CN105162043A - Line suspension device for spanning line change of distribution aerial circuit, and application thereof - Google Patents

Line suspension device for spanning line change of distribution aerial circuit, and application thereof Download PDF

Info

Publication number
CN105162043A
CN105162043A CN201510673428.7A CN201510673428A CN105162043A CN 105162043 A CN105162043 A CN 105162043A CN 201510673428 A CN201510673428 A CN 201510673428A CN 105162043 A CN105162043 A CN 105162043A
Authority
CN
China
Prior art keywords
double pulleies
pulleies unit
thread
changing
wrap attachment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510673428.7A
Other languages
Chinese (zh)
Other versions
CN105162043B (en
Inventor
杨宏伟
李冬冬
郭婷婷
陈中一
刘永生
李丹
陆先菊
史乃强
刘青广
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Liaocheng Power Supply Co of State Grid Shandong Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Liaocheng Power Supply Co of State Grid Shandong Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Liaocheng Power Supply Co of State Grid Shandong Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201510673428.7A priority Critical patent/CN105162043B/en
Publication of CN105162043A publication Critical patent/CN105162043A/en
Application granted granted Critical
Publication of CN105162043B publication Critical patent/CN105162043B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Electric Cable Installation (AREA)

Abstract

The invention relates to a line suspension device for spanning line change of a distribution aerial circuit, and the application thereof. The line suspension device comprises a hoisting support and pulling components arranged on the bottom of the hoisting support. The hoisting support comprises a top phase twin pulley block, two side twin pulley blocks and telescoping poles; the top phase twin pulley block and the two side twin pulley blocks are connected to form a triangular support through the telescoping poles. According to the invention, distribution lines respectively penetrate the three twin pulley blocks; old lines drive new lines to perform spanning line change; in a whole line change process, lines can only touch pulleys up and down, avoiding wearing lines by upper and lower frames of the pulleys, and improving safety; meanwhile the line suspension device can adapt for the line change work of different line spaces, has great versatility and high safety coefficiency, and is convenient to operate.

