CN104988900B - A kind of method of explosion drainage sunk well liquefied foundation - Google Patents

A kind of method of explosion drainage sunk well liquefied foundation Download PDF

Info

Publication number
CN104988900B
CN104988900B CN201510339413.7A CN201510339413A CN104988900B CN 104988900 B CN104988900 B CN 104988900B CN 201510339413 A CN201510339413 A CN 201510339413A CN 104988900 B CN104988900 B CN 104988900B
Authority
CN
China
Prior art keywords
liquefied foundation
explosive
liquefied
blast hole
foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510339413.7A
Other languages
Chinese (zh)
Other versions
CN104988900A (en
Inventor
张文龙
吴海清
水伟厚
梁志荣
李伟
魏欢
吴其泰
戴海峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANGHAI SHENYUAN GEOTECHNICAL ENGINEERING Co Ltd
Original Assignee
SHANGHAI SHENYUAN GEOTECHNICAL ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANGHAI SHENYUAN GEOTECHNICAL ENGINEERING Co Ltd filed Critical SHANGHAI SHENYUAN GEOTECHNICAL ENGINEERING Co Ltd
Priority to CN201510339413.7A priority Critical patent/CN104988900B/en
Publication of CN104988900A publication Critical patent/CN104988900A/en
Application granted granted Critical
Publication of CN104988900B publication Critical patent/CN104988900B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

The invention discloses a kind of method of explosion drainage sunk well liquefied foundation, this method comprises the following steps:Some vertical drainage plates through easy liquefaction soil layers of arranged for interval in pending liquefied foundation region, the embedding explosive in the easy liquefaction soil layers, the impulsive force ignited the explosive and produced using the explosive is rearranged the soil structures in the liquefied foundation, is squeezed the water out and is discharged by the drain bar.It is an advantage of the invention that 1)Process provides vertical drainage channel, the instant impact that blast is produced can accelerate the dissipation of pore water pressure, discharge the moisture of ground, reach and settle closely knit, the liquefied purpose of elimination rapidly;2)Speed of application is greatly improved, shortens construction period, for pile foundation processing liquefied foundation, with low cost, simple to operate, anti-liquefaction effect is good;3)It is applied widely, it is applicable for general liquefied foundation.

Description

A kind of method of explosion drainage sunk well liquefied foundation
Technical field
The invention belongs to foundation treatment technology field, and in particular to a kind of method of explosion drainage sunk well liquefied foundation.
Background technology
Earthquake is one of big threat for facing mankind, not only results in huge casualties, also results in substantial amounts of Building, road bridge tunnel, the deformation failure of underground utilities, to find out its cause, liquefaction is one of assignable cause.With in recent years Carry out the frequent of earthquake disaster, liquefaction of soil mass problem is increasingly paid attention to and studied.
Liquefied measure is resisted mainly to have:(1)Improve the grain structure of sand, improve the compactness and grain skeleton of the soil body Stability;(2)Improve the group structure of sand, conventional traditional treatment method is sand improvement, chemical grouting, pile foundation processing etc..
Substantially there are heavy-tamping method, broken stone pile method, soil-layer displacement method etc. currently used for the method for processing liquefied foundation.
Heavy-tamping method be by increase sand quite to compactness, reduce its liquefied possibility, this method easy construction, It is with low cost, but have the shortcomings that as follows:
(1)The crowd in-out effects and close to buildings of soil are had a certain impact, noise is big during construction, vibrations are big.
(2)It is not largely effective to the soil layer based on fine grained because fine grained soil infiltration coefficient is smaller, drainage channel not Freely space is caused to be difficult to compress.
(3)Influence depth is limited, can only achieve 10 meters or so.
Broken stone pile rule is to utilize pre- immersed tube pore-forming, is then filled out with medium coarse sand, is allowed to compacted liquefiable sandy soil, improves ground Bearing capacity, improves thixotropy condition.This method use is flexible, equipment is simple, economy, hypsography strong adaptability, but Ultra-clean pore water pressure is easily produced during soil compaction pile, is particularly carried out on the stratum of liquefiable sandy soil and weak soil symbiosis During operation, the phenomenon that it produces excess pore water pore pressure is quite obvious, the ultra-clean pore water pressure produced by soil compaction formation of pile When power exceedes saturation soil body ability to bear, a series of problems, such as soil body will produce disturbance, protuberance, sidesway, so as to cause lateral anti- Cut intensity reduction, traditional concrete-pile generally there are in construction pile body breaking, necking down, folder mud, evacuate, hang the quality such as pin lack Fall into, so that it is difficult to ensure the continuity and integrality of vertical drainage passage, this will have a strong impact on the consolidation effect of soil layer, causes Shock resistance is low.
Soil-layer displacement method is also a kind of conventional method of anti-liquefying treatment, and it is by a range of liquid under the bottom of foundation Change soil layer to cut out, change the non-liquefaction discrete material for the low compressibility for filling out other non-corrosive property, compaction in layers is used as ground holding force Layer.This method construction is simple, but has the disadvantage that:
(1)When easy liquidized layer buried depth is compared with depth or larger thickness, the method just loses the meaning used;
(2)Deep Foundation Excavation needs to solve many technical barriers, improves cost.
The content of the invention
According to the deficiencies of the prior art described above, It is an object of the present invention to provide a kind of explosion drainage sunk well liquefied foundation Method, this method is by pending liquefied foundation embedded set drain bar and explosive, the impulsive force produced using explosive charge, Soil structures are rearranged, squeezes the water out and is discharged by drain bar, the soil body is consolidated under Gravitative Loads, to eliminate ground base fluid Change.
The object of the invention is realized and completed by following technical scheme:
A kind of method of explosion drainage sunk well liquefied foundation, it is characterised in that methods described comprises the following steps:Waiting to locate Some vertical drainage plates through liquefaction soil layers of arranged for interval in liquefied foundation region are managed, it is embedding fried in the easy liquefaction soil layers Medicine, the impulsive force ignited the explosive and produced using the explosive is rearranged the soil structures in the liquefied foundation, Squeeze the water out and discharged by the drain bar.
Spacing between some rectangular uniform intervals arrangements of the drain bar, adjacent drainage channel plate is 1~2m.
The length of embedment of the drain bar is located at 1~2m below the easy liquefaction soil layers.
The embedding and igniting method of the explosive is:It is vertical in the pending liquefied foundation region to drill to pre- depthkeeping Degree forms blast hole, the explosive is put to the blast hole bottom, perfusion mortar is sealed in the blast hole afterwards; The explosive uses millisecond short delay blasting, and ignition order is ecto-entad.
Some blast holes are in quincuncial arrangement.
Dynamite charge amount is in each blast hole:
Wherein, Q is the dynamite charge amount in the single blast hole, and unit is Kg;
R is distance of the observation station to fried source, and unit is m;
K is the coefficient relevant with the calculating of blow-up point to landform, geological conditions;
α is the attenuation coefficient relevant with the calculating of blow-up point to landform, geological conditions.
It is an advantage of the invention that 1)Process provides vertical drainage channel, the instant impact that produces of exploding can be with Accelerate the dissipation of pore water pressure, discharge the moisture of ground, reach and settle closely knit, the liquefied purpose of elimination rapidly;2)Greatly improve Speed of application, shortens construction period, with low cost for pile foundation processing liquefied foundation, simple to operate, anti-liquefaction effect It is really good;3)It is applied widely, it is applicable for general liquefied foundation.
Brief description of the drawings
Fig. 1 is borehole blasting drainage sunk well liquefied foundation principle schematic of the present invention;
Fig. 2 is drain bar horizontal layout schematic diagram in the present invention;
Fig. 3 is explosive horizontal layout schematic diagram in the present invention.
Embodiment
The feature and other correlated characteristics of the present invention are described in further detail by embodiment below in conjunction with accompanying drawing, with It is easy to the understanding of technical staff of the same trade:
Mark 1-6 is respectively in such as Fig. 1-3, figure:Liquefied foundation 1, drain bar 2, explosive 3, easy liquefaction soil layers 4, blasting fuse 5th, blast hole 6.
Embodiment:The present embodiment is specifically related to a kind of method of explosion drainage sunk well liquefied foundation, and explosion resists liquefied original Reason is:(1)The instant impact that blast is produced can effectively extrude the moisture in sand, by being closely arranged in place Vertical drainage plate is rapid to discharge ground by pore water, reduces excess pore water pressure, controls the rise of excess pore water pressure; (2)Pinking effect causes the dissipation of pore pressure to may be such that soil nature obtains new enhancing and becomes more to consolidate;(3)What blast was produced rushes Power is hit, soil structures are rearranged, the soil body is consolidated under Gravitative Loads, is settled rapidly closely knit.
As Figure 1-3, the method for the present embodiment borehole blasting drainage sunk well liquefied foundation specifically includes following steps:
(1)Place is reconnoitred, the depth of clay distribution and easy liquefaction soil layers 4 is determined, determines that soil layer is joined by soil test Number, geological conditions;The spacing of arrangement drain bar 2 is determined according to soil parameters and geological conditions, and according to the depth of easy liquefaction soil layers 4 Spend the drain bar 2 that is prepared in advance, it is ensured that the length of drain bar 2 is enough to penetrate the depth of easy liquefaction soil layers 4;According to soil parameters, Geological conditions, the depth of easy liquefaction soil layers 4 determine the consumption of explosive 3;The consumption of explosive 3 is calculated by following formula and controlled:
Wherein, Q is the dynamite charge amount placed in single blast hole, and unit is Kg;
R is observation station to fried source(That is explosive)Distance, unit is m;
K is the coefficient relevant with the calculating of blow-up point to landform, geological conditions;
α is the attenuation coefficient relevant with the calculating of blow-up point to landform, geological conditions;
(2)Place is arranged, uniform intervals are laid some through easy liquefaction soil layers 4 in the pending region of liquefied foundation 1 Vertical drainage plate 2, each drain bar 2 is in rectangular arrangement as shown in Figure 2, and the spacing between adjacent drainage channel plate 2 is 1~2m, draining Depending on depth of the specific length of plate 2 according to pending easy liquefaction soil layers 4, generally it lays depth positioned at easy liquefaction soil layers 4 Position at 1~2m of lower section;Wherein, drain bar 2 is plastic draining belt, and permeability performance is good, can be for pending liquefaction Base 1 provides good vertical drainage passage, accelerates the dissipation of pore water pressure, maintains effective stress, significantly reduces liquefied possibility Property;
(3)Ground on the scene is arranged a few road gutters and is connected with each drain bar 2, after the water that drain bar 2 is discharged collects Discharge outside place, the several area sizes according to pending liquefied foundation 1 in road in gutter are determined;
(4)Vertical drilling construction is carried out up to easy liquefaction soil layers 4 in the pending region of liquefied foundation 1 by rig Centre position forms blast hole 6, and each blast hole 6 is in that the spacing between quincuncial arrangement as shown in Figure 3, adjacent blast hole 6 takes 15~20m(For general sand foundation);Explosive 3 is respectively put into the bottom hole of each blast hole 6, by the blasting fuse 5 of explosive 3 Exported through plastic flexible pipe to ground, perfusion mortar is sealed in each blast hole 6 afterwards, prevent the force of explosion of blast from concentrating on Drill hole, so as to reduce the liquefied effect of processing;
As the depth < 5m of easy liquefaction soil layers 4, and in the case that job site is narrow, preferably from shallow blasting, A diameter of 60~the 75mm of blast hole 6, in this case, will strictly control the consumption of explosive 3, prevent blasting impact power it is excessive so as to Soil layer is broken through, for such case, preloading processing can be carried out after explosive 3 and drain bar 2 is arranged in pending ground, Ignition charge 3 again, the effect of preloading has at 2 points, and one is accelerates the discharge of pore water, and two be that after in explosion, can accelerate the soil body Again consolidated compacting;
As easy liquefaction soil layers depth >=5m, during the larger situation of basement process area, deep hole blasting, blast hole can be used 75~130mm of diameter;
(5)To reduce the influence to ground using millisecond short delay blasting mode, the ignition order of explosive 3 is:First ignite and treat The explosive 3 in each blast hole 6 of the area periphery of liquefied foundation 1 is handled, the explosive 3 in middle blast hole 6 is ignited again afterwards;
(6)Impulsive force produced by being exploded by explosive 3, soil structures is rearranged, the soil body is consolidated under Gravitative Loads, Settle rapidly closely knit;In addition the instant impact produced by exploding effectively extrudes the moisture in sand, by being closely arranged in Pore water is discharged ground by the drain bar 2 in place rapidly, reduces excess pore water pressure, caused pore pressure is acted on by pinking Dissipate and soil nature is obtained new enhancing and is become more to consolidate.
The beneficial effect of the present embodiment is,(1)The vertical drain bar by setting, can accelerate disappearing for pore water pressure Dissipate, the moisture in discharge ground, reach and settle closely knit, the liquefied purpose of elimination rapidly;(2)Speed of application is greatly speeded up, is shortened Construction period, for pile foundation processing liquefied foundation, cost is more cheap, and simple to operate, and anti-liquefaction effect is more preferable.

Claims (4)

1. a kind of method of explosion drainage sunk well liquefied foundation, it is characterised in that methods described comprises the following steps:Reconnoitre place, Determine the depth of clay distribution and easy liquefaction soil layers;Arranged for interval is some through easily liquefaction in pending liquefied foundation region The vertical drainage plate of soil layer, vertically drill the spacing formed between blast hole, the adjacent blast hole in the liquefied foundation 15~20m is taken, the blast hole bottom is located in the easy liquefaction soil layers, in the embedding explosive in blast hole bottom, Zhi Hou Perfusion mortar is sealed in the blast hole, to prevent the force of explosion of blast from concentrating on drill hole, ignites the explosive and profit The impulsive force produced with the explosive rearranges the soil structures in the liquefied foundation, squeezes the water out and by the row Water plate is discharged;Wherein, dynamite charge amount is in each blast hole:
Wherein, Q is the dynamite charge amount in the single blast hole, and unit is Kg;
R is distance of the observation station to fried source, and unit is m;
V is the Safe vibration velocity of ground particle, and unit is m/s;
K is the coefficient relevant with the calculating of blow-up point to landform, geological conditions;
α is the attenuation coefficient relevant with the calculating of blow-up point to landform, geological conditions.
2. a kind of method of explosion drainage sunk well liquefied foundation according to claim 1, it is characterised in that some rows Spacing between the rectangular uniform intervals arrangement of water plate, adjacent drainage channel plate is 1~2m.
3. a kind of method of explosion drainage sunk well liquefied foundation according to claim 1, it is characterised in that the drain bar Length of embedment be located at 1~2m below the easy liquefaction soil layers.
4. the method for a kind of explosion drainage sunk well liquefied foundation according to claim 1, it is characterised in that some described Blast hole is in quincuncial arrangement.
CN201510339413.7A 2015-06-18 2015-06-18 A kind of method of explosion drainage sunk well liquefied foundation Active CN104988900B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510339413.7A CN104988900B (en) 2015-06-18 2015-06-18 A kind of method of explosion drainage sunk well liquefied foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510339413.7A CN104988900B (en) 2015-06-18 2015-06-18 A kind of method of explosion drainage sunk well liquefied foundation

Publications (2)

Publication Number Publication Date
CN104988900A CN104988900A (en) 2015-10-21
CN104988900B true CN104988900B (en) 2017-08-25

Family

ID=54300782

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510339413.7A Active CN104988900B (en) 2015-06-18 2015-06-18 A kind of method of explosion drainage sunk well liquefied foundation

Country Status (1)

Country Link
CN (1) CN104988900B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107129251B (en) * 2017-05-17 2020-06-05 中冶集团武汉勘察研究院有限公司 Curing agent for treating soft soil foundation by blasting drainage consolidation and treatment method
CN115262651B (en) * 2022-08-08 2023-11-07 上海建工集团股份有限公司 Underground diaphragm wall local self-collapsing type water stopping method

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5353109A (en) * 1976-10-25 1978-05-15 Chiyuuwa Kensetsu Kougiyou Kk Method of consolidating poor subsoil with explosion
US6003912A (en) * 1996-04-09 1999-12-21 Chrysler Corporation Bi-metal vehicle bumper structure
US5800090A (en) * 1996-04-09 1998-09-01 Geotechnics America, Inc. Apparatus and method for liquefaction remediation of liquefiable soils
CN1104533C (en) * 1998-05-28 2003-04-02 中国科学院力学研究所 Blast-tamping method for compacting underwater sand foundation
CN100374655C (en) * 2005-11-17 2008-03-12 中国矿业大学 Synchronous blast-enlarging treatment method for liquified soil foundation of highway
CN102635107B (en) * 2012-03-30 2014-12-03 连云港港口工程设计研究院有限公司 Surface-layer fast solidification method for soft foundation with dredger soil

Also Published As

Publication number Publication date
CN104988900A (en) 2015-10-21

Similar Documents

Publication Publication Date Title
Gao et al. Model test and numerical simulation research of water leakage in operating tunnels passing through intersecting faults
CN110359497B (en) High-performance gravel pile liquefaction-resistant treatment method for foundation of existing building
CN103487569B (en) Thick loose rock-soil layer bottom water injection sedimentation deformation analog device and method
CN106948340B (en) A kind of construction method of the Manual excavated pile structure of high polymer grouting protection
CN110029679B (en) Method for promoting graded landslide of landslide body by adopting active mode
CN1277995C (en) Draining and reinforcing treating method for soft soil foundation
CN102995622A (en) Casing draining end bearing pile for treating liquefied foundation and construction method
Wang et al. Grout diffusion characteristics during chemical grouting in a deep water-bearing sand layer
Jiang et al. New karst sinkhole formation mechanism discovered in a mine dewatering area in Hunan, China
CN104988900B (en) A kind of method of explosion drainage sunk well liquefied foundation
Fu et al. Practices in constructing high rockfill dams on thick overburden layers
Dai et al. The failure characteristics and evolution mechanism of the expansive soil trench slope
CN103938651B (en) The stake of Large stone porous concrete and treatment process of composite foundation thereof under water
CN106194185B (en) The lower thick aqueous soil layer sand control coal and rock pillar for safety of hydraulic pressure effect stays equipment, method
CN106049413B (en) A kind of composite power drain consolidation system and construction method applied to deep layer foundation in saturated soft soil
CN202644589U (en) Soft soil geology pre-stress tube pile static pressing anti-soil-squeezing structure
CN109139057B (en) Coal mining roadway floor water absorption bottom heave treatment method
CN205224009U (en) A blasting drainage system for handle liquefaction ground
CN203490213U (en) Water-injection settlement deformation simulation device for water-bearing stratum at bottom of thick and loose rock-soil bed
CN103122631A (en) Soft soil foundation preloading stamping reinforcement method
CN100374655C (en) Synchronous blast-enlarging treatment method for liquified soil foundation of highway
CN106049508B (en) A kind of swag type depression earth rock placement structure and construction method
CN106149631B (en) High mountain strid arch dam avalanche type Slope Treatment method
Wang et al. Three-dimensional fluid–solid coupling numerical simulation of effects of underlying karst cave on shield tunnel through sand stratum
CN107129251A (en) A kind of curing agent and processing method for explosion discharging consolidation soft soil foundation

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant