CN105019553A - Bracing structure for annular supports of basement - Google Patents

Bracing structure for annular supports of basement Download PDF

Info

Publication number
CN105019553A
CN105019553A CN201510284234.8A CN201510284234A CN105019553A CN 105019553 A CN105019553 A CN 105019553A CN 201510284234 A CN201510284234 A CN 201510284234A CN 105019553 A CN105019553 A CN 105019553A
Authority
CN
China
Prior art keywords
support
basement
deck
concrete
template
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510284234.8A
Other languages
Chinese (zh)
Other versions
CN105019553B (en
Inventor
朱奎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Dezhou Paier Mechanical Equipment Co ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201710189946.0A priority Critical patent/CN106894420B/en
Priority to CN201710189849.1A priority patent/CN106836240B/en
Priority to CN201710189850.4A priority patent/CN106958247B/en
Priority to CN201510284234.8A priority patent/CN105019553B/en
Publication of CN105019553A publication Critical patent/CN105019553A/en
Application granted granted Critical
Publication of CN105019553B publication Critical patent/CN105019553B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/10Restraining of underground water by lowering level of ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/16Restraining of underground water by damming or interrupting the passage of underground water by placing or applying sealing substances
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • E02D29/05Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • E02D31/04Watertight packings for use under hydraulic pressure
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2200/00Geometrical or physical properties
    • E02D2200/16Shapes
    • E02D2200/1607Shapes round, e.g. circle
    • E02D2200/1621Shapes round, e.g. circle made from multiple elements
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0007Production methods using a mold
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/002Concrete
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The invention discloses a bracing structure for annular supports of a basement. The bracing structure is characterized in that two support systems are arranged; a first support system is arranged at the top of the basement; a second support system is arranged in the middle of the basement; a first support annular support is of a truss-type structure; a beam-type annular support is adopted by the second support system; a four-part enclosing structure and support top structures of the annular supports are made to be concrete plates; the distance between a first-layer annular external support and an enclosure wall is kept between 1.5 and 3 cm; a propping support is arranged between the first-layer annular external support and the enclosure wall; a concrete truss web member is arranged between the first-layer annular external support and a first-layer annular internal support; and support columns are arranged underneath the first-layer annular internal support and the first-layer annular external support.

Description

Basement annular brace supporting and protection structure
Technical field
Basement structure is increased, particularly basement annular brace supporting and protection structure after the present invention relates to one.
Background technology
In basement support system, inner support supporting and protection structure has the features such as safe and reliable, economical rationality, is used widely in base pit engineering.But routine causes great inconvenience to the construction of inner support to basement soil excavation and underground structure that support mode is arranged, the consequences such as the generation construction period extends, less economical.Adopt annular brace to substitute the conventional supporting structure system to support mode, higher economic benefit can be obtained.But annular brace is when when basement excavation is darker, especially multiple tracks supports, suffered by first annular brace, lateral pressure can exceed concrete ultimate compressive strength usually, and it is excessive that annular brace there will be displacement, and the bad phenomenon such as cracking occurs annular brace concrete.
Summary of the invention
The present invention is to provide a kind of basement annular brace supporting and protection structure, solves the problem of prior art.
For this reason, the present invention arranges twice support system, first supports and is arranged on basement top, second supports and is arranged in the middle part of basement, is excavated to the stressed meeting in absolute altitude position, the end very greatly, according to the loading characteristic that first is supported in construction, annular brace is made truss structure because first is supported on basement, this rigidity of structure is larger, non-deformability is strong, and the stressed meeting of second support system obviously reduces, and adopts beam type annular brace so just simple.Consider that bight is stressed can concentrate by stress, therefore four corners position space enclosing structure and annular brace top support structure are made concrete slab, carry out resistance to deformation to strengthen bight rigidity.
Enclosure wall width is 60 ~ 80mm, the degree of depth is basement cutting depth 2 ~ 3 times, the concrete that enclosure wall adopts is C30 or more than C30, one deck annular outer support is 1.5 ~ 3m from the distance of enclosure wall, one deck annular outer support width is 30cm, be highly 40 ~ 50cm, one deck circular inner support is 1.2 ~ 1.6m from one deck annular outer support distance, arrange to prop up between one deck annular outer support and enclosure wall and shore, shoring width is 30cm, be highly 40 ~ 50cm, one deck circular inner support width is 30cm, be highly 40 ~ 50cm, between one deck annular outer support and one deck circular inner support, concrete truss web member is set, concrete truss web member width is 20cm, be highly 40 ~ 50cm, below one deck circular inner support and one deck annular outer support, support column is set, support column adopts coagulation post or steel column, support column is arranged on above engineering pile as far as possible, otherwise below support column, temporary support pile is set.
Two layers of annular brace and enclosure wall top support structure adopt concrete slab and prop up to shore and combine, in basement long side direction 1/4 length range and short side direction 1/3 length range, concrete slab is set, basement medium position arranges to prop up to be shored, to shore for two layers and to prop up with one deck that to shore projected position identical, the support column of two layers of annular brace is identical with the support column of one deck annular outer support.
Care-supporting of propping up one deck stretches into enclosure wall inside, is formed be rigidly connected with enclosure wall, and two layers care-supportings are welded with the reserved steel bar outside enclosure wall, form articulated structure, to adapt to the feature of space enclosing structure.According to test situation, one deck props up after care-supporting and enclosure wall form and be rigidly connected, and evenly and distortion is relatively little, and enclosure wall distortion is relatively large in annular brace distortion; After two layers care-supportings and enclosure wall form articulated structure, be out of shape relatively large, but enclosure wall distortion is relatively little.
Construction sequence comprises:
(1) enclosure wall construction.
Enclosure wall not only will carry out bank protection, and also will prevent infiltration, enclosure wall doubles as outer wall of basement.Enclosure wall construction adopts template on an empty stomach, template sinks to stratum by the vertical exciting force of the vertical generation of reciprocating vibration of vibrating hammer on an empty stomach, slurries are filled immediately in empty stomach, when vibration dip mould promotes, slurries inject in slotted eye from template lower end under gravity, sink to the guide strip of template after the template first having sunk to stratum becomes, two pieces of templates present the effect that plate plate interlocks, and ensure that each veneer body is closely integrated into wall in a plane.
Construction technology comprises:
1) preformed groove is excavated;
2) prebored hole;
In the junction prebored hole of two pieces of templates, prebored hole diameter is 90 ~ 110cm;
3) vibration dip mould;
Start vibration hammer, first piece of template sunk in stratum, reaches projected depth, then by second piece of template along construction axis first piece of front side with first piece of template tight side by side, with first piece of template for guide strip, sink to stratum and reach projected depth;
4) lifting first piece of template is poured into;
In first piece of template, pour into slurry, then limit lifting limit perfusion, until extract ground, slurry is stayed in slotted eye, after perfusion lifting terminates, slurry be kept to reach wall top design altitude;
5) template is sunk to again;
With second piece of template for guide strip, sink to stratum and reach projected depth, Reperfu-sion promotes second piece of template; Construct by above program cycle, can enclosure wall be completed.
Current traditional handicraft be adopt cut the earth fluting, mud off, scarfing cinder, build underwater concrete, process seam series operation, be easy to collapse hole when slotting in permeable stratum, enclosure wall often do not reach thickness and occur break wall phenomenon.And the present invention is with powerful vertical exciting force, empty stomach template is sunk to soil layer, template and slurries serve retaining wall effect, not only not soil stress rationally release in work progress, and in vibration dip mould process, by its soil at both sides dense extrusion, improve impermeability.Due to the present invention original soil body by template squeezing action under complete.And mould marginal not slurry is carried on limit in promotion template procedure, slurries produce in note people groove at the bottom of template, starch column pressure in addition and are greater than soil body lateral pressure, therefore there will not be contracting wall and wall phenomenon of collapsing.
(2) support column construction.
Look like under support column without engineering pile, after temporary support pile of first constructing, support column is inserted temporary support pile.If there is engineering pile, directly support column is inserted temporary support pile.
(3) do one deck annular outer support, one deck circular inner support, concrete truss web member, one deck prop up and shore.
(4) cut the earth to absolute altitude position at the bottom of two layers of annular brace, do two layers of annular brace, enclosure wall, at two layers of support zone localized delamination concrete, welds reserved steel bar outside exposed main muscle, then concreting plate, finally do two layers and shore.
(5) 10cm below absolute altitude at the bottom of shoveling to basement bottom board, first does plain concrete cushion layer, then builds basement bottom board concrete.
When building basement bottom board construction, the position that water yield is large is adopted and dredges the stifled technical scheme combined, little for water yield, the position that water pressure is little adopts the method for shutoff by force, water smash plain concrete cushion layer time, with the casting and compacting of concrete mixing accelerating admixture in subrange, namely concrete solidifies at 1 ~ 2min.For the situation that water yield is large, with plastic flexible pipe water guide in sump, when cushion cap base plate waters and smash and reached 80% intensity, close sump again.The shutoff of sump is carried out as follows: water is concentrated in steel pipe, and diameter of steel tube is 50mm, and steel pipe inner wall has screw thread; Close water pipe with in spiral shell head precession steel pipe, build the concrete that base plate reserves hole.The inwall in reserved hole arranges groove for sealing, and rear pouring concrete mixes U EA expansion agent, guarantees the good combination of new-old concrete.
(6) to two layers of annular brace, concrete slab, two layers to shore and carry out explosion, remove support column after explosion.
Adopt static blasting, static blasting adopt the expansion force of expanding material more than 30MPa, static blasting reserving hole diameter is 30 ~ 40mm, reserving hole spacing is that 0.3 ~ 0.4m controls, reserving hole indwelling position, end is apart from structure floor 150mm ~ 200mm, and on member cross-sections, hole area is no more than section area 10%; In reserving hole, the main muscle of reinforced concrete member or stirrup cut off, and guarantee that the binding force of reinforcing bar does not affect demolition effect.
(7) two layers of basement roof are built.
(8) one deck annular outer support, one deck circular inner support, concrete truss web member, one deck are propped up to shore and carry out explosion.
(9) one deck basement roof is built.
Accompanying drawing explanation
Fig. 1 is one deck basement annular brace supporting and protection structure schematic diagram, and Fig. 2 is two layers of basement annular brace supporting and protection structure schematic diagram.
In each accompanying drawing: 1, enclosure wall, 2, one deck props up and shore, 3, one deck annular outer support, 4, one deck circular inner support, 5, concrete truss web member, 6, support column, 7, two layers of annular brace, 8, concrete slab, shore for 9, two layers.
Detailed description of the invention
Certain engineering is 18 layers of building, and be frame cylinder shear wall structure, basement cutting depth is 7.2m, and basement is irregularly shaped, and engineering pile is bored pile, and the bored pile degree of depth is 42m.
The present embodiment arranges twice support system, and first supports and is arranged on basement top, and second supports and is arranged in the middle part of basement, and first supports annular brace and makes truss structure, and second support system adopts beam type annular brace.Four corners position space enclosing structure and annular brace top support structure make two layers of annular brace 8.
Enclosure wall 1 width is 70mm, the degree of depth is basement cutting depth 2.5 times, the concrete that enclosure wall 1 adopts is C30, one deck annular outer support 3 is 2m from the distance of enclosure wall 1, one deck annular outer support 3 width is 30cm, be highly 45cm, one deck circular inner support 4 from one deck annular outer support 3 apart from being 1.4m, arrange to prop up between one deck annular outer support 3 and enclosure wall 1 and shore, shoring width is 30cm, be highly 45cm, one deck circular inner support 4 width is 30cm, be highly 45cm, between one deck annular outer support 3 and one deck circular inner support 4, concrete truss web member 5 is set, concrete truss web member 5 width is 20cm, be highly 45cm, one deck circular inner support 4 and one deck annular outer support 3 arrange support column 6 below, support column 6 adopts coagulation post or steel column, support column 6 is arranged on above engineering pile as far as possible, otherwise support column 6 arranges temporary support pile below.
Two layers of annular brace 7 and enclosure wall 1 top support structure adopt two layers of annular brace 8 and prop up to shore and combine, in basement long side direction 1/4 length range and short side direction 1/3 length range, concrete slab is set, basement medium position arranges to prop up to be shored, to shore 9 for two layers and to prop up with one deck that to shore 2 projected positions identical, the support column 6 of two layers of annular brace 7 is identical with the support column 6 of the annular outer support 3 of one deck.
It is inner that care-supporting of propping up one deck stretches into enclosure wall 1, formed be rigidly connected with enclosure wall 1, and two layers care-supportings are welded with the reserved steel bar outside enclosure wall 1, form articulated structure.
Construction sequence comprises:
(1) enclosure wall 1 is constructed.
Enclosure wall 1 is constructed and is adopted template on an empty stomach, template sinks to stratum by the vertical exciting force of the vertical generation of reciprocating vibration of vibrating hammer on an empty stomach, slurries are filled immediately in empty stomach, when vibration dip mould promotes, slurries inject in slotted eye from template lower end under gravity, sink to the guide strip of template after the template first having sunk to stratum becomes, two pieces of templates present the effect that plate plate interlocks, and ensure that each veneer body is closely integrated into wall in a plane.
Construction technology comprises:
1) preformed groove is excavated;
2) prebored hole;
In the junction prebored hole of two pieces of templates, prebored hole diameter is 100cm;
3) vibration dip mould;
Start vibration hammer, first piece of template sunk in stratum, reaches projected depth, then by second piece of template along construction axis first piece of front side with first piece of template tight side by side, with first piece of template for guide strip, sink to stratum and reach projected depth;
4) lifting first piece of template is poured into;
In first piece of template, pour into slurry, then limit lifting limit perfusion, until extract ground, slurry is stayed in slotted eye, after perfusion lifting terminates, slurry be kept to reach wall top design altitude;
5) template is sunk to again;
With second piece of template for guide strip, sink to stratum and reach projected depth, Reperfu-sion promotes second piece of template; Construct by above program cycle, enclosure wall 1 can be completed.
(2) support column 6 is constructed.
Support column is looked like without engineering pile 6 times, after temporary support pile of first constructing, support column 6 is inserted temporary support pile.If there is engineering pile, directly support column 6 is inserted temporary support pile.
(3) do one deck annular outer support 3, one deck circular inner support 4, concrete truss web member 5, one deck prop up and shore 2.
(4) cut the earth to two layers of annular brace 7 end absolute altitude position, do two layers of annular brace 7, enclosure wall 1, at two layers of support zone localized delamination concrete, welds reserved steel bar outside exposed main muscle, then builds two layers of annular brace 8, finally does two layers and shore 9.
(5) 10cm below absolute altitude at the bottom of shoveling to basement bottom board, first does plain concrete cushion layer, then builds basement bottom board concrete.
When building basement bottom board construction, the position that water yield is large is adopted and dredges the stifled technical scheme combined, little for water yield, the position that water pressure is little adopts the method for shutoff by force, water smash plain concrete cushion layer time, with the casting and compacting of concrete mixing accelerating admixture in subrange, namely concrete solidifies at 1 ~ 2min.For the situation that water yield is large, with plastic flexible pipe water guide in sump, when cushion cap base plate waters and smash and reached 80% intensity, close sump again.The shutoff of sump is carried out as follows: water is concentrated in steel pipe, and diameter of steel tube is 50mm, and steel pipe inner wall has screw thread; Close water pipe with in spiral shell head precession steel pipe, build the concrete that base plate reserves hole.The inwall in reserved hole arranges groove for sealing, and rear pouring concrete mixes U EA expansion agent, guarantees the good combination of new-old concrete.
(6) 9 are shored to two layers of annular brace, 7, two layers of annular brace 8, two layers and carry out explosion, after explosion, remove support column 6.
Adopt static blasting, static blasting adopt the expansion force of expanding material to be 35MPa, static blasting reserving hole diameter is 35mm, reserving hole spacing is that 0.3 ~ 0.4m controls, reserving hole indwelling position, end is apart from structure floor 200mm, and on member cross-sections, hole area is no more than section area 10%; In reserving hole, the main muscle of reinforced concrete member or stirrup cut off, and guarantee that the binding force of reinforcing bar does not affect demolition effect.
(7) two layers of basement roof are built.
(8) one deck annular outer support 3, one deck circular inner support 4, concrete truss web member 5, one deck are propped up shore 2 and carry out explosion.
(9) one deck basement roof is built.
Analyzed by computer simulation emulation, this structure and other support systems are contrasted.The first situation is for adopting the present embodiment, and the second situation is for adopt inner support merely, and the third situation is that one deck two layers adopts annular brace.Table 1 is different support system displacement and mechanical property contrast, and find in table that the supporting maximum horizontal displacement of the present embodiment is far smaller than the second situation and the third situation, being respectively 38.6% of the second situation, is 57.9% of the second situation.The greatest axis power of the present embodiment significantly reduces, and is respectively 59.6% of the second situation, is 79.9% of the second situation.The maximal bending moment of the present embodiment significantly reduces, and is respectively 62.8% of the second situation, is 79.0% of the second situation.
The different support system displacement of table 1 and mechanical property contrast
Through this basement of Site Detection Stability Analysis of Structures in work progress, supporting displacement is no more than 11mm, and support beam structure is stablized, and phenomenon without exception occurs.