Description

Distribution overhead line crosses over thread-changing wrap attachment and application thereof
Technical field
The present invention relates to a kind of distribution overhead line and cross over thread-changing wrap attachment and application thereof, belong to electric power overhaul technical field of tools.
Background technology
Rural power distribution overhead transmission line is because of its line properties reason, and the street corner, downtown area that the high-grade highway that leap vehicle is intensive often, the stream of people collect together and field etc., when above location restringing, there will be the safety problem of civil problem and vehicle and pedestrian.And the general methods such as taking crossing frame, crane suspension ring, road closure Feng Hang that adopts in existing thread-changing construction, mostly there is the problems such as time-consuming, effort, expense are high in these methods of present, affect efficiency of construction, increase construction cost, mobility and flexibility deficiency, and crossing frame, crane etc. itself exists by vehicle collision or the risk injuring pedestrian by a crashing object, the safety of crossing over thread-changing construction site can not be ensured.Meanwhile, the condition of construction that 10kV distribution overhead line crosses over high-grade highway particularly I and II highway is more common, and because vehicle flowrate is large, roadbed span is large, road traffic condition is complicated, and highway division is difficult to accomplish to seal row completely.
Therefore, need a kind of distribution overhead line of development badly and cross over thread-changing wrap attachment, meet and require low to operating environment, highly versatile, cost is low, and making uses simple, the requirement that coefficient of safety is high, under the prerequisite ensureing road, complete thread-changing construction operation safely.
Summary of the invention
For the deficiencies in the prior art, the invention provides a kind of distribution overhead line and cross over thread-changing wrap attachment.
The present invention also provides above-mentioned a kind of distribution overhead line to cross over the using method of thread-changing wrap attachment.
Technical scheme of the present invention is as follows:
A kind of distribution overhead line crosses over thread-changing wrap attachment, comprise hoisting bracket and be arranged on the drawing part bottom hoisting bracket, described hoisting bracket comprises top phase double pulleies unit, two side double pulleies unit and telescopic strut, and described top phase double pulleies unit is connected for triangular supports by telescopic strut with two side double pulleies unit.Wrap attachment of the present invention makes distribution line run through wherein by three double pulleies unit respectively, leap thread-changing operation is carried out by the thread-changing mode of the new line of old tape, in whole thread-changing process, wire all can only touch pulley up and down, there will not be the situation of pulley upper and lower frames wearing and tearing wire, improve fail safe.
Preferably, described top phase double pulleies unit comprises fixed frame and is symmetricly set on two pulleys in fixed frame, is provided with active blade, is provided with suspension ring on the top of fixed frame, the bilateral symmetry of bottom is provided with U-shaped ring in the side of fixed frame.
Preferably, described side double pulleies unit comprises fixed frame and is symmetricly set on two pulleys in fixed frame, is provided with active blade, is provided with U-shaped ring on the top of fixed frame, bottom is provided with suspension ring in the side of fixed frame.
Preferably, described telescopic strut comprises round steel bar and connects the screw mandrel at round steel bar two ends, and one end of screw mandrel is provided with link, and link is fixedly connected with U-shaped ring by bolt.
Preferably, screw mandrel is provided with multiple stop nut.The benefit of this design is, stop nut is used for fixing screw mandrel, fixes for the position after regulating screw mandrel precession round steel bar, thus the length of fixing telescopic strut.
Preferably, the two ends of described round steel bar are respectively equipped with reinforcing nut, and screw mandrel is connected with round steel bar after running through reinforcing nut.The benefit of this design is, when screw mandrel is connected with the threaded one end of round steel bar, reinforces the intensity that nut can strengthen screw mandrel and round steel bar link, improves fastness and the fail safe of hoisting bracket further.
Preferably, be also connected with described telescopic strut in the bottom of two side double pulleies unit, the two ends of telescopic strut are connected by the hold-down nut be arranged on side double pulleies unit fixed frame.The benefit of this design is, because the suspension ring of side double pulleies unit bottom connect drawing part, connect telescopic strut in its bottom corresponding with the telescopic strut on the top of side double pulleies unit, ensure that the stability of two side double pulleies unit, also ensure that the resistance to overturning of triangular supports.
Preferably, described drawing part comprises safety warning tape and crash bearer, and one end of safety warning tape is connected with the suspension ring of side double pulleies unit bottom, and the other end is connected with crash bearer.
Distribution overhead line crosses over a using method for thread-changing wrap attachment, comprises the following steps,
(1) this wrap attachment is winched to electric wire masthead, open the active blade of phase double pulleies unit side, top, phase conductor in the loading of phase double pulleies unit will be pushed up;
