CN103161471A - Construction method in which large-diameter shield advances across air shaft in long distance - Google Patents

Construction method in which large-diameter shield advances across air shaft in long distance Download PDF

Info

Publication number
CN103161471A
CN103161471A CN2011104248360A CN201110424836A CN103161471A CN 103161471 A CN103161471 A CN 103161471A CN 2011104248360 A CN2011104248360 A CN 2011104248360A CN 201110424836 A CN201110424836 A CN 201110424836A CN 103161471 A CN103161471 A CN 103161471A
Authority
CN
China
Prior art keywords
shield
air shaft
shield structure
long distance
ventilating shaft
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2011104248360A
Other languages
Chinese (zh)
Inventor
杨成龙
龚金弟
顾振伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANGHAI FOUNDATION ENGINEERING Co Ltd
Original Assignee
SHANGHAI FOUNDATION ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANGHAI FOUNDATION ENGINEERING Co Ltd filed Critical SHANGHAI FOUNDATION ENGINEERING Co Ltd
Priority to CN2011104248360A priority Critical patent/CN103161471A/en
Publication of CN103161471A publication Critical patent/CN103161471A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The invention relates to a construction method in which a large-diameter shield advances across an air shaft in long distance. The pushing forward construction method of the large-diameter shield across the air shaft in a long distance comprises the following steps of determining the axis of the shield across the air shaft, determining the base form of precast concrete beams and steel box beams when a shield tunneling machine penetrates through the air shaft, and determining the piecing form and the supporting mode of air shaft negative ring pipe pieces. With the pushing forward construction method, maintenance time can be saved, the shield can be reused, construction period is greatly shortened, and materials are greatly saved. When the large-diameter shield penetrates through the air shaft in a long distance, side pressure on the shield does not exist, and piecing of the negative ring pipe pieces is extremely prone to deforming transversely. Meanwhile, when the shield is pushed forward in the air shaft, front pressure on the shield does not exist, and the negative ring pipe pieces are prone to tightening longitudinally (namely among rings). According to the construction method in which the large-diameter shield advances across the air shaft in long distance, the deformation problem of pipe pieces is well solved.

Description

The long distance of large-diameter shield is passed through ventilating shaft propelling construction method
Technical field
The present invention relates to a kind of shield structure length apart from the propelling construction method, especially a kind of for the long job practices apart from passing through ventilating shaft of large-diameter shield.
Background technology
At present, further exploitation along with urban underground space, the urban railway transit train speed of service improves constantly, tunnel clearance is required also to increase, large-diameter shield will get more and more to be applied in track traffic and use, it is inevitable that large-diameter shield passes through the ventilating shaft construction, and the large shield structure ventilating shaft construction technology how safe traverse distance is grown is to need the problem of solution badly.
Tight phenomenon of municipal engineering ubiquity duration, adopt precast concrete+steel case beam pedestal form not only can solve curing time, and can also reuse at present, greatly saves duration and material.
Large-diameter shield is when long distance is passed through in the ventilating shaft, and the shield structure is all without side pressure, and negative endless tube sheet assembly unit very easily produces lateral deformation, and when the shield structure advances in ventilating shaft simultaneously, also without positive pressure, negative endless tube sheet vertically (i.e. ring and encircle between) tightens up also being difficult for.Adopt the present invention can solve well the segment deformation problem.
Summary of the invention
The present invention will provide the long distance of a kind of large-diameter shield to pass through ventilating shaft propelling construction method, is used for solving the problem on deformation that advances the section of jurisdiction to produce in ventilating shaft.
For achieving the above object, the job practices that the present invention adopts is: the long distance of a kind of large-diameter shield is passed through ventilating shaft propelling construction method, and its Specific construction step is as follows:
Shield structure axis when 1) determining to pass through ventilating shaft
During according to shield, for going up a slope, appearing is the situation of descending:
Plane: take actual measurement into and out of the hole portal line of centres as shield structure pedestal axis in place
Elevation: when the shield structure passes through ventilating shaft, shield structure vertical axis is taked and designs axis phase segmentation method, namely enters the center, hole by the design centre, and the center of appearing is than the low 4cm of design;
Precast concrete beam+steel case beam pedestal form when 2) determining that shield machine passes through
Adopt 20 Pin concrete beam as pedestal when the shield structure passes through, at two steel case beams of concrete beam both sides layout, lay the Qu80 crane runway on the steel case;
3) determine the negative endless tube sheet assembly form of ventilating shaft and supporting way
Place respectively two shaped steel in ventilating shaft inner tunnel center along axis direction both sides before the shield structure passes through, and every propelling 75cm is welded and fixed with channel-section steel in progradation.
The invention has the beneficial effects as follows:
Job practices of the present invention can be saved curing time, and can also reuse, and greatly saves duration and material.Large-diameter shield is when long distance is passed through in the ventilating shaft, and the shield structure is all without side pressure, and negative endless tube sheet assembly unit very easily produces lateral deformation, and when the shield structure advances in ventilating shaft simultaneously, also without positive pressure, negative endless tube sheet vertically (i.e. ring and encircle between) tightens up also being difficult for.Adopt the present invention can solve well the segment deformation problem.
Description of drawings
Fig. 1 is that the shield structure that the present invention will construct passes through the ventilating shaft longitudinal plan;
Fig. 2 is that the shield structure that the present invention will construct passes through the ventilating shaft drawing in side sectional elevation.
The specific embodiment
Below in conjunction with specific embodiment, further set forth the present invention.Should be understood that these embodiment only to be used for explanation the present invention and be not used in and limit the scope of the invention.Should be understood that in addition those skilled in the art can make various changes or modifications the present invention after the content of having read the present invention's instruction, these equivalent form of values fall within the application's appended claims limited range equally.
The construction technology that the present invention passes through in No. 16 lines of Shanghai Rail Transit 5 long distances of mark Project Shield shield structure, the tunnel that construct (Fig. 1 is shown in 2), the concrete step of executing is:
Shield structure axis when 1) determining to pass through ventilating shaft
When the shield structure passes through ventilating shaft, turnover hole section design plane axis is straight line, and be vertically the convex curve of R=10000m, and the curve peak is positioned at ventilating shaft, and when namely entering the hole, the shield structure is upward slope, and appearing is descending.
Plane: take actual measurement into and out of the hole portal line of centres as shield structure pedestal axis in place
Elevation: when the shield structure passes through ventilating shaft, shield structure vertical axis is taked and designs axis phase segmentation method, namely enters the center, hole by the design centre, and the center of appearing is than the low 4cm of design.
Precast concrete beam+steel case beam pedestal form when 2) determining that shield machine passes through
Adopt 20 Pin concrete beam as pedestal when the shield structure passes through, at two steel case beams of concrete beam both sides layout, lay the Qu80 crane runway on the steel case.
3) the negative endless tube sheet assembly form of ventilating shaft and supporting way
Place respectively two shaped steel in ventilating shaft inner tunnel center along axis direction both sides before the shield structure passes through, and every propelling 75cm is welded and fixed with channel-section steel in progradation.

Claims (1)

1. the long distance of large-diameter shield is passed through ventilating shaft propelling construction method, it is characterized in that, the Specific construction step is as follows:
Shield structure axis when 1) determining to pass through ventilating shaft
During according to shield, for going up a slope, appearing is the situation of descending:
Plane: take actual measurement into and out of the hole portal line of centres as shield structure pedestal axis in place
Elevation: when the shield structure passes through ventilating shaft, shield structure vertical axis is taked and designs axis phase segmentation method, namely enters the center, hole by the design centre, and the center of appearing is than the low 4cm of design;
Precast concrete beam+steel case beam pedestal form when 2) determining that shield machine passes through
Adopt 20 Pin concrete beam as pedestal when the shield structure passes through, at two steel case beams of concrete beam both sides layout, lay the Qu80 crane runway on the steel case;
3) determine the negative endless tube sheet assembly form of ventilating shaft and supporting way
Place respectively two shaped steel in ventilating shaft inner tunnel center along axis direction both sides before the shield structure passes through, and every propelling 75cm is welded and fixed with channel-section steel in progradation.
CN2011104248360A 2011-12-19 2011-12-19 Construction method in which large-diameter shield advances across air shaft in long distance Pending CN103161471A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011104248360A CN103161471A (en) 2011-12-19 2011-12-19 Construction method in which large-diameter shield advances across air shaft in long distance

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011104248360A CN103161471A (en) 2011-12-19 2011-12-19 Construction method in which large-diameter shield advances across air shaft in long distance

Publications (1)

Publication Number Publication Date
CN103161471A true CN103161471A (en) 2013-06-19

Family

ID=48584966

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011104248360A Pending CN103161471A (en) 2011-12-19 2011-12-19 Construction method in which large-diameter shield advances across air shaft in long distance

Country Status (1)

Country Link
CN (1) CN103161471A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103742154A (en) * 2013-12-31 2014-04-23 中交第二航务工程局有限公司 Shield tunnel ventilation shaft construction method
CN104389608A (en) * 2014-11-19 2015-03-04 中交隧道工程局有限公司 Air shaft shield crossing construction method
CN109162741A (en) * 2018-10-29 2019-01-08 中铁十二局集团有限公司 The method in shield crossing piston air duct and piston air duct superstructure synchronous construction
CN109989760A (en) * 2019-03-20 2019-07-09 中铁四局集团有限公司 A kind of method of shield crossing ventilating shaft near a river
CN111535823A (en) * 2020-06-15 2020-08-14 中铁二局集团有限公司 Shield construction method for pipe gallery working well
CN112647962A (en) * 2020-12-18 2021-04-13 上海隧道工程有限公司 Method for rapidly entering and exiting hole under air shaft with small curvature radius and shield base

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000054784A (en) * 1998-08-10 2000-02-22 Kajima Corp Diameter contracting shield tunneling and device therefor
JP2001098883A (en) * 1999-09-29 2001-04-10 Taisei Corp Tunnel construction method and shield machine for use therein
CN102094650A (en) * 2009-12-14 2011-06-15 上海市基础工程有限公司 Construction method for shield holing under complicated working conditions
CN102146679A (en) * 2010-02-09 2011-08-10 中铁十一局集团有限公司 Construction method for complex geological section earth pressure balance shield passing middle air shaft

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000054784A (en) * 1998-08-10 2000-02-22 Kajima Corp Diameter contracting shield tunneling and device therefor
JP2001098883A (en) * 1999-09-29 2001-04-10 Taisei Corp Tunnel construction method and shield machine for use therein
CN102094650A (en) * 2009-12-14 2011-06-15 上海市基础工程有限公司 Construction method for shield holing under complicated working conditions
CN102146679A (en) * 2010-02-09 2011-08-10 中铁十一局集团有限公司 Construction method for complex geological section earth pressure balance shield passing middle air shaft

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
杨成龙: "上海人民路越江隧道北线盾构施工关键技术", 《特种工程》, vol. 33, no. 4, 25 April 2011 (2011-04-25) *
杨红军: "广州地铁3号线北延段盾构区间条形基础过中风井施工技术", 《地下工程建设与环境和谐发展》, 1 October 2009 (2009-10-01) *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103742154A (en) * 2013-12-31 2014-04-23 中交第二航务工程局有限公司 Shield tunnel ventilation shaft construction method
CN104389608A (en) * 2014-11-19 2015-03-04 中交隧道工程局有限公司 Air shaft shield crossing construction method
CN109162741A (en) * 2018-10-29 2019-01-08 中铁十二局集团有限公司 The method in shield crossing piston air duct and piston air duct superstructure synchronous construction
CN109989760A (en) * 2019-03-20 2019-07-09 中铁四局集团有限公司 A kind of method of shield crossing ventilating shaft near a river
CN109989760B (en) * 2019-03-20 2020-10-02 中铁四局集团有限公司 Method for shield to penetrate through near-river air shaft
CN111535823A (en) * 2020-06-15 2020-08-14 中铁二局集团有限公司 Shield construction method for pipe gallery working well
CN111535823B (en) * 2020-06-15 2022-03-01 中铁二局集团有限公司 Shield construction method for pipe gallery working well
CN112647962A (en) * 2020-12-18 2021-04-13 上海隧道工程有限公司 Method for rapidly entering and exiting hole under air shaft with small curvature radius and shield base

Similar Documents

Publication Publication Date Title
CN103161471A (en) Construction method in which large-diameter shield advances across air shaft in long distance
CN102155237B (en) Device for exchanging tail brush during shield tunneling, and construction method of device
CN103046933B (en) Shield station-crossing tunneling and station parallel construction method
CN104612718A (en) Supporting trolley for overlapped shield tunnel construction and supporting trolley system
CN103032081B (en) Cross-river large-diameter slurry shield excavation and double-lining parallel construction method
CN104775825A (en) Shield machine single well overall originating construction method
CN107060823B (en) Non-dismantling trolley for tunnel anchor section secondary lining concrete construction
CN105179807A (en) Moving device used for large steel pipe to penetrate through roadbed sleeve
CN205101674U (en) Be used for large -scale steel pipe to pass through road bed sheathed tube mobile device
CN212531167U (en) Simple material conveying device under mountain abrupt slope condition
CN107762552B (en) The rapid translation trolley and method of mating trailer after TBM
CN104653222B (en) Prefabricated evacuation platform for shield interval tunnel
CN204436457U (en) The prefabricated evacuation platform of a kind of shield structure running tunnel
CN203270392U (en) Mine rail vehicle translation device
CN201991536U (en) Device for replacing tail brush during shield excavation process
CN204608519U (en) Three row horizontal transport tracks in tunnel
CN204873485U (en) River course is bridge crane usefulness walking portal frame for pier
CN204823870U (en) Bridge crane and dolly
CN204020444U (en) A kind of railroad track sleeper conventional flat-panel car
CN210948674U (en) Auxiliary system for shield air-assisted pushing forming underground excavation tunnel in pipe gallery construction
CN111550253A (en) A novel platform of dodging that is used for major diameter shield to construct shaping tunnel box culvert both sides
CN209510323U (en) A kind of mounting device for shield tunnel guidance system instrument
CN207672429U (en) A kind of cast-in-place guardrail activity tool car of highway bridge
CN202848508U (en) On-line steering device for double positive pole casting carbon block transport system
CN202707076U (en) Double-line railway tunnel trolley

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20130619