CN104912003A - Construction method for strengthening track crane - Google Patents

Construction method for strengthening track crane Download PDF

Info

Publication number
CN104912003A
CN104912003A CN201510252170.3A CN201510252170A CN104912003A CN 104912003 A CN104912003 A CN 104912003A CN 201510252170 A CN201510252170 A CN 201510252170A CN 104912003 A CN104912003 A CN 104912003A
Authority
CN
China
Prior art keywords
crawler crane
track crane
crane
construction method
roadbed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510252170.3A
Other languages
Chinese (zh)
Inventor
寿建军
孙占利
陈勇锋
寿顶鹤
王建新
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHEJIANG BADA CONSTRUCTION GROUP CO Ltd
Original Assignee
ZHEJIANG BADA CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHEJIANG BADA CONSTRUCTION GROUP CO Ltd filed Critical ZHEJIANG BADA CONSTRUCTION GROUP CO Ltd
Priority to CN201510252170.3A priority Critical patent/CN104912003A/en
Publication of CN104912003A publication Critical patent/CN104912003A/en
Pending legal-status Critical Current

Links

Abstract

The invention provides a construction method for strengthening a track crane. The construction method comprises the following steps: firstly fitting up welding roadbed boxes in a workshop by using hot rolled section steel, then paving the roadbed boxes in place at a construction site through a vehicle crane, and finally assembling the track crane by using the vehicle crane; the step of paving the roadbed boxes comprises the following steps: firstly mounting a main engine of the track crane, then mounting tracks on two sides, mounting a balance weight block, mounting a rod, finally threading a steel rope and mounting a lifting hook. After the track crane is completed, the lifting operation can be officially started after an acceptance check is qualified, the track crane runs on the roadbed boxes during the lifting operation of the track crane, and the track crane can lift a roadbed box at the rear part of the track crane to the front part of the track crane, so that long-distance forward running operation is completed; according to the construction method for strengthening the track crane, the length of a roadbed box is at least larger than a distance between supports of a girder through paving the roadbed boxes, so that weight of the roadbed boxes and the weight of the track crane are applied to the supports of the girder; besides according to the track crane, the roadbed boxes can be paved on a running route of the track crane, so that the paving time is shortened, and the construction progress is accelerated.

Description

Crawler crane reinforced construction method
Technical field
The present invention relates to a kind of crawler crane field of operation, particularly a kind of crawler crane reinforced construction method.
Background technology
Because its weight is comparatively large during crawler crane construction of the prior art, easily damage ground, need to carry out iron plate laying to ground before construction, to increase load supporting ability of ground, cause construction speed slow, construction cost increases.Full use cannot be carried out to construction plant in existing crawler crane work progress in addition, affect construction speed.
Summary of the invention
The object of the invention is the deficiency in order to solve above-mentioned technology and a kind of beam column frame that crawler crane load can be directly delivered to bridge is provided, avoiding bridge floor to be subject to direct destruction, reduce the construction method of Deck Consolidation job area.
In order to achieve the above object, the crawler crane reinforced construction method designed by the present invention, crawler crane track route lays subgrade case, and the distance between length at least two construction plant crossbeams of described subgrade case or large beam support is equal.
Described subgrade case is made up of the main brace summer of both sides, and main brace summer is welded side by side by three i iron, and two main brace summers of both sides are connected by channel-section steel, and the centerline of channel-section steel is fixed by angle steel again.
The bottom at described main brace summer two ends is provided with padded steel plate.
In order to realize the long distance advance operation of crawler crane, first use hot-rolled steel section welding subgrade case in workshop, then hung by vapour at the construction field (site) and subgrade case laying is put in place, then vapour is used to hang assembling crawler crane, first crawler crane main frame is installed, deals with problems arising from an accident and both sides crawler belt is installed, then carry out the installation of counterweight, then carry out the installation of penholder, finally carry out the installation of cable wire threading and suspension hook; After crawler crane completes, formally can start lifting operation through checking and accepting, in crawler crane lifting operation, crawler crane is walked on subgrade case, and the subgrade case at its rear portion can be lifted into front portion by crawler crane, thus completes long distance advance operation.
The crawler crane reinforced construction method that the present invention obtains, it is by the laying of subgrade case, and the length of subgrade case equals the distance between at least two construction plant crossbeams or large beam support, the weight of subgrade case and crawler crane is made all to be applied on crossbeam or large beam support, crane can lay subgrade case on self passing line, can effectively reduce the laying time, construction speed is accelerated.Devise the simple subgrade case structure of structure simultaneously, only need to form main brace summer by simple three i iron as main material, then by channel-section steel and angle steel permanent position, subgrade case processing can be completed, reduce further construction cost and time.
Detailed description of the invention
The present invention is further described by the following embodiment.
Embodiment 1.
The crawler crane reinforced construction method that the present embodiment describes, crawler crane track route lays subgrade case, length and at least two construction plant crossbeams or the large beam support of described subgrade case, described subgrade case is made up of the main brace summer of both sides, main brace summer is welded side by side by three i iron, two main brace summers of both sides are connected by channel-section steel, and the centerline of channel-section steel is fixed by angle steel again, and the bottom at described main brace summer two ends is provided with padded steel plate.
In order to realize the long distance advance operation of crawler crane, first use hot-rolled steel section welding subgrade case in workshop, then hung by vapour at the construction field (site) and subgrade case laying is put in place, then vapour is used to hang assembling crawler crane, first crawler crane main frame is installed, then both sides crawler belt is installed, then carries out the installation of counterweight, then carry out the installation of armed lever, finally carry out the installation of cable wire threading and suspension hook; After crawler crane completes, formally can start lifting operation through checking and accepting, in crawler crane lifting operation, crawler crane is walked on subgrade case, and the subgrade case 1 at its rear portion can be lifted into front portion by crawler crane, thus completes long distance advance operation.

Claims (4)

1. a crawler crane reinforced construction method, is characterized in that laying subgrade case on crawler crane track route, and the length of described subgrade case is equal with at least two construction plant crossbeams or large beam support.
2. crawler crane reinforced construction method according to claim 1, it is characterized in that described subgrade case is made up of the main brace summer of both sides, main brace summer is welded side by side by three i iron, and two main brace summers of both sides are connected by channel-section steel, and the centerline of channel-section steel is fixed by angle steel again.
3. crawler crane reinforced construction method according to claim 2, is characterized in that the bottom at described main brace summer two ends is provided with padded steel plate.
4. crawler crane reinforced construction method according to claim 1, its feature first uses hot-rolled steel section welding subgrade case in workshop, then hung by vapour at the construction field (site) and subgrade case laying is put in place, then vapour is used to hang assembling crawler crane, first crawler crane main frame is installed, deals with problems arising from an accident and both sides crawler belt is installed, then carry out the installation of counterweight, then carry out the installation of penholder, finally carry out the installation of cable wire threading and suspension hook; After crawler crane completes, formally can start lifting operation through checking and accepting, in crawler crane lifting operation, crawler crane is walked on subgrade case, and the subgrade case at its rear portion can be lifted into front portion by crawler crane, thus completes long distance advance operation.
CN201510252170.3A 2015-05-19 2015-05-19 Construction method for strengthening track crane Pending CN104912003A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510252170.3A CN104912003A (en) 2015-05-19 2015-05-19 Construction method for strengthening track crane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510252170.3A CN104912003A (en) 2015-05-19 2015-05-19 Construction method for strengthening track crane

Publications (1)

Publication Number Publication Date
CN104912003A true CN104912003A (en) 2015-09-16

Family

ID=54081409

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510252170.3A Pending CN104912003A (en) 2015-05-19 2015-05-19 Construction method for strengthening track crane

Country Status (1)

Country Link
CN (1) CN104912003A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105401741A (en) * 2015-11-24 2016-03-16 中建钢构有限公司 Basement roof reinforcing and construction device and construction method thereof

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4488833A (en) * 1982-04-27 1984-12-18 Kaiser Aluminum & Chemical Corporation Rapidly deployed assault vehicle surfacing or trackway system
CN2839354Y (en) * 2005-10-20 2006-11-22 上海老港废弃物处置有限公司 The steel plate subgrade case
CN201801796U (en) * 2010-09-07 2011-04-20 中冶实久建设有限公司 Roadbed box of large-scale crawler engineering vehicle
CN102020208A (en) * 2010-11-26 2011-04-20 大连益利亚工程机械有限公司 Novel arm support system for crawler crane
CN202610677U (en) * 2012-04-24 2012-12-19 天津二十冶建设有限公司 Auxiliary tool for soft soil earthwork construction
CN103046451A (en) * 2013-01-29 2013-04-17 中国核工业中原建设有限公司 Roadbed box for large crawler crane
CN203213637U (en) * 2013-03-28 2013-09-25 中国建筑第八工程局有限公司 Roadbed box for walking on floor of larger crawler crane
CN203270402U (en) * 2013-06-08 2013-11-06 马国胜 Road bed box
CN203878436U (en) * 2014-04-15 2014-10-15 天津三建建筑工程有限公司 Steel plate box road

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4488833A (en) * 1982-04-27 1984-12-18 Kaiser Aluminum & Chemical Corporation Rapidly deployed assault vehicle surfacing or trackway system
CN2839354Y (en) * 2005-10-20 2006-11-22 上海老港废弃物处置有限公司 The steel plate subgrade case
CN201801796U (en) * 2010-09-07 2011-04-20 中冶实久建设有限公司 Roadbed box of large-scale crawler engineering vehicle
CN102020208A (en) * 2010-11-26 2011-04-20 大连益利亚工程机械有限公司 Novel arm support system for crawler crane
CN202610677U (en) * 2012-04-24 2012-12-19 天津二十冶建设有限公司 Auxiliary tool for soft soil earthwork construction
CN103046451A (en) * 2013-01-29 2013-04-17 中国核工业中原建设有限公司 Roadbed box for large crawler crane
CN203213637U (en) * 2013-03-28 2013-09-25 中国建筑第八工程局有限公司 Roadbed box for walking on floor of larger crawler crane
CN203270402U (en) * 2013-06-08 2013-11-06 马国胜 Road bed box
CN203878436U (en) * 2014-04-15 2014-10-15 天津三建建筑工程有限公司 Steel plate box road

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
《1000MW超超临界火电机组施工技术丛书》编委会: "《起重运输机械》", 30 September 2012, 中国电力出版社 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105401741A (en) * 2015-11-24 2016-03-16 中建钢构有限公司 Basement roof reinforcing and construction device and construction method thereof

Similar Documents

Publication Publication Date Title
CN205078283U (en) Tunnel geotechnique's cloth, waterproof board shop cloth machine
CN104060844A (en) Sliding device and lifting device for truss frame of steel structural transfer floor of the high-rise building and construction method thereof
CN103010949B (en) Method for traveling and operating portal crane on large-angle slope
CN104060542B (en) Compound beam cable stayed bridge direction across bridge prestress application device and applying method thereof
CN105152032A (en) Installing method for bridge crane in enclosed environment workshop
CN104195948B (en) Bridge suspension pipe pushing installation construction method
CN104863374B (en) Large-span steel slipping mechanism and its gliding method
CN208995928U (en) A kind of multi-functional erection crane suitable for composite beam construction
CN203947421U (en) Compound beam cable stayed bridge direction across bridge prestress application device
CN205662832U (en) Under hold formula beiLei beam steel suspension bridge
CN102837705B (en) Traveling bogie in steel box
CN202879487U (en) Transfer carriage in steel box
CN107059656A (en) Active service bridge maintenance repairs the construction method of boat scaffold operating platform
CN103938508B (en) A kind of track-laying machine complete machine long-distance transport handling method
CN108797339A (en) A kind of safe construction method of cast-in-situ steel reinforced concrete anticollision barrier
CN108625270A (en) Nose girder gantry crane installs bridge prefabrication box girder construction method
CN104912003A (en) Construction method for strengthening track crane
CN106809725A (en) The bottom trolley structure that a kind of large-sized gantry hangs
CN209065230U (en) A kind of towed vertical transferring apparatus system
CN104372746B (en) The prefabricated post stretching Simple T-Girders note concrete form support of railroad bridge and mounting process thereof
CN105421246A (en) Installation method of towing cable hanging baskets
CN103434992B (en) Bridge crane hydraulic push-type trolley carrying system
CN104164838A (en) Light combined type beam moving trolley
CN204959611U (en) A lifting device for highway construction bridge railing base template
CN104674669B (en) Beam car is transformed into the construction method of integration of transporting and building machine

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20150916

WD01 Invention patent application deemed withdrawn after publication