CN105098679B - A kind of combination column for cable testing bridge - Google Patents

A kind of combination column for cable testing bridge Download PDF

Info

Publication number
CN105098679B
CN105098679B CN201510381101.2A CN201510381101A CN105098679B CN 105098679 B CN105098679 B CN 105098679B CN 201510381101 A CN201510381101 A CN 201510381101A CN 105098679 B CN105098679 B CN 105098679B
Authority
CN
China
Prior art keywords
column
trailing arm
basic stand
stand column
steel plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510381101.2A
Other languages
Chinese (zh)
Other versions
CN105098679A (en
Inventor
赵琪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Guiyang Engineering Corp Ltd
Original Assignee
PowerChina Guiyang Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Guiyang Engineering Corp Ltd filed Critical PowerChina Guiyang Engineering Corp Ltd
Priority to CN201510381101.2A priority Critical patent/CN105098679B/en
Publication of CN105098679A publication Critical patent/CN105098679A/en
Application granted granted Critical
Publication of CN105098679B publication Critical patent/CN105098679B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a kind of combination column for cable testing bridge, belong to cable mounting technique field, including floor, steel plate and reinforcing bar, the reinforcing bar is welded with steel plate and is embedded in jointly in floor, the steel plate lower plane is fixedly connected with basic stand column, the basic stand column underside is connected with trailing arm columns assemblies, and the basic stand column is provided with some bolts hole.The technical program passes through combined vertical pole, the location of simple and fast adjustment trailing arm height, when job site occur the barriers such as crane span structure and pipeline occur interference need to adjust trailing arm height when, the crane span structure number of plies need to increase or decrease when, trailing arm columns assemblies can easily and flexibly be adjusted to realize live adjustment, coordinate site operation.

Description

A kind of combination column for cable testing bridge
Technical field
The invention belongs to cable mounting technique field, it is related to the technology by cable testing bridge cabling, more particularly, to A kind of combination column for cable testing bridge.
Background technology
Cable it is general by cable testing bridge, cable shaft, cable duct, wear pipe laying etc. and laid.As shown in figure 1, passing through When cable testing bridge is laid, then column 3 is welded on steel plate 2 by the general first pre-embedded steel slab 2 in floor 1, then in column Designed height and position drilling, trailing arm a4 is fixed on the position drilled on column 3, is finally positioned over crane span structure 5 on 3 On trailing arm a4.Because the number of plies of crane span structure 5 and setting height(from bottom) demand of different parts are different, therefore, the length of column 3 is also a variety of It is various, along with being interfered due to power station crane span structure and pipeline etc., or the reason such as load is augmented temporarily, cable passage adjustment, Usually make situations such as strut length of initial plan is long, the crane span structure number of plies is more than needed or not enough, so that needing in adjustment short distance The height or the number of plies of crane span structure 5, and the strut length of original order is set, field condition is changeable, and column is once installed, then Scene is needed to be adjusted, difficulty is very big, workload also can be very big;Along with due to power station whole audience crane span structure, order number Amount is more, and species and model are more, and statistical work is cumbersome, building site store keeping and the operating efficiency from personnel is dropped significantly It is low.
The content of the invention
In order to solve the above problems, the invention provides a kind of combination column for cable testing bridge, so as to reach mark Standardization is used, convenient adjustment, the effect for statistics of being more convenient for.
The present invention is achieved by following technical solution.
A kind of combination column for cable testing bridge, including floor, steel plate and reinforcing bar, the reinforcing bar are welded and are total to steel plate With being embedded in floor, the steel plate lower plane is fixedly connected with basic stand column, and the basic stand column underside is connected with support Arm columns assemblies, the basic stand column is provided with some bolts hole.
Further, the basic stand column is divided into some sections of column units, and bolt hole is uniformly distributed in every section of column In unit.
Further, the trailing arm columns assemblies include connection column and trailing arm b, trailing arm b are fixedly connected with being connected column.
Further, the minimum length of the connection column is the length of 4 column units, decile same with basic stand column And provided with the bolt hole matched with basic stand column.
Further, the basic stand column and connection column are made of channel-section steel.
The beneficial effects of the invention are as follows:
A kind of combination column for cable testing bridge of the present invention, with reference to power station slab and girder feature, passes through group Box-like column, simple and fast adjusts the location of trailing arm height, occurs when the barriers such as crane span structure and pipeline occurs in job site When interference is when need to adjust trailing arm height, the crane span structure number of plies needs to increase or decrease, you can easily and flexibly adjust trailing arm columns assemblies To realize live adjustment, coordinate site operation.Standardized production can be achieved with being connected column in basic stand column, without according to difference Strut length needed for position is different and carries out point size storage and manages, and simplifies the workflow of type selecting, statistics and management Journey.
Brief description of the drawings
Fig. 1 is bridge upright structural representation of the prior art;
Fig. 2 is structural representation of the invention;
Fig. 3 is the structural representation of trailing arm columns assemblies in the present invention;
Fig. 4 is the sectional view of basic stand column in the present invention;
Fig. 5 is the top view of trailing arm columns assemblies in the present invention;
The sectional view that Fig. 6 assembles for trailing arm columns assemblies in the present invention with basic stand column;
The structural representation that Fig. 7 assembles for many trailing arm columns assemblies in the present invention with basic stand column;
Structural representations of the Fig. 8 for the present invention in installation process during the interference of experience barrier.
In figure:1- floors, 2- steel plates, 3- columns, 4- trailing arms a, 5- crane span structure, 6- reinforcing bars, 7- basic stand columns, 701- column lists Member, 8- trailing arm columns assemblies, 801- connection columns, 802- trailing arms b, 9- bolt hole, 10- bolts, 11- barriers.
Embodiment
Technical scheme is further described below in conjunction with the accompanying drawings, but claimed scope is not limited to institute State.
As shown in figs. 1 to 6, a kind of combination column for cable testing bridge of the present invention, including floor 1, the and of steel plate 2 Reinforcing bar 6, the reinforcing bar 6 is welded and is embedded in jointly in floor 1 with steel plate 2, and it is vertical that the lower plane of steel plate 2 is fixedly connected with basis Post 7, the basic stand column 7 is divided into some sections of column units 701, and basic stand column 7 is provided with some bolts hole 9, bolt hole 9 It is uniformly distributed in every section of column unit 701;The underside of basic stand column 7 is connected with trailing arm columns assemblies 8, trailing arm columns assemblies 8 are fixedly connected including connection column 801 and trailing arm b802, trailing arm b802 with being connected column 801;The connection column 801 is most Small length is the length of four column units 701, connection column 801 and the same decile of basic stand column 7 and is provided with and basic stand column 7 The bolt hole 9 matched;The basic stand column 7 and connection column 801 are made of channel-section steel.
The length of basic stand column 7 highly determines by 1 time highest beam bottom of floor, and usual beam bottom height down can at 200mm First layer crane span structure 5 is laid, then down by every layer of setting of 300mm.Consider that adapting to crane span structure 5 is distributed more and less position, is set The full-length of basic stand column 7 is 1000mm, and graduation mark is set on basic stand column 7, and vertical using every 100mm as a decile Pole unit 701, the bolt hole for being used for fixing trailing arm columns assemblies 8 is provided with per column unit 701;As shown in figure 3, connection column The length of four column units 701 of column 7 based on 801 minimum length, trailing arm is welded on connection column 801 from the bottom up At second column unit 701 of number, so as to which when needing to increase trailing arm columns assemblies 8 column 801 and its lowest part will be connected Column unit 701 is connected;Trailing arm columns assemblies 8 are dispatched from the factory after being completed, and can arbitrarily be arranged in pairs or groups and be applied with adapting to scene with basic stand column 7 Work.
During installation, the connection column 801 of trailing arm columns assemblies 8 and basic stand column 7 need to only be fastened, needed for being then adjusted to Height, make after the bolt hole 9 on column unit 701 aligns respectively, bolt 10 to be passed through into bolt hole 9, tightened fixed.
Embodiment one
As shown in fig. 7, according to job site beam bottom height and number of cables, trailing arm columns assemblies 8 are installed into basis On column 7, according to the number of plies of crane span structure 5 and arrangement demand, trailing arm columns assemblies 8 can be arranged at the both sides of basic stand column 7 simultaneously, and Many set trailing arm columns assemblies 8 can be down connected, to obtain Multilayer bridge frame 5.
Embodiment two
As shown in figure 8, when the barrier 11 that crane span structure 5 can be disturbed to arrange occurs in the lower section of crane span structure 5, can be stood by adjusting trailing arm Installation site of the column assembly 8 on basic stand column 7 carrys out avoiding obstacles 11, to realize the reasonable Arrangement of crane span structure 5, it is to avoid with obstacle Thing 11 is interfered.

Claims (3)

1. a kind of combination column for cable testing bridge, including floor (1), steel plate (2) and reinforcing bar (6), the reinforcing bar (6) and steel Plate (2) is welded and is embedded in jointly in floor (1), it is characterised in that:Steel plate (2) lower plane is fixedly connected with basic stand column (7), basic stand column (7) underside is connected with trailing arm columns assemblies (8), and the basic stand column (7) is provided with some spiral shells Keyhole (9);The basic stand column (7) is divided into some sections of column units (701), and bolt hole (9) is uniformly distributed in every section and stood In pole unit (701);The trailing arm columns assemblies (8) include connection column (801) and trailing arm b (802), trailing arm b (802) with connecting Column (801) is connect to be fixedly connected.
2. a kind of combination column for cable testing bridge according to claim 1, it is characterised in that:The connection column (801) minimum length is the length of four column units (701), with the same decile of basic stand column (7) and provided with vertical with basis The bolt hole (9) that post (7) matches.
3. a kind of combination column for cable testing bridge according to claim 1, it is characterised in that:The basic stand column (7) it is made with connection column (801) of channel-section steel.
CN201510381101.2A 2015-07-02 2015-07-02 A kind of combination column for cable testing bridge Active CN105098679B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510381101.2A CN105098679B (en) 2015-07-02 2015-07-02 A kind of combination column for cable testing bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510381101.2A CN105098679B (en) 2015-07-02 2015-07-02 A kind of combination column for cable testing bridge

Publications (2)

Publication Number Publication Date
CN105098679A CN105098679A (en) 2015-11-25
CN105098679B true CN105098679B (en) 2017-10-24

Family

ID=54578559

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510381101.2A Active CN105098679B (en) 2015-07-02 2015-07-02 A kind of combination column for cable testing bridge

Country Status (1)

Country Link
CN (1) CN105098679B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107611865A (en) * 2017-08-07 2018-01-19 浩翔电气集团有限公司 A kind of crane span structure installation and adjustment method
CN107448540A (en) * 2017-09-22 2017-12-08 浩翔电气集团有限公司 One kind, which rises, dials formula crane span structure adjusting method
CN108011338A (en) * 2017-12-06 2018-05-08 国网江苏省电力公司徐州供电公司 Combined cable support for cable duct
CN108616104A (en) * 2018-07-13 2018-10-02 安徽华电工程咨询设计有限公司 A kind of open caisson of staggered floor cable laying

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3516273A1 (en) * 1985-05-07 1986-11-13 Rieth & Co GmbH, 7312 Kirchheim Cable rack having arms whose height is adjustable on vertical posts or stands
CN2200091Y (en) * 1994-09-27 1995-06-07 郑永德 Hanger or support for electric cable
JP2003299222A (en) * 2002-03-29 2003-10-17 Burest Kogyo Kenkyusho Co Ltd Splice metal fitting for cable racks
CN202280152U (en) * 2011-11-09 2012-06-20 贵阳铝镁设计研究院有限公司 Structure for arranging embedded part at bottom of reinforced concrete plate
CN104061369B (en) * 2014-06-27 2016-09-07 李志良 The assembled movable cable support of medium and high voltage cable line arrangement in a kind of distance passage
CN204706854U (en) * 2015-07-02 2015-10-14 中国电建集团贵阳勘测设计研究院有限公司 A kind of combined type bridge pillar construction

Also Published As

Publication number Publication date
CN105098679A (en) 2015-11-25

Similar Documents

Publication Publication Date Title
CN105098679B (en) A kind of combination column for cable testing bridge
CN203640309U (en) Adjustable pipe carrier used on large-span steel structure roof primary truss general assembly jig frame
CN202810173U (en) Mounting and construction platform for steel lining bracket and circular crane track girder of nuclear power plant
CN206072522U (en) A kind of novel pipeline support of attached wall
CN203783165U (en) Multi-directional accurate adjusting device for embedded part
CN201723853U (en) Integrated supporting and hanging frame with comprehensive pipeline arrangement technology for large public building installation project
CN103243621B (en) Method for mounting integrated steel rail supporting frame for adjustment of groove type steel rails of tramcar
CN101736925B (en) Modular construction method for nuclear island of nuclear power station
CN204706854U (en) A kind of combined type bridge pillar construction
CN203755451U (en) Connecting device for dual-layer full-steel structure floor embedded with channel steel beam and column
CN104060838B (en) A kind of vestibule divides into groups aerial group to Method for Installation
PH12016501449B1 (en) Members for constituting mount for installing solar panels
CN105545059A (en) Modularization tower device and construction transport method thereof
CN105202265A (en) Multilayer bridge framework bracket arm mounting locating device and method
CN102191866A (en) Device and method for removal construction of vertical posts positioned on lower part of large-span net rack
CN102174969B (en) Steel wire hanging frame and construction method thereof
CN204753382U (en) Prefabricated pavement of voiced protective screen of inter -city railway
CN104343382B (en) Pedestrain raise solar steel design and construction method
CN111042482A (en) Non-integrated raised floor supporting structure and construction method thereof
CN203131227U (en) Multi-layer multi-row bridge support
CN112554277A (en) Integrated pump set and construction method thereof
CN203667842U (en) Freely-assembled hoisting device
KR20110103773A (en) Improved support system
CN106638650B (en) Fabricated concrete foundation structure
CN205231680U (en) Urban rail transit engineering cable support

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant