CN104895094A - Automatic water level adjusting drainage anti-slide pile and construction method thereof - Google Patents

Automatic water level adjusting drainage anti-slide pile and construction method thereof Download PDF

Info

Publication number
CN104895094A
CN104895094A CN201510252389.3A CN201510252389A CN104895094A CN 104895094 A CN104895094 A CN 104895094A CN 201510252389 A CN201510252389 A CN 201510252389A CN 104895094 A CN104895094 A CN 104895094A
Authority
CN
China
Prior art keywords
water inlet
inlet pipe
pipe group
pile body
outlet pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510252389.3A
Other languages
Chinese (zh)
Other versions
CN104895094B (en
Inventor
邓华锋
肖志勇
李建林
孙旭曙
胡亚运
周美玲
胡安龙
李春波
常德龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Three Gorges University CTGU
Original Assignee
China Three Gorges University CTGU
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Three Gorges University CTGU filed Critical China Three Gorges University CTGU
Priority to CN201510252389.3A priority Critical patent/CN104895094B/en
Publication of CN104895094A publication Critical patent/CN104895094A/en
Application granted granted Critical
Publication of CN104895094B publication Critical patent/CN104895094B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

An automatic water level adjusting drainage anti-slide pile comprises a pile body. Concrete is poured into a steel reinforcement cage to form the pile body, the pile body comprises a concrete pile body and a rectangular hollow pile body arranged on the concrete pile body, an outer steel formwork encloses the outer side of the pile body, an inner steel formwork encloses the rectangular hollow pile body, a plurality of water inlet pipe groups are longitudinally and parallelly arranged on the upper portion of one side of a tension end of the rectangular hollow pile body, a plurality of adjusting water inlet pipe groups are longitudinally and parallelly arranged on the lower portion of one side of the tension end of the rectangular hollow pile body, a plurality of water outlet pipe groups are longitudinally and parallelly arranged on one side of the tension end of the rectangular hollow pile body, and the rectangular hollow pile body is provided with a punching device. The automatic water level adjusting drainage anti-slide pile and a construction method thereof can solve the problems that water level cannot be automatically adjusted, operations are difficult and manufacturing cost is high, rainfall can be realized in a peak shifting manner, the pressure of flowing water in slope soil is decreased, potential risks of landslide damage are reduced, and automation of drainage and water level adjustment is realized.

Description

A kind of draining antislide pile of automatic adjustment water level and construction method thereof
Technical field
The present invention relates to field of civil engineering, the draining antislide pile of the automatic adjustment water level that especially a kind of reservoir stability is reinforced and construction method thereof.
Background technology
As one of global three large geological disasters, the unstable failure of side slope often brings huge disaster to the mankind.Compared with coming down with mountain region, the accident of reservoir stability is too numerous to enumerate.According to incompletely statistics, in reservoir area of Three Gorges, the landslide with obviously distortion sign just reaches more than 1000.The deformation instability of this kind of side slope, often relevant with reservoir water level fluctuation.When storehouse water rapid drawdown, the whereabouts of slope underground water lag behind storehouse water disappear, in side slope, form flowing pressure and be unfavorable for the stable of slope body.As the measure of slope treatment, the advantages such as antislide pile is strong with its anti-slide performance, applicable elements is wide, construction safety is easy are used widely.Therefore, there are many scholars to carry out large quantifier elimination and improvement to antislide pile, propose more novel antislide pile.Wherein, also devise many draining antislide piles, but these and be not suitable for reservoir stability, and exist automatically can not regulate water level, operating difficulties, high cost problem.
Summary of the invention
Technical problem to be solved by this invention is to provide a kind of draining antislide pile and construction method thereof of automatic adjustment water level, solution must not can automatically regulate the problem that water level, operating difficulties, cost are high, to avoid the peak hour precipitation, reduce flowing pressure in slope soil, reduce the potential risk that landslide is destroyed, achieve the automation of draining and adjustment water level.
For solving the problems of the technologies described above, the technical solution adopted in the present invention is: a kind of draining antislide pile of automatic adjustment water level, comprises the pile body that filling concrete is formed on reinforcing cage,
Pile body is made up of concrete pile body and the rectangle hollow pile body be arranged in concrete pile body, outer steel mould plate is with outside pile body, rectangle hollow pile body is with interior steel form, the top, pull end side that is subject to of rectangle hollow pile body is longitudinally arranged with many group water inlet pipe groups in parallel, longitudinally being arranged with many groups in parallel by bottom, pull end side and regulating water inlet pipe group of rectangle hollow pile body, rectangle hollow pile body be longitudinally arranged with many group outlet pipe groups in parallel by pressure side side;
Water inlet pipe group is made up of the water inlet pipe of steel form and outer steel mould plate in the connection of multiple parallel horizontal positioned, water inlet pipe group is regulated to be made up of the adjustment water inlet pipe of steel form and outer steel mould plate in the connection of parallel horizontal positioned, the water outlet of each adjustment water inlet pipe group is provided with water inlet pipe port lid, water inlet pipe port lid upper end and interior steel form hinged, water inlet pipe port lid is connected with the boring device in the hollow body being installed on rectangle hollow pile body;
Outlet pipe group is made up of the outlet pipe of steel form and outer steel mould plate in multiple parallel connection, and being provided with in outlet pipe can only the outside unidirectional outlet pipe port lid opened.
The distance of the bottom distance slope sliding band of rectangle hollow pile body is 1 meter.
The quantity sum of water inlet pipe group and adjustment water inlet pipe group is less than the quantity of outlet pipe group, and the installation site of bottom outlet pipe group is higher than reservoir level lowest water level 1 ~ 3 meter.
In outlet pipe group, the oblique placement of the gradient of 3% ~ 6% pressed by each outlet pipe.
Reinforcing cage, outer steel mould plate, interior steel form, many group water inlet pipe groups, many groups regulate water inlet pipe group, many group outlet pipe groups and multiple shedding motion to form an entirety.
In boring device, montant one end is connected with buoyancy aid, the montant other end and the first cross bar and the second cross bar hinged, the first cross bar and the second cross bar hinged, the water inlet pipe port lid of first cross bar one end and water inlet pipe group is hinged, second cross bar one end and interior steel form hinged.
The first hinged cross bar be provided with the two hinged shelves lids matched above the second cross bar.
Loaded filter has been filled before and after pile body.
A construction method for the draining antislide pile of automatic adjustment water level, the method comprises the following steps:
1) design water inlet pipe group, regulate water inlet pipe group and outlet pipe group: according to the distribution situation of underground water and the size of pile body, appropriate design water inlet pipe group, the size regulating water inlet pipe group and outlet pipe group, quantity and position;
2) make reinforcing cage, outer steel mould plate and interior steel form and form overall skeleton: under the prerequisite taking into account water pipe group, the size regulating water inlet pipe group and outlet pipe group, quantity and position, by pile body stressed configuration reinforcement cage, outer steel mould plate and interior steel form;
3) boring device is installed: in the cavity that steel form is formed in overall skeleton, according to design and installation boring device;
4) be installed into water pipe group, regulate water inlet pipe group and outlet pipe group: on overall skeleton, be installed into water pipe group, adjustment water inlet pipe group and outlet pipe group according to design, make the entirety that reinforcing cage, outer steel mould plate, interior steel form, many group water inlet pipe groups, many group adjustment water inlet pipe groups, many group outlet pipe groups and multiple shedding motion are formed;
5) by step 4) entirety made puts in the stake holes excavated, before and after overall, fill loaded filter;
It is 6) shaping to concreting in the entirety of having filled loaded filter,
Namely the draining antislide pile automatically regulating water level is made.
Step 4) in, according to the mode of manually digging hole, then need the reserved water inlet in relevant position and water outlet on steel form and interior steel form outside, aperture is slightly larger than the caliber of water inlet pipe, outlet pipe.
Step 5) in, loaded filter is that thickness is not less than 0.3m seepage material layer or non-fine concrete flaggy or geotextile layer.
Mentality of designing of the present invention is as follows:
With 2 meters × 1.5 meters × 20 meters, (stake sectional dimension is for long: 2 meters, wide 1.5 meters, stake is long is 20.0 meters) common antislide pile is example, design by least favorable situation, according to " Code for design of concrete structures " (GB 50010-2010), with symmetric reinforcement, under the detailing requiments prerequisite meeting concrete component, the hollow section that can obtain antislide pile is of a size of 1.1 meters × 1.2 meters, area is 1.32 square metres, volume is 26.4 cubic metres.The minimum bending bearing capacity of this hollow antislide pile is 17280 kilonewton meters, and minimum shear resistant capacity is 2,556 thousand newton.(minimum bending resistance is 27340 kilonewton meters to the solid antislide pile of contrast same size, minimum shear resistant capacity is 9,588 thousand newton), the bending resistance of hollow antislide pile, shear resistant capacity is by weakening to a certain extent, but the distance of the bottom of rectangle hollow pile body distance slope sliding band is 1 meter, therefore, the maximum shear resistance impact of the hollow part of antislide pile on reality is little, simultaneously, otherwise measure can be taked to improve the supporting capacity of hollow antislide pile, such as change sectional dimension, reinforcement manner, adopt combining structure etc., be equally applicable to the slope reinforcement under the same terms.
Therefore, then commonly use the quantity (general 8 ~ 20) of antislide pile according to slope reinforcement, cumulative volume can reach 211 cubic metres, this footpath fluid space very large for underground water provides, also for underground water storage provides very large space.Accordingly, the present invention is in conjunction with the actual conditions of reservoir stability, on the basis utilizing antislide pile cavity volume, design according to the thinking of draining after first filling water, before Drawdown of Reservoir Water Level, groundwater table first reduces to a certain extent, after Drawdown of Reservoir Water Level, antislide pile carries out draining again, thus realize avoiding the peak hour precipitation, reduce flowing pressure in slope soil, reduce the object of the potential danger on landslide.The present invention better can be applicable to reservoir stability, and it is simply effective, and achieves the automation of draining and adjustment water level.
The draining antislide pile of a kind of automatic adjustment water level provided by the invention and construction method thereof, its beneficial effect is as follows:
1, hollow cavity is formed by rectangular hollow section pile body, water inlet pipe group is set by pull end side and regulates water inlet pipe group at rectangular hollow section pile body, rectangular hollow section pile body set out water pipe group by pressure side side, water inlet pipe group is regulated to be connected with the boring device in hollow cavity, design according to the thinking of draining after first filling water, before Drawdown of Reservoir Water Level, groundwater table first reduces to a certain extent, after Drawdown of Reservoir Water Level, antislide pile carries out draining again, solution automatically can must not regulate water level, operating difficulties, the problem that cost is high, to avoid the peak hour precipitation, reduce flowing pressure in slope soil, reduce the potential danger on landslide, better can be applicable to reservoir stability, effectively simple, and achieve the automation of draining and adjustment water level, reach the object reduced due to the differential water pressures of the delayed generation of underground water when reservoir level declines fast.
2, the distance of the bottom distance slope sliding band of rectangle hollow pile body is 1 meter, and upper end, until pile body top, avoids the excessive situation of Lack of support that causes of shearing force near slope sliding band to occur.
3, the quantity sum of water inlet pipe group and adjustment water inlet pipe group is less than the quantity of outlet pipe group, and the installation site of bottom outlet pipe group can draining better higher than the design of reservoir level lowest water level 1 ~ 3 meter.
4, the design of boring device achieves the automatic adjustment of water level.
5, water inlet pipe group setting height(from bottom) below reservoir level peak level 1 ~ 3 meter, guarantees to inject pile body after slope underground water rises to certain altitude (close to water level peak height) inner; Meanwhile, meet with heavy rain effect when considering that high water level runs, within the scope of above high water mark 1 ~ 2 meter, be also provided with water inlet pipe, make full use of the effect of catchmenting of antislide pile.
Accompanying drawing explanation
Below in conjunction with drawings and Examples, the invention will be further described:
Fig. 1 is the structural representation of draining antislide pile of the present invention;
Fig. 2 is that the A-A of Fig. 1 of the present invention is to sectional view;
Fig. 3 is the schematic diagram that an outlet pipe of outlet pipe group in draining antislide pile of the present invention is arranged in rectangular hollow section pile body;
Fig. 4 is the half sectional view of an outlet pipe of outlet pipe group in draining antislide pile of the present invention;
Fig. 5 is the right view of the water inlet pipe port lid regulating the water outlet of water inlet pipe group to arrange in draining antislide pile of the present invention;
Fig. 6 is the left view of the water inlet pipe port lid regulating the water outlet of water inlet pipe group to arrange in draining antislide pile of the present invention;
Fig. 7 is the front view of the water inlet pipe port lid regulating the water outlet of water inlet pipe group to arrange in draining antislide pile of the present invention;
Fig. 8 is the right top view of the water inlet pipe port lid regulating the water outlet of water inlet pipe group to arrange in draining antislide pile of the present invention;
Fig. 9 is the structural representation of boring device of the present invention;
Figure 10 is the view of boring device water inlet pipe port lid of the present invention when opening;
Figure 11 is draining antislide pile drainage procedure schematic diagram of the present invention;
Figure 12 is the illustraton of model of (anhydrous in pile body) under the embodiment of the present invention four original state;
Figure 13 is the illustraton of model of the embodiment of the present invention 4 first cross bar when overlapping with water inlet pipe port lid.
Detailed description of the invention
Embodiment one
As Figure 1-Figure 8, a kind of draining antislide pile of automatic adjustment water level, comprises the pile body 1 that filling concrete is formed on reinforcing cage,
Pile body is made up of concrete pile body 1 and the rectangle hollow pile body 2 be arranged in concrete pile body 1, outer steel mould plate 3 is with outside pile body, rectangle hollow pile body 2 is with interior steel form 4, the top, pull end side that is subject to of rectangle hollow pile body 2 is longitudinally arranged with many group water inlet pipe groups 5 in parallel, longitudinally being arranged with many groups in parallel by bottom, pull end side and regulating water inlet pipe group 6 of rectangle hollow pile body 2, rectangle hollow pile body 2 be longitudinally arranged with many group outlet pipe groups 7 in parallel by pressure side side;
Water inlet pipe group 5 is made up of the water inlet pipe 5-1 of steel form 4 and outer steel mould plate 3 in the connection of multiple parallel horizontal positioned, water inlet pipe group 6 is regulated to be made up of the adjustment water inlet pipe 6-1 of steel form 4 and outer steel mould plate 3 in the connection of parallel horizontal positioned, the delivery port 6-2 place of each adjustment water inlet pipe group 6 is provided with water inlet pipe port lid 6-3, water inlet pipe port lid 6-3 upper end and interior steel form 4 hinged, water inlet pipe port lid 6-3 is connected with the boring device 8 in the hollow body being installed on rectangle hollow pile body 2;
Outlet pipe group 7 is made up of the outlet pipe 7-1 of steel form 4 and outer steel mould plate 3 in multiple parallel connection, is provided with outlet pipe port lid 7-2 in outlet pipe 7-1, and outlet pipe port lid 7-2 is added with a gear, makes it outwards unidirectionally open.
The distance of the bottom distance slope sliding band of rectangle hollow pile body 2 is 1 meter.
The size in water inlet pipe group 5, the quantity regulating water inlet pipe group 6 and outlet pipe group 7 to install, height and aperture is determined by the water yield of underground water and the height change of water level, the quantity sum of water inlet pipe group 5 and adjustment water inlet pipe group 6 is less than the quantity of outlet pipe group 7, and the installation site of bottom outlet pipe group 7 is higher than reservoir level lowest water level 1 ~ 3 meter.
In outlet pipe group 7, each outlet pipe 7-1 presses the oblique placement of the gradient of 3% ~ 6%, and preferred slope is 4%.
Water inlet pipe group 5, adjustment water inlet pipe group 6 and outlet pipe group 7 adopt stainless-steel pipe to make, and in order to prevent pipeline from getting clogged, water inlet pipe group 5, the import department of adjustment water inlet pipe group 6 and the exit of outlet pipe group 7 are provided with filter screen.
Water inlet pipe port lid 6-3 and outlet pipe port lid 7-2 adopts stainless steel material to make, and is provided with elastic tape, plays the effect of sealing in lid.
Reinforcing cage, outer steel mould plate 3, interior steel form 4, many group water inlet pipe groups 5, many groups regulate water inlet pipe group 6, many group outlet pipe groups and multiple shedding motion to form an entirety.
As shown in Figure 9, in boring device 8, montant 8-2 one end is connected with buoyancy aid 8-1, the montant 8-2 other end and the first cross bar 8-3 and the second cross bar 8-4 hinged, first cross bar 8-3 and the second cross bar 8-4 is hinged, the water inlet pipe port lid 6-3 of first cross bar 8-3 one end and water inlet pipe group 5 is hinged, second cross bar 8-4 one end and interior steel form 4 hinged.In drainage procedure, in stake, water level can change, and the open and close that boring device controls water inlet pipe port lid 6-3 also change thereupon, thus can realize the automatic adjustment of water level.
The first hinged cross bar 8-3 be provided with the two hinged shelves lid 8-5 matched above the second cross bar 8-4, its effect prevents the first cross bar 8-3 and the second cross bar 8-4 sagging deflections.
Loaded filter 11 (thickness is not less than the seepage material of 0.3 meter or goods non-fine concrete plate or geotextile) is filled before and after pile body.
Outer steel mould plate 3 and interior steel form 4 are corrugated steel template.
Embodiment two
A construction method for the draining antislide pile of automatic adjustment water level, the method comprises the following steps:
1) design water inlet pipe group 5, regulate water inlet pipe group 6 and outlet pipe group 7: according to the distribution situation of underground water and the size of pile body, appropriate design water inlet pipe group 5, the size regulating water inlet pipe group 6 and outlet pipe group 7, quantity and position;
2) make reinforcing cage, outer steel mould plate 3 and interior steel form 4 and form overall skeleton: under the prerequisite taking into account water pipe group 5, the size regulating water inlet pipe group 6 and outlet pipe group 7, quantity and position, by pile body stressed configuration reinforcement cage, outer steel mould plate 3 and interior steel form 4;
3) boring device 8 is installed: in the cavity that steel form 4 is formed in overall skeleton, according to design and installation boring device 8;
4) be installed into water pipe group 5, regulate water inlet pipe group 6 and outlet pipe group 7: according to designing perforate on overall skeleton and being installed into water pipe group 5, adjustment water inlet pipe group 6 and outlet pipe group 7, make reinforcing cage, outer steel mould plate 3, interior steel form 4, many group water inlet pipe groups 5, the entirety organized adjustment water inlet pipe group 6, many group outlet pipe groups and multiple shedding motion and formed more;
5) entirety that step 4 is made is put in the stake holes excavated, before and after overall, fill loaded filter 11;
It is 6) shaping to concreting in the entirety of having filled loaded filter 11,
Namely the draining antislide pile automatically regulating water level is made.
Step 4) in, according to the mode of manually digging hole, then need the reserved water inlet in relevant position and water outlet on steel form 3 and interior steel form 4 outside, aperture is slightly larger than the caliber of water inlet pipe, outlet pipe.
Step 5) in, loaded filter 11 is not less than 0.3m seepage material layer or non-fine concrete flaggy or geotextile layer for thickness.
Embodiment three
As shown in figure 11, the process adopting draining antislide pile of the present invention to carry out draining is as follows:
After antislide pile has been constructed, because the change of water level can form phreatic line 10 in slope body 9;
When reservoir level rises, groundwater table also rises the same period, each adjustment water inlet pipe group water inlet pipe port lid 6-3 closes because of the constraint by the first cross bar 8-3 and the second cross bar 8-4, after the height that water level reaches certain, water just can each water inlet pipe group 5 flows in the cavity of pile body from the top of rectangular hollow section pile body 2, the water level in pile body is made constantly to increase, the buoyancy aid 8-1 of boring device 8 can be subject to buoyancy and move up (as shown in Figure 10), then drive first cross bar 8-3 one end to tilt, open the delivery port 6-2 of each adjustment water inlet pipe group 6 of stake successively.Because the outlet pipe port lid 7-2 in the outlet pipe 7-1 of design can only unidirectionally open, water can only flow out in pile body, and like this, the part underflow after stake has entered in pile body, and water level can obtain reduction to a certain extent before Drawdown of Reservoir Water Level.
In the process of Drawdown of Reservoir Water Level, the water level in pile body is higher than the water level after stake, and the water in pile body will be discharged from outlet pipe 7-1, and the water level in pile body reduces, and the buoyancy causing boring device 8 to be subject to reduces, under deadweight, return to original position.Moving in circles with this, regulates the water inlet pipe port lid 6-3 open and close of water inlet pipe group 6 repeatedly to change, completes the draining of antislide pile, reach reduction water-head, reduce the object of flowing pressure in slope soil.
Embodiment four
In above-mentioned drainage procedure, can boring device 8 reach opens closed function, plays decisive role to whole design.
For this reason, verified by founding mathematical models, as shown in figure 12, under initial position (anhydrous in pile body), second cross bar 8-4 and the first cross bar 8-3 is level under deadweight, laterally props up water inlet pipe port lid 6-3, in order to avoid water inlet pipe port lid 6-3 is opened by the dynamic water after stake.When after the power (buoyancy) that Node B is subject to straight up, the second cross bar 8-4 can around center of circle O 1upwards rotate, and affect the first cross bar 8-3 to be upwards out of shape, the first cross bar 8-3 affects water inlet pipe port lid 6-3 around fixed point center of circle O again 2rotate up, be about to regulate the delivery port 6-2 aperture of water inlet pipe group 6 to open.
In addition, the influence of dynamic water formed by the differential water pressures inside and outside pile body, delivery port 6-2 can open in aperture further.Wherein, the trace moved between the second cross bar 8-4 and the first cross bar 8-3 reflects by following equation:
(sinα-0.05+0.05cosγ) 2+(2-cosα-0.05sinγ) 2=1
sinβ=sinα-0.05+0.05cosγ
In formula, α is the angle that the second cross bar 8-4 rotates; β is the angle that the first cross bar 8-3 is out of shape thereupon; γ is the angle that water inlet pipe port lid 6-3 rotates.The result calculated is as shown in table 1 below.(B, A represent the two-end-point of the first cross bar 8-3 in Figure 12,13)
Table 1 result of calculation statistical form
Can draw from upper table 1 final position that rod member moves, the final angle that the second cross bar 8-4 rotates up is 14.3490 °, and the final angle that the first cross bar 8-3 and water inlet pipe port lid 6-3 rotates thereupon is 10.8598 ° and 100.8598 °.Map accordingly, the first cross bar 8-3 can be obtained and finally overlap with water inlet pipe port lid 6-3, as shown in figure 13, center of circle O 2and the length between B ' is 1050mm, be the second cross bar 8-4, the first cross bar 8-3 and water inlet pipe port lid 6-3 radius sum.Behind this position, the motion of the first cross bar 8-3 makes boring device 8 move up by water inlet pipe port lid 6-3 retrains again.
In sum from the initial position of boring device 8 and the result of calculation of final position, boring device 8 can realize self-draining function.
In the present invention, the Thrust of Landslide side of bearing claiming pile body is after stake, otherwise for before stake.

Claims (10)

1. automatically regulate a draining antislide pile for water level, comprise the pile body (1) that filling concrete is formed on reinforcing cage, it is characterized in that:
Pile body is made up of concrete pile body (1) and the rectangle hollow pile body (2) be arranged in concrete pile body (1), outer steel mould plate (3) is with outside pile body, rectangle hollow pile body (2) is with interior steel form (4), the top, pull end side that is subject to of rectangle hollow pile body (2) is longitudinally arranged with many groups water inlet pipe group (5) in parallel, longitudinally being arranged with many groups in parallel by bottom, pull end side and regulating water inlet pipe group (6) of rectangle hollow pile body (2), rectangle hollow pile body (2) be longitudinally arranged with many groups outlet pipe group (7) in parallel by pressure side side;
Water inlet pipe group (5) is made up of the water inlet pipe (5-1) of steel form (4) and outer steel mould plate (3) in the connection of multiple parallel horizontal positioned, water inlet pipe group (6) is regulated to be made up of the adjustment water inlet pipe (6-1) of steel form (4) and outer steel mould plate (3) in the connection of parallel horizontal positioned, delivery port (6-2) place of each adjustment water inlet pipe group (6) is provided with water inlet pipe port lid (6-3), water inlet pipe port lid (6-3) upper end and interior steel form (4) hinged, water inlet pipe port lid (6-3) is connected with the boring device (8) in the hollow body being installed on rectangle hollow pile body (2),
Outlet pipe group (7) is made up of the outlet pipe (7-1) of steel form (4) and outer steel mould plate (3) in multiple parallel connection, and being provided with in outlet pipe (7-1) can only the outside unidirectional outlet pipe port lid (7-2) opened.
2. the draining antislide pile of a kind of automatic adjustment water level according to claim 1, is characterized in that: the distance of the bottom distance slope sliding band of rectangle hollow pile body (2) is 1 meter.
3. the draining antislide pile of a kind of automatic adjustment water level according to claim 1, it is characterized in that: the quantity sum of water inlet pipe group (5) and adjustment water inlet pipe group (6) is less than the quantity of outlet pipe group (7), and the installation site of bottom outlet pipe group (7) is higher than reservoir level lowest water level 1 ~ 3 meter.
4. the draining antislide pile of a kind of automatic adjustment water level according to claim 1, is characterized in that: in outlet pipe group (7), each outlet pipe (7-1) by 3% ~ 6% the oblique placement of the gradient.
5. the draining antislide pile of a kind of automatic adjustment water level according to claim 1, is characterized in that: reinforcing cage, outer steel mould plate (3), interior steel form (4), many groups water inlet pipe group (5), many groups regulate water inlet pipe group (6), many group outlet pipe groups and multiple shedding motion to form an entirety.
6. the draining antislide pile of a kind of automatic adjustment water level according to claim 1, it is characterized in that: in boring device (8), montant (8-2) one end is connected with buoyancy aid (8-1), montant (8-2) other end and the first cross bar (8-3) and the second cross bar (8-4) hinged, first cross bar (8-3) is hinged with the second cross bar (8-4), the water inlet pipe port lid (6-3) of the first cross bar (8-3) one end and water inlet pipe group (5) is hinged, the second cross bar (8-4) one end and interior steel form (4) hinged.
7. the draining antislide pile of a kind of automatic adjustment water level according to claim 6, is characterized in that: hinged the first cross bar (8-3) is provided with the second cross bar (8-4) top the two hinged shelves lids (8-5) matched.
8. the draining antislide pile of a kind of automatic adjustment water level according to claim 1, is characterized in that: filled loaded filter (11) before and after pile body.
9. automatically regulate a construction method for the draining antislide pile of water level, it is characterized in that the method comprises the following steps:
1) design water inlet pipe group (5), regulate water inlet pipe group (6) and outlet pipe group (7): according to the distribution situation of underground water and the size of pile body, appropriate design water inlet pipe group (5), the size regulating water inlet pipe group (6) and outlet pipe group (7), quantity and position;
2) make reinforcing cage, outer steel mould plate (3) and interior steel form (4) and form overall skeleton: under the prerequisite taking into account water pipe group (5), adjustment water inlet pipe group (6) and the size of outlet pipe group (7), quantity and position, by pile body stressed configuration reinforcement cage, outer steel mould plate (3) and interior steel form (4);
3) boring device (8) is installed: in the cavity that steel form (4) is formed in overall skeleton, according to design and installation boring device (8);
4) be installed into water pipe group (5), regulate water inlet pipe group (6) and outlet pipe group (7): on overall skeleton, be installed into water pipe group (5), adjustment water inlet pipe group (6) and outlet pipe group (7) according to design, make the entirety that reinforcing cage, outer steel mould plate (3), interior steel form (4), many groups water inlet pipe group (5), many groups adjustment water inlet pipe group (6), many group outlet pipe groups and multiple shedding motion are formed;
5) entirety that step 4) is made is put in the stake holes excavated, before and after overall, fill loaded filter (11);
It is 6) shaping to concreting in the entirety of having filled loaded filter (11),
Namely the draining antislide pile automatically regulating water level is made.
10. the construction method of the draining antislide pile of a kind of automatic adjustment water level according to claim 8, it is characterized in that: in step 4), according to the mode of manually digging hole, then need the reserved water inlet of steel form (3) and the upper relevant position of interior steel form (4) and water outlet outside, aperture is slightly larger than the caliber of water inlet pipe, outlet pipe.
CN201510252389.3A 2015-05-18 2015-05-18 A kind of draining friction pile being automatically adjusted water level and construction method thereof Active CN104895094B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510252389.3A CN104895094B (en) 2015-05-18 2015-05-18 A kind of draining friction pile being automatically adjusted water level and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510252389.3A CN104895094B (en) 2015-05-18 2015-05-18 A kind of draining friction pile being automatically adjusted water level and construction method thereof

Publications (2)

Publication Number Publication Date
CN104895094A true CN104895094A (en) 2015-09-09
CN104895094B CN104895094B (en) 2016-08-24

Family

ID=54028023

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510252389.3A Active CN104895094B (en) 2015-05-18 2015-05-18 A kind of draining friction pile being automatically adjusted water level and construction method thereof

Country Status (1)

Country Link
CN (1) CN104895094B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108661061A (en) * 2018-06-07 2018-10-16 中铁二院工程集团有限责任公司 Hinged joint opposite supporting type anchors pilework
CN109853591A (en) * 2019-01-24 2019-06-07 石家庄铁道大学 Drain friction pile and preparation method thereof
CN110700288A (en) * 2019-10-17 2020-01-17 中国地质大学(武汉) Method and system suitable for preventing and controlling deep drainage of landslide of hydrodynamic pressure type reservoir

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101230577A (en) * 2007-12-28 2008-07-30 中国科学院水利部成都山地灾害与环境研究所 Construction method for vertical prestressed anchor rope friction pile slope-sliding prevention and treatment
JP3181195U (en) * 2012-11-05 2013-01-31 東洋鋼業株式会社 Slope placement steps and slope placement steps
CN102953389A (en) * 2012-11-07 2013-03-06 宁波大学 Novel side slope retainer anchor anti-sliding pile
CN202787281U (en) * 2012-09-12 2013-03-13 中铁第四勘察设计院集团有限公司 Hydrophobic anti-slide structure
CN202913416U (en) * 2012-11-07 2013-05-01 宁波大学 Drainage slide-resistant pile
CN103266594A (en) * 2013-05-21 2013-08-28 中南大学 Slide-resistant pile
JP5290461B1 (en) * 2012-12-04 2013-09-18 矢作建設工業株式会社 Slope reinforcement method
CN104389307A (en) * 2014-12-08 2015-03-04 中铁西北科学研究院有限公司勘察设计分公司 Self-resetting slide-resistant pile structure with energy consumption function and implementation method thereof

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101230577A (en) * 2007-12-28 2008-07-30 中国科学院水利部成都山地灾害与环境研究所 Construction method for vertical prestressed anchor rope friction pile slope-sliding prevention and treatment
CN202787281U (en) * 2012-09-12 2013-03-13 中铁第四勘察设计院集团有限公司 Hydrophobic anti-slide structure
JP3181195U (en) * 2012-11-05 2013-01-31 東洋鋼業株式会社 Slope placement steps and slope placement steps
CN102953389A (en) * 2012-11-07 2013-03-06 宁波大学 Novel side slope retainer anchor anti-sliding pile
CN202913416U (en) * 2012-11-07 2013-05-01 宁波大学 Drainage slide-resistant pile
JP5290461B1 (en) * 2012-12-04 2013-09-18 矢作建設工業株式会社 Slope reinforcement method
CN103266594A (en) * 2013-05-21 2013-08-28 中南大学 Slide-resistant pile
CN104389307A (en) * 2014-12-08 2015-03-04 中铁西北科学研究院有限公司勘察设计分公司 Self-resetting slide-resistant pile structure with energy consumption function and implementation method thereof

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108661061A (en) * 2018-06-07 2018-10-16 中铁二院工程集团有限责任公司 Hinged joint opposite supporting type anchors pilework
CN109853591A (en) * 2019-01-24 2019-06-07 石家庄铁道大学 Drain friction pile and preparation method thereof
CN110700288A (en) * 2019-10-17 2020-01-17 中国地质大学(武汉) Method and system suitable for preventing and controlling deep drainage of landslide of hydrodynamic pressure type reservoir

Also Published As

Publication number Publication date
CN104895094B (en) 2016-08-24

Similar Documents

Publication Publication Date Title
CN107587516B (en) A kind of efficient sealing resistance sand precipitation composite system of Follow-up type and its construction method
CN102041845B (en) United draining system for effectively lowering seepage lines in fill dam of tailing reservoir
CN208328950U (en) A kind of In-pit water drainage friction pile suitable for dregs loose structure slope
CN101270582B (en) Method for setting bracing column in underground cavity
CN106968712A (en) Water rich strata tunnel bottom discharge structure and its construction method
CN104895094A (en) Automatic water level adjusting drainage anti-slide pile and construction method thereof
CN205679610U (en) A kind of piping experimental rig that can uniformly lift water level and measure soil pressure
CN103938634B (en) A kind of deep foundation pit supporting structure and construction method
CN102296572B (en) Earth and rockfill dam body seepage monitoring structure provided with abandoned dreg site behind dam and construction method thereof
CN112211199A (en) Large deep foundation pit supporting construction structure and method thereof
CN207147941U (en) Curtain withdrawal device and curtain withdrawal system
CN106884431B (en) A kind of building pit foundation construction safety supporting construction
CN207714348U (en) A kind of deep basal pit fast rainfall device
CN104652383B (en) Tailings warehouse dam body free-draining device
CN108149775A (en) A kind of prefabricated Boosting pumping station of PE and its mounting process
CN207032270U (en) Catch pit immersible pump precipitation system
CN106248495A (en) The indoor long-term assay device of post grouting pile of simulated groundwater flowing and test method thereof
CN110219305A (en) The pile making method of supporting construction
CN202323899U (en) Arrangement structure for underground gate chambers of diversion tunnels
CN207176668U (en) Underground water pressure limiting backflow device and underground water pressure limiting recharge system
CN108104158A (en) A kind of assembled underground pipe gallery and assembled in situ method
CN208072087U (en) A kind of high-speed railway foundation ruggedized construction of lossless karez function
CN211646407U (en) Attached drainage device under stock girder steel
CN105507376B (en) A kind of rectangle frame precast concrete reservoir
CN204679292U (en) Construction and operation phase seepage field of tunnel model assay systems

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant