CN104912522A - 一种高应力区煤层气井合层排采装置及工艺 - Google Patents

一种高应力区煤层气井合层排采装置及工艺 Download PDF

Info

Publication number
CN104912522A
CN104912522A CN201510236023.7A CN201510236023A CN104912522A CN 104912522 A CN104912522 A CN 104912522A CN 201510236023 A CN201510236023 A CN 201510236023A CN 104912522 A CN104912522 A CN 104912522A
Authority
CN
China
Prior art keywords
mining
bed gas
pressure
gas well
coal bed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510236023.7A
Other languages
English (en)
Other versions
CN104912522B (zh
Inventor
周效志
桑树勋
金军
侯登才
侯丁根
黄华州
姜立君
王冉
刘世奇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Mining and Technology CUMT
Original Assignee
China University of Mining and Technology CUMT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Mining and Technology CUMT filed Critical China University of Mining and Technology CUMT
Priority to CN201510236023.7A priority Critical patent/CN104912522B/zh
Publication of CN104912522A publication Critical patent/CN104912522A/zh
Application granted granted Critical
Publication of CN104912522B publication Critical patent/CN104912522B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Financial Or Insurance-Related Operations Such As Payment And Settlement (AREA)

Abstract

本发明公开了一种高应力区煤层气井合层排采装置及工艺,该采排装置包括游梁式抽油机、井下排采管柱和监测控制系统;井下排采管柱包括设置在煤层气井生产套管内的油管、设置在油管内与游梁式抽油机连接的抽油杆以及与抽油杆底部依次连接的管式泵、尾管、压力计托筒、气锚、绕丝筛管、沉砂管和丝堵;监测控制系统包括设置在生产套管的采气管线上的套压表和针型阀、设置在油管的排水管线上的旋塞阀以及设置在压力计托筒内的双直读电子压力计;该排采工艺包含多个排采循环,每个循环划分为排水憋压、稳压增产、控压稳产、降压衰减四个阶段。本发明解决了高应力区合层排采条件下煤储层易伤害的难题,可显著延长煤层气井高产、稳产时间。

Description

一种高应力区煤层气井合层排采装置及工艺
技术领域
本发明属于煤层气地面开采技术领域,特别涉及一种高应力区煤层气井合层排采的装置及工艺。
背景技术
我国煤层气资源丰富,预测埋深2000m以浅煤层气地质资源量达36.8×1012m3,与常规天然气资源量相当。煤层气规模化开发能够缓解我国常规油气能源短缺形势,降低煤矿瓦斯事故发生几率,减少煤矿生产中温室气体排放量,可产生显著的经济、环境、安全及社会效益。
以滇东黔西为代表的我国西南地区煤层气资源丰富,资源开发潜力巨大。滇东黔西地处我国高应力区,煤储层压力、含气饱和度高,且区内上二叠统煤系煤层群发育,单煤层厚度小、煤层气资源丰度低。因此,进行合层开发是滇东黔西地区煤层气地面开发获得经济效益的前提。为了全面推进我国西南地区煤层气地面勘查开发工作,就需要解决高应力区煤层气井合层排采中煤储层易伤害,煤层气井难以长期高产、稳产的技术难题。
发明内容
本发明的目的是提供一种高应力区煤层气井合层排采装置及工艺,以解决现有技术中存在的高应力区煤储层敏感性强,合层排采过程中易受伤害,煤层气井难以长期高产、稳产的问题。
为实现上述目的,本发明采用以下技术方案:
一种高应力区煤层气井合层排采装置,包括游梁式抽油机、井下排采管柱和监测控制系统;
所述游梁式抽油机设置在地面;
所述井下排采管柱包括设置在煤层气井生产套管内的油管、设置在油管内与游梁式抽油机连接的抽油杆以及与抽油杆底部依次连接的管式泵、尾管、压力计托筒、气锚、绕丝筛管、沉砂管和丝堵;
所述监测控制系统包括设置在生产套管的采气管线上的套压表和针型阀、设置在油管的排水管线上的旋塞阀以及设置在压力计托筒内的双直读电子压力计,双直读电子压力计通过电缆与设置于地面的温压显示仪连接。
进一步的,所述沉砂管的长度为15m-20m,绕丝筛管的长度为3m-5m,尾管的长度为20m-25m。
进一步的,所述绕丝筛管底端位于最下部开发煤层的顶面之上2m。
一种高应力区煤层气井合层排采工艺,该排采工艺包含多个排采循环,每个排采循环划分为排水憋压、稳压增产、控压稳产、降压衰减四个阶段。
在第一排采循环的排水憋压阶段,关闭井口的针型阀,煤层气井排水量控制在2m3/d-4m3/d,当套压上升至1.4MPa-1.6MPa时,进入稳压增产阶段;在稳压增产阶段,日排水量增大至4m3/d-8m3/d,使环空液面逐渐下降,通过调节针型阀维持套压稳定,当煤层气井日产气量增加至2000m3/d时,进入控压稳产阶段;在控压稳产阶段,保持套压及日产气量稳定,环空液面降幅控制在1.5m/d-2.5m/d,当环空液面降至最上部开发煤层顶板位置时,进入降压衰减阶段;在降压衰减阶段,以0.01MPa/d-0.03MPa/d的速度缓慢降低套压,控制环空液面在最上部开发煤层之上10m-20m,使煤层气井日产气量缓慢下降;当套压下降至0.4MPa时,进入第二排采循环;
在第二排采循环的排水憋压阶段,通过增大日排水量使环空液面缓慢降至最上部开发煤层之下,且高于第二开发煤层,并使套压逐渐升高至1.2MPa;随后,开展第二排采循环后续的稳压增产、控压稳产、降压衰减阶段作业;当套压再次下降至0.4MPa时,进入第三排采循环;以此类推,直到环空液面降至最下部开发煤层顶板位置。
本发明的有益效果是:与当前煤层气井合层排采装置及工艺相比,采用本发明的装置及工艺,可尽可能避免高应力条件下煤层气井合层排采所产生的储层伤害,显著延长煤层气井高产、稳产时间,使煤层气地面开发获得更好的经济、环境与社会效益。
附图说明
图1为本发明的高应力区煤层气井合层排采装置示意图。
图中:1-游梁式抽油机;2-丝堵;3-沉砂管;4-绕丝筛管;5-气锚;6-压力计托筒;7-尾管;8-管式泵;9-油管;10-抽油杆;11-套压表;12-针型阀;13-旋塞阀;14-温压显示仪;15-电缆;16-双直读电子压力计;17-环空液面;18-最下部开发煤层;19-最上部开发煤层;20-第二开发煤层;21-生产套管;22-采气管线;23-排水管线。
具体实施方式
下面结合附图和贵州省六盘水煤田某煤层气井为例对本发明作进一步的详细描述,但不限定本发明的实施范围。
在工区内选择地形、地质条件适宜的地面位置作为井场,施工煤层气直井或最大井斜小于35°的定向井。煤层气井具“二开结构”,一开钻径钻至基岩之下15m,下入外径J55钢级的表层套管并固井,固井水泥浆返至地面;二开钻径钻至最下部开发煤层18之下50m完钻,下入外径N80钢级的生产套管并固井,二开固井水泥浆返至最上部开发煤层19之上200m。
分层射孔、压裂工作结束后,缓慢放溢流至井口压力为零,地面连接并安装高应力区煤层气井合层排采装置。高应力区煤层气井合层排采装置包括游梁式抽油机1、井下排采管柱、监测控制系统。游梁式抽油机1设置在地面;井下排采管柱包括设置在煤层气井生产套管21内的油管9、设置在油管9内与游梁式抽油机1连接的抽油杆10以及与抽油杆10底部依次连接的管式泵8、尾管7、压力计托筒6、气锚5、绕丝筛管4、沉砂管3和丝堵2;测控制系统包括设置在生产套管21的采气管线22上的套压表11和针型阀12、设置在油管9的排水管线23上的旋塞阀13以及设置在压力计托筒6内的双直读电子压力计16,双直读电子压力计16通过电缆15与设置于地面的温压显示仪14连接,井下温度、压力数据通过电缆15传输至温压显示仪14。
井下排采管柱中,沉砂管3的长度为18m,绕丝筛管的4长度为4m,尾管7的长度为21m。
井下排采管柱入井作业时,绕丝筛管4底端位于最下部开发煤层18的顶面之上2m。
下入井下排采管柱后,地面安装采气井口、气水管线、套力表11、针型阀12、旋塞阀13等。
在第一排采循环的排水憋压阶段,关闭井口的针型阀12,煤层气井排水量控制在2m3/d-4m3/d,当套压上升至1.4MPa-1.6MPa时,进入稳压增产阶段;在稳压增产阶段,日排水量增大至4m3/d-8m3/d,使环空液面17逐渐下降,通过及时调节针型阀12维持套压稳定,当煤层气井日产气量增加至2000m3/d时,进入控压稳产阶段;在控压稳产阶段,保持套压及日产气量稳定,环空液面17降幅控制在1.5m/d-2.5m/d,当环空液面17降至最上部开发煤层19顶板位置时,进入降压衰减阶段;在降压衰减阶段,以0.01MPa/d-0.03MPa/d的速度缓慢降低套压,控制环空液面17在最上部开发煤层19之上10m-20m,使煤层气井日产气量缓慢下降;当套压下降至0.4MPa时,进入第二排采循环。本实施例中,在排水憋压阶段,煤层气井排水量控制在3m3/d左右,当套压上升至1.5MPa左右时,进入稳压增产阶段;在稳压增产阶段,日排水量增大至6m3/d左右,通过及时调节针型阀12维持套压稳定在1.5MPa左右;在控压稳产阶段,环空液面17降幅控制在2m/d左右;在降压衰减阶段,以0.02MPa/d左右的速度缓慢降低套压,控制环空液面17在最上部开发煤层19之上15m左右。
在第二排采循环的排水憋压阶段,通过增大日排水量使环空液面17缓慢降至最上部开发煤层19之下,且高于第二开发煤层20,并使套压逐渐升高至1.2MPa;随后,开展第二排采循环后续的稳压增产、控压稳产、降压衰减阶段作业。当套压再次下降至0.4MPa时,进入第三排采循环。以此类推,直到环空液面17降至最下部开发煤层18顶板位置。
以上所述仅是本发明的优选实施方式,应当指出:对于本技术领域的普通技术人员来说,在不脱离本发明原理的前提下,还可以做出若干改进和润饰,这些改进和润饰也应视为本发明的保护范围。

Claims (5)

1.一种高应力区煤层气井合层排采装置,其特征在于:包括游梁式抽油机(1)、井下排采管柱和监测控制系统;
所述游梁式抽油机(1)设置在地面;
所述井下排采管柱包括设置在煤层气井生产套管(21)内的油管(9)、设置在油管(9)内与游梁式抽油机(1)连接的抽油杆(10)以及与抽油杆(10)底部依次连接的管式泵(8)、尾管(7)、压力计托筒(6)、气锚(5)、绕丝筛管(4)、沉砂管(3)和丝堵(2);
所述监测控制系统包括设置在生产套管(21)的采气管线(22)上的套压表(11)和针型阀(12)、设置在油管(9)的排水管线(23)上的旋塞阀(13)以及设置在压力计托筒(6)内的双直读电子压力计(16),双直读电子压力计(16)通过电缆(15)与设置于地面的温压显示仪(14)连接。
2.如权利要求1所述的高应力区煤层气井合层排采装置,其特征在于:所述沉砂管(3)的长度为15m-20m,绕丝筛管的(4)长度为3m-5m,尾管(7)的长度为20m-25m。
3.如权利要求1或2所述的高应力区煤层气井合层排采装置,其特征在于:所述绕丝筛管(4)底端位于最下部开发煤层(18)的顶面之上2m。
4.一种高应力区煤层气井合层排采工艺,其特征在于:该排采工艺包含多个排采循环,每个排采循环划分为排水憋压、稳压增产、控压稳产、降压衰减四个阶段。
5.如权利要求4所述的高应力区煤层气井合层排采工艺,其特征在于:在第一排采循环的排水憋压阶段,关闭井口的针型阀(12),煤层气井排水量控制在2m3/d-4m3/d,当套压上升至1.4MPa-1.6MPa时,进入稳压增产阶段;在稳压增产阶段,日排水量增大至4m3/d-8m3/d,使环空液面(17)逐渐下降,通过调节针型阀(12)维持套压稳定,当煤层气井日产气量增加至2000m3/d时,进入控压稳产阶段;在控压稳产阶段,保持套压及日产气量稳定,环空液面(17)降幅控制在1.5m/d-2.5m/d,当环空液面(17)降至最上部开发煤层(19)顶板位置时,进入降压衰减阶段;在降压衰减阶段,以0.01MPa/d-0.03MPa/d的速度缓慢降低套压,控制环空液面(17)在最上部开发煤层(19)之上10m-20m,使煤层气井日产气量缓慢下降;当套压下降至0.4MPa时,进入第二排采循环;
在第二排采循环的排水憋压阶段,通过增大日排水量使环空液面(17)缓慢降至最上部开发煤层(19)之下,且高于第二开发煤层(20),并使套压逐渐升高至1.2MPa;随后,开展第二排采循环后续的稳压增产、控压稳产、降压衰减阶段作业;当套压再次下降至0.4MPa时,进入第三排采循环;以此类推,直到环空液面(17)降至最下部开发煤层(18)顶板位置。
CN201510236023.7A 2015-05-11 2015-05-11 一种高应力区煤层气井合层排采装置及工艺 Expired - Fee Related CN104912522B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510236023.7A CN104912522B (zh) 2015-05-11 2015-05-11 一种高应力区煤层气井合层排采装置及工艺

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510236023.7A CN104912522B (zh) 2015-05-11 2015-05-11 一种高应力区煤层气井合层排采装置及工艺

Publications (2)

Publication Number Publication Date
CN104912522A true CN104912522A (zh) 2015-09-16
CN104912522B CN104912522B (zh) 2017-06-23

Family

ID=54081915

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510236023.7A Expired - Fee Related CN104912522B (zh) 2015-05-11 2015-05-11 一种高应力区煤层气井合层排采装置及工艺

Country Status (1)

Country Link
CN (1) CN104912522B (zh)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105332676A (zh) * 2015-12-02 2016-02-17 中国矿业大学 合层开发煤层气井上部产层暴露的排采控制方法及装置
CN106988707A (zh) * 2017-04-10 2017-07-28 中煤科工集团西安研究院有限公司 双煤层四通道封隔器分层控压联合排采装置及方法
CN106996282A (zh) * 2017-06-08 2017-08-01 成都北方石油勘探开发技术有限公司 气顶圈闭的复合型完井方法
CN107067867A (zh) * 2017-06-01 2017-08-18 晋城职业技术学院 一种煤层气排采职业考核模拟系统及方法
CN108071376A (zh) * 2016-11-17 2018-05-25 中国石油天然气股份有限公司 一种煤层气井中的注采管柱
CN109458161A (zh) * 2018-10-24 2019-03-12 中国矿业大学 一种多煤层独立含气系统控压单泵排采装置及排采方法
CN109519157A (zh) * 2018-09-29 2019-03-26 山西晋城无烟煤矿业集团有限责任公司 煤层气井井下加热增产工艺
CN112268833A (zh) * 2020-09-27 2021-01-26 周少玺 一种多功能瓦斯参数测试仪器及其使用方法
CN115707855A (zh) * 2021-08-19 2023-02-21 中国石油天然气股份有限公司 基于水力管式泵的排采控制方法、装置、设备和存储介质

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5033550A (en) * 1990-04-16 1991-07-23 Otis Engineering Corporation Well production method
CN201835799U (zh) * 2010-10-11 2011-05-18 常州凯锐自动化控制设备有限公司 基于物联网的煤层气井螺杆式排采系统
CN102434135A (zh) * 2011-12-02 2012-05-02 河南理工大学 多煤层发育区合层排采设备
CN102493788A (zh) * 2011-12-15 2012-06-13 中国石油天然气股份有限公司 高煤阶煤层气井排水采气的方法
CN103527148A (zh) * 2013-09-26 2014-01-22 中煤科工集团西安研究院有限公司 一种双套管单泵分层控压合层排采技术及装置
CN204253909U (zh) * 2014-11-18 2015-04-08 王一兵 一种煤层气用线性套压调节阀

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5033550A (en) * 1990-04-16 1991-07-23 Otis Engineering Corporation Well production method
CN201835799U (zh) * 2010-10-11 2011-05-18 常州凯锐自动化控制设备有限公司 基于物联网的煤层气井螺杆式排采系统
CN102434135A (zh) * 2011-12-02 2012-05-02 河南理工大学 多煤层发育区合层排采设备
CN102493788A (zh) * 2011-12-15 2012-06-13 中国石油天然气股份有限公司 高煤阶煤层气井排水采气的方法
CN103527148A (zh) * 2013-09-26 2014-01-22 中煤科工集团西安研究院有限公司 一种双套管单泵分层控压合层排采技术及装置
CN204253909U (zh) * 2014-11-18 2015-04-08 王一兵 一种煤层气用线性套压调节阀

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
黄华州等: "多压裂层煤层气井合层排采工艺控制指标体系研究", 《2013年煤层气学术研讨会论文集》 *

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105332676A (zh) * 2015-12-02 2016-02-17 中国矿业大学 合层开发煤层气井上部产层暴露的排采控制方法及装置
CN105332676B (zh) * 2015-12-02 2018-01-16 中国矿业大学 合层开发煤层气井上部产层暴露的排采控制方法及装置
CN108071376A (zh) * 2016-11-17 2018-05-25 中国石油天然气股份有限公司 一种煤层气井中的注采管柱
CN106988707A (zh) * 2017-04-10 2017-07-28 中煤科工集团西安研究院有限公司 双煤层四通道封隔器分层控压联合排采装置及方法
CN106988707B (zh) * 2017-04-10 2019-12-17 中煤科工集团西安研究院有限公司 双煤层四通道封隔器分层控压联合排采装置及方法
CN107067867A (zh) * 2017-06-01 2017-08-18 晋城职业技术学院 一种煤层气排采职业考核模拟系统及方法
CN107067867B (zh) * 2017-06-01 2023-03-14 晋城职业技术学院 一种煤层气排采职业考核模拟系统及方法
CN106996282B (zh) * 2017-06-08 2019-06-18 成都北方石油勘探开发技术有限公司 气顶圈闭的复合型完井方法
CN106996282A (zh) * 2017-06-08 2017-08-01 成都北方石油勘探开发技术有限公司 气顶圈闭的复合型完井方法
CN109519157A (zh) * 2018-09-29 2019-03-26 山西晋城无烟煤矿业集团有限责任公司 煤层气井井下加热增产工艺
CN109458161A (zh) * 2018-10-24 2019-03-12 中国矿业大学 一种多煤层独立含气系统控压单泵排采装置及排采方法
CN112268833A (zh) * 2020-09-27 2021-01-26 周少玺 一种多功能瓦斯参数测试仪器及其使用方法
CN112268833B (zh) * 2020-09-27 2024-05-07 周少玺 一种多功能瓦斯参数测试仪器及其使用方法
CN115707855A (zh) * 2021-08-19 2023-02-21 中国石油天然气股份有限公司 基于水力管式泵的排采控制方法、装置、设备和存储介质

Also Published As

Publication number Publication date
CN104912522B (zh) 2017-06-23

Similar Documents

Publication Publication Date Title
CN104912522B (zh) 一种高应力区煤层气井合层排采装置及工艺
CN105332676B (zh) 合层开发煤层气井上部产层暴露的排采控制方法及装置
CN106285617B (zh) 天然气水平井完井方法
CN104533287B (zh) 一种钻鱼刺状多级分支水平井页岩气储层钻完井和增产系统
CN110397428B (zh) 一种直井与u型对接井联合开采煤层气的驱替煤层气增产方法
CN104533288B (zh) 一种钻鱼刺状多级分支水平井页岩气储层钻完井和增产的方法
CN102979498B (zh) 一种煤层气多分支水平井系统
CN107605451B (zh) 一种基于组合型射孔的阶梯排量压裂泵注方法
CN105952378A (zh) 一种树状结构井的钻完井和增产方法
CN104790918B (zh) 复杂地形条件下丛式井与水平井联合地面开采煤层气方法
CN107620581B (zh) 一井两用煤矿井筒检查孔的施工方法
CN106703880A (zh) 矿用高位离层水疏放的直通式导流泄水孔及其施工方法
CN104453803A (zh) 一种复合煤成气藏多层合采方法及结构
CN103603643A (zh) 一种煤层气u型井分段压裂开采技术
CN114135265B (zh) 一种海上油田低渗储层低成本高效改造工艺方法
CN106593393A (zh) 一种提高碎软油气储层渗透率的方法
CN102434192A (zh) 增加煤层致裂效果的装置及增加煤层致裂效果的方法
CN204238921U (zh) 一种复合煤成气藏多层合采结构
CN104234682B (zh) 一种适用于多、薄煤层的连续油管分层压裂方法
RU2612060C1 (ru) Способ разработки карбонатных сланцевых нефтяных отложений
CN105569602A (zh) 一种油井管外封窜的方法
RU2524703C1 (ru) Способ разработки мелких нефтяных залежей
CN114439428B (zh) 穿采空区群下组煤煤层气水平井强化抽采方法
CN201526309U (zh) 地下水文观测孔
CN208950558U (zh) 提高油藏次动层采收率的次动层采油管柱

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170623

Termination date: 20210511