CN105060134A - Novel large-lifted-weight high-safety tower crane for counterweight balance mechanism and reforming and upgrading of tower crane - Google Patents

Novel large-lifted-weight high-safety tower crane for counterweight balance mechanism and reforming and upgrading of tower crane Download PDF

Info

Publication number
CN105060134A
CN105060134A CN201510442779.7A CN201510442779A CN105060134A CN 105060134 A CN105060134 A CN 105060134A CN 201510442779 A CN201510442779 A CN 201510442779A CN 105060134 A CN105060134 A CN 105060134A
Authority
CN
China
Prior art keywords
tower
tower crane
counterweight
crane
lifting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510442779.7A
Other languages
Chinese (zh)
Inventor
高士炳
高阳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201510442779.7A priority Critical patent/CN105060134A/en
Publication of CN105060134A publication Critical patent/CN105060134A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/62Constructional features or details
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/62Constructional features or details
    • B66C23/72Counterweights or supports for balancing lifting couples

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Jib Cranes (AREA)

Abstract

The invention relates to a novel tower crane for a counterweight balance mechanism and reforming and upgrading of the tower crane. The lifting capacity is improved. The implementation scheme is characterized in that the counterweight force on a counterweight arm of the tower crane is changed into a tension mode of a steel zipper; the upper end of the steel zipper is fixed to the tail part of a balance arm of the tower crane, and the lower end of the steel zipper is connected with a track sliding vehicle mechanism in a sliding chute integrally embedded through a tower crane base foundation and a counterweight water tank by pulling. During lifting operation, a sliding vehicle dynamically transmits the counterweight pulling force to the foundation by sliding the sliding chute, and the counterweight pulling force is counteracted with the pressure of a tower body, and meanwhile the sliding vehicle and a crane jib synchronously carry out rotating and lifting operation at the same angle. The lifting weight is transmitted to the crane jib through a lifting steel wire rope, and then the crane jib transmits the lifting weight to the top of the tower body by obliquely pulling the steel zipper. The pulling forces of the crane jib and the balance arm are changed into pressure through top of the tower body and transmitted to a ground foundation through the tower body. The pulling force of the crane jib to the tower top is larger than that of the crane jib to the balance arm and is the counterweight force of the novel tower crane of the counterweight balance mechanism, and the force is automatically increased and decreased along with the increasing and decreasing of the weight of a lifting object. The automatic counterweight balance of the tower crane is realized, and the lifting capacity and the safety are improved.

Description

Novel counterweight equalizing gear plays great high security tower crane and tower crane transformation and upgrade
Technical field
A kind of noveltower crane and noveltower crane counterweight balancing mechanism, and to the existing tower crane transformation and upgrade embodiment just widely used, belong to building vertical hoisting machinery and manufacture renovation technique field.
Technical background
China's tower crane industry oneself have passed through the development of ISUZU company, take a broad view of the development course of ISUZU company, grow out of nothing from small to large, progressively define more complete system, become one of the fastest new industry of China's amplification, existing oneself becomes civilian tower crane big producing country of the world and uses big country.
Although China's development of ISUZU company time, west has been caught up with and surpassed in output and the application of tower crane countrythe development of more than 100 year, oneself becomes production application big country, but at tower crane technical performance, products innovation upgrading and raising load-carrying ability safety performance aspect, with west countrycompare and also there is larger gap.Especially to rectify framework component assembled architecture new process along with China greatly develops green building and ferro-concrete, more highlight the deficiency of tower crane load-carrying ability, for executing the needs of answering Modern Green to build, practical solution tower crane upgrades upgrading, improve load-carrying ability and optimize scope of work, improving tower crane job safety performance and seem particularly important.
For this reason of the present invention this noveltower crane and noveltower crane counterweight balancing mechanism, and transformation and upgrade are carried out to present just widely used tower crane, improve the safety performance of load-carrying ability and lifting operation.The principle of getting more done on less money by state's information in conjunction with China, utilizes the condition precedent that the existing tower crane storage world of China is maximum, scientific and effectively carries out transformation and upgrade to tower crane, should the needs of modern build-up type green building to execute.
Summary of the invention
Of the present invention noveltower crane, and the new-type counterweight balancing mechanism of tower crane, and to the tower crane transformation and upgrade just widely used now, improve load-carrying ability and strengthen lifting operation safety performance.
First technical matters that the present invention solves is, make full use of mechanical structure, scientific and reasonable stressed configuration, square tower body bracing frame is changed into column type, because column type end face 360 deg is stressed all equal large with cylinder holding capacity, distortion resistance is strong, has increased considerably the anti-twist of tower body and has carried what ability.
Second technical matters that the present invention solves is, the two ends of column type tower stature, use the inside and outside straight mouth close fit connection structure of Big Diameter Flange instead, outer for the upper flanges convex of lower pitch circle column type tower stature straight mouth, in insertion in the interior straight mouth of pitch circle column type tower stature flange lower end matrix inner circle, upper and lower two pitch circle column type tower statures are made fixedly to be decided to be one with bolted two flange.By that analogy some joint tower statures being connected successively makes the tower body of whole tower crane be fixed as one.
The 3rd technical matters that the present invention solves is, eliminate the counterweight on former tower crane equilibrium arm, use steel slide fastener instead and be fixed on equilibrium arm afterbody, pull on the slip sport car in sliding rail groove that ground and tower body counterweight foundation be integrated, counterweight forces required when upwards the power of lift slip sport car is exactly tower crane lifting operation, this counterweight forces synchronously increases and decreases along with the increase and decrease playing weight weight, and in the sliding wheel and sliding tray of slip sport car sliding wheel track, passing terraced mode dynamically to slide makes tower body basis and counterweight be subject to upper pulling force, with tower body and the downward pressure of counterweight water tank mutually mutually Arrived disappear and balance, so of the present invention novelor it is improved noveltower crane, can not only have the biggest lifting capacity at the minimum operating radius of tower crane, also can have identical load-carrying ability in maximum operation radial location, can also guarantee that lifting operation is safe and reliable.
The 4th technical matters that the present invention solves is, on the basis of the 3rd technical matters solved in the present invention another Bian get a kind of in periphery, tower crane ground with tower body center for the center of circle, be fixed wtih circular ring type track with tower crane balance brachium for radius is arranged on the corresponding vertical ground of equilibrium arm tail down, the meshing rotary actuation rail vehicle of rail vehicle driven wheel that on track one side elevation, build-in on circular ring type tooth bar and track makes circumference crank motion.Rail vehicle loads weight and be greater than counterweight balance weight needed for the tower crane biggest lifting capacity.The lower end fixed strain of the steel slide fastener utilizing tower crane equilibrium arm afterbody to connect is connected on rail vehicle.Can determine according to the size of hoisting capacity the size needing counterweight forces when tower crane lifting operation, the gravity that this power upwards lifts the rail vehicle of fully loaded clump weight downward through the steel slide fastener of equilibrium arm afterbody offset, and the gravity that remaining clump weight is downward is passed to surface based through rail vehicle and track and balanced.In order to ensure arm and equidirectional, the same angle of counterweight track car, simultaneously synchronous rotary, drive electricity computer autonomous cruise speed system chain control realization two drive motor to keep when lifting operation starting arm rotary drive motor and rail vehicle simultaneously, same to stopping, equidirectional while synchronously, with angle drive operation.
5th technical matters of solution of the present invention is, according to mechanical structure at the former square-column-shaped tower stature of reservation, on the basis retaining the former connecting bolt of upper and lower tower stature, turn increase and respectively reinforce on interior angle by one piece of triangular steel plate at upper end four interior angle of square-column-shaped tower stature, set square center build-in thick arm steel pipe flange, flange inner circle is processed into the outer straight mouth of convex-type, and flange periphery circle arranges some equal angular screws.The lower end of square-column-shaped tower stature uses triangular steel plate reinforcement of weld equally on four interior angles, and the center build-in of triangular steel plate thick arm steel pipe flange, and the inner circumferential circle of flange is processed into straight mouth in spill, and the periphery circle of flange arranges several bolts hole.When assembling tower crane tower body outer for angle flange convex in lower joint tower stature upper end four straight mouth, insertion saving in the interior straight mouth of flange spill of corner in tower stature, with each flange that bolted upper and lower tower stature corner is corresponding, upper and lower two joint tower bodies being fixed as one.The like some tower statures are connected and fixed is an overall tower body.
The 6th technical matters that the present invention solves and beneficial effect are, tower crane only needs when mounted to build and a small amount of squarely gives the concrete foundation square column burying and sit bolt of rear end plate at the bottom of tower crane, sit at the bottom of tower crane is inner cross shape, cylindrical annular girder steel tower seat, with give bury bolted be decided to be one, end taken by outer ring inner cross shape tower, pressing several Plate Weldings becomes interior dihedral neighboring to be circular arc water tank, the cylindrical shaped weight body be combined into, and some water tanks are the overall counterweight of tower crane after filling water.The chute inner orbit of semicircle slip sport car is fixed wtih in the upper end of column type balance weight body, through the sliding wheel of slip sport car under the constraint of sliding tray inner orbit, the actual counterweight pulling force of tower crane when lifting operation, through sliding tray, the counterweight cylinder water tank be fixed as one is subject to upper pulling force to pull-up sliding tray inner orbit in sliding manner through slip sport car, this power is offseted by the downward pressure from pinnacle of a pagoda again simultaneously, well imagines of the present invention utility modelor the tower body connection fastening structure of improved tower crane and can automatically increase or decrease required counterweight balance power according to the increase and decrease of lifting object weight, not only hoisting capacity is large to ensure that tower crane, and safe and reliable thereupon.
The 7th technical matters that the present invention solves and beneficial effect are: tower crane adopts computer program automatically to control spacing, safety interlocking function such as limit overload, speed limit, limit Wu operation, self-actuating brake etc.Eliminating operator's compartment achieves at loading or unloading lifting object on-the-spot, with wired or wireless remote manipulation tower crane operation simultaneously tower crane driver from high-altitude, high-risk harsh environments solution holds out.Also withdrawn deposit tower crane in installation or removal and transportation, what all show is convenient, fast, safe, laborsaving, some shaped steel combinations are adopted to form because tower crane is sat, only build to give and bury bolt, counterweight is that several steel water tank combine, accounting for the large water conservancy of anharmonic ratio example with bleeding off, the water tank that only resettlement weight is little during resettlement, no matter install or remove, all eliminate large crane lifting operation be practical, novel, energy-conservation, joint money, the friendly shape of environmental protection weight-lifting equipment.
Accompanying drawing illustrates:
As shown in Figure 1, for novelthe upper end butt flange of a wherein joint tower stature of tower crane tower body.
as Fig. 2shown in, for novela wherein joint tower stature lower end butt flange signal of tower crane tower body figure.
as Fig. 3shown in, for of the present invention novelthe overall tower crane signal that tower crane installs figure.
as Fig. 4shown in, for novelsit at the bottom of tower crane or improved tower crane to give with basis and bury bolt and be fixed as one and illustrate figure.
as Fig. 5shown in, be a wherein joint tower stature lower end joint face signal of improved square-column-shaped tower crane tower body figure.
as Fig. 6shown in, be a wherein joint tower stature upper end joint face signal of improved square-column-shaped tower crane tower body figure.
as Fig. 7shown in, be connected and fixed signal for sitting at the bottom of improved square-column-shaped tower crane tower body coxopodite and tower crane figure.
as Fig. 8shown in, for counterweight water tank presses the signal being fixed on and taking at the bottom of tower crane figure.
as Fig. 9shown in, run rail signal in the U-shaped chute for the slip sport car of the steel chain stay cord connection of tower crane equilibrium arm afterbody hanging figure.
as Fig. 1shown in 0, for improved square-column-shaped tower body and repacking are equipped with novelthe remodeling tower crane of equilibrium arm counterweight balancing mechanism and water filling box type integral counterweight installs overall signal figure.
Detailed description of the invention:
Make object of the present invention and invention noveltower crane and to the simpler aobvious easy Dong of the advantage of tower crane transformation and upgrade technical scheme, state below in conjunction with specific embodiment is continuous in detail further again:
as Fig. 1embodiment is illustrated figure instituteshow: be of the present invention noveltower crane tower body wherein a joint tower stature upper flanges (as fig. 1in mark 1), the outer straight mouth of convex ( as Fig. 1in mark 2), flange bolt hole ( as Fig. 1in sign 3), solid drawn pipe support post ( as Fig. 1in mark 4), lower hold-carrying (mark 5 as in 1), lower end method bolt hole ( as Fig. 1in mark 6) composition.
as Fig. 1embodiment is illustrated figure instituteshow: be novelcolumn type tower crane tower body is joint tower stature lower end butt flange (marks 1 as in 2) wherein, the interior straight mouth of flange inner circle matrix inner circle ( as Fig. 2in mark 2), flange bolt hole ( as Fig. 2in mark 3), solid drawn pipe support post ( as Fig. 2in mark 4) lower end butt flange ( as Fig. 2in mark 5), and flange bolt hole ( as Fig. 2in mark 6) composition.
as Fig. 3embodiment is illustrated figure instituteshow: be of the present invention noveloverall tower crane structural representation after tower crane installs figure, it have press take at the bottom of tower crane four counterweight water tanks ( as Fig. 3in mark 1,2,3,4), some joint tower statures connect fastening tower body ( as Fig. 3in mark 5), U-shaped sliding tray ( as Fig. 3in mark 6) slide in U-shaped slip sport car and drive sport car motor transmission (as
as Fig. 4embodiment is illustrated figure instituteshow: be of the present invention novelsit at the bottom of tower crane or improved tower crane, with give bury be bolted to cross girder steel on basis ( as Fig. 4in mark 1), several circular arc type girder steels ( as Fig. 4in mark 2), install fixed weight water tank give bury bolt ( as Fig. 4in mark 3) and the lance of installing fixed tower tower crane body bury bolt ( as Fig. 4in mark 4) combine.
as Fig. 5embodiment is illustrated figure instituteshow: be to the improved connection mode of square-column-shaped tower crane tower body and tower stature lower end ( as Fig. 5in mark 1), former link bolt hole ( as Fig. 5in mark 2), increase during transformation be connected and fixed flange ( as Fig. 5in mark 3), straight mouth in the matrix inner circle being connected and fixed in flange ( as Fig. 5in sign 4), be connected and fixed method screw ( as Fig. 5in mark 5), type steel support corner post ( as Fig. 5in sign 6), the former link bolt hole in pylon upper end ( as Fig. 5in mark 7) and transformation time increase be connected and fixed flange ( as Fig. 5in mark 8) combine.
as Fig. 6embodiment is illustrated figure instituteshow: be improved tower stature upper end ( as Fig. 1in mark 1), former link bolt hole ( as Fig. 6in mark 2), increase during transformation be connected and fixed flange ( as Fig. 6in mark 3), be connected and fixed the outer straight mouth of flange convex cylindrical ( as Fig. 6middle mark 4), flange plate bolt hole ( as Fig. 6in mark 5), type steel support corner post ( as Fig. 6in mark 6), the former link bolt hole in tower stature lower end ( as Fig. 6in mark 7) and transformation time increase be connected and fixed flange) combine.
as Fig. 7embodiment is illustrated figure instituteshow: improved with sit at the bottom of tower crane be connected and fixed square-column-shaped tower stature upper end joint face ( as Fig. 7in mark 1), former be connected and fixed bolt hole ( as Fig. 7in mark 2), increase during transformation be connected and fixed flange ( as Fig. 7in mark 3), be connected and fixed the outer straight mouth of flange convex cylindrical ( as Fig. 7in mark 4), be connected and fixed flange plate bolt hole ( as Fig. 7in mark 5), type steel support corner post ( as Fig. 7in mark 6), sit at the bottom of tower crane cross girder steel ( as Fig. 7in mark 7), the bolt of fixed weight water tank ( as Fig. 7in mark 8) and tower crane at the bottom of take circular arc girder steel ( as Fig. 7in mark 9) combine.
as Fig. 8embodiment is illustrated figure instituteshow: press-fit be fixed on take at the bottom of tower crane several counterweight water tanks ( as Fig. 8in mark 7,8,9,10) combine.
as Fig. 9embodiment is illustrated figure instituteshow: press be fixed on take at the bottom of tower crane several counterweight water tanks ( as Fig. 9in mark 1,2,3,4) be fastened on take at the bottom of tower crane tower stature upper end ( as Fig. 9in mark 5) and be fastened on U-shaped slip sport car slideway chute on counterweight water tank ( as Fig. 9in mark 6) combine.
as Fig. 10 embodiment signal figure instituteshow: be the overall tower crane signal to just installing after widely used tower crane is transformed figure, it adopt several to press to be fixed on the water tank taken at the bottom of tower crane fill after water as counterweight ( as Fig. 1mark 1,2,3,4 in 0), with improved some joint tower statures, up and down with four interior angles increased when original screw bolt and transformation, the lower outside straight mouth of each a set of flange insert upper in straight mouth inner bolt is fastening that upper and lower two joint tower statures are fixed as one, so successively some joint tower statures be connected and fixed the overall tower crane tower body of shape ( as Fig. 1mark 5 in 0), be fastened on the U-shaped semi-circular slip sport car on counterweight water tank sliding rail groove ( as Fig. 1mark 6 in 0), be arranged on slip sport car in U-shaped sliding rail groove ( as Fig. 1mark 7 in 0), upper end be fastened on equilibrium arm afterbody lower end be fastened on steel chain stay cord on slip sport car ( as Fig. 10 mark in 8), bear counterweight pulling force equilibrium arm ( as Fig. 1mark 9 in 0), carry lifting operation horizontal ceiling mounted arm ( as Fig. 1mark 10 in 0), hang haul horizontal ceiling mounted arm many steel ropes ( as Fig. 1mark 11 in 0), with tower body point for the strong point hang haul counterweight forces many steel ropes ( as Fig. 1mark 12 in 0) for support fulcrum tower body point ( as Fig. 1mark 13 in 0), carry lifting luffing operation actuated small roadster ( as Fig. 1mark 14 in 0), lifting steel rope ( as Fig. 1mark 15 in 0), band movable pulley load hook ( as Fig. 1mark 16 in 0), be known as strong man crane winch ( as Fig. 1mark 17 in 0), be arranged on lower end, pinnacle of a pagoda, tower body upper end support equilibrium arm and the operation of horizontal ceiling mounted arm rotary hoisting tower crane turntable ( as Fig. 1mark 18 in 0), be mounted in the U-shaped sliding tray inner circle of semicircle or track one side elevation driving internally toothed annulus ( as Fig. 1sign 19 in 0) with the meshing rotation of driven wheel on slip sport car or rail vehicle, drive slip sport car or rail vehicle to make semicircle crank motion when lifting operation, and be arranged on the slip sport car that sliding tray inner orbit slides sliding wheel ( as Fig. 1mark 20 in 0) combine utility modelrepacking upgrading tower crane.
The foregoing is only of the present invention noveltower crane and noveltower crane counterweight balancing mechanism and transformation and upgrade are carried out to the tower crane just widely used now; actv. increases substantially the load-carrying ability of tower crane; with the renovation technique preferred embodiment of safety; not to limit the present invention; all within concept of the present invention; any amendment of doing, equal replacement, improvement etc., all should be included within protection scope of the present invention.

Claims (6)

1. a Novel counterweight equalizing gear tower crane and utilize the new construction of described novel tower crane, up-to-date technology, new process to carry out transformation and upgrade to the tower crane widely used, its load-carrying ability and safety performance and lifting operation its feature efficient that improves is, giving on tower crane bury screw to be fixed wtih at the bottom of tower crane and sit, and the end is taken and presses multiple water tank and fill the counterweight of water as tower crane.With water tank with water do counterweight not only draw materials easily also be convenient to remove stage makeup and costume, carry time put water and only transported the advantages such as water tank.
2. its feature of new tower crane according to claim 1 is, its tower body combines up and down with some pitch circle column type tower statures, column type tower stature two ends are the shaping annulus of cast steel, through the large-diameter flange plates of vertical car lathe fine limit work, weld with several high intensity seamless pipe anchors inside two flange end faces, two flanges are fixedly connected to form column type, upper surface flange inner circle is the outer Zhi Kou periphery of convex is several screws, flange Inner circle in lower surface is straight mouth in matrix, and periphery is several screws and combine one joint tower stature.The installation of tower crane tower body, first the lower end flange plate screw hole of first segment column type tower stature, tower crane is fixedly connected with that screw is corresponding to be inserted with giving being embedded in, is anchored on basis is solidified as a whole with nut.Lifting under second section column type tower stature straight mouth and the outer straight mouth of round convex type in first segment column type tower stature upper flanges in end flanges inner circle matrix again to insert under second section column type tower stature in the interior directly mouth of end flanges inner circle matrix, two flange periphery screw bolted make two flanges be solidified as a whole, namely one or two pitch circle column type tower statures connections are solidified as a whole, the column type tower body that diameter is greater than column type tower stature is installed so more successively and raises excessive frame, rotary turnplate and driver train, equilibrium arm, ceiling mounted arm, lifting winch, hoisting cable, promote fixed pulley, movable pulley and load hook, amplitude variation trolley and driver train, tower body point and draw some steel wire tow lines of arm and equilibrium arm, with be fastened on equilibrium arm afterbody and replace the counterweight forces on weight arm to become the steel chain stay cord of downward tightening force, described steel chain stay cord is some joints composition, often joint and column type tower body save contour so that raise one and save tower body and save and increase by one and save steel slide fastener and be consistent simultaneously, steel slide fastener lower end is fastened on and tower body counterweight, on the sliding sport car of the chute inner orbit of tower crane one, that is this draws sliding sport car pulling force upwards, it is exactly the counterweight forces of tower crane actual needs when lifting operation, this power can increase and decrease along with the increase and decrease of lifting weight, and downward counteracted by pressure is handed down with tower body point through sliding sport car draws tower crane and counterweight upwards stressed in a dynamic fashion while, the column type of this Novel practical tower crane visible is not only outside 360 deg holding capacity is even, several column type tower statures are straight mouth connection mode inside and outside Bian flange all, steel pipe flange is supported, outer straight tight-lipped cooperation is inserted interior straight mouth Inner and is accurately located, bolted makes several column type tower statures be solidified as a whole, increase considerably the stress performance of tower body, actv. improves tower crane job stabilization.
3. according to claim 1,2, just carry out transformation and upgrade at widely used tower crane to existing, its feature of embodiment such as its load-carrying ability and lifting operation safety that improves is, it utilizes the existing tower crane widely used to transform, several the square-column-shaped tower statures with shaped steel welding fabrication being combined into tower body, wear outside original corner on basis that pin connects, then Bian gets that four interior angles newly increase that four cover steel pipe flanges support, inside and outside straight mouth location, bolted close-fitting to be connected the integral vertical type tower body of institute of mechanism assembled formation.Vertical tower body lower end is fixed on tower and sits and on basis, and tower is taken face and pressed multiple water tank and fill overall counterweight as tower crane after water.
4. according to claim 1, 2, its feature of new-type counterweight balancing mechanism described in 3 is, which eliminate the clump weight on equilibrium arm, use the downward pulling force mode of steel slide fastener instead and be connected to be mounted in tower crane and counterweight one chute inner orbit pulley sport car on, slip sport car the counterweight forces required when being exactly tower crane lifting of the pulling force born upwards, this power has four of pulley sport car bottom to slide at the sliding wheel of chute inner orbit, with four sliding wheels slided at sliding tray inner orbit through the both sides track of U-shaped chute to the dynamic constrained power of sliding wheel and counterweight pulling force, tower crane and counterweight is passed to and the Ya Li Xiang Arrived descended with tower body point disappears through U-shaped sliding tray.When lifting operation, pulley sport car is while being subject to weight arm afterbody steel slide fastener pulling force upwards, also must keep with tower crane equilibrium arm afterbody is all the same angle in the center of circle with tower body, equidirectional, synchronous rotary carries out lifting operation, for this reason at tower crane arm rotary drive mechanism, and between the driver train bearing the slip sport car of dynamic counterweight pulling force, be provided with computer autonomous cruise speed system, with the anglec of rotation according to ceiling mounted arm rotary drive mechanism, the drive motor carrying out instruction slip sport car drives slip sport car to keep keeping concentric with ceiling mounted arm afterbody, equidirectional, same angle, synchronous axial system completes the lifting operation of tower crane simultaneously.According to the feature of this counterweight balancing mechanism described, it has also possessed an advantage is exactly be connected to one piece all overall for the counterweight of whole tower crane with basis, pull sliding tray rail slip sport car in a dynamic fashion required counterweight balance power with steel slide fastener, with ground base and counterweight water tank balance to the counteract gravity forces pressed down fully achieve counterweight balance power can according to the increase and decrease of lifting object weight along with synchronously automatically increasing or decreasing simultaneously, automatic weighing and balancing.
5. the new-type counterweight balancing mechanism of tower crane according to claim 4 separately has a kind of complete its feature of clump weight rail vehicle mode counterweight balancing mechanism to be on the basis of its advantage and safety, it changes pressure downward for the clump weight on tower crane equilibrium arm as the downward pulling force of the steel slide fastener rope that is fixed on equilibrium arm afterbody into equally, it is the center of circle that the lower end of steel slide fastener rope is fixed on tower body, balance brachium is radius of rotation and with on the rail vehicle on the orthogonal circular ring type track of equilibrium arm afterbody, rail vehicle loads and is greater than the maximum lifting tonnage of tower crane, the large proportion clump weight of required counterweight tonnage, one side elevation build-in of circular ring type track and the circular ring type tooth bar of track with radius of circle, the meshing rotation of the driven wheel corresponding with rail vehicle side carrys out drive track car, along circular ring type track and equilibrium arm, the same angle of ceiling mounted arm, in the same way, synchronously reciprocating, for guaranteeing to be fully loaded with tower crane, the rail vehicle of the clump weight needed for the biggest lifting capacity, remain accurately and equilibrium arm, the same angle of ceiling mounted arm, in the same way, synchronous reciprocating along circular ring type track, tower crane is driven the motor of turntable rotation for this reason, the motor brain autonomous cruise speed system walked with drive track garage is chain, ensure that two motors are accomplished to start in lifting operation process simultaneously, with turning to, same radius of rotation, same angle, synchronous reciprocating has moved lifting operation task.When tower crane hoisting operation, the weight playing weight hanging over suspension hook passes to arm through lift hook steel slide fastener rope, arm take tower body as fulcrum Bian lever mode, a part of power is passed to equilibrium arm afterbody pulling force upwards, with to the downward pressure of tower body, another portion is the steel slide fastener rope and equilibrium arm afterbody and the sharp steel slide fastener rope hung of tower body that tower body is sharp and hanging is in ceiling mounted arm, in the mode that tower body point is fulcrum, a part has passed to the downward pressure of tower body, a part has passed to equilibrium arm afterbody pulling force upwards, these two parts that equilibrium arm bears are to upper pulling force sum, namely the counterweight balance power that tower crane is required when lifting operation, the gravity that this power finally upwards lifts the rail vehicle of fully loaded clump weight downward through the steel slide fastener rope of equilibrium arm afterbody offset, be greater than the gravity that the clump weight of the counterweight forces of lifting weight time institute actual needs is downward, be pressed in and rail vehicle passes to ground base through track accomplish each equilibrium of forces for this reason.As can be seen here this counterweight balance mode fully achieve the power of tower crane when lifting operation needed for counterweight balance be along with lifted weight increase and decrease and synchronous, with amount, automatically increase or decrease simultaneously, the gravity of unnecessary clump weight is passed to ground base through rail vehicle and track and is kept each force balance simultaneously.The Beijing South Maxpower Technology Co. Ltd's steady quick and safe of large lifting operation highlighting this new-type tower crane counterweight balancing mechanism is reliable.
6. novel tower crane counterweight balancing mechanism according to claim 1 and the upgrading of transformation tower crane improve load-carrying ability and lifting efficiency; improve the working environment of counterweight balance performance and operating personal; realize tower crane intellectuality, automation Bian electricity consumption Brain autonomous cruise speed system have carried out safe spacing interlock protection and overweight, the large restriction safety interlocking protection of hypervelocity, wind the top to bottom, left and right, front and rear of tower crane in operation process; guarantee that lifting operation is steady, safety, reliably its feature are; have employed computer autonomous cruise speed system wireless operated signal receiver with, two movements are just formula wireless transmission operation control has been engaged in initial point and each hand-held one of the terminal operative employee of weight, commanding officer when achieving on-the-spot manipulation tower crane operation, signalman, driver and Si lock multiple posies such as work and hold and be integrated, tower crane driver is freed from severe high-risk working environment, closes and exempted from because of many posies adjust the not good hidden danger etc. that causes the accident.Embody the working environment that novel tower crane small investment, instant effect, operation hoisting capacity can increase about several times on former basis, lifting operation is steady, safe and reliable, operating efficiency is high, convenient effective optimization of removing improves operating personal.
CN201510442779.7A 2015-08-20 2015-08-20 Novel large-lifted-weight high-safety tower crane for counterweight balance mechanism and reforming and upgrading of tower crane Pending CN105060134A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510442779.7A CN105060134A (en) 2015-08-20 2015-08-20 Novel large-lifted-weight high-safety tower crane for counterweight balance mechanism and reforming and upgrading of tower crane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510442779.7A CN105060134A (en) 2015-08-20 2015-08-20 Novel large-lifted-weight high-safety tower crane for counterweight balance mechanism and reforming and upgrading of tower crane

Publications (1)

Publication Number Publication Date
CN105060134A true CN105060134A (en) 2015-11-18

Family

ID=54489728

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510442779.7A Pending CN105060134A (en) 2015-08-20 2015-08-20 Novel large-lifted-weight high-safety tower crane for counterweight balance mechanism and reforming and upgrading of tower crane

Country Status (1)

Country Link
CN (1) CN105060134A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106287105A (en) * 2016-08-31 2017-01-04 武汉冶钢结构有限责任公司 A kind of large-scale pipeline internal installation device
CN107939301A (en) * 2017-12-20 2018-04-20 平煤建工集团特殊凿井工程有限公司 A kind of drilling tool assembles tower
CN114772490A (en) * 2022-04-13 2022-07-22 广西路建工程集团有限公司 Construction method of rotary crane of asynchronous cradle belt anchoring system
CN115303965A (en) * 2022-10-11 2022-11-08 济南汇友建工机械有限公司 Flat-top tower crane balance arm assembly without tower top

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106287105A (en) * 2016-08-31 2017-01-04 武汉冶钢结构有限责任公司 A kind of large-scale pipeline internal installation device
CN106287105B (en) * 2016-08-31 2018-01-23 武汉一冶钢结构有限责任公司 A kind of large-scale pipeline internal installation device
CN107939301A (en) * 2017-12-20 2018-04-20 平煤建工集团特殊凿井工程有限公司 A kind of drilling tool assembles tower
CN107939301B (en) * 2017-12-20 2024-04-19 平煤建工集团特殊凿井工程有限公司 Drilling tool assembling tower
CN114772490A (en) * 2022-04-13 2022-07-22 广西路建工程集团有限公司 Construction method of rotary crane of asynchronous cradle belt anchoring system
CN115303965A (en) * 2022-10-11 2022-11-08 济南汇友建工机械有限公司 Flat-top tower crane balance arm assembly without tower top

Similar Documents

Publication Publication Date Title
CN201058789Y (en) Wheel-track type girder gantry crane
CN202358849U (en) Small-size suspension crane
CN207129869U (en) A kind of crane equipment that lifting force is obtained by counterweight
CN105060134A (en) Novel large-lifted-weight high-safety tower crane for counterweight balance mechanism and reforming and upgrading of tower crane
CN201176373Y (en) Hoisting device for pylon
CN201942435U (en) Special trolley for double-beam gantry crane
CN202321978U (en) Combined lifting appliance for metallurgical environment
CN108275561B (en) Active lower shaft rotation hoisting tool
CN109231026B (en) Hoisting device for key parts of offshore wind turbine generator
CN202508791U (en) Novel tower section lead-in device
CN2761563Y (en) Special crane for extra-high, banding, autolifting type wind power generator
CN201351102Y (en) Hydraulic lifting steel strand retractable device
CN209601953U (en) A kind of self-contained replacement sliding suspender of steelmaking system buggy ladle deceleration locomotive wheel
CN209098058U (en) A kind of novel universal gantry crane
CN202390116U (en) High-intensity small-tonnage hoist
CN202449763U (en) Simple pneumatic crane
CN201317648Y (en) Vehicle well cover lifting device
CN201176372Y (en) Novel demountable traveling mast crane
CN204000817U (en) The large-scale counterweight block privileged sites of vertical ship lift move assembling device
CN201825690U (en) Small-size hoisting device for replacing ladle pipe of aluminum output ladle
CN201942465U (en) Steel cable threading and winding system
CN201746232U (en) Portal bridge crane and trolley thereof
CN201343379Y (en) Crane used for maintenance of large-size wind power equipment
CN201746271U (en) Single hoisting point trolley and hoist employing same
CN202744219U (en) Lifting frame

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20151118

WD01 Invention patent application deemed withdrawn after publication