CN104899681A - Outburst-prevention dynamic management and analysis method and system - Google Patents

Outburst-prevention dynamic management and analysis method and system Download PDF

Info

Publication number
CN104899681A
CN104899681A CN201510249590.6A CN201510249590A CN104899681A CN 104899681 A CN104899681 A CN 104899681A CN 201510249590 A CN201510249590 A CN 201510249590A CN 104899681 A CN104899681 A CN 104899681A
Authority
CN
China
Prior art keywords
workplace
dispelling
protrusion
information
outburst
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510249590.6A
Other languages
Chinese (zh)
Other versions
CN104899681B (en
Inventor
赵旭生
张庆华
韩文骥
谈国文
刁勇
李明建
宁小亮
马国龙
崔俊飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCTEG Chongqing Research Institute Co Ltd
Original Assignee
CCTEG Chongqing Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCTEG Chongqing Research Institute Co Ltd filed Critical CCTEG Chongqing Research Institute Co Ltd
Priority to CN201510249590.6A priority Critical patent/CN104899681B/en
Publication of CN104899681A publication Critical patent/CN104899681A/en
Application granted granted Critical
Publication of CN104899681B publication Critical patent/CN104899681B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention relates to an outburst-prevention dynamic management and analysis method and system, and belongs to the field of coal mine safety. The method mainly comprises the following steps: 1) the dynamic acquisition and storage of outburst-prevention information: enabling the obtained working surface and outburst-prevention information to be collected in the system, and to be classified and stored; 2) the specific analysis and management: the specified analysis of each link of regional and local comprehensive outburst-prevention measures and the process control of outburst prevention according to the collected outburst-prevention information; 3) the integration and output of outburst-prevention information: the integration, visual display and output of the outburst-prevention information and analysis results. The method and system can provide technical means for the daily outburst-prevention standard, fine management and analysis, reduce the tedious workload of conventional manual processing and analysis, and avoid problems that the manual analysis is incomplete and not fine.

