CN105113412A - 一种预应力夹板台背回填加固的施工方法 - Google Patents

一种预应力夹板台背回填加固的施工方法 Download PDF

Info

Publication number
CN105113412A
CN105113412A CN201510529573.8A CN201510529573A CN105113412A CN 105113412 A CN105113412 A CN 105113412A CN 201510529573 A CN201510529573 A CN 201510529573A CN 105113412 A CN105113412 A CN 105113412A
Authority
CN
China
Prior art keywords
clamping plate
abutment
concrete
construction method
stretch
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510529573.8A
Other languages
English (en)
Inventor
金玲玲
谢兰敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN201510529573.8A priority Critical patent/CN105113412A/zh
Publication of CN105113412A publication Critical patent/CN105113412A/zh
Pending legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

本发明公开了一种预应力夹板台背回填加固的施工方法。它包括以下步骤:1)整平台背两侧面边角,在台背两侧安放预制好的钢筋混凝土夹板,混凝土夹板上预留锚垫板及张拉管道孔;2)在填筑靠近上面层安放两头带螺丝扣的塑料管道,塑料管道穿插到锚垫板上张拉管道孔,向塑料管道内充满水后将其两端封闭;3)将上面层填筑压实,进行穿插入钢绞线,两端用张拉千斤顶进行张拉,等张拉力使两侧夹板夹紧稳定后,进行封锚,压浆,完成夹板的安装及施工过程。本施工方法通过张拉力的应力控制,从而避免了台背在受力的情况容易产生变形,从而起到保证台背回填土的稳定,减小回填土的沉降量。

Description

一种预应力夹板台背回填加固的施工方法
技术领域
本发明属于台背施工技术领域,尤其涉及一种预应力夹板台背回填加固的施工方法。
背景技术
随着国家对交通基础设施建设投入的加大,公路桥梁的建设越来越多,许多桥梁的台背回填土较高,由于桥梁台背回填土一般采用透水性砂性土,土颗粒之间粘结力较弱,建好后在汽车荷载的反复作用下,桥梁台后砂性回填土容易产生向道路两侧的变形,引起台后回填土的下降,产生桥台“跳车”现象,对行车安全造成影响。
近年来,国内外不少科研机构及专家对桥台“跳车”现象进行研究,取得不少成果,但多数集中在通过提高地基承载力的途经来解决。本研究想通过在提高地基承载力的基础上,增加桥梁台背回填土的侧向约束力,控制台背回填土在汽车荷载下的侧向变形,以达到降低台背回填土竖向变形,从而解决桥梁台背“跳车”现象。
发明内容
本发明的目的在于提供一种预应力夹板台背回填加固的施工方法,以解决上述背景技术中提出的问题。
为实现上述目的,本发明采用了以下技术方案:
一种预应力夹板台背回填加固的施工方法,包括以下步骤:
1)整平台背两侧面边角,在台背两侧安放预制好的钢筋混凝土夹板,混凝土夹板上预留锚垫板及张拉管道孔;
2)在填筑靠近上面层安放两头带螺丝扣的塑料管道,塑料管道穿插到锚垫板上张拉管道孔,向塑料管道内充满水后将其两端封闭;
3)将上面层填筑压实,进行穿插入钢绞线,两端用张拉千斤顶进行张拉,等张拉力使两侧夹板夹紧稳定后,进行封锚,压浆,完成夹板的安装及施工过程。
优选的,步骤1)中所述混凝土夹板的面积为1.8-2.2平方米。
优选的,步骤1)中所述混凝土的强度等级不低于C30混凝土的强度等级。
与现有技术相比,本发明的有益效果如下:
本施工方法通过张拉力的应力控制,从而避免了台背在受力的情况容易产生变形,从而起到保证台背回填土的稳定,减小回填土的沉降量。
具体实施方式
下面结合实施例对本发明的优选方式作进一步详细的描述。
一种预应力夹板台背回填加固的施工方法,包括以下步骤:
1)整平台背两侧面边角,在台背两侧安放预制好的钢筋混凝土夹板,混凝土夹板的面积为1.8-2.2平方米,混凝土的强度等级不低于C30混凝土的强度等级,混凝土夹板上预留锚垫板及张拉管道孔。
2)在填筑靠近上面层安放两头带螺丝扣的塑料管道,塑料管道穿插到锚垫板上张拉管道孔,向塑料管道内充满水后将其两端封闭。
3)将上面层填筑压实,进行穿插入钢绞线,两端用张拉千斤顶进行张拉,等张拉力使两侧夹板夹紧稳定后,进行封锚,压浆,完成夹板的安装及施工过程。
本发明提出了一种预应力夹板台背回填加固的施工方法。本发明针对桥梁桥头现象,提出一种新的技术方案,它尤其适用于8M以上的高桥梁台背砂性土回填施工,有效的避免上述台背的变形以产生台背“跳车”现象的发生。
以上的实施例仅仅是对本发明的优选实施方式进行描述,并非对本发明的范围进行限定,在不脱离本发明设计精神的前提下,本领域普通技术人员对本发明的技术方案作出的各种变形和改进,均应落入本发明权利要求书确定的保护范围内。

Claims (3)