(2) open the active blade of two side double pulleies unit sides successively, side double pulleies unit is loaded limit phase conductor;
(3) utilize security warning Tape movement wrap attachment to hoisting point position, when after wrap attachment determination hoisting point position, move and place crash bearer with fixing suspension centre;
(4) adopt the thread-changing mode of the new line of old tape, with first limit phase conductor, the order of rear middle phase conductor carries out wire replacing;
(5) after thread-changing completes, utilize safety warning tape to be moved to by wrap attachment and cross over electric pole place, shelves side, wire is withdrawn from from top phase double pulleies unit and side double pulleies unit, wrap attachment is hung down.
Preferably, in step (2), by the position regulating the length of telescopic strut to adjust two side double pulleies unit, load limit phase conductor to make two side double pulleies unit.
Beneficial effect of the present invention is:
1. wrap attachment of the present invention can shorten and crosses over the thread-changing on-the-spot thread-changing place operating time, can save and cross over thread-changing operating expenses, retrieves to cross over thread-changing and to have a power failure the loss caused, and can obtain good economic benefit;
2. utilize wrap attachment of the present invention to reduce number of work that distribution overhead line crosses over thread-changing demand, significantly reduces the labour intensity of staff, obtains personnel's benefit, saving manually can put in other O&M service works; Crossing over the thread-changing construction working time by shortening, also reducing construction interruption duration, significantly improving power supply reliability.
3. wrap attachment smart structural design of the present invention, functional, degree of safety is high, greatly can ensure the process of thread-changing operation, its Be very effective, and effect obviously, has good economic worth and application value.
Accompanying drawing explanation
Fig. 1 is the overall structure schematic diagram of wrap attachment of the present invention;
Fig. 2 a is the front view pushing up phase double pulleies unit in the present invention;
Fig. 2 b is the vertical view pushing up phase double pulleies unit in the present invention;
Fig. 3 a is the front view of side double pulleies unit in the present invention;
Fig. 3 b is the vertical view of side double pulleies unit in the present invention;
Fig. 3 c is the left view of side double pulleies unit in the present invention;
Fig. 4 is the structural representation of the telescopic strut of side double pulleies unit lower end in the present invention;
Fig. 5 is the position relationship schematic diagram of the telescopic strut of hoisting bracket in the present invention;
Wherein: 1, push up phase double pulleies unit; 2, side double pulleies unit; 3, telescopic strut; 4, safety warning tape; 5, crash bearer; 101, fixed frame; 102, pulley; 103, suspension ring; 104, active blade; 105, U-shaped ring; 201, fixed frame; 202, pulley; 203, U-shaped ring; 204, suspension ring; 205, active blade; 301, round steel bar; 302, nut is reinforced; 303, stop nut; 304, screw mandrel; 305, link; 306, nut.
Embodiment
Below by embodiment, also the present invention will be further described by reference to the accompanying drawings, but be not limited thereto.
Embodiment 1:
The present embodiment provides a kind of distribution overhead line to cross over thread-changing wrap attachment, its overall structure as shown in Figure 1, comprise hoisting bracket and be arranged on the drawing part bottom hoisting bracket, hoisting bracket comprises top phase double pulleies unit 1, two side double pulleies unit 2 and telescopic strut 3, and top phase double pulleies unit 1 is connected for triangular supports by telescopic strut 3 with two side double pulleies unit 2.
Wherein, top phase double pulleies unit 1 comprises fixed frame 101 and symmetry and is arranged on two pulleys 102 in fixed frame, pass for wire between two pulleys 102, in whole thread-changing process, wire only rotates with pulley and rubs, do not rub with frame, decrease the frictional resistance of wire in moving process, simultaneously available protecting wire, prevent wire due to the excessive wearing and tearing caused that rub, fixed frame 101 side is provided with opening, opening is between two pulleys, being convenient to wire snaps in two pulleys, active blade 104 is provided with on the side of a side opening of fixed frame, one end and the fixed frame of active blade 104 are hinged, active blade can open or close opening, its objective is wire to snap in after in two pulleys and close active blade, prevent wire slippage from two pulleys in moving process, at the top welding hanging ring 103 of fixed frame, these suspension ring 103 are convenient is used for whole wrap attachment to sling high empty position, U-shaped ring 105 is welded in the bilateral symmetry of the bottom of fixed frame 101, U-shaped ring 105 is used for connecting telescopic strut.
Side double pulleies unit 2 comprises fixed frame 201 and symmetry and is arranged on two pulleys 202 in fixed frame, fixed frame 201 1 side opening, active blade 205 is provided with on the side of a side opening of fixed frame, one end and the fixed frame 201 of active blade 205 are hinged, active blade 205 can open or close opening, welds U-shaped ring 203, bottom welding hanging ring 204 on the top of fixed frame 201.Side double pulleies unit is substantially identical with the structure of top phase double pulleies unit, its difference is that U-shaped ring is different with the installation site of suspension ring, and the bottom of top phase double pulleies unit is symmetrical arranged two U-shaped rings, and in vertical state, the top of side double pulleies unit only arranges a U-shaped ring, and is the level of state.
Telescopic strut 3 comprises round steel bar 301 and connects the screw mandrel 304 at round steel bar two ends, and the two ends of round steel bar 301 are processed with a hole, and screw mandrel is threaded with silk hole, and one end of screw mandrel 304 is welded with spherical link 305, and screw mandrel is provided with two stop nuts 303.After the position after regulating screw mandrel precession round steel bar is fixing, stop nut 303 is tightened screw mandrel, thus the length of fixing telescopic strut.
When being combined into triangular supports, two U-shaped rings 105 of phase double pulleies unit 1 bottom, top are connected with it by the link 305 of bolt-through telescopic strut, the link of the other end 305 of telescopic strut 3 is connected with it by the horizontally U-shaped ring 203 on bolt-through side double pulleies unit top, connect horizontally U-shaped ring by the link at telescopic strut two ends between two side double pulleies unit, namely install between such three double pulleies unit and constitute triangular supports.
The suspension ring 204 of the bottom of two side double pulleies unit hang safety warning tape 4, and the bottom of safety warning tape 4 connects crash bearer 5.In thread-changing process, safety warning tape 4 effectively can play warning function, prevents the Pedestrians and vehicles generation security incident on road, improves the fail safe in operation process.Crash bearer 5 can the stability of available protecting wrap attachment in operation process.
The wrap attachment that the present embodiment provides adopts the mode of three groups of double pulleies unit, three groups of double pulleies unit are installed by telescopic strut and combines formation triangular supports, and the length of side of this triangular supports, adjustable angle (being regulated by telescopic strut), enable this triangular supports adapt to the thread-changing operation of different conductor spacing.During operation, make distribution line run through wherein respectively by three double pulleies unit, carry out leap thread-changing operation by the thread-changing mode of the new line of old tape, in whole thread-changing process, wire all can only touch pulley up and down, there will not be the situation of pulley upper and lower frames wearing and tearing wire, improves fail safe.
Embodiment 2:
The present embodiment provides a kind of distribution overhead line to cross over thread-changing wrap attachment, and as described in Example 1, its difference is structure: the two ends of round steel bar 301 are welded with respectively and reinforce nut 302, and screw mandrel 304 is threaded with round steel bar 301 after running through reinforcing nut 302.Consider the connective stability of screw mandrel 304 and round steel bar 301, be provided with in the end of round steel bar and reinforce nut 302, when screw mandrel is connected with the threaded one end of round steel bar, reinforce nut 302 and can strengthen screw mandrel 304 and the intensity of round steel bar 301 link, improve fastness and the fail safe of hoisting bracket further.
Embodiment 3:
The present embodiment provides a kind of distribution overhead line to cross over thread-changing wrap attachment, structure as described in Example 1, its difference is: in order to ensure the structural stability of two side double pulleies unit, described telescopic strut is also connected with in the bottom of two side double pulleies unit, and hold-down nut is welded with in the lower end of side double pulleies unit fixed frame, screw mandrel 304 two ends of this telescopic strut are connected with nut 306, this nut 306 plays fixation, when after the hold-down nut that the screw mandrel 304 at telescopic strut two ends welds through both sides, undertaken tightening by the nut 306 at screw mandrel two ends and fixedly connect.Because the suspension ring of side double pulleies unit bottom connect drawing part, connect telescopic strut in its bottom corresponding with the telescopic strut on the top of side double pulleies unit, ensure that the stability of two side double pulleies unit, also ensure that the resistance to overturning of triangular supports.
Embodiment 4:
The present embodiment provides a kind of distribution overhead line leap thread-changing wrap attachment to carry out thread-changing to 10kV distribution overhead line, and its operating process comprises the following steps,
(1) utilize crane that this wrap attachment is winched to electric wire masthead, open the active blade 104 of phase double pulleies unit 1 side, top, phase conductor in being loaded by top phase double pulleies unit 1;
(2) length of telescopic strut is first regulated to adjust the position of two side double pulleies unit 2, limit phase conductor can be loaded to make two side double pulleies unit 2, then open the active blade 205 of two side double pulleies unit sides successively, side double pulleies unit 2 is loaded limit phase conductor;
(3) utilize safety warning tape 4 to move wrap attachment to hoisting point position, when after wrap attachment determination hoisting point position, move and place crash bearer 5 with fixing suspension centre;
(4) adopt the thread-changing mode of the new line of old tape, with first limit phase conductor, the order of rear middle phase conductor carries out wire replacing;
(5) after thread-changing completes, utilize safety warning tape 4 to be moved to by wrap attachment and cross over electric pole place, shelves side, wire is withdrawn from from top phase double pulleies unit 1 and side double pulleies unit 2, wrap attachment is hung down, so far completes thread-changing operation.

Claims (10)

1. a distribution overhead line crosses over thread-changing wrap attachment, it is characterized in that, comprise hoisting bracket and be arranged on the drawing part bottom hoisting bracket, described hoisting bracket comprises top phase double pulleies unit, two side double pulleies unit and telescopic strut, and described top phase double pulleies unit is connected for triangular supports by telescopic strut with two side double pulleies unit.
2. distribution overhead line as claimed in claim 1 crosses over thread-changing wrap attachment, it is characterized in that, described top phase double pulleies unit comprises fixed frame and is symmetricly set on two pulleys in fixed frame, be provided with active blade in the side of fixed frame, be provided with suspension ring on the top of fixed frame, the bilateral symmetry of bottom is provided with U-shaped ring.
3. distribution overhead line as claimed in claim 1 crosses over thread-changing wrap attachment, it is characterized in that, described side double pulleies unit comprises fixed frame and is symmetricly set on two pulleys in fixed frame, be provided with active blade in the side of fixed frame, be provided with U-shaped ring on the top of fixed frame, bottom is provided with suspension ring.
4. distribution overhead line crosses over thread-changing wrap attachment as claimed in claim 2 or claim 3, it is characterized in that, described telescopic strut comprises round steel bar and connects the screw mandrel at round steel bar two ends, and one end of screw mandrel is provided with link, and link is fixedly connected with U-shaped ring by bolt.
5. distribution overhead line as claimed in claim 4 crosses over thread-changing wrap attachment, it is characterized in that, screw mandrel is provided with multiple stop nut.
6. distribution overhead line as claimed in claim 4 crosses over thread-changing wrap attachment, and it is characterized in that, the two ends of described round steel bar are respectively equipped with reinforcing nut, and screw mandrel is connected with round steel bar after running through reinforcing nut.
7. distribution overhead line as claimed in claim 3 crosses over thread-changing wrap attachment, it is characterized in that, also be connected with described telescopic strut in the bottom of two side double pulleies unit, the two ends of telescopic strut are connected by the hold-down nut be arranged on side double pulleies unit fixed frame.
8. distribution overhead line as claimed in claim 3 crosses over thread-changing wrap attachment, and it is characterized in that, described drawing part comprises safety warning tape and crash bearer, and one end of safety warning tape is connected with the suspension ring of side double pulleies unit bottom, and the other end is connected with crash bearer.
9. the distribution overhead line as described in any one of claim 1-8 crosses over a using method for thread-changing wrap attachment, comprises the following steps,
(1) this wrap attachment is winched to electric wire masthead, open the active blade of phase double pulleies unit side, top, phase conductor in the loading of phase double pulleies unit will be pushed up;
(2) open the active blade of two side double pulleies unit sides successively, side double pulleies unit is loaded limit phase conductor;
(3) utilize security warning Tape movement wrap attachment to hoisting point position, when after wrap attachment determination hoisting point position, move and place crash bearer with fixing suspension centre;
(4) adopt the thread-changing mode of the new line of old tape, with first limit phase conductor, the order of rear middle phase conductor carries out wire replacing;
(5) after thread-changing completes, utilize safety warning tape to be moved to by wrap attachment and cross over electric pole place, shelves side, wire is withdrawn from from top phase double pulleies unit and side double pulleies unit, wrap attachment is hung down.
10. distribution overhead line as claimed in claim 9 crosses over the using method of thread-changing wrap attachment, it is characterized in that, in step (2), by the position regulating the length of telescopic strut to adjust two side double pulleies unit, load limit phase conductor to make two side double pulleies unit.
CN201510673428.7A 2015-10-15 2015-10-15 Distribution overhead line crosses over thread-changing wrap attachment and its application Active CN105162043B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510673428.7A CN105162043B (en) 2015-10-15 2015-10-15 Distribution overhead line crosses over thread-changing wrap attachment and its application

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510673428.7A CN105162043B (en) 2015-10-15 2015-10-15 Distribution overhead line crosses over thread-changing wrap attachment and its application

Publications (2)

Publication Number Publication Date
CN105162043A true CN105162043A (en) 2015-12-16
CN105162043B CN105162043B (en) 2017-11-14

Family

ID=54802840

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510673428.7A Active CN105162043B (en) 2015-10-15 2015-10-15 Distribution overhead line crosses over thread-changing wrap attachment and its application

Country Status (1)

Country Link
CN (1) CN105162043B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110492389A (en) * 2019-07-11 2019-11-22 广东电网有限责任公司 A kind of overhead transmission line erecting tools
CN112421481A (en) * 2020-10-26 2021-02-26 国网新疆电力有限公司吐鲁番供电公司 Tackle device for treating foreign matters in electrified manner

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11157796A (en) * 1997-11-28 1999-06-15 Aichi Corp Device for calculating lateral force of boom
CN101436746A (en) * 2008-08-12 2009-05-20 深圳市泛友科技有限公司 Whole air-cooled end pump laser
CN201478738U (en) * 2009-09-01 2010-05-19 代孟铎 Multifunctional combined auxiliary support for line erection
CN201708479U (en) * 2010-06-28 2011-01-12 河南省电力公司平顶山供电公司 Cable stretching construction cross pulley
CN201868780U (en) * 2010-10-18 2011-06-15 新疆电力公司乌鲁木齐电业局 Insulating bracket for electrically hoisting and supporting lead
CN202423961U (en) * 2011-11-17 2012-09-05 河南省电力公司安阳供电公司 Triangular hook for leads
CN202616664U (en) * 2012-05-18 2012-12-19 辽宁省电力有限公司鞍山供电公司 Insulation wire lifter
CN102842869A (en) * 2012-09-11 2012-12-26 武绍模 Method for replacing overhead ground wire or conducting wire rapidly
CN202840375U (en) * 2012-11-05 2013-03-27 衡水供电公司 Insulating rod type wire winding device

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11157796A (en) * 1997-11-28 1999-06-15 Aichi Corp Device for calculating lateral force of boom
CN101436746A (en) * 2008-08-12 2009-05-20 深圳市泛友科技有限公司 Whole air-cooled end pump laser
CN201478738U (en) * 2009-09-01 2010-05-19 代孟铎 Multifunctional combined auxiliary support for line erection
CN201708479U (en) * 2010-06-28 2011-01-12 河南省电力公司平顶山供电公司 Cable stretching construction cross pulley
CN201868780U (en) * 2010-10-18 2011-06-15 新疆电力公司乌鲁木齐电业局 Insulating bracket for electrically hoisting and supporting lead
CN202423961U (en) * 2011-11-17 2012-09-05 河南省电力公司安阳供电公司 Triangular hook for leads
CN202616664U (en) * 2012-05-18 2012-12-19 辽宁省电力有限公司鞍山供电公司 Insulation wire lifter
CN102842869A (en) * 2012-09-11 2012-12-26 武绍模 Method for replacing overhead ground wire or conducting wire rapidly
CN202840375U (en) * 2012-11-05 2013-03-27 衡水供电公司 Insulating rod type wire winding device

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
林生得: "更换导线新法", 《农村电工》 *
陈景彦,白俊峰: "《输电线路运行维护理论与技术》", 31 October 2009, 中国电力出版社 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110492389A (en) * 2019-07-11 2019-11-22 广东电网有限责任公司 A kind of overhead transmission line erecting tools
CN112421481A (en) * 2020-10-26 2021-02-26 国网新疆电力有限公司吐鲁番供电公司 Tackle device for treating foreign matters in electrified manner

Also Published As

Publication number Publication date
CN105162043B (en) 2017-11-14

Similar Documents

Publication Publication Date Title
CN202202256U (en) Suspension frame for bridge maintenance
CN201862167U (en) Safety belt hanging stand for overhaul of isolating switch
CN105780646B (en) A kind of bridge maintenance equipment of automatically walk
CN103898832A (en) Bridge cable hanging anchoring end detection working platform
CN202969267U (en) Hoisting device of overhead work equipment for bridge overhauling
CN105162043A (en) Line suspension device for spanning line change of distribution aerial circuit, and application thereof
CN205653069U (en) Steady gantry crane rises
CN205348935U (en) Street lamp is torn installation fast open and is put
CN204849595U (en) Frame bridge crane landing leg suitable for set up precast beam under heavy grade circumstances
CN205004685U (en) Distribution overhead line stridees across line changing plumb -line device
CN201234081Y (en) 220kV bus support column porcelain bottle inspection rack
CN203096609U (en) Bridge girder cable hanging anchoring end detection work platform
CN104836161A (en) Hanger frame of fixed-steering pulley
CN201817208U (en) Simple lifting machine
CN206769343U (en) It is a kind of to be used for the travelling bridge that guardrail is constructed that builds a bridge
CN207062738U (en) A kind of bridge of fast demountable
CN206288881U (en) A kind of tower crane counter-jib dumping device
CN204212065U (en) Bridge crossing anticollision barrier punching block erection equipment
CN103015314B (en) Bridge maintenance overhead working equipment lifting device
CN205653066U (en) Take gantry crane of windrow dolly linkage
CN206070370U (en) A kind of bridge maintenance equipment of automatically walk
CN103896153A (en) Zig-zag derrick for replacing disconnecting link
CN201174560Y (en) Elevated DC feeding power supplying apparatus
CN208986479U (en) A kind of safe and efficient formula electricity comb line hanger
CN103556574B (en) The using method of fast hoisting steel girder member bar

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant