CN105046345A - Method of rapidly creating power grid plant station diagram - Google Patents

Method of rapidly creating power grid plant station diagram Download PDF

Info

Publication number
CN105046345A
CN105046345A CN201510260008.6A CN201510260008A CN105046345A CN 105046345 A CN105046345 A CN 105046345A CN 201510260008 A CN201510260008 A CN 201510260008A CN 105046345 A CN105046345 A CN 105046345A
Authority
CN
China
Prior art keywords
plant stand
template
warehouse
electrical network
batch
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510260008.6A
Other languages
Chinese (zh)
Inventor
张令涛
鹿军
张亮
王恩江
贾威
田国辉
马仲佳
于淼
李朗
刘惠雅
田立平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Kedong Electric Power Control System Co Ltd
State Grid Liaoning Electric Power Co Ltd
Original Assignee
Beijing Kedong Electric Power Control System Co Ltd
State Grid Liaoning Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Kedong Electric Power Control System Co Ltd, State Grid Liaoning Electric Power Co Ltd filed Critical Beijing Kedong Electric Power Control System Co Ltd
Priority to CN201510260008.6A priority Critical patent/CN105046345A/en
Publication of CN105046345A publication Critical patent/CN105046345A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a method of rapidly creating a power grid plant station diagram. In a plant station diagram drafting stage, a plant station diagram template drafted in advance is imported and fine-tuned according to the real plant station conditions to acquire a new plant station diagram. In a diagram storage stage, elements in the new plant station diagram are stored in batches to finish the whole station creating process. Compared with the prior art, the method which uses the plant station diagram template for rapid drafting of the plant station diagram and further makes elements stored in batches during the diagram storage stage makes the station creating speed of power grid technical personnel obviously improved. The station creating efficiency is further improved.

Description

A kind of method of fast creation electrical network plant stand figure
Technical field
The present invention relates to a kind of method of fast creation electrical network plant stand figure, belong to electric power system dispatching technical field.
Background technology
Existing electrical network plant stand figure process of building a station mainly comprises plant stand figure drafting and figure puts two stages in storage, and concrete operation step as shown in Figure 1.In the plant stand figure drafting stage, need to draw required element or a partiting template (Bay) one by one.Although a partiting template can other plant stands multiplexing template that structure is similar when building a station, be also merely able to manually add one by one, although can use functions such as copying stickup, the workloads such as pendulum position, typesetting, layout, connecting line are still very large.At figure binning phase, first choose element to check component information panel again, preserve after filling in required field.This is for partiting template between an element or.Plant stand figure has how many elements or a partiting template just need to do the such operation of how many times, workload is numerous and diverse and repetitive operation is too many.Element or a partiting template more in, whole process is quite numerous and diverse and easily make mistakes, and work efficiency is very low.Therefore, the existing electrical network plant stand figure main Problems existing of process of building a station is that step is complicated, repetitive operation is many, and processing ease is made mistakes, and efficiency is not high.
Be in the Chinese patent application of 201410606802.7 at application number, disclose a kind of automatic generation method of the electric system interval component based on free template, comprise: based on graphics template technology, create the free template comprising blank posting and band parameterized graphics element according to different interval type; On the plant stand figure that routine is drawn, select a switch arbitrarily, according to the free template of type selecting, and the interval component that interval sectional drawing generates this interval, switch place can be intercepted; Select the switch of multiple same type, can the interval component of the multiple identical type of Mass production.The method is applied to automation system for the power network dispatching, greatly simplifies interval component making step, makes interval component enter into the automatic generation epoch from the manual drawing epoch.Adopting said method can avoid plant stand equipment repeat draw, reduce the workload of automation personnel, improve the accuracy of figure.
On the other hand, domestic each electric power research mechanism and producer are under the tissue of The National Electric Power Communication Center, and the interoperability of having carried out based on IEC61970CIS series standard is tested, and have worked out " the common graphics exchange form based on SVG " accordingly.But in actual applications, this form still exists following problem: there is distortion when 1. figure imports, cause figure between each system, share practical value low; If add the pel storehouse of origin system when each off-line exchanges in SVG, the SVG file of derivation is inevitable excessive, inefficiency during importing goal systems; 2. SVG can not directly describe power equipment model.Need tens row with SVG complete description power equipment object, and need be expert at and carry out associating between row quoting.This mode causes SVG document size comparatively large, and during on-line operation, analyzing efficiency is low.
In order to address this problem, about electric power research mechanism has worked out the figure Description standard based on CIM further, be called CIM/G specification.CIM/G is divided into defined file and graphic file two kinds of file layouts.Wherein, defined file is used for the description in pel storehouse, painted repository and Dynamic Announce style storehouse, graphic file be used for plant stand figure, electric network current diagram, power grid GIS figure public information quote the description with graphic element.The essential element of graphic file comprises Include label and G label.Include label comprises these 3 attributes of element, color and style, loads public information bag, call the pel storehouse in public information bag, painted repository and Dynamic Announce style storehouse respectively when showing for figure; The predefined painted allocation plan of painted configuration library storage; The predefined figure dynamic display style of Dynamic Announce style library storage.Primary graphic element and the electric system pattern primitive element of graphing is defined in G label.Power equipment graphic element by reference pel definition realizes the instantiation of Drawing Object.
Summary of the invention
Technical matters to be solved by this invention is a kind of method providing fast creation electrical network plant stand figure.
For realizing above-mentioned goal of the invention, the present invention adopts following technical scheme:
A method of fast creation electrical network plant stand figure, comprises the steps:
Draw the stage at plant stand figure, first import plant stand figure template drawn in advance, then finely tune according to the actual conditions of plant stand, obtain new plant stand figure;
At figure binning phase, the element in described new plant stand figure is carried out batch warehouse-in, complete whole process of building a station.
Wherein more preferably, described plant stand figure template is the general graphical file defined by graphic editor, and CIM/G specification followed by the label used in described general graphical file.
Wherein more preferably, described plant stand figure template is selected not exclusively drafting but is had the plant stand figure of certain universal architecture.
Wherein more preferably, described batch warehouse-in once inputs a set of pieces and a partiting template allly must fill out attribute, and once preserve the operation of warehouse-in.
Wherein more preferably, when carrying out batch and putting in storage, select the element preparing warehouse-in to assemble many monomers warehouse-in messages to user, and adopt one independently thread process.
Wherein more preferably, when carrying out batch and putting in storage, whether the attribute information of decision element is legal; Batch in-stockroom operation is performed under the prerequisite that described attribute information is legal.
Wherein more preferably, when carrying out batch and putting in storage, the some list file provided by substation is imported, manually pull after importing warehouse-in required input must number completion certificate.
Compared with prior art, the method of fast creation electrical network plant stand figure provided by the present invention utilizes plant stand figure template to carry out the Fast Drawing of plant stand figure, by element batch warehouse-in in figure warehouse-in process, thus significantly accelerate the speed that electric power network technique personnel build a station, improve the efficiency of building a station.
Accompanying drawing explanation
Fig. 1 is that existing electrical network plant stand figure builds a station the process flow diagram of process;
Fig. 2 is the method flow diagram of fast creation electrical network plant stand figure provided by the present invention;
Fig. 3 is in the present invention, the constructive process process flow diagram of plant stand figure template;
Fig. 4 is in the present invention, the use procedure process flow diagram of plant stand figure template;
Fig. 5 is in the present invention, the process flow diagram of batch in-stockroom operation.
Embodiment
Below in conjunction with the drawings and specific embodiments, technology contents of the present invention is described in further detail.
Before address, the process of building a station of electrical network plant stand figure mainly comprises plant stand figure and to draw and figure puts two stages in storage.For Problems existing in existing process of building a station, the present invention proposes the technical scheme of the drawing of plant stand figure template and batch warehouse-in.Specifically, draw the stage at plant stand figure, first utilize corresponding plant stand figure template drawn in advance, then need the plant stand figure drawn to carry out finely tuning according to current and revise, obtaining new plant stand figure; At figure binning phase, by element batch warehouse-in instead of one by one element put in storage respectively, complete whole process of building a station.Can the time of building a station be shortened like this, simplify process of building a station.
As shown in Figure 2, in the method for fast creation electrical network plant stand figure provided by the present invention, first start warehouse-in work of mapping, import previous plant stand figure template.On the other hand, draw plant stand figure A (A is the corresponding plant stand similar with current plant stand situation) or in plant stand chart database, find corresponding plant stand figure A, then being derived the template model.pic.g as existing plant stand figure.Then, the operation of component trimming and connecting line fine setting is carried out according to the actual conditions of existing plant stand.Operate in above-mentioned fine setting, after plant stand figure meets the actual conditions of existing plant stand, its batch added in shape library, thus completes the process of building a station of whole plant stand figure.
Below, composition graphs 3 and Fig. 4 further illustrate establishment and the use procedure of plant stand figure template.In the present invention, define a class general graphical file as plant stand figure template by graphic editor, can reuse to improve the speed of building a station in the editing process of plant stand figure, plant stand figure template is different based on partiting template between CIM/G specification from existing.Specifically, a partiting template is a class particular components of definition, is used for representing the set of a set of pieces, and plant stand figure template describes plant stand figure by the general graphical file of definition, and CIM/G specification followed by the label used in this general graphical file.
The constructive process of plant stand figure template as shown in Figure 3.Because the effect of plant stand figure template uses as a kind of template in plant stand figure drafting afterwards, therefore plant stand figure template should select the plant stand figure (or primary connection figure) with universal architecture.This plant stand figure normally not exclusively draws but has certain universal architecture.In practical operation, can according to concrete graphic plotting needs, the plant stand figure drawn will be needed to classify, then drawing out one group of corresponding plant stand figure template, corresponding plant stand figure template can be called when drawing concrete plant stand figure.In practical operation, the element in plant stand figure template is fewer, and its versatility is better; Element in plant stand figure template is more, and it uses also with regard to Vietnamese side just.
The use procedure of plant stand figure template as shown in Figure 4.In the process of drawing plant stand figure, first open the plant stand figure that a width prepares to draw, then open drawn plant stand figure template, perform and import plant stand figure template.In importing process, select a suitable plant stand figure template according to template name, thumbnail, then added in wiring diagram.In the process of adding wiring diagram to, if current canvas size is less than selected template size, then preferentially to import according to template canvas size.By aforesaid operations, plant stand figure template is imported in wiring diagram, then carry out finely tuning and revising on plant stand artwork plate base, just can complete the drafting of new plant stand figure.The multiplexing repetitive operation can reducing mapping process of typeset in a large number of plant stand figure template, significantly improves the efficiency of building a station.
Next, the principle of work realizing batch warehouse-in at figure binning phase is introduced.Batch warehouse-in once inputs a set of pieces and a partiting template allly must fill out attribute (normally scheduling number, dual order, electric pressure, application belonging to record), and once preserve the operation of warehouse-in.In batch in-stockroom operation, bottom still adopts the interactive mode of receiving and dispatching message with Graphics Device Interface (GDI).After submission batch warehouse-in, select the element preparing warehouse-in to assemble many monomer warehouse-in messages to user, and adopt independently thread to process.
The operating process of batch warehouse-in as shown in Figure 5.After plant stand figure completes, next step needs the equipment (i.e. element) in plant stand figure to carry out in-stockroom operation.Now, prepare the wiring diagram that a width element or a partiting template are not yet put in storage, next select batch warehouse-in mode not put element in storage to present.Then, the attribute information that the scheduling number, dual name, electric pressure etc. of editor's batch warehouse-in element must be filled out, and preserve.In preservation process, need to judge that whether the attribute information filled in is legal.If illegal words, then pointed out and returned edit step and modified; If legal, then perform batch in-stockroom operation.In batch in-stockroom operation, one group of equipment can be selected to click batch again and to enter library button, the equipment of not putting in storage in such range of choice as this batch warehouse-in equipment, if non-selected any equipment, then can using in plant stand figure all do not enter library facilities as this batch warehouse-in equipment.In the process performing batch warehouse-in, the progress bar of similar 10/50 can be had to point out the concrete progress of batch warehouse-in.
The effect of batch warehouse-in is the number of times reducing user's " click figure-warehouse-in ", the point list file that file lead-in mode support in mass simultaneous warehouse-in process is provided by substation imports, only need after importing manually to pull warehouse-in required input must number completion according to, so greatly accelerate the drawing efficrence of electrical network plant stand figure.
Compared with prior art, the method of fast creation electrical network plant stand figure provided by the present invention utilizes plant stand figure template to carry out the Fast Drawing of plant stand figure, by element batch warehouse-in in figure warehouse-in process, thus significantly accelerate the speed that electric power network technique personnel build a station, improve the efficiency of building a station.
Above the method for fast creation electrical network plant stand figure provided by the present invention has been described in detail, but obvious specific implementation form of the present invention is not limited thereto.For the those skilled in the art of the art, the various apparent change carried out it when not deviating from spirit of the present invention and right is all within protection scope of the present invention.

Claims (7)

1. a method of fast creation electrical network plant stand figure, is characterized in that comprising the steps:
Draw the stage at plant stand figure, first import plant stand figure template drawn in advance, then finely tune according to the actual conditions of plant stand, obtain new plant stand figure;
At figure binning phase, the element in described new plant stand figure is carried out batch warehouse-in, complete whole process of building a station.
2. the method for fast creation electrical network plant stand figure as claimed in claim 1, is characterized in that:
Described plant stand figure template is the general graphical file defined by graphic editor, and CIM/G specification followed by the label used in described general graphical file.
3. the method for fast creation electrical network plant stand figure as claimed in claim 1, is characterized in that:
Described plant stand figure template is selected not exclusively drafting but is had the plant stand figure of certain universal architecture.
4. the method for fast creation electrical network plant stand figure as claimed in claim 1, is characterized in that:
Described batch warehouse-in once inputs a set of pieces and a partiting template allly must fill out attribute, and once preserve the operation of warehouse-in.
5. the method for fast creation electrical network plant stand figure as claimed in claim 1, is characterized in that:
When carrying out batch and putting in storage, select the element preparing warehouse-in to assemble many monomer warehouse-in messages to user, and adopt independently thread to process.
6. the method for fast creation electrical network plant stand figure as claimed in claim 1, is characterized in that:
When carrying out batch and putting in storage, whether the attribute information of decision element is legal; Batch in-stockroom operation is performed under the prerequisite that described attribute information is legal.
7. the method for fast creation electrical network plant stand figure as claimed in claim 1, is characterized in that:
When carrying out batch and putting in storage, the some list file provided by substation is imported, manually pull after importing warehouse-in required input must number completion certificate.
CN201510260008.6A 2015-05-20 2015-05-20 Method of rapidly creating power grid plant station diagram Pending CN105046345A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510260008.6A CN105046345A (en) 2015-05-20 2015-05-20 Method of rapidly creating power grid plant station diagram

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510260008.6A CN105046345A (en) 2015-05-20 2015-05-20 Method of rapidly creating power grid plant station diagram

Publications (1)

Publication Number Publication Date
CN105046345A true CN105046345A (en) 2015-11-11

Family

ID=54452872

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510260008.6A Pending CN105046345A (en) 2015-05-20 2015-05-20 Method of rapidly creating power grid plant station diagram

Country Status (1)

Country Link
CN (1) CN105046345A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106649452A (en) * 2016-09-22 2017-05-10 广东电网有限责任公司电力调度控制中心 Method of generating template graphics
CN109272564A (en) * 2018-09-21 2019-01-25 国网江苏省电力有限公司连云港供电分公司 A kind of plant stand figure automatic generation method based on machine learning

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20110184870A1 (en) * 2009-10-21 2011-07-28 Kana Software, Inc. Form processing in a user interface workflow composition tool
CN103390079A (en) * 2013-07-08 2013-11-13 国电南瑞科技股份有限公司 Interval light indicator graph generating method based on general template
CN104462645A (en) * 2014-10-30 2015-03-25 中国南方电网有限责任公司 Method for automatically generating gap subgraphs based on free template
CN104462473A (en) * 2014-12-19 2015-03-25 国家电网公司 Method for automatically generating CIM-G-format plant-station internal wiring diagram based on CIM-E power grid model
CN104616207A (en) * 2015-01-27 2015-05-13 中国科学院计算机网络信息中心 Power grid topological visualization system and power grid topological visualization method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20110184870A1 (en) * 2009-10-21 2011-07-28 Kana Software, Inc. Form processing in a user interface workflow composition tool
CN103390079A (en) * 2013-07-08 2013-11-13 国电南瑞科技股份有限公司 Interval light indicator graph generating method based on general template
CN104462645A (en) * 2014-10-30 2015-03-25 中国南方电网有限责任公司 Method for automatically generating gap subgraphs based on free template
CN104462473A (en) * 2014-12-19 2015-03-25 国家电网公司 Method for automatically generating CIM-G-format plant-station internal wiring diagram based on CIM-E power grid model
CN104616207A (en) * 2015-01-27 2015-05-13 中国科学院计算机网络信息中心 Power grid topological visualization system and power grid topological visualization method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106649452A (en) * 2016-09-22 2017-05-10 广东电网有限责任公司电力调度控制中心 Method of generating template graphics
CN109272564A (en) * 2018-09-21 2019-01-25 国网江苏省电力有限公司连云港供电分公司 A kind of plant stand figure automatic generation method based on machine learning
CN109272564B (en) * 2018-09-21 2023-03-28 国网江苏省电力有限公司连云港供电分公司 Plant station diagram automatic generation method based on machine learning

Similar Documents

Publication Publication Date Title
CN107292003B (en) Automatic generation method of power grid station wiring diagram
CN104376416B (en) Production Managementsystem For Electricpower Network and dispatch automated system graphic interaction method
CN102360398B (en) IEC61850-based CAD electric power graphic generation analysis method
CN104407576A (en) Realization method for general type production and manufacturing unit and control system thereof
CN104484166A (en) Graphical modeling device and method for automatic testing system
CN106372040A (en) Difference comparison system of intelligent substation configuration file
CN108537891A (en) The method that three-dimensional material and textures data are automatically switched to UE4
CN104951844A (en) Layout optimization method of distribution network thematic maps
CN108733441A (en) A kind of rendering method for visualizing and system suitable for large scale electric network symbolic device
CN103123660B (en) A kind of method to software and hardware system CAD mathematics library
CN107590592A (en) Job dependence relation method for expressing, operation displaying and dispatch control method and device
CN105184011A (en) Automatic transformer substation WEB primary connection diagram forming method and device
CN108053460B (en) Drawing method and device of electric power system diagram
CN105046345A (en) Method of rapidly creating power grid plant station diagram
CN104656543A (en) PLC gradient diagram matrix editing display method
CN111914376B (en) Automatic construction method and device for power grid bus mode diagram and storage medium
CN104750468A (en) Server side topological data conversion method and device
CN106168793A (en) A kind of method automatically generating control equipment and system
CN111115093B (en) Method for realizing compatibility of warehouse management software
US8291313B1 (en) Generation of a container hierarchy from a document design
CN112309313A (en) Module controller configuration method, device and system and computer readable storage medium
CN113706088A (en) Industrial data automatic generation report system
CN110737980B (en) Electrical design system and electrical design method
CN106651142A (en) Transformer station main equipment type selection method based on three-dimensional design platform
CN106157366A (en) Ultra-large scene based on BIM renders optimization method and system in mobile terminal

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20151111

RJ01 Rejection of invention patent application after publication