CN105020474A - 一种管道过河加固结构 - Google Patents

一种管道过河加固结构 Download PDF

Info

Publication number
CN105020474A
CN105020474A CN201510448148.6A CN201510448148A CN105020474A CN 105020474 A CN105020474 A CN 105020474A CN 201510448148 A CN201510448148 A CN 201510448148A CN 105020474 A CN105020474 A CN 105020474A
Authority
CN
China
Prior art keywords
pipeline
layer
diameter
river
backfill layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510448148.6A
Other languages
English (en)
Inventor
阮磊磊
叶华
徐传磊
张晓斌
齐茜茹
郭清峰
郑鑫
鲍燕寒
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Urban Planning and Design Institute Co Ltd
Original Assignee
China Railway Urban Planning and Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Urban Planning and Design Institute Co Ltd filed Critical China Railway Urban Planning and Design Institute Co Ltd
Priority to CN201510448148.6A priority Critical patent/CN105020474A/zh
Publication of CN105020474A publication Critical patent/CN105020474A/zh
Pending legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/12Laying or reclaiming pipes on or under water
    • F16L1/16Laying or reclaiming pipes on or under water on the bottom

Abstract

本发明的目的是一种管道过河加固结构,通过设置球墨铸铁管的管道,在管道下方包覆有中粗砂垫层,管道上方从内到外设置袋装回填土层、碎石回填层和浆砌块石防冲刷层,中粗砂垫层有效保护了管道,碎石回填层增强了管道的抗浮能力,浆砌块石防冲刷层具有很强的抗冲刷能力保护了管道;本发明结构简单,加固效果优异,取材方便,施工简单,节约造价。

Description

一种管道过河加固结构
技术领域
本发明涉及过河管道的安装领域,尤其涉及一种管道过河加固结构。
背景技术
管道一般用于输送饮用水、污水,管道的铺设会遇到各种各样的自然情况,其中过河管道经常使用到,但是过河管道目前还存在一些缺陷,管道会发生漂浮,被河水冲刷冲击导致破损,因此需要提供一种可以解决这些问题的管道过河加固结构应用于过河管道的加固。
发明内容
为解决上述问题,本发明的目的是提供一种管道过河加固结构,通过设置球墨铸铁管的管道,在管道下方包覆有中粗砂垫层,管道上方从内到外设置袋装回填土层、碎石回填层和浆砌块石防冲刷层,中粗砂垫层有效保护了管道,碎石回填层增强了管道的抗浮能力,浆砌块石防冲刷层具有很强的抗冲刷能力保护了管道,解决了背景技术中出现的问题。
本发明提供一种管道过河加固结构,包括有管道,所述管道为球墨铸铁管,所述管道外侧上方包裹有截面呈圆弧形的袋装回填土层,所述管道外侧下方包覆有截面呈倒梯形的中粗砂垫层;所述袋装回填土层上方包覆有截面呈六边形的碎石回填层,所述碎石回填层上方填有与碎石回填层上方三条边平行的浆砌块石防冲刷层;所述浆砌块石防冲刷层两侧上方填有素土夯实层。
进一步改进在于:所述袋装回填土层的截面圆弧的直径为管道直径的两倍;所述碎石回填层顶部边的边长为管道直径的五倍。
进一步改进在于:所述中粗砂垫层的厚度为管道直径的0.6-0.7倍;所述袋装回填土层的厚度为管道直径的0.5-07倍;所述碎石回填层的厚度为管道直径的1.4-1.6倍;所述浆砌块石防冲刷层的厚度为管道直径的0.4-0.6倍。
本发明的有益效果:通过设置球墨铸铁管的管道,在管道下方包覆有中粗砂垫层,管道上方从内到外设置袋装回填土层、碎石回填层和浆砌块石防冲刷层,中粗砂垫层有效保护了管道,碎石回填层增强了管道的抗浮能力,浆砌块石防冲刷层具有很强的抗冲刷能力保护了管道;本发明结构简单,加固效果优异,取材方便,施工简单,节约造价。
附图说明
图1是本发明的截面图。
其中:1-管道,2-袋装回填土层,3-中粗砂垫层,4-碎石回填层,5-浆砌块石防冲刷层,6-素土夯实层。
具体实施方式
为了加深对本发明的理解,下面将结合实施例对本发明作进一步详述,该实施例仅用于解释本发明,并不构成对本发明保护范围的限定。
如图1所示,本实施例提供一种管道过河加固结构,包括有管道1,所述管道1为球墨铸铁管,所述管道1外侧上方包裹有截面呈圆弧形的袋装回填土层2,所述管道1外侧下方包覆有截面呈倒梯形的中粗砂垫层3;所述袋装回填土层2上方包覆有截面呈六边形的碎石回填层4,所述碎石回填层4上方填有与碎石回填层4上方三条边平行的浆砌块石防冲刷层5;所述浆砌块石防冲刷层5两侧上方填有素土夯实层6。所述袋装回填土层2的截面圆弧的直径为管道1直径的两倍;所述碎石回填层4顶部边的边长为管道1直径的五倍。所述中粗砂垫层3的厚度为管道1直径的0.6-0.7倍;所述袋装回填土层2的厚度为管道1直径的0.5-07倍;所述碎石回填层4的厚度为管道1直径的1.4-1.6倍;所述浆砌块石防冲刷层5的厚度为管道1直径的0.4-0.6倍。
通过设置球墨铸铁管的管道1,在管道1下方包覆有中粗砂垫层2,管道1上方从内到外设置袋装回填土层2、碎石回填层4和浆砌块石防冲刷层5,中粗砂垫层3有效保护了管道,碎石回填层4增强了管道的抗浮能力,浆砌块石防冲刷层5具有很强的抗冲刷能力保护了管道。
本实施例结构简单,加固效果优异,取材方便,施工简单,节约造价。

Claims (3)

1.一种管道过河加固结构,包括有管道(1),其特征在于:所述管道(1)为球墨铸铁管,所述管道(1)外侧上方包裹有截面呈圆弧形的袋装回填土层(2),所述管道(1)外侧下方包覆有截面呈倒梯形的中粗砂垫层(3);所述袋装回填土层(2)上方包覆有截面呈六边形的碎石回填层(4),所述碎石回填层(4)上方填有与碎石回填层(4)上方三条边平行的浆砌块石防冲刷层(5);所述浆砌块石防冲刷层(5)两侧上方填有素土夯实层(6)。
2.如权利要求1所述一种管道过河加固结构,其特征在于:所述袋装回填土层(2)的截面圆弧的直径为管道(1)直径的两倍;所述碎石回填层(4)顶部边的边长为管道(1)直径的五倍。
3.如权利要求1所述一种管道过河加固结构,其特征在于:所述中粗砂垫层(3)的厚度为管道(1)直径的0.6-0.7倍;所述袋装回填土层(2)的厚度为管道(1)直径的0.5-07倍;所述碎石回填层(4)的厚度为管道(1)直径的1.4-1.6倍;所述浆砌块石防冲刷层(5)的厚度为管道(1)直径的0.4-0.6倍。
CN201510448148.6A 2015-07-28 2015-07-28 一种管道过河加固结构 Pending CN105020474A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510448148.6A CN105020474A (zh) 2015-07-28 2015-07-28 一种管道过河加固结构

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510448148.6A CN105020474A (zh) 2015-07-28 2015-07-28 一种管道过河加固结构

Publications (1)

Publication Number Publication Date
CN105020474A true CN105020474A (zh) 2015-11-04

Family

ID=54410655

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510448148.6A Pending CN105020474A (zh) 2015-07-28 2015-07-28 一种管道过河加固结构

Country Status (1)

Country Link
CN (1) CN105020474A (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107559502A (zh) * 2017-10-25 2018-01-09 东北石油大学 水底附着式自稳定油气输送管道
CN112376607A (zh) * 2020-05-31 2021-02-19 中国二十二冶集团有限公司 过河管道抗浮施工方法及过河管道抗浮结构
CN112376607B (zh) * 2020-05-31 2024-05-17 中国二十二冶集团有限公司 过河管道抗浮施工方法及过河管道抗浮结构

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2369797C1 (ru) * 2008-06-02 2009-10-10 Общество с ограниченной ответственностью "ТюменНИИгипрогаз" Способ укрепления обваловки трубопровода
JP4614217B2 (ja) * 2004-06-24 2011-01-19 三井化学産資株式会社 管状体の埋設工法
CN202001726U (zh) * 2011-03-25 2011-10-05 浙江省火电建设公司 大型超深循环水管道回填结构
RU2447348C2 (ru) * 2010-03-25 2012-04-10 Государственное образовательное учреждение высшего профессионального образования "Уфимский государственный нефтяной технический университет" Способ прокладки трубопроводов в сейсмических районах
CN103898884A (zh) * 2014-03-26 2014-07-02 重庆地质矿产研究院 一种排除滑坡体区梯田壤中流的方法

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4614217B2 (ja) * 2004-06-24 2011-01-19 三井化学産資株式会社 管状体の埋設工法
RU2369797C1 (ru) * 2008-06-02 2009-10-10 Общество с ограниченной ответственностью "ТюменНИИгипрогаз" Способ укрепления обваловки трубопровода
RU2447348C2 (ru) * 2010-03-25 2012-04-10 Государственное образовательное учреждение высшего профессионального образования "Уфимский государственный нефтяной технический университет" Способ прокладки трубопроводов в сейсмических районах
CN202001726U (zh) * 2011-03-25 2011-10-05 浙江省火电建设公司 大型超深循环水管道回填结构
CN103898884A (zh) * 2014-03-26 2014-07-02 重庆地质矿产研究院 一种排除滑坡体区梯田壤中流的方法

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107559502A (zh) * 2017-10-25 2018-01-09 东北石油大学 水底附着式自稳定油气输送管道
CN107559502B (zh) * 2017-10-25 2020-09-01 东北石油大学 水底附着式自稳定油气输送管道
CN112376607A (zh) * 2020-05-31 2021-02-19 中国二十二冶集团有限公司 过河管道抗浮施工方法及过河管道抗浮结构
CN112376607B (zh) * 2020-05-31 2024-05-17 中国二十二冶集团有限公司 过河管道抗浮施工方法及过河管道抗浮结构

Similar Documents

Publication Publication Date Title
CN104153304B (zh) 一种波纹钢管涵洞填筑结构及其填筑方法
CN202300445U (zh) 超浅埋下穿公路长管棚隧道支护结构
CN102878351A (zh) 一种长距离管道输煤的管道敷设方法
CN204645027U (zh) 散体后注浆劲芯复合桩
CN208330397U (zh) 一种联合受力的压力输水盾构隧洞衬砌结构
CN105020474A (zh) 一种管道过河加固结构
CN101476309A (zh) 超高混凝土面板堆石坝坝体预压反台填筑施工方法
CN208252157U (zh) 一种隧道岩溶裂隙水的双重排水结构
CN208219692U (zh) 一种改良型输送管道保护基础结构
CN207212364U (zh) 衬砌背后虚渣处理后的复合衬砌结构
CN102409701A (zh) 一种砼墙壁施工缝处理方法及结构
CN102162554A (zh) 矿浆管道在地震断裂带地段的敷设方法和敷设结构
JP6361889B2 (ja) 人工浅場又は干潟
CN205399343U (zh) 一种加固型防水防渗护坡
CN103999592A (zh) 一种防止酸性矿区废石场植被退化的方法
CN104358245B (zh) 一种水工建筑物软基处理的方法
CN207143843U (zh) 一种预制拼装式防爆土堤
CN202899144U (zh) 一种挡水围堰结构
CN104278660B (zh) 水平埋管分层注浆直接固结强化的土石坝筑坝建造方法
CN104631425B (zh) 一种加快粉煤灰排渗固结的方法
CN103277116B (zh) 毛石钢筋混凝土优化拱结构治理软岩巷道底鼓的方法
CN202284334U (zh) 一种砼墙壁施工缝结构
CN205152962U (zh) 顺层临空边坡桩锚支挡体系
JP2016176275A (ja) サンドコンパクションパイル用材料、サンドコンパクションパイルおよびサンドコンパクションパイルの造成方法
JP6213749B2 (ja) 人工浅場又は干潟

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20151104

RJ01 Rejection of invention patent application after publication