1.一种预应力夹板台背回填加固的施工方法,其特征在于,包括以下步骤:
1)整平台背两侧面边角,在台背两侧安放预制好的钢筋混凝土夹板,混凝土夹板上预留锚垫板及张拉管道孔;
2)在填筑靠近上面层安放两头带螺丝扣的塑料管道,塑料管道穿插到锚垫板上张拉管道孔,向塑料管道内充满水后将其两端封闭;
3)将上面层填筑压实,进行穿插入钢绞线,两端用张拉千斤顶进行张拉,等张拉力使两侧夹板夹紧稳定后,进行封锚,压浆,完成夹板的安装及施工过程。
2.根据权利要求1所述的预应力夹板台背回填加固的施工方法,其特征在于,步骤1)中所述混凝土夹板的面积为1.8-2.2平方米。
3.根据权利要求1所述的预应力夹板台背回填加固的施工方法,其特征在于,步骤1)中所述混凝土的强度等级不低于C30混凝土的强度等级。
CN201510529573.8A 2015-08-26 2015-08-26 一种预应力夹板台背回填加固的施工方法 Pending CN105113412A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510529573.8A CN105113412A (zh) 2015-08-26 2015-08-26 一种预应力夹板台背回填加固的施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510529573.8A CN105113412A (zh) 2015-08-26 2015-08-26 一种预应力夹板台背回填加固的施工方法

Publications (1)

Publication Number Publication Date
CN105113412A true CN105113412A (zh) 2015-12-02

Family

ID=54661506

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510529573.8A Pending CN105113412A (zh) 2015-08-26 2015-08-26 一种预应力夹板台背回填加固的施工方法

Country Status (1)

Country Link
CN (1) CN105113412A (zh)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113235551A (zh) * 2021-05-24 2021-08-10 兰州交通大学 一种加速回填土固结的地基结构及施工方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011520054A (ja) * 2008-05-13 2011-07-14 韓国道路公社 鋼箱桁を用いたセミインテグラルアバット橋の施工方法
CN102966046A (zh) * 2012-11-28 2013-03-13 华南理工大学 一种u型桥台的台身外倾加固方法
CN203546747U (zh) * 2013-07-09 2014-04-16 中铁第四勘察设计院集团有限公司 整板式带肋柱锚索挡墙
CN104674843A (zh) * 2015-03-06 2015-06-03 山西省交通科学研究院 用于加固挡土墙的悬臂式型钢混凝土预应力组合结构

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011520054A (ja) * 2008-05-13 2011-07-14 韓国道路公社 鋼箱桁を用いたセミインテグラルアバット橋の施工方法
CN102966046A (zh) * 2012-11-28 2013-03-13 华南理工大学 一种u型桥台的台身外倾加固方法
CN203546747U (zh) * 2013-07-09 2014-04-16 中铁第四勘察设计院集团有限公司 整板式带肋柱锚索挡墙
CN104674843A (zh) * 2015-03-06 2015-06-03 山西省交通科学研究院 用于加固挡土墙的悬臂式型钢混凝土预应力组合结构

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113235551A (zh) * 2021-05-24 2021-08-10 兰州交通大学 一种加速回填土固结的地基结构及施工方法

Similar Documents

Publication Publication Date Title
CN104213514B (zh) 一种覆土波纹钢板-混凝土组合拱桥的加强方法
CN108951425A (zh) 现浇预应力混凝土连续箱梁一次性浇筑成型施工方法
CN109853381B (zh) 一种防治桥头跳车的过渡结构及其施工方法
CN109235499A (zh) 一种明挖地下建筑结构装配式施工方法
WO2019237678A1 (zh) 桥台刚构桥的构造及其施工方法
CN108797249A (zh) 软土路基高填方陡坡路段泡沫轻质土的施工方法
CN202466342U (zh) 高速铁路深厚土质地基的加固结构
CN103924525B (zh) 城市立交桥工业化短线预制拼装施工方法
CN104195911A (zh) 一种临水悬壁高挡墙填方段拓宽路堤结构及施工方法
CN107524159A (zh) 一种混合式加筋挡土墙
CN105507170A (zh) 钢筋混凝土盖板涵的强化方法
CN204753604U (zh) 一种用于膨胀土地区的基坑支护体系
CN104863162A (zh) 一种用于膨胀土地区的基坑支护体系及其施工方法
CN106930315B (zh) 一种移动塔吊基础结构及施工方法
CN103015414A (zh) 一种预制混凝土后注浆桩及注浆工艺
CN203334154U (zh) 一种高架桥下桩基承台伸入路基的路堤结构
CN202000234U (zh) 托盘式u形加筋路基结构
CN113073680B (zh) 一种高原高寒区的弃碴场挡墙结构及其构筑方法
CN206800166U (zh) 整体加固改造主拱的石拱桥
CN206830380U (zh) 一种风电机组下部分片预制混合塔架
CN106917358B (zh) 一种斜拉桥主梁组合施工方法及其配重结构体系
CN105113412A (zh) 一种预应力夹板台背回填加固的施工方法
CN103225512A (zh) 一种制作预应力后背进行箱涵顶进施工方法
CN110144784A (zh) 基于预应力混凝土板桩构筑的市政道路及其施工方法
CN111305093A (zh) 一种自卸载的钢波纹板拱形涵洞

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20151202

RJ01 Rejection of invention patent application after publication