Description

Protrusion-dispelling dynamic management and analytical approach and system
Technical field
The invention belongs to field of coal mine safety, relate to a kind of protrusion-dispelling dynamic management and analytical approach and system.
Background technology
Coal and gas prominent (hereinafter referred to as " giving prominence to ") is a kind of extremely complicated dynamic phenomenon, and destructive power is strong, harmfulness is large, and a large amount of gas gushed out instantaneously may cause the secondary enlargement disaster accidents such as secondary gas explosion, gas asphyxiation.Outstanding accident causes huge economic loss and bad social influence to mine, becomes one of the principal element of restriction mine safety, High-efficient Production.China gives prominence to one of the most serious country of disaster in the world, projecting mine is many, distributional region is wide, outstanding accident is many, the number of casualties is many and along with the increase of the pit mining degree of depth and intensity, coal and gas prominent danger strengthens day by day, and the difficulty of outburst prevention work also increases gradually.So, relevant institutions standard and the management expectancy of the outstanding aspect of control are strict gradually, " control coal and gas prominent detailed rules and regulations " also upgrade to " control coal and gas prominent regulation ", define the outburst hazard prediction of a set of collection region, the inspection of region outburst prevention measures, region measure effect, area validation, and the prediction of workplace outburst hazard, the inspection of workplace outburst prevention measures, workplace measure effect, safety prevention measure in interior region and local " quaternity " comprehensive outburst control measure technical system, effectively control the generation of coal and gas prominent accident.
But due to various consciousness, management and technical elements reason, China still adopts Traditional Man pattern to protrusion-dispelling management, analysis, in daily protrusion-dispelling management with in implementation dynamics, there is protrusion-dispelling and manage not science, protrusion-dispelling execution many situations lack of standardization, in protrusion-dispelling information analysis, there is only heavy surface data result, do not carry out unilateral, the coarse analysis situation of concentrating statistics, detail analysis comprehensively, cause outstanding accident still often to occur so far.As can be seen here, improve Safety of Coal Mine Production level, the generation of containment colliery severe and great casualty, not simple is the problem of outburst prevention measures, protrusion-dispelling management and the not science analyzed, lack of standardization, not meticulously also occupies very large responsibility.Protrusion-dispelling managerial personnel carry out work with subjective consciousness and experience, the planning and implementation of the information work of Safety of Coal Mine Production lacks the tissue of competent authorities, coordination and support, and this traditional management mode and means can not adapt to Gas Disaster accident now complicated and changeable again.
In recent years, along with calculating and the infiltration of informationization technology, the concept of " digital mine " is also frequently mentioned, but really to implement in safety in production and what have effect is not too many, mostly rest on the data management to observation data, and scale is less.For mine control coal and gas prominent, how according to protrusion-dispelling technology and management expectancy, for current protrusion-dispelling technology and management aspect deficiency, determine the management of scientific and rational protrusion-dispelling and analytical technique, advanced computer technology is utilized to develop the protrusion-dispelling supervisory computer infosystem being applicable to Safety of Coal Mine Production, promote protrusion-dispelling management and science, the specification analyzed, become more meticulous level, becomes the task of top priority.
Summary of the invention
In view of this, the object of the present invention is to provide a kind of protrusion-dispelling dynamic management and analytical approach and system, automatic analysis and control are carried out to the specification of the information of workplace region and each link of Local synthesis outburst prevention measures, information, integration Management and the proceduring of whole protrusion-dispelling techniqueflow.
An object of the present invention is to provide protrusion-dispelling dynamic management and analytical approach, and two of object of the present invention is to provide protrusion-dispelling dynamic management and analytic system.
An object of the present invention is achieved through the following technical solutions:
Protrusion-dispelling dynamic management and analytical approach, the method comprises the following steps:
Step 1) protrusion-dispelling information dynamic collection and storage;
Described protrusion-dispelling information, comprise face gas geologic map, mining engineering plan or workplace design drawing, the workplace construction graphical information such as Dynamic Graph, workplace geology instructions, also comprise produce in execution area and Local synthesis outburst prevention measures process all constructions, detection, observation information and face advance information;
Step 2) carry out managing and analyze to protrusion-dispelling information; Specifically comprise: 2-1) index analysis of workplace region and Local synthesis outburst prevention measures and early warning; 2-2) outburst prevention measures construction effect is analyzed; 2-3) outburst prevention work process control;
Step 3) protrusion-dispelling information integerated and output.
Further, described step 2-1) index analysis of workplace region and Local synthesis outburst prevention measures and early warning specifically comprise:
2-1-1) the auxiliary prediction of region outburst hazard: according to the workplace place coal-bed gas geologic map, mining engineering plan, the workplace geology instructions information that obtain, in conjunction with gas and geological structure information in contiguous workplace construction, by regulation requirement and standard, outburst hazard auxiliary prediction is automatically carried out to this working face extraction region;
2-1-2) index safety analysis: according to the gas pumping information obtained and region measure effect checking information, whether analyzed area measure is up to standard, if below standard, be defined as outburst dangerous area, and remind around check point within the scope of radius 100m; Predict or workplace measure effect check borehole parameter and indexes information according to the area validation boring obtained or workplace, analyzed area checking or workplace prediction, workplace measure effect assay whether safety, if result does not reach regulation safety standard by analysis, give warning reminding.
2-1-3) index development trend early warning: the index variation tendency that comparative analysis area validation or workplace are predicted, continuous several history of workplace measure effect inspection circulate and amplitude, matching change curve, if the index of continuous several history circulation continues to increase to certain value or continuous a few cycle indicator maintenance higher (close to exceeding standard critical value), then carry out early warning prompting.
Further, described step 2-2) in the analysis of outburst prevention measures control effects comprise adopt that boring is taken out in advance, the region outburst prevention measures of exhaust method and workplace outburst prevention measures, according to patent of invention " mine outburst prevention measures effect analysis method " described method, automatic analysis.
Further, described step 2-3) in outburst prevention work process control comprise: 2-3-1) protrusion-dispelling construction process control; 2-3-2) workplace construction progress control; 2-3-3) coalbed gas geology exceptions area controls.
Further, described step 2-3-1) control of protrusion-dispelling construction process, specifically comprise the following steps:
A) the auxiliary prediction of region outburst hazard: outburst hazard auxiliary prediction is automatically carried out to working face extraction region;
B) region outburst prevention measures is analyzed: after monitoring, getting region measure drilling parameter, analyzed area outburst prevention measures control effects, if region outburst prevention measures control effects does not reach regulation control criterion, then give the alarm and remind ore deposit side, ore deposit side analyzes after supplementing boring again; If region outburst prevention measures control effects reaches regulation control criterion, then next step can be jumped to;
C) region measure effect check analysis: after monitoring, getting region measure effect checking information, whether analyzed area measure effect reaches regulation safety standard, if do not reach regulation safety standard, step b is jumped to after then supplementing region measure boring), or proceed gas pre-drainage and adopt repetition step c); If reach regulation safety standard, then next step can be jumped to;
D) area validation analysis: after monitoring, getting area validation drilling parameter and indication information, carry out area validation analysis, if area validation result reaches regulation safety standard, then jump to step h), also can jump to next step; If area validation result does not reach regulation safety standard, then jump to next step;
E) workplace outburst hazard forecast analysis: monitor, get workplace prediction drilling parameter and indication information after, carry out workplace forecast analysis, if workplace predicts the outcome reach regulation safety standard, then can jump to step h), or jump to next step; If workplace predicts the outcome do not reach regulation safety standard, jump to next step;
F) workplace outburst prevention measures is analyzed: after monitoring, getting workplace outburst prevention measures drilling parameter, analytical work face outburst prevention measures control effects, if control effects does not reach required standard, then give the alarm and remind ore deposit side, again analyze after supplementing measure boring on request; If control effects reaches required standard, then next step can be jumped to;
G) validity check of workplace outburst prevention measures is analyzed: after monitoring, getting workplace outburst prevention measures validity check drilling parameter and indication information, carry out the check analysis of workplace measure effect, if validity check is analyzed do not reach regulation safety standard, after then construction or supplementary measure are holed again, jump to step f), or after supplementing other measures, repeat step g); If the inspection of workplace measure effect reaches regulation safety standard, then next step can be entered;
H) construct after taking safety prevention measure: construct after taking safety prevention measure, and send out by construction progress control method, monitoring, control workplace construction speed.
Further, described 2-3-2) workplace construction progress control is specially: monitors this Local synthesis outburst prevention measures circulation inner working face and adds up construction speed, if accumulative construction speed exceedes this Local synthesis outburst prevention measures allow construction speed, then report to the police, remind and carry out area validation or workplace prediction next time; Monitoring epicycle regional complex outburst prevention measures inner working face adds up construction speed, if workplace construction allows boundary of works area border to the measure of epicycle region, then reports to the police, reminds the region outburst prevention measures of carrying out next round.
Further, described 2-3-3) coalbed gas geology exceptions area control be specially: according to workplace mining progress and locus, coalbed gas geology exceptions area, dynamic calculation workplace and coalbed gas geology exceptions area distance, if workplace is close to coalbed gas geology exceptions area, then carry out warning reminding; Described coalbed gas geology exceptions area specifically comprises ocurrence of coal seam exceptions area, soft layering is composed and deposited the various abnormal areas affecting coal and gas prominent such as exceptions area, outburst dangerous area, geological structural belt, area of stress concentration.
Further, the information of described protrusion-dispelling information integerated comprises: workplace and face gas geological information; Region and workplace measure drilling construction planimetric map; Region measure check borehole and test rating information; Area validation index change curve; Area validation, prediction boring, effect inspection drilling plane arrangenent diagram; Along the coal seam sketch map of aspect, tunnel; And draw protrusion-dispelling drawing.
Further, described protrusion-dispelling information exports and comprises special report, statistical form and curve, the displaying of structure tree formula procedure.
Two of object of the present invention is achieved through the following technical solutions:
Protrusion-dispelling dynamic management and analytic system, described system comprises WEB server, protrusion-dispelling dynamic management sends platform with analysis client, protrusion-dispelling information;
Described WEB server is used for protrusion-dispelling information analysis process and deposits protrusion-dispelling information database; Protrusion-dispelling information analysis pack processing contains information analysis and protrusion-dispelling process control module, for carrying out analysis and the outburst prevention work process control of protrusion-dispelling information;
Described protrusion-dispelling dynamic management is used for information acquisition, information inquiry and analysis to analysis client, exports relevant protrusion-dispelling information;
Described information sends platform, issues above-mentioned protrusion-dispelling information by website to user in LAN (Local Area Network); Danger and abnormal information is issued in time to main protrusion-dispelling personnel by note.
Beneficial effect of the present invention is: protrusion-dispelling dynamic management provided by the invention and analytical approach and system, main according to workplace comprehensive outburst control measure technical system and method, realize dynamic, information-based, automatic analysis and the management of protrusion-dispelling information, and the process control of overall protrusion-dispelling techniqueflow, can be daily protrusion-dispelling specification, precision management and analysis and technological means is provided, alleviate the tedious work amount of Traditional Man process, analysis, and can avoid manual analysis not comprehensively, the problem such as not meticulous, there is great economic benefit and social benefit.
Accompanying drawing explanation
In order to make the object, technical solutions and advantages of the present invention clearly, below in conjunction with accompanying drawing, the present invention is described in further detail, wherein:
Fig. 1 is the process flow diagram of the method for the invention;
Fig. 2 is protrusion-dispelling construction process control flow chart.
Embodiment
Below in conjunction with accompanying drawing, the preferred embodiments of the present invention are described in detail.
Protrusion-dispelling dynamic management provided by the invention and analytical approach, as shown in Figure 1, mainly comprise the following steps:
Step 1) protrusion-dispelling information Dynamic Acquisition and storage: for the workplace that will obtain and protrusion-dispelling information acquisition in protrusion-dispelling dynamic management and analytic system, and classified and stored.
Protrusion-dispelling information dynamic collection, described protrusion-dispelling information, comprise face gas geologic map, mining engineering plan or workplace design drawing, the workplace construction graphical information such as Dynamic Graph, workplace geology instructions, also comprise produce in execution area and Local synthesis outburst prevention measures process all constructions, detection, observation information and face advance information.Mainly through obtaining with under type:
(1) graphical information is directly uploaded in protrusion-dispelling dynamic management and analytic system by supvr, according to the actual update status of figure in workplace work progress, carries out renewal and uploads;
(2) according to mine protrusion-dispelling information management mode, customized development drilling parameter table, indication information table or prediction address list, gas pumping information table, face advance information table, performed and the timely typing of the condition of production according to actual protrusion-dispelling by mine protrusion-dispelling technician.
Protrusion-dispelling information stores, and utilizes SQL Server 2005 Express as data base management system (DBMS), sets up protrusion-dispelling information database, for storing all protrusion-dispelling information datas.
Step 2) make a concrete analysis of and management: according to the protrusion-dispelling information gathered, carry out the labor of region and each link of Local synthesis outburst prevention measures and the process control of outburst prevention work flow process.
Concrete analysis and management, comprise the index analysis to workplace region and Local synthesis outburst prevention measures and early warning, the analysis of outburst prevention measures construction effect and outburst prevention work process control.
2-1) index analysis and early warning
Index analysis and early warning, mainly carry out region aids prediction, and the inspection of analyzed area measure effect, area validation, workplace prediction, workplace measure effect inspection index security and developing state, mainly comprise following content:
2-1-1) the auxiliary prediction of region outburst hazard: according to the information such as coal seam, workplace place (or exploiting field) gas-geologic map, mining engineering plan, workplace geology instructions obtained, in conjunction with the information such as gas and tectonic structure in contiguous workplace construction, by regulation requirement and standard, outburst hazard auxiliary prediction is automatically carried out to this working face extraction region, formulates rational region for workplace and Local synthesis outburst prevention measures provides foundation.
2-1-2) index safety analysis: according to the gas pumping information obtained and region measure effect checking information, whether analyzed area measure is up to standard, if below standard, be defined as outburst dangerous area, and remind around check point within the scope of radius 100m; According to the area validation obtained (workplace prediction, the inspection of workplace measure effect) drilling parameter and indication information, analyzed area checking (workplace prediction, workplace measure effect inspection) result whether safety, if result does not reach regulation safety standard by analysis, give warning reminding.
Above-mentioned zone measure effect is up to standard, refers to that the ore deposit side required according to " coal mine gas drainage temporary provisions up to standard ", " control coal and gas prominent specify " investigates the gas pre-drainage rate determined and reaches minimum standard, gas remainder quantity or gas pressure and do not exceed critical value, there is not the dynamic phenomenons such as spray orifice, there is not outstanding omen etc.
Before the inspection of analyzed area measure effect, first whether analyzed area measure effect check point (boring) meets the requirements, comprise whether check point number and density in region to be tested meet the requirements, whether check point within the scope of construction area measure etc., if there is above-mentioned arbitrary situation, then think that range test point is invalid or not enough, carry out corresponding situation prompting.
Above-mentioned zone checking (workplace prediction, workplace measure effect inspection) analysis result safety, refers to require according to " control coal and gas prominent specify " or ore deposit side investigates that the area validation index determined does not exceed critical value, there is not dynamic phenomenon, there is not outstanding omen, soft point of thickness and ocurrence of coal seam change all in normal range etc.
Before carrying out area validation (workplace prediction, the inspection of workplace measure effect) and analyzing, first analyze boring and whether meet the requirements, comprise construction point position, construction point number, boring number, boring significant depth etc.
2-1-3) index development trend early warning: the index variation tendency that comparative analysis area validation or workplace are predicted, continuous several history of workplace measure effect inspection circulate and amplitude, matching change curve, if the index of continuous several history circulation continues to increase to certain value or continuous a few cycle indicator maintenance higher (close to exceeding standard critical value), then carry out early warning prompting.
2-2) outburst prevention measures control effects is analyzed
The analysis of outburst prevention measures control effects comprise adopt that boring is taken out in advance, the region outburst prevention measures of exhaust method and workplace outburst prevention measures, concrete grammar is as follows:
According to the measure drilling parameter obtained, whether reach required standard according to mine outburst prevention measures effect analysis method analysis measures control effects.If control effects is not up to standard, then report to the police, remind and take and treatment measures.
Whether can reach required standard by " mine outburst prevention measures effect analysis method " analysis measures control effects according to patent of invention.
Outburst prevention measures drilling parameter mainly comprises boring perforate height, position angle or drift angle, inclination angle and drillable length etc.
2-3) outburst prevention work process control
Outburst prevention work process control comprises the control of protrusion-dispelling construction process, workplace construction progress control and geological structure control, specific as follows:
2-3-1) protrusion-dispelling construction process controls: the comprehensive outburst control measure techniqueflow specified according to " control coal and gas prominent specifies ", each protrusion-dispelling links (shown in Fig. 2) such as series connection regional prediction, region outburst prevention measures, the inspection of region measure effect, area validation, workplace prediction, workplace outburst prevention measures, the inspection of workplace measure effect, monitor implementation status and the result of each link, link must be performed do not perform if monitored, then give to remind and limit and gather next link information, until collect this link information; If monitor certain link analysis result for dangerous or below standard alignment request, then require to take treatment measures or to construct next link by the step of regulation requirement, until through last area validation (or workplace prediction, the validity check of workplace outburst prevention measures) workplace without danger, collecting work face mining progress information or comprehensive outburst control Action Message next time can be allowed.Specific as follows:
A) the auxiliary prediction of region outburst hazard: outburst hazard auxiliary prediction is automatically carried out to working face extraction region;
B) region outburst prevention measures is analyzed: after monitoring, getting region measure drilling parameter, analyzed area outburst prevention measures control effects, if region outburst prevention measures control effects does not reach regulation control criterion, then give the alarm and remind ore deposit side, ore deposit side analyzes after supplementing boring again; If region outburst prevention measures control effects reaches regulation control criterion, then next step can be jumped to;
C) region measure effect check analysis: after monitoring, getting region measure effect checking information, whether analyzed area measure effect reaches regulation safety standard, if do not reach regulation safety standard, step b is jumped to after then supplementing region measure boring), or proceed gas pre-drainage and adopt repetition step c); If reach regulation safety standard, then next step can be jumped to;
D) area validation analysis: after monitoring, getting area validation drilling parameter and indication information, carry out area validation analysis, if area validation result reaches regulation safety standard, then jump to step h), also can jump to next step; If area validation result does not reach regulation safety standard, then jump to next step;
E) workplace outburst hazard forecast analysis: monitor, get workplace prediction drilling parameter and indication information after, carry out workplace forecast analysis, if workplace predicts the outcome reach regulation safety standard, then can jump to step h), or jump to next step; If workplace predicts the outcome do not reach regulation safety standard, jump to next step;
F) workplace outburst prevention measures is analyzed: after monitoring, getting workplace outburst prevention measures drilling parameter, analytical work face outburst prevention measures control effects, if control effects does not reach required standard, then give the alarm and remind ore deposit side, again analyze after supplementing measure boring on request; If control effects reaches required standard, then next step can be jumped to;
G) validity check of workplace outburst prevention measures is analyzed: after monitoring, getting workplace outburst prevention measures validity check drilling parameter and indication information, carry out the check analysis of workplace measure effect, if validity check is analyzed do not reach regulation safety standard, after then construction or supplementary measure are holed again, jump to step f), or after supplementing other measures, repeat step g); If the inspection of workplace measure effect reaches regulation safety standard, then next step can be entered;
H) construct after taking safety prevention measure: construct after taking safety prevention measure, and send out by construction progress control method, monitoring, control workplace construction speed.
2-3-2) monitor this Local synthesis outburst prevention measures circulation inner working face and add up construction speed, if accumulative construction speed exceedes this Local synthesis outburst prevention measures allow construction speed, then report to the police, remind and carry out area validation or workplace prediction next time; Monitoring epicycle regional complex outburst prevention measures inner working face adds up construction speed, if workplace construction allows boundary of works area border to the measure of epicycle region, then reports to the police, reminds the region outburst prevention measures of carrying out next round.
2-3-3) coalbed gas geology exceptions area controls: according to workplace mining progress and locus, coalbed gas geology exceptions area, dynamic calculation workplace and coalbed gas geology exceptions area distance, if workplace is close to coalbed gas geology exceptions area, then carry out warning reminding.Coalbed gas geology exceptions area specifically comprises ocurrence of coal seam exceptions area, soft layering is composed and deposited the various abnormal areas affecting coal and gas prominent such as exceptions area, outburst dangerous area, geological structural belt, area of stress concentration.
Step 3) protrusion-dispelling information integerated and output: carry out protrusion-dispelling information and analysis result integrated, show and export.
Protrusion-dispelling information integerated, main by all for workplace protrusion-dispelling information and construction speed information, temporally embody a concentrated reflection of on a figure with spatial relationship, i.e. the dynamic drawing of protrusion-dispelling, systematically, all sidedly, dynamically reflects outburst prevention measures implementation status and the information change situation of workplace.
Integrated protrusion-dispelling information comprises: 1. workplace and face gas geological information; 2. region and workplace measure drilling construction planimetric map (the boring different colours display of abnormal occurrence occurs); 3. region measure check borehole and test rating information; 4. area validation (workplace prediction, the inspection of workplace measure effect) index change curve; 5. area validation, prediction boring, effect inspection drilling plane arrangenent diagram; 6. along coal seam, aspect, tunnel (soft layering) sketch map.
The drafting of protrusion-dispelling drawing, preparing and the time order and function order of the protrusion-dispelling of stoping period and digging information and locus distribution according to obtaining workplace, automatically drawing, supplementing.First respectively workplace machine lane between the preparatory stage of drawing face, air way, cut the protrusion-dispelling drawing of eye, then drawing face back production protrusion-dispelling drawing, finally integrates, and forms complete workplace protrusion-dispelling drawing.
Protrusion-dispelling information display comprises:
(1) special report: according to mine protrusion-dispelling pattern, every periodic duty face prediction index, drilling parameter, construction schematic diagram (sectional drawing, planimetric map, elevation drawing) and three-dimensional plot, supplementary etc. are classified, with protrusion-dispelling account simple form formula centralized displaying, and be furnished with relevant departments, leader's signature and examination & approval hurdle, directly can print examination & approval, replace traditional artificial papery to make a report on the method for examination & approval.
(2) statistical form and curve: be divided into warning message statistical form and each protrusion-dispelling link main protrusion-dispelling Information Statistics table, all crucial general view information (time, place, workmen, boring number, Maximum Index, coalbed gas geology situation) of centralized displaying workplace warning message and each protrusion-dispelling link; Statistic curve presses time, the spatial sequence relation of index, automatic production target change curve table.
(3) structure tree formula procedure is shown: according to protrusion-dispelling basic procedure, system sorts out level and the belonging relation of the basic procedures such as region protrusion-dispelling circulation, local protrusion-dispelling circulation, according to construction location, time sequencing, show with structure tree form, click each node, system shows the protrusion-dispelling flow conditions of having constructed automatically, advises making outburst prevention work process management very clear by next step protrusion-dispelling process name etc. taked.
Protrusion-dispelling dynamic management provided by the invention and analytic system are mainly used in dynamic acquisition, manage coal and gas outburst prominent controlling information, realize above-mentioned protrusion-dispelling dynamic management and analysis.Mainly comprise WEB server, protrusion-dispelling dynamic management sends platform with analysis client, protrusion-dispelling information.
WEB server is used for protrusion-dispelling information analysis process and deposits protrusion-dispelling information database, ensures that protrusion-dispelling dynamic management and analytical approach are implemented.Protrusion-dispelling information analysis pack processing contains information analysis and protrusion-dispelling process control module, for carrying out analysis and the outburst prevention work process control of protrusion-dispelling information.
Protrusion-dispelling dynamic management is used for information acquisition, information inquiry and analysis to analysis client, exports relevant protrusion-dispelling information.Protrusion-dispelling information acquisition, the protrusion-dispelling information daily according to mine makes a report on pattern, develops the input of special protrusion-dispelling information list, form, makes user can not change the use habit of oneself, input various daily protrusion-dispelling information easily.
Information sends platform, issues above-mentioned protrusion-dispelling information, issue danger and abnormal information by note in time to main protrusion-dispelling personnel by website to user in LAN (Local Area Network).
What finally illustrate is, above preferred embodiment is only in order to illustrate technical scheme of the present invention and unrestricted, although by above preferred embodiment to invention has been detailed description, but those skilled in the art are to be understood that, various change can be made to it in the form and details, and not depart from claims of the present invention limited range.

Claims (10)

1. protrusion-dispelling dynamic management and analytical approach, is characterized in that: the method comprises the following steps:
Step 1) protrusion-dispelling information dynamic collection and storage;
Described protrusion-dispelling information, comprise the graphical information of face gas geologic map, mining engineering plan or workplace design drawing, workplace construction Dynamic Graph, workplace geology instructions, also comprise produce in execution area and Local synthesis outburst prevention measures process all constructions, detection, observation information and face advance information;
Step 2) carry out managing and analyze to protrusion-dispelling information; Specifically comprise: 2-1) index analysis of workplace region and Local synthesis outburst prevention measures and early warning; 2-2) outburst prevention measures construction effect is analyzed; 2-3) outburst prevention work process control;
Step 3) protrusion-dispelling information integerated and output.
2. protrusion-dispelling dynamic management according to claim 1 and analytical approach, is characterized in that: described step 2-1) index analysis of workplace region and Local synthesis outburst prevention measures and early warning specifically comprise:
2-1-1) the auxiliary prediction of region outburst hazard: according to the workplace place coal-bed gas geologic map, mining engineering plan, the workplace geology instructions information that obtain, in conjunction with gas and geological structure information in contiguous workplace construction, by regulation requirement and standard, outburst hazard auxiliary prediction is automatically carried out to this working face extraction region;
2-1-2) index safety analysis: according to the gas pumping information obtained and region measure effect checking information, whether analyzed area measure is up to standard, if below standard, be defined as outburst dangerous area, and remind around check point within the scope of radius 100m; According to obtain area validation or workplace prediction, workplace measure effect check borehole parameter and indexes information, analyzed area checking or workplace prediction, workplace measure effect assay whether safety, if result does not reach regulation safety standard by analysis, give warning reminding;
2-1-3) index development trend early warning: the index variation tendency that comparative analysis area validation or workplace are predicted, several history continuous of workplace measure effect inspection circulates and amplitude, matching change curve, if the index of several history circulation continuously continues to increase to certain value or continuous a few cycle indicator keeps higher, close to exceeding standard critical value, then carry out early warning prompting.
3. protrusion-dispelling dynamic management according to claim 1 and analytical approach, is characterized in that: described step 2-2) in the analysis of outburst prevention measures control effects comprise adopt that boring is taken out in advance, the region outburst prevention measures of exhaust method and workplace outburst prevention measures.
4. protrusion-dispelling dynamic management according to claim 1 and analytical approach, is characterized in that: described step 2-3) in outburst prevention work process control comprise: 2-3-1) protrusion-dispelling construction process control; 2-3-2) workplace construction progress control; 2-3-3) coalbed gas geology exceptions area controls.
5. protrusion-dispelling dynamic management according to claim 4 and analytical approach, is characterized in that: described step 2-3-1) control of protrusion-dispelling construction process, specifically comprise the following steps:
A) the auxiliary prediction of region outburst hazard: outburst hazard auxiliary prediction is automatically carried out to working face extraction region;
B) region outburst prevention measures is analyzed: after monitoring, getting region measure drilling parameter, analyzed area outburst prevention measures control effects, if region outburst prevention measures control effects does not reach regulation control criterion, then give the alarm and remind ore deposit side, ore deposit side analyzes after supplementing boring again; If region outburst prevention measures control effects reaches regulation control criterion, then next step can be jumped to;
C) region measure effect check analysis: after monitoring, getting region measure effect checking information, whether analyzed area measure effect reaches regulation safety standard, if do not reach regulation safety standard, step b is jumped to after then supplementing region measure boring), or proceed gas pre-drainage and adopt repetition step c); If reach regulation safety standard, then next step can be jumped to;
D) area validation analysis: after monitoring, getting area validation drilling parameter and indication information, carry out area validation analysis, if area validation result reaches regulation safety standard, then jump to step h), also can jump to next step; If area validation result does not reach regulation safety standard, then jump to next step;
E) workplace outburst hazard forecast analysis: monitor, get workplace prediction drilling parameter and indication information after, carry out workplace forecast analysis, if workplace predicts the outcome reach regulation safety standard, then can jump to step h), or jump to next step; If workplace predicts the outcome do not reach regulation safety standard, jump to next step;
F) workplace outburst prevention measures is analyzed: after monitoring, getting workplace outburst prevention measures drilling parameter, analytical work face outburst prevention measures control effects, if control effects does not reach required standard, then give the alarm and remind ore deposit side, again analyze after supplementing measure boring on request; If control effects reaches required standard, then next step can be jumped to;
G) validity check of workplace outburst prevention measures is analyzed: after monitoring, getting workplace outburst prevention measures validity check drilling parameter and indication information, carry out the check analysis of workplace measure effect, if validity check is analyzed do not reach regulation safety standard, after then construction or supplementary measure are holed again, jump to step f), or after supplementing other measures, repeat step g); If the inspection of workplace measure effect reaches regulation safety standard, then next step can be entered;
H) construct after taking safety prevention measure: construct after taking safety prevention measure, and send out by construction progress control method, monitoring, control workplace construction speed.
6. protrusion-dispelling dynamic management according to claim 4 and analytical approach, it is characterized in that: described 2-3-2) workplace construction progress control is specially: monitors this Local synthesis outburst prevention measures circulation inner working face and adds up construction speed, if accumulative construction speed exceedes this Local synthesis outburst prevention measures allow construction speed, then report to the police, remind and carry out area validation or workplace prediction next time; Monitoring epicycle regional complex outburst prevention measures inner working face adds up construction speed, if workplace construction allows boundary of works area border to the measure of epicycle region, then reports to the police, reminds the region outburst prevention measures of carrying out next round.
7. protrusion-dispelling dynamic management according to claim 4 and analytical approach, it is characterized in that: described 2-3-3) coalbed gas geology exceptions area control be specially: according to workplace mining progress and locus, coalbed gas geology exceptions area, dynamic calculation workplace and coalbed gas geology exceptions area distance, if workplace is close to coalbed gas geology exceptions area, then carry out warning reminding; Described coalbed gas geology exceptions area specifically comprises ocurrence of coal seam exceptions area, soft layering is composed and deposited the various abnormal areas affecting coal and gas prominent such as exceptions area, outburst dangerous area, geological structural belt, area of stress concentration.
8. protrusion-dispelling dynamic management according to claim 1 and analytical approach, is characterized in that: the information of described protrusion-dispelling information integerated comprises: workplace and face gas geological information; Region and workplace measure drilling construction planimetric map; Region measure check borehole and test rating information; Area validation index change curve; Area validation, prediction boring, effect inspection drilling plane arrangenent diagram; Along the coal seam sketch map of aspect, tunnel; And draw protrusion-dispelling drawing.
9. protrusion-dispelling dynamic management according to claim 1 and analytical approach, is characterized in that: described protrusion-dispelling information exports and comprises special report, statistical form and curve, the displaying of structure tree formula procedure.
10. protrusion-dispelling dynamic management and analytic system, is characterized in that: described system comprises WEB server, protrusion-dispelling dynamic management sends platform with analysis client, protrusion-dispelling information;
Described WEB server is used for protrusion-dispelling information analysis process and deposits protrusion-dispelling information database; Protrusion-dispelling information analysis pack processing contains protrusion-dispelling information analysis and outburst prevention work process control module, for carrying out analysis and the outburst prevention work process control of protrusion-dispelling information;
Described protrusion-dispelling dynamic management is used for information acquisition, information inquiry and analysis to analysis client, exports relevant protrusion-dispelling information;
Described information sends platform, issues above-mentioned protrusion-dispelling information by website to user in LAN (Local Area Network); Danger and abnormal information is issued in time to main protrusion-dispelling personnel by note.
CN201510249590.6A 2015-05-15 2015-05-15 The management of protrusion-dispelling dynamic and analysis method and system Active CN104899681B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510249590.6A CN104899681B (en) 2015-05-15 2015-05-15 The management of protrusion-dispelling dynamic and analysis method and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510249590.6A CN104899681B (en) 2015-05-15 2015-05-15 The management of protrusion-dispelling dynamic and analysis method and system

Publications (2)

Publication Number Publication Date
CN104899681A true CN104899681A (en) 2015-09-09
CN104899681B CN104899681B (en) 2018-11-23

Family

ID=54032334

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510249590.6A Active CN104899681B (en) 2015-05-15 2015-05-15 The management of protrusion-dispelling dynamic and analysis method and system

Country Status (1)

Country Link
CN (1) CN104899681B (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108182642A (en) * 2017-12-28 2018-06-19 中煤科工集团重庆研究院有限公司 Gas outburst parameter online management system and method
WO2018201714A1 (en) * 2017-05-02 2018-11-08 中国矿业大学 Accurate extraction method for coal mine gas
CN112324487A (en) * 2020-10-20 2021-02-05 中煤科工集团重庆研究院有限公司 Double-index evaluation method for outburst prevention effect of coal roadway strip
CN112446689A (en) * 2020-12-15 2021-03-05 中煤能源研究院有限责任公司 Method for managing and controlling implementation process of outburst prevention measure
CN112487542A (en) * 2020-12-17 2021-03-12 中煤能源研究院有限责任公司 Automatic drawing method, system and device for outburst prevention measure drilling graph and readable storage medium
CN113107581A (en) * 2021-05-12 2021-07-13 中煤科工集团重庆研究院有限公司 Method and system for managing and controlling whole extraction and drilling process based on mutual driving of graphs and data
CN116485189A (en) * 2023-06-21 2023-07-25 天津矿智科技有限公司 Coal mine outburst prevention project progress value calculation method, calculation system, terminal and medium
CN117172618A (en) * 2023-11-01 2023-12-05 天津矿智科技有限公司 Coal mine outburst prevention measure engineering quality early warning method, early warning system, equipment and medium

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2004086271A1 (en) * 2003-03-24 2004-10-07 Nissho Iwai Research Institute, Ltd. System for managing remover of freon substitution gas or freon gas
CN1715615A (en) * 2005-08-05 2006-01-04 郑州煤炭工业(集团)有限责任公司 Gas preventing and control navigation system for coal mine production mine
CN101550841A (en) * 2009-05-08 2009-10-07 煤炭科学研究总院重庆研究院 Coal and gas outburst hazard early warning system and early warning method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2004086271A1 (en) * 2003-03-24 2004-10-07 Nissho Iwai Research Institute, Ltd. System for managing remover of freon substitution gas or freon gas
CN1715615A (en) * 2005-08-05 2006-01-04 郑州煤炭工业(集团)有限责任公司 Gas preventing and control navigation system for coal mine production mine
CN101550841A (en) * 2009-05-08 2009-10-07 煤炭科学研究总院重庆研究院 Coal and gas outburst hazard early warning system and early warning method

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
韩文骥 等: "煤与瓦斯突出防治动态管理的信息化实现技术", 《万方数据 企业知识服务平台》 *
黄磊 等: "煤矿防突信息管理系统设计", 《西南大学学报(自然科学版)》 *

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2018201714A1 (en) * 2017-05-02 2018-11-08 中国矿业大学 Accurate extraction method for coal mine gas
US11060384B2 (en) 2017-05-02 2021-07-13 China University Of Mining And Technology Method for precisely extracting coal-mine gas
CN108182642A (en) * 2017-12-28 2018-06-19 中煤科工集团重庆研究院有限公司 Gas outburst parameter online management system and method
CN112324487A (en) * 2020-10-20 2021-02-05 中煤科工集团重庆研究院有限公司 Double-index evaluation method for outburst prevention effect of coal roadway strip
CN112446689A (en) * 2020-12-15 2021-03-05 中煤能源研究院有限责任公司 Method for managing and controlling implementation process of outburst prevention measure
CN112487542B (en) * 2020-12-17 2024-03-01 中煤能源研究院有限责任公司 Automatic drawing method, system and device for anti-burst measure borehole graph and readable storage medium
CN112487542A (en) * 2020-12-17 2021-03-12 中煤能源研究院有限责任公司 Automatic drawing method, system and device for outburst prevention measure drilling graph and readable storage medium
CN113107581A (en) * 2021-05-12 2021-07-13 中煤科工集团重庆研究院有限公司 Method and system for managing and controlling whole extraction and drilling process based on mutual driving of graphs and data
CN113107581B (en) * 2021-05-12 2022-06-10 中煤科工集团重庆研究院有限公司 Method and system for managing and controlling whole extraction and drilling process based on mutual driving of graphs and data
CN116485189A (en) * 2023-06-21 2023-07-25 天津矿智科技有限公司 Coal mine outburst prevention project progress value calculation method, calculation system, terminal and medium
CN116485189B (en) * 2023-06-21 2023-10-03 天津矿智科技有限公司 Coal mine outburst prevention project progress value calculation method, calculation system, terminal and medium
CN117172618A (en) * 2023-11-01 2023-12-05 天津矿智科技有限公司 Coal mine outburst prevention measure engineering quality early warning method, early warning system, equipment and medium
CN117172618B (en) * 2023-11-01 2024-02-23 天津矿智科技有限公司 Coal mine outburst prevention measure engineering quality early warning method, early warning system, equipment and medium

Also Published As

Publication number Publication date
CN104899681B (en) 2018-11-23

Similar Documents

Publication Publication Date Title
CN104899681A (en) Outburst-prevention dynamic management and analysis method and system
CN110147948B (en) Coal mine enterprise risk identification management and control platform and implementation method thereof
CN103233741B (en) Method for quantitatively evaluating surrounding rock stability of ultra-large underground cavern group in construction period
CN105678481B (en) A kind of pipeline health state evaluation method based on Random Forest model
CN101550841B (en) Coal and gas outburst hazard early warning system and early warning method
CN117152893B (en) Forest disaster prevention method and system
CN101726568A (en) Early-warning prediction method for water environment safety
CN102162370B (en) Mine safety management information system based on GIS
CN107144891A (en) The monitoring of water burst precursor information dash forward with merging early warning system and method in tunnel
CN103489036B (en) Emergency advance warning stress and strain model system and method based on blending space association analysis
Zhou et al. Development of a database exclusively for subway construction accidents and corresponding analyses
CN110121053A (en) A kind of video monitoring method of situ of drilling well risk stratification early warning
CN107861446A (en) A kind of monitoring system and its application method for protecting building
CN117172556B (en) Construction risk early warning method and system for bridge engineering
Zhou et al. A BIM-based identification and classification method of environmental risks in the design of Beijing subway
CN109740890A (en) A kind of influencing factors of quality correlation analysis
CN116542517B (en) Mine wisdom monitoring management system based on three-dimensional visualization
CN116151482B (en) Method, device, equipment and medium for predicting mining earthwork of open-pit mining area
CN108119121A (en) A kind of horizontal well refracturing potentiality well rapid screening method
CN108563746B (en) Mine gas geological dynamic mapping system and construction method thereof
Baghaei Naeini et al. Identification and categorization of hazards in the mining industry: A systematic review of the literature
CN107784376A (en) A kind of screening technique for prognostic reserves block
CN115630848B (en) Regional security state dynamic evaluation management and control method and system
Xusheng et al. Research on comprehensive early-warning technology of coal and gas outburst
Chen et al. Research on technical support SaaS platform of soil pollution control based on the whole process management

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant