traction equipment, and the traction equipment drives the transport cart to drive the steel pipe to move to penetrate through the roadbed sleeve. The device has the advantages of being simple in structure, convenient to use and capable of guaranteeing safe construction and operation at the same time.
Description
Technical field
The present invention relates to the poling technology of the large-scale pipeline of the roadbed such as highway, railway, particularly relate to a kind of shifter passing through roadbed sleeve pipe for large-scale steel pipe.
Background technique
Generally adopt non-excavating construction method when roadbeds such as large-scale pipeline highway crossing, railways, after cover pipe construction completes, poling operational method affects pipeline construction quality and security of operation.In prior art, when the roadbeds such as certain section of highway, railway carry out poling operation, enclosing must be carried out to this section of highway and railway, utilize large-scale lifting appliance to construct to pipeline performance.The method makes large-scale lifting appliance be in the security operation zone of highway, railway, has had a strong impact on the normal safe operation of highway, railway; Meanwhile, the Security of work progress cannot also be ensured.
Summary of the invention
The technical problem to be solved in the present invention overcomes the deficiencies in the prior art, provides the shifter passing through roadbed sleeve pipe for large-scale steel pipe that a kind of structure is simple, easy to use, can ensure safe construction and safe operation simultaneously.
For solving the problems of the technologies described above, the present invention by the following technical solutions:
A kind of shifter passing through roadbed sleeve pipe for large-scale steel pipe, comprise pulling equipment and the transport vehicle for carrying steel pipe, described pulling equipment is arranged on the side of roadbed, be connected with pulling equipment in the sleeve pipe that described transport vehicle is slidedly arranged on roadbed opposite side, described pulling equipment orders about transport vehicle and drives steel pipe movement to pass through the sleeve pipe of roadbed.
Further improvement as technique scheme:
Described transport vehicle comprises vehicle frame and is arranged on the roller of frame side, and described vehicle frame top is provided with the curved support plate be affixed with steel pipe outer arc.
Described curved support plate is provided with buffer layer.
Described vehicle frame is also provided with stiffening plate.
Described pulling equipment is winch, and described winch is fixed on the side of roadbed and is connected with transport vehicle by its wire rope.
Also comprise guide rail, described guide rail is laid in sleeve pipe, and described transport vehicle is slidedly arranged on guide rail.
Also comprise upper saw pulley, described upper saw pulley one end and steel pipe sidepiece affixed, the other end and inside pipe casing slip.
Compared with prior art, the invention has the advantages that:
The shifter passing through roadbed sleeve pipe for large-scale steel pipe of the present invention, comprises pulling equipment and the transport vehicle for carrying steel pipe, and pulling equipment orders about transport vehicle and drives steel pipe movement to pass through the sleeve pipe of roadbed.Its structure is simple, this installation takes the method pulled to the other end by one end to construct, namely first in roadbed side, two joint steel-pipe weldings are completed, and carry out outer preservative treatment, rear utilization is installed on the pulling equipment traction of opposite side, and the steel pipe of soldering is pulled certain length (at every turn pulling length to be save the length of steel pipe) by the transport vehicle in sleeve pipe, Rewelding like this, traction, until all penstock installations put in place in sleeve pipe, it is very easy to use.This structure makes to pass through in roadbed sleeve pipe work progress at steel pipe; steel pipe is transported to mounting point by transport vehicle low speed rotation; avoid within large-scale lifting appliance is in the safe operation zone of protection of highway, railway; both ensure that the safe construction of penstock installation, and also can ensure the safe operation of highway, railway simultaneously.
Accompanying drawing explanation
Fig. 1 is the present invention passes through the shifter of roadbed sleeve pipe main TV structure schematic diagram for large-scale steel pipe.
Fig. 2 is the present invention passes through the shifter of roadbed sleeve pipe side-looking structural representation for large-scale steel pipe.
Fig. 3 is that the present invention passes through the main TV structure schematic diagram of transport vehicle in the shifter of roadbed sleeve pipe for large-scale steel pipe.
Fig. 4 is that the present invention passes through the plan structure schematic diagram of transport vehicle in the shifter of roadbed sleeve pipe for large-scale steel pipe.
In figure, each label represents:
1, pulling equipment; 2, transport vehicle; 21, vehicle frame; 22, roller; 23, curved support plate; 24, buffer layer; 25, stiffening plate; 3, sleeve pipe; 4, steel pipe; 5, guide rail; 6, upper saw pulley.
Embodiment
Below with reference to Figure of description and specific embodiment, the present invention is described in further details.
Fig. 1 to Fig. 4 shows the present invention passes through the shifter of roadbed sleeve pipe a kind of embodiment for large-scale steel pipe, this shifter comprises pulling equipment 1 and the transport vehicle 2 for carrying steel pipe, pulling equipment 1 is arranged on the side of roadbed, be connected with pulling equipment 1 in the sleeve pipe 3 that transport vehicle 2 is slidedly arranged on roadbed opposite side, pulling equipment 1 orders about the sleeve pipe 3 that transport vehicle 2 drives steel pipe 4 to move to pass through roadbed.Its structure is simple, this installation takes the method pulled to the other end by one end to construct, namely first in roadbed side, two joint steel pipes 4 have been welded, and carry out outer preservative treatment, the pulling equipment 1 that rear utilization is installed on opposite side draws, and the steel pipe 4 of soldering is pulled certain length (at every turn pulling length to be the length of 1 joint steel pipe 4) by the transport vehicle 2 in sleeve pipe, Rewelding like this, traction, until all steel pipes 4 are in place in sleeve pipe 3, operation is very easy for it.This structure makes to pass through in roadbed sleeve pipe 3 work progress at steel pipe 4; steel pipe 4 is transported to mounting point by transport vehicle 2 low speed rotation; avoid within large-scale lifting appliance is in the safe operation zone of protection of highway, railway; both ensure that the safe construction that steel pipe 4 is installed, and also can ensure the safe operation of highway, railway simultaneously.
In the present embodiment, transport vehicle 2 comprises vehicle frame 21 and is arranged on the roller 22 of vehicle frame 21 sidepiece, and vehicle frame 21 top is provided with the curved support plate 23 be affixed with steel pipe 4 outer arc.In this structure, vehicle frame 21, roller 22 and curved support plate 23 form integrally-built transport vehicle 2, and curved support plate 23 can be affixed with steel pipe 4 outer arc, ensure that steel pipe 4 can not roll on transport vehicle 2 in moving process, improves stability and the reliability of movement.
In the present embodiment, curved support plate 23 is provided with buffer layer 24.When placing steel tubes 4, this buffer layer 24 can play buffer function to steel pipe 4, avoids steel pipe 4 and produces rigidity with curved support plate 23 and contact, and protects curved support plate 23 and steel pipe 4 is not impaired simultaneously, plays a very good protection.
In the present embodiment, vehicle frame 21 is also provided with stiffening plate 25.This stiffening plate 25 is arranged on curved support plate 23 both sides, greatly can improve the bulk strength of transport vehicle 2, further increase the stability of movement.
In the present embodiment, pulling equipment 1 is winch, and winch is fixed on the side of roadbed and is connected with transport vehicle 2 by its wire rope.First 2/3 place of first segment steel pipe 4 is placed on the transport vehicle 2 in sleeve pipe 3, at first segment steel pipe 4 foremost, inside bottom 30 ° of scope places each side weld open pore steel plate one piece, steel pipe 4 is drawn for fixing wire rope and sheave block, (sheave block adopts one, 4 strand sheave block), namely start subsequently to carry out first segment steel pipe 4 and the welding with rear steel pipe 4, then starting winch pulls transport vehicle to move by wire rope, thus realizes the movement of steel pipe 4, and its structure is simple, with low cost.
In the present embodiment, also comprise guide rail 5, guide rail 5 is laid in sleeve pipe 3, and transport vehicle 2 is slidedly arranged on guide rail 5.Consider and directly can not carry out EXPANSION ANCHOR BOLTS construction at concrete sleeve 3, first in the scope of concrete sleeve 3 interior bottom portion 58 °, carry out fist stage concrete build and pre-buried dowel, it is highly 120mm that fist stage concrete is built, dowel layout pattern is single 2 groups, 1 group 2, fore-and-aft clearance is 500mm.After fist stage concrete has been built, be laid in by guide rail 5 in the scope of bottom concrete sleeve 3 22 °, guide rail 5 adopts the angle steel of 2 L100 × 63 × 6 to divide restraining peace to form along pipeline axial, track space 664mm; Between guide rail 5, the welding of employing 40 × 4mm angle steel, spacing are 500mm, weld solid during construction by dowel, reinforcing angle bar with guide rail 5.Guide rail 5 installation is also carried out second stage concrete and is built after acceptance(check), building is highly 128mm.Transport vehicle 2 is adopted with steel pipe 4 surface of contact, often save steel pipe and place 2 transport vehicles 24 times, each transport vehicle 2 is made up of four driving wheels and 10# channel-section steel skeleton (800mm × 650mm × 100mm), and guide rail 5 can ensure the movement direction of transport vehicle 2, improves stability and the convenience of movement further.
In the present embodiment, also comprise upper saw pulley 6, upper saw pulley 6 one end and steel pipe 4 sidepiece affixed, the other end and sleeve pipe 3 inside sliding.In the steel pipe 4 center line axis elevation location left and right sides, one upper saw pulley 6 is installed respectively, upper saw pulley installing space is pressed 12m and is controlled, to guarantee installation direction when steel pipe 4 pulls, due to the guidance of steel pipe about 4 upper saw pulley 6, overcome the forced centering problem of steel wire rope of windlass.
Although the present invention discloses as above with preferred embodiment, but and be not used to limit the present invention.Any those of ordinary skill in the art, when not departing from technical solution of the present invention scope, can utilize the technology contents of above-mentioned announcement to make many possible variations and modification to technical solution of the present invention, or being revised as the Equivalent embodiments of equivalent variations.Therefore, every content not departing from technical solution of the present invention, according to the technology of the present invention essence to any simple modification made for any of the above embodiments, equivalent variations and modification, all should drop in the scope of technical solution of the present invention protection.
Claims (9)
1. one kind is passed through the shifter of roadbed sleeve pipe for large-scale steel pipe, it is characterized in that: comprise pulling equipment (1) and the transport vehicle (2) for carrying steel pipe, described pulling equipment (1) is arranged on the side of roadbed, be connected with pulling equipment (1) in the sleeve pipe (3) that described transport vehicle (2) is slidedly arranged on roadbed opposite side, described pulling equipment (1) orders about transport vehicle (2) and drives steel pipe (4) movement to pass through the sleeve pipe (3) of roadbed.
2. the shifter passing through roadbed sleeve pipe for large-scale steel pipe according to claim 1, it is characterized in that: described transport vehicle (2) comprises vehicle frame (21) and is arranged on the roller (22) of vehicle frame (21) sidepiece, and described vehicle frame (21) top is provided with the curved support plate (23) be affixed with steel pipe (4) outer arc.
3. the shifter passing through roadbed sleeve pipe for large-scale steel pipe according to claim 2, is characterized in that: described curved support plate (23) is provided with buffer layer (24).
4. the shifter passing through roadbed sleeve pipe for large-scale steel pipe according to claim 2, is characterized in that: described vehicle frame (21) is also provided with stiffening plate (25).
5. the shifter passing through roadbed sleeve pipe for large-scale steel pipe according to any one of claim 1 to 4, it is characterized in that: described pulling equipment (1) is winch, described winch is fixed on the side of roadbed and is connected with transport vehicle (2) by its wire rope.
6. the shifter passing through roadbed sleeve pipe for large-scale steel pipe according to any one of claim 1 to 4, it is characterized in that: also comprise guide rail (5), described guide rail (5) is laid in sleeve pipe (3), and described transport vehicle (2) is slidedly arranged on guide rail (5).
7. the shifter passing through roadbed sleeve pipe for large-scale steel pipe according to claim 5, it is characterized in that: it is characterized in that: also comprise guide rail (5), described guide rail (5) is laid in sleeve pipe (3), and described transport vehicle (2) is slidedly arranged on guide rail (5).
8. the shifter passing through roadbed sleeve pipe for large-scale steel pipe according to any one of claim 1 to 4, it is characterized in that: also comprise upper saw pulley (6), described upper saw pulley (6) one end and steel pipe (4) sidepiece affixed, the other end and sleeve pipe (3) inside sliding.
9. the shifter passing through roadbed sleeve pipe for large-scale steel pipe according to claim 7, it is characterized in that: it is characterized in that: also comprise upper saw pulley (6), described upper saw pulley (6) one end and steel pipe (4) sidepiece affixed, the other end and sleeve pipe (3) inside sliding.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510691924.5A CN105179807A (en) | 2015-10-23 | 2015-10-23 | Moving device used for large steel pipe to penetrate through roadbed sleeve |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510691924.5A CN105179807A (en) | 2015-10-23 | 2015-10-23 | Moving device used for large steel pipe to penetrate through roadbed sleeve |
Publications (1)
Publication Number | Publication Date |
---|---|
CN105179807A true CN105179807A (en) | 2015-12-23 |
Family
ID=54902096
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510691924.5A Pending CN105179807A (en) | 2015-10-23 | 2015-10-23 | Moving device used for large steel pipe to penetrate through roadbed sleeve |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105179807A (en) |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106594388A (en) * | 2016-12-27 | 2017-04-26 | 北京市政路桥管理养护集团有限公司 | Pipe working platform and method for laying pipes by applying pipe working platform |
CN107587390A (en) * | 2017-09-27 | 2018-01-16 | 重庆市瀚德高科机器人有限公司 | Laying rail method in a kind of pipeline |
CN108426094A (en) * | 2018-03-22 | 2018-08-21 | 北京中润宝成工程技术有限公司 | A kind of push pipe poling construction equipment and its method |
CN108644470A (en) * | 2018-07-04 | 2018-10-12 | 中国二十冶集团有限公司 | A kind of construction method of interior conduit concrete bearing |
CN109050381A (en) * | 2018-08-06 | 2018-12-21 | 武汉冶建筑安装工程有限责任公司 | Pipe gallery is constructed the transportation resources of medium-and-large-sized pipeline |
CN109854813A (en) * | 2018-10-15 | 2019-06-07 | 中铁第四勘察设计院集团有限公司 | Pipe laying construction method and system in a kind of casing based on wheel-track type pipe collar |
CN111336315A (en) * | 2020-03-25 | 2020-06-26 | 五冶集团上海有限公司 | Method for laying and installing plastic-coated steel pipes in concrete sleeve |
CN112879661A (en) * | 2020-12-31 | 2021-06-01 | 中铁十六局集团路桥工程有限公司 | Traction device for water supply steel pipe in bypass sleeve and construction method |
CN114352804A (en) * | 2022-03-17 | 2022-04-15 | 中铁九局集团第四工程有限公司 | Construction method for underground small-space corrugated pipe to pass through pipeline by using track pulley |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE19705566A1 (en) * | 1997-02-13 | 1998-08-20 | Horst Dipl Ing Brabender | Pipe laying equipment for replacing steel pipelines with plastic, avoiding trenching |
CN2586034Y (en) * | 2002-11-16 | 2003-11-12 | 胜利油田胜利石油化工建设有限责任公司三分公司 | Core tube through bushing appts. for prefabricated seabea pipeline |
CN201944432U (en) * | 2011-01-25 | 2011-08-24 | 北京城建亚泰建设工程有限公司 | Pipe penetrating construction device in long-distance sleeve pipe |
CN102261517A (en) * | 2011-07-13 | 2011-11-30 | 中国建筑第二工程局有限公司 | Method for mounting prestress steel cylinder concrete pipe in narrow space in sleeve |
CN104154325A (en) * | 2014-06-23 | 2014-11-19 | 中交一航局第二工程有限公司 | Installation adjustment device and method for large-diameter pipeline roadbed crossing casing |
CN205101674U (en) * | 2015-10-23 | 2016-03-23 | 中国水利水电第八工程局有限公司 | Be used for large -scale steel pipe to pass through road bed sheathed tube mobile device |
-
2015
- 2015-10-23 CN CN201510691924.5A patent/CN105179807A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE19705566A1 (en) * | 1997-02-13 | 1998-08-20 | Horst Dipl Ing Brabender | Pipe laying equipment for replacing steel pipelines with plastic, avoiding trenching |
CN2586034Y (en) * | 2002-11-16 | 2003-11-12 | 胜利油田胜利石油化工建设有限责任公司三分公司 | Core tube through bushing appts. for prefabricated seabea pipeline |
CN201944432U (en) * | 2011-01-25 | 2011-08-24 | 北京城建亚泰建设工程有限公司 | Pipe penetrating construction device in long-distance sleeve pipe |
CN102261517A (en) * | 2011-07-13 | 2011-11-30 | 中国建筑第二工程局有限公司 | Method for mounting prestress steel cylinder concrete pipe in narrow space in sleeve |
CN104154325A (en) * | 2014-06-23 | 2014-11-19 | 中交一航局第二工程有限公司 | Installation adjustment device and method for large-diameter pipeline roadbed crossing casing |
CN205101674U (en) * | 2015-10-23 | 2016-03-23 | 中国水利水电第八工程局有限公司 | Be used for large -scale steel pipe to pass through road bed sheathed tube mobile device |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106594388A (en) * | 2016-12-27 | 2017-04-26 | 北京市政路桥管理养护集团有限公司 | Pipe working platform and method for laying pipes by applying pipe working platform |
CN107587390A (en) * | 2017-09-27 | 2018-01-16 | 重庆市瀚德高科机器人有限公司 | Laying rail method in a kind of pipeline |
CN108426094A (en) * | 2018-03-22 | 2018-08-21 | 北京中润宝成工程技术有限公司 | A kind of push pipe poling construction equipment and its method |
CN108644470A (en) * | 2018-07-04 | 2018-10-12 | 中国二十冶集团有限公司 | A kind of construction method of interior conduit concrete bearing |
CN109050381A (en) * | 2018-08-06 | 2018-12-21 | 武汉冶建筑安装工程有限责任公司 | Pipe gallery is constructed the transportation resources of medium-and-large-sized pipeline |
CN109854813A (en) * | 2018-10-15 | 2019-06-07 | 中铁第四勘察设计院集团有限公司 | Pipe laying construction method and system in a kind of casing based on wheel-track type pipe collar |
CN111336315A (en) * | 2020-03-25 | 2020-06-26 | 五冶集团上海有限公司 | Method for laying and installing plastic-coated steel pipes in concrete sleeve |
CN112879661A (en) * | 2020-12-31 | 2021-06-01 | 中铁十六局集团路桥工程有限公司 | Traction device for water supply steel pipe in bypass sleeve and construction method |
CN114352804A (en) * | 2022-03-17 | 2022-04-15 | 中铁九局集团第四工程有限公司 | Construction method for underground small-space corrugated pipe to pass through pipeline by using track pulley |
CN114352804B (en) * | 2022-03-17 | 2022-06-24 | 中铁九局集团第四工程有限公司 | Construction method for underground small-space corrugated pipe to pass through pipeline by using track pulley |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105179807A (en) | Moving device used for large steel pipe to penetrate through roadbed sleeve | |
CN205101674U (en) | Be used for large -scale steel pipe to pass through road bed sheathed tube mobile device | |
CN201077958Y (en) | Beam movement carriage for road and bridge construction | |
CN201697897U (en) | Automatic under-floor ultrasonic defect detector for railway vehicle | |
CN107059629B (en) | Sightseeing line track bridge hoisting bridge equipment | |
JP5485076B2 (en) | Tunnel construction equipment and construction method | |
CN105347188A (en) | Traction type arch-bridge crane of crane carriage | |
CN107762552B (en) | The rapid translation trolley and method of mating trailer after TBM | |
KR20150070578A (en) | Construction Method | |
CN101949133A (en) | Straddle type bridge girder erection machine | |
CN110529156B (en) | Tunnel excavation shield initial segment transportation system and method | |
CN103161471A (en) | Construction method in which large-diameter shield advances across air shaft in long distance | |
JP2001146716A (en) | Erection method for bridge beam | |
CN103449313A (en) | Maintenance crane special for rail container door type portal crane trolley travel mechanism | |
CN204022363U (en) | Rail mounted actuator | |
CN102275828A (en) | I-steel track manual-chain bridge crane | |
WO2023025325A1 (en) | Construction method for corrugated pipe to pass through pipeline by means of rail sliders in small underground space | |
CN202220465U (en) | Automobile shifting bench used for three-dimensional garage | |
CN209011776U (en) | Coiled tubing injection device and system | |
CN107869112B (en) | Traction system and method for bridge with large curvature radius | |
JP2008190221A (en) | Traverse facility in start shaft | |
CN204210478U (en) | A kind of load carrying ability 360 tons of transfer platforms | |
CN201932139U (en) | Rotary trolley on flat truck | |
CN201809726U (en) | Straddle-type bridge girder erection machine | |
JP7299103B2 (en) | Elevated structure construction system and construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20151223 |
|
RJ01 | Rejection of invention patent application after publication |