Claims (7)

1. a basement annular brace supporting and protection structure, it is characterized in that arranging twice support system, first supports and is arranged on basement top, and second supports and is arranged in the middle part of basement, first supports annular brace and makes truss structure, and second support system adopts beam type annular brace; Four corners position space enclosing structure and annular brace top support structure make concrete slab;
Enclosure wall width is 60 ~ 80mm, the degree of depth is basement cutting depth 2 ~ 3 times, the concrete that enclosure wall adopts is C30 or more than C30, one deck annular outer support is 1.5 ~ 3m from the distance of enclosure wall, one deck annular outer support width is 30cm, be highly 40 ~ 50cm, one deck circular inner support is 1.2 ~ 1.6m from one deck annular outer support distance, arrange to prop up between one deck annular outer support and enclosure wall and shore, shoring width is 30cm, be highly 40 ~ 50cm, one deck circular inner support width is 30cm, be highly 40 ~ 50cm, between one deck annular outer support and one deck circular inner support, concrete truss web member is set, concrete truss web member width is 20cm, be highly 40 ~ 50cm, below one deck circular inner support and one deck annular outer support, support column is set, support column adopts coagulation post or steel column, support column is arranged on above engineering pile as far as possible, otherwise below support column, temporary support pile is set,
Two layers of annular brace and enclosure wall top support structure adopt concrete slab and prop up to shore and combine, in basement long side direction 1/4 length range and short side direction 1/3 length range, concrete slab is set, basement medium position arranges to prop up to be shored, to shore for two layers and to prop up with one deck that to shore projected position identical, the support column of two layers of annular brace is identical with the support column of one deck annular outer support.
2. basement annular brace supporting and protection structure according to claim 1, is characterized in that construction sequence comprises:
(1) enclosure wall construction;
Enclosure wall construction adopts template on an empty stomach, template sinks to stratum by the vertical exciting force of the vertical generation of reciprocating vibration of vibrating hammer on an empty stomach, slurries are filled immediately in empty stomach, when vibration dip mould promotes, slurries inject in slotted eye from template lower end under gravity, sink to the guide strip of template after the template first having sunk to stratum becomes, two pieces of templates present the effect that plate plate interlocks, and ensure that each veneer body is closely integrated into wall in a plane;
(2) support column construction;
Look like under support column without engineering pile, after temporary support pile of first constructing, support column is inserted temporary support pile; If there is engineering pile, directly support column is inserted temporary support pile;
(3) do one deck annular outer support, one deck circular inner support, concrete truss web member, one deck prop up and shore;
(4) cut the earth to absolute altitude position at the bottom of two layers of annular brace, do two layers of annular brace, enclosure wall, at two layers of support zone localized delamination concrete, welds reserved steel bar outside exposed main muscle, then concreting plate, finally do two layers and shore;
(5) 10cm below absolute altitude at the bottom of shoveling to basement bottom board, first does plain concrete cushion layer, then builds basement bottom board concrete;
(6) to two layers of annular brace, concrete slab, two layers to shore and carry out explosion, remove support column after explosion;
(7) two layers of basement roof are built;
(8) one deck annular outer support, one deck circular inner support, concrete truss web member, one deck are propped up to shore and carry out explosion;
(9) one deck basement roof is built.
3. basement annular brace supporting and protection structure according to claim 1, it is characterized in that one deck props up care-supporting and stretches into revetment inside, grain bin, formed with grain bin revetment and be rigidly connected, two layers care-supportings are welded with the reserved steel bar outside enclosure wall, form articulated structure.
4. basement annular brace supporting and protection structure according to claim 1, is characterized in that enclosure wall not only will carry out bank protection, and also will prevent infiltration, enclosure wall doubles as outer wall of basement.
5. basement annular brace supporting and protection structure according to claim 1, is characterized in that enclosure wall construction technology comprises:
1) preformed groove is excavated;
2) prebored hole;
In the junction prebored hole of two pieces of templates, prebored hole diameter is 90 ~ 110cm;
3) vibration dip mould;
Start vibration hammer, first piece of template sunk in stratum, reaches projected depth, then by second piece of template along construction axis first piece of front side with first piece of template tight side by side, with first piece of template for guide strip, sink to stratum and reach projected depth;
4) lifting first piece of template is poured into;
In first piece of template, pour into slurry, then limit lifting limit perfusion, until extract ground, slurry is stayed in slotted eye, after perfusion lifting terminates, slurry be kept to reach wall top design altitude;
5) template is sunk to again;
With second piece of template for guide strip, sink to stratum and reach projected depth, Reperfu-sion promotes second piece of template; Construct by above program cycle, can enclosure wall be completed.
6. basement annular brace supporting and protection structure according to claim 2, it is characterized in that when building basement bottom board construction, the position that water yield is large is adopted and dredges the stifled technical scheme combined, little for water yield, the position that water pressure is little adopts the method for shutoff by force, water smash plain concrete cushion layer time, with the casting and compacting of concrete mixing accelerating admixture in subrange, namely concrete solidifies at 1 ~ 2min; For the situation that water yield is large, with plastic flexible pipe water guide in sump, when cushion cap base plate waters and smash and reached 80% intensity, close sump again; The shutoff of sump is carried out as follows: water is concentrated in steel pipe, and diameter of steel tube is 50mm, and steel pipe inner wall has screw thread; Close water pipe with in spiral shell head precession steel pipe, build the concrete that base plate reserves hole; The inwall in reserved hole arranges groove for sealing, and rear pouring concrete mixes UEA expansion agent, guarantees the good combination of new-old concrete.
7. basement annular brace supporting and protection structure according to claim 2, it is characterized in that adopting static blasting, static blasting adopt the expansion force of expanding material more than 30MPa, static blasting reserving hole diameter is 30 ~ 40mm, reserving hole spacing is that 0.3 ~ 0.4m controls, reserving hole indwelling position, end is apart from structure floor 150mm ~ 200mm, and on member cross-sections, hole area is no more than section area 10%.In reserving hole, the main muscle of reinforced concrete member or stirrup cut off, and guarantee that the binding force of reinforcing bar does not affect demolition effect.
CN201510284234.8A 2015-05-22 2015-05-22 Basement annular brace supporting construction Active CN105019553B (en)

Priority Applications (4)

Application Number Priority Date Filing Date Title
CN201710189946.0A CN106894420B (en) 2015-05-22 2015-05-22 Basement construction method for supporting
CN201710189849.1A CN106836240B (en) 2015-05-22 2015-05-22 Basement annular brace construction method for supporting
CN201710189850.4A CN106958247B (en) 2015-05-22 2015-05-22 Basement annular brace support system
CN201510284234.8A CN105019553B (en) 2015-05-22 2015-05-22 Basement annular brace supporting construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510284234.8A CN105019553B (en) 2015-05-22 2015-05-22 Basement annular brace supporting construction

Related Child Applications (3)

Application Number Title Priority Date Filing Date
CN201710189946.0A Division CN106894420B (en) 2015-05-22 2015-05-22 Basement construction method for supporting
CN201710189850.4A Division CN106958247B (en) 2015-05-22 2015-05-22 Basement annular brace support system
CN201710189849.1A Division CN106836240B (en) 2015-05-22 2015-05-22 Basement annular brace construction method for supporting

Publications (2)

Publication Number Publication Date
CN105019553A true CN105019553A (en) 2015-11-04
CN105019553B CN105019553B (en) 2017-07-28

Family

ID=54409820

Family Applications (4)

Application Number Title Priority Date Filing Date
CN201510284234.8A Active CN105019553B (en) 2015-05-22 2015-05-22 Basement annular brace supporting construction
CN201710189849.1A Active CN106836240B (en) 2015-05-22 2015-05-22 Basement annular brace construction method for supporting
CN201710189850.4A Active CN106958247B (en) 2015-05-22 2015-05-22 Basement annular brace support system
CN201710189946.0A Active CN106894420B (en) 2015-05-22 2015-05-22 Basement construction method for supporting

Family Applications After (3)

Application Number Title Priority Date Filing Date
CN201710189849.1A Active CN106836240B (en) 2015-05-22 2015-05-22 Basement annular brace construction method for supporting
CN201710189850.4A Active CN106958247B (en) 2015-05-22 2015-05-22 Basement annular brace support system
CN201710189946.0A Active CN106894420B (en) 2015-05-22 2015-05-22 Basement construction method for supporting

Country Status (1)

Country Link
CN (4) CN105019553B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108442508A (en) * 2018-02-24 2018-08-24 广州大学 A kind of double confinement ring frame structure systems
CN109680722A (en) * 2019-01-24 2019-04-26 江苏南通三建集团股份有限公司 The construction method for setting external building access port is directly stayed on outer wall of basement body

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108867661B (en) * 2017-09-15 2020-10-09 叶长青 Foundation pit supporting construction method
CN108560582B (en) * 2018-04-09 2023-08-29 成都利拓重工机械有限公司 Movable support shield for urban pipe bag construction and limiting hinge thereof
CN108487261A (en) * 2018-04-10 2018-09-04 江西科技学院 A kind of arch steel structure support
CN113550329A (en) * 2021-09-03 2021-10-26 朱彦达 Multilayer basement supporting structure and supporting construction method

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09264024A (en) * 1996-03-29 1997-10-07 Kawasaki Steel Corp Retaining or coffering method
KR100412162B1 (en) * 2001-09-25 2003-12-24 (주)신성엔지니어링 Method of construction for excavating the ground by using trusstype support structures
EP1243702B1 (en) * 2001-03-13 2005-08-10 Spie Fondations Buttressing apparatus for an excavation shoring and use of the apparatus
CN201347558Y (en) * 2008-12-10 2009-11-18 广州市设计院 Ring-shaped bracing structure system of deep and large foundation pit
CN101666095A (en) * 2009-09-11 2010-03-10 朱奎 Irregular foundation pit support and construction method
CN102535478A (en) * 2011-12-30 2012-07-04 北京工业大学 Enclosing purlin comprising square steel pipe and light concrete for supporting foundation pit
CN102828520A (en) * 2012-09-11 2012-12-19 中煤科工集团武汉设计研究院中汉岩土工程分公司 Ring-shaped inner supporting structure used in deep peat soil deep foundation pit
CN203684233U (en) * 2013-12-27 2014-07-02 中铁大桥局集团第一工程有限公司 Circular support structure for deep foundation pit

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4865300B2 (en) * 2005-11-07 2012-02-01 株式会社ピーエス三菱 Semi-underground road construction method
CN201151909Y (en) * 2007-11-15 2008-11-19 王平 Deep foundation pit composite structure annular inner support
KR101036173B1 (en) * 2010-11-10 2011-05-23 영인산업 주식회사 Spherical supporting type land pressing apparatus
CN202416324U (en) * 2011-12-21 2012-09-05 上海建工一建集团有限公司 Beam and slab structure superposed through top-down beam and down-top slab construction of foundation pit project
CN103510524A (en) * 2012-06-26 2014-01-15 邹宗煊 Inclined circular annular pile and construction method thereof
CN203403422U (en) * 2013-06-06 2014-01-22 广西建工集团第五建筑工程有限责任公司 Long-span reinforced concrete inner support structure of rectangular deep foundation pit
CN103397777B (en) * 2013-08-06 2015-12-02 胡彦彬 A kind of attachment truss-like concrete wall template supports
CN104264688B (en) * 2014-10-22 2016-06-08 广州市城市规划勘测设计研究院 Manually digging hole non-uniform pile support construction process

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09264024A (en) * 1996-03-29 1997-10-07 Kawasaki Steel Corp Retaining or coffering method
EP1243702B1 (en) * 2001-03-13 2005-08-10 Spie Fondations Buttressing apparatus for an excavation shoring and use of the apparatus
KR100412162B1 (en) * 2001-09-25 2003-12-24 (주)신성엔지니어링 Method of construction for excavating the ground by using trusstype support structures
CN201347558Y (en) * 2008-12-10 2009-11-18 广州市设计院 Ring-shaped bracing structure system of deep and large foundation pit
CN101666095A (en) * 2009-09-11 2010-03-10 朱奎 Irregular foundation pit support and construction method
CN102535478A (en) * 2011-12-30 2012-07-04 北京工业大学 Enclosing purlin comprising square steel pipe and light concrete for supporting foundation pit
CN102828520A (en) * 2012-09-11 2012-12-19 中煤科工集团武汉设计研究院中汉岩土工程分公司 Ring-shaped inner supporting structure used in deep peat soil deep foundation pit
CN203684233U (en) * 2013-12-27 2014-07-02 中铁大桥局集团第一工程有限公司 Circular support structure for deep foundation pit

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108442508A (en) * 2018-02-24 2018-08-24 广州大学 A kind of double confinement ring frame structure systems
CN108442508B (en) * 2018-02-24 2023-07-14 广州大学 Double-constraint ring frame structure system
CN109680722A (en) * 2019-01-24 2019-04-26 江苏南通三建集团股份有限公司 The construction method for setting external building access port is directly stayed on outer wall of basement body

Also Published As

Publication number Publication date
CN106958247A (en) 2017-07-18
CN106958247B (en) 2018-11-09
CN105019553B (en) 2017-07-28
CN106836240A (en) 2017-06-13
CN106894420B (en) 2018-08-10
CN106894420A (en) 2017-06-27
CN106836240B (en) 2018-08-10

Similar Documents

Publication Publication Date Title
CN101614125B (en) Construction method of V-level surrounding rock tunnel
CN105019553A (en) Bracing structure for annular supports of basement
CN103982188B (en) The supporting structure system of rocky stratum big cross section deep shaft and construction method thereof
CN205742213U (en) Foundation pit supporting construction
CN108086343B (en) Cantilever type single-side wall body mixed reinforcement and replacement structure and construction method thereof
CN203879506U (en) Supporting structure system for large-section deep vertical shaft in rock stratum
CN105484763B (en) A kind of semiclosed reinforced concrete segment method for protecting support of deep coalmine
CN104929278A (en) Assembly type dense column hollow shear wall structure
CN101560766B (en) Grid-like underground continuous wall plate and production method thereof
CN106120803A (en) Base pit stand construction in the case of artesian water
CN108316328A (en) A kind of pressurization sinking device and its construction method for open caisson construction
CN203160254U (en) Pit support structure
CN108374663B (en) Twice-molding construction method for sandy gravel geological tunnel
CN104878763B (en) Main building basement supporting construction with annex
CN105569329A (en) Unilateral formwork support basement construction method and basement
CN205977233U (en) Tunnel lock foot spouts pilework soon
CN212642730U (en) Collapsible loess area tunnel passes people's air defense structure
CN107724423A (en) Crane beam on rock wall for underground power house present situation foundation reinforcing structure and its construction method
CN103821149A (en) Large-scale deep foundation pit slope remaining soil digging and pit-in-pit concrete post casting construction method
CN212270943U (en) Prefabricated assembled steel concrete combined supporting pile
CN208473890U (en) Tunnel bottom inverted arch constructing structure
CN207659988U (en) Crane beam on rock wall for underground power house present situation foundation reinforcing structure
CN207405615U (en) A kind of supporting construction of canal formula cutting cement soil continuous wall combination work shape prefabricated pile
CN105625435A (en) Fast forming method for multi-section and multi-layer special-shaped equipment deep foundation pit of marine accumulation island
CN217999598U (en) Joint stratum large-span tunnel pilot tunnel subsection step excavation supporting construction in advance

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP02 Change in the address of a patent holder
CP02 Change in the address of a patent holder

Address after: No. 16, Tongjiang Avenue, Chengguan Town, Nandan county, Hechi City, Guangxi Zhuang Autonomous Region

Patentee after: Zhu Kui

Address before: Ouhai District of Zhejiang city in Wenzhou province 325000 Rong Road No. 39

Patentee before: Zhu Kui

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20221216

Address after: 251221 Building A4, Collaborative Development Industrial Park, Dezhou High tech Zone, south of the west section of Tianchen Road, Yucheng National High tech Industrial Development Zone, Dezhou, Shandong

Patentee after: Dezhou Paier mechanical equipment Co.,Ltd.

Address before: No.16 Tongjiang Avenue, Chengguan Town, Nandan county, Hechi City, Guangxi Zhuang Autonomous Region 547200

Patentee before: Zhu Kui