CN104895008A - Construction method for environmental-friendly ecological plate type retaining wall revetment with ribbed walls - Google Patents
Construction method for environmental-friendly ecological plate type retaining wall revetment with ribbed walls Download PDFInfo
- Publication number
- CN104895008A CN104895008A CN201510313886.XA CN201510313886A CN104895008A CN 104895008 A CN104895008 A CN 104895008A CN 201510313886 A CN201510313886 A CN 201510313886A CN 104895008 A CN104895008 A CN 104895008A
- Authority
- CN
- China
- Prior art keywords
- ecological
- wall
- concrete
- sheet pile
- pile
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Revetment (AREA)
Abstract
The invention discloses a construction method for an environmental-friendly ecological plate type retaining wall revetment with ribbed walls. The construction method includes following steps: a sheet pile is constructed at the spot, the sheet pile is provided with the ribbed walls with an interval, and an inserting groove with certain depth is arranged in the sheet pile at the positions of the ribbed walls; a precast pile and an ecological wall are fabricated; the precast pile is inserted into the preset inserting groove of the sheet pile, and the connection is realized via the pouring of concrete; the ecological wall is connected with the precast pile via plugs at two ends; a slop surface of the revetment is provided with anchor cables, and the slop surface is also provided with a water-permeable concrete layer in an injection manner; ecological holes of the ecological wall is planted with plants, and the ecological concrete is poured to an elevation position of the ecological hole at the top between the ecological wall and the water-permeable concrete layer; and the ecological concrete is backfilled with planting soil, and the plants are planted on the planting soil so that the construction of the environmental-friendly ecological plate type retaining wall revetment with the ribbed walls is completed.
Description
Technical field
The present invention relates to a kind of Ecological Retaining Wall bank protection construction method, particularly the environmentally friendly ecology of one wallboard type barricade with ribbing bank protection construction method.
Background technology
Traditional bank protection structure mainly contains reinforced earth bank protection structure, grouts or placed rockfill bank protection structure, cast-in-situ concrete Form Gravity Breast Wall bank protection structure and precast concrete block bank protection structure etc., these bank protection structures are firm, durable, be widely used in the bank protection work such as navigation channel, river, harbour, but also there is many deficiencies, as large in differential settlement, destruction ecological environment, resistance to overturning difference etc.
At present, for the problem that existing bank protection structure differential settlement is large, the mode that general employing sets sheet pile solves, wherein reinforced concrete sheet pile is because of its long-lived feature, in Practical Project, have more cost performance, but conventional steel bar concrete sheet pile exist set difficulty, structure thick and heavy, with the shortcoming such as run-of-bank gravel slope connectivity difference.The problem of ecological environment is destroyed for existing bank protection structure, generally improve by the mode of back fill course after wall being planted green vegetation, but this traditional approach still destroys resource function and the ecological functions in navigation channel, also destroy navigation channel, river biological chain simultaneously, cause environment to worsen.For the problem of resistance to overturning difference, usually adopt the mode of later stage artificial second consolidation to alleviate, both wasted time and energy, and be difficult to again fundamentally solve problems.
Therefore, need badly at present seek a kind of can meet simultaneously intensity large, take into account the band Ecological Retaining Wall bank protection construction method that amphibious, easy construction saves.
Summary of the invention
The object of the invention is to overcome above-mentioned defect or the deficiencies in the prior art, a kind of environmentally friendly ecology wallboard type barricade with ribbing bank protection construction method is provided.The object of the invention is to be achieved through the following technical solutions:
A construction method for environmentally friendly ecology wallboard type barricade with ribbing shore protection, is characterized in that, described barricade shore protection is primarily of Ecological Wall, sheet pile, rib wall, preformed pile, anchor cable, eco-concrete, pervious concrete layer, planting soil and vegetation composition; Sheet pile sets along shore protection, and sheet pile interval arranges rib wall, in the sheet pile of rib wall portion position, be provided with slot, and preformed pile is fixed in slot; Ecological Wall is connected with preformed pile by the plug at its two ends; Ecological Wall forms by eco-concrete is prefabricated, and in the wall body of Ecological Wall, be provided with ecological hole and dowel, ribs is connected with Ecological Wall by dowel; On shore protection is domatic, is inserted with anchor cable, and sprays pervious concrete layer; Built eco-concrete between Ecological Wall and pervious concrete layer, eco-concrete lays planting soil, vegetation is planted in the ecological hole of planting soil and Ecological Wall;
Shown construction method mainly comprises the following steps:
(1) according to designing requirement, set sheet pile at the scene, sheet pile arranges rib wall every 2-3m, in the sheet pile of rib wall portion position, arrange slot;
(2) make preformed pile and Ecological Wall, Ecological Wall two ends arrange plug, arrange ribs in Ecological Wall wall body, and plug and ribs are fixed by dowel and Ecological Wall, are provided with groove in preformed pile, for being connected with the plug at Ecological Wall two ends;
(3) be inserted in by preformed pile in the default slot of sheet pile, concrete perfusion connects;
(4) after preformed pile has connected, the plug of Ecological Wall by its two ends is connected with preformed pile;
(5) anchor cable is set on shore protection is domatic, and sprays pervious concrete layer on domatic; In the ecological hole of Ecological Wall, plant vegetation, build the ecological hole absolute altitude place of eco-concrete to row at Ecological Wall and pervious concrete interlayer;
(6) on eco-concrete, backfill planting soil, planting soil plants vegetation, complete the construction of environmentally friendly ecology wallboard type barricade with ribbing shore protection.
Further, ecological hole by outer and in large from little change, horizontally set vegetation in ecological hole.
Rib wall progressively reduces from top to bottom, in upside-down triangle shape.
Each parts in environmentally friendly ecology wallboard type with ribbing barricade shore protection in the present invention are all prefabricated to be formed, quality controllable, and what adopt is rigid foundation, and continuity is good, intensity is large, stability is high, applied widely, ensure that shore protection quality.
Have employed rib wall type structure in the junction of sheet pile and preformed pile in the present invention, ensure that intensity and the fixing of junction.
In the present invention, preformed pile and Ecological Wall adopt plug-in type connected mode, improve efficiency of construction.
The horizontally set ecosystem in the present invention, does not only weaken the ecological value of shore protection, and what also add shore protection barricade can usable floor area.
Accompanying drawing explanation
Fig. 1 is environmentally friendly ecology wallboard type barricade with ribbing shore protection sectional drawing.
Fig. 2 is construction process figure.
Fig. 3 is Ecological Retaining Wall schematic diagram.
In figure: 1-Ecological Wall; The ecological hole of 2-; 3-dowel; 4-plug; 5-ribs; 6-sheet pile; 7-rib wall; 8-preformed pile; 9-slot; 10-rolling earth behind retaining wall; 11-anchor cable; 12-pervious concrete layer; 13-eco-concrete; 14-planting soil; 15-vegetation.
Detailed description of the invention
Fig. 1 is environmentally friendly ecology wallboard type barricade with ribbing shore protection sectional drawing.Fig. 2 is construction process portion.Fig. 3 is Ecological Wall schematic diagram.
Forming primarily of Ecological Wall 1, sheet pile 6, rib wall 7, preformed pile 8, anchor cable 11, eco-concrete 13, pervious concrete layer 12, planting soil 14 and vegetation 15 as shown in Figure 1-Figure 3.
Sheet pile 6 sets along shore protection, and sheet pile 6 interval arranges rib wall 7, in the sheet pile of rib wall portion position, be provided with slot 9, and preformed pile 8 is fixed in slot 9.
Ecological Wall 1 is connected with preformed pile 8 by the plug 4 at its two ends.Ecological Wall 1 forms by eco-concrete is prefabricated, and in the wall body of Ecological Wall 1, be provided with ecological hole 2 and dowel 3, ribs 5 is connected with Ecological Wall 1 by dowel 3.
On shore protection is domatic, is inserted with anchor cable 11, and sprays pervious concrete layer 13; Built eco-concrete 13 between Ecological Wall 1 and pervious concrete layer 12, eco-concrete 13 is laid planting soil 14,15 kinds, vegetation is planted in the ecological hole 2 of planting soil 14 and Ecological Wall 1.
The construction method of environmentally friendly ecology wallboard type barricade with ribbing shore protection comprises the following steps:
Shown in Fig. 1 and Fig. 2, set the sheet pile 6 that 0.75m is thick, 2.5m is long, 7m is dark at the scene, and arrange every 2.5m spacing at sheet pile 6 top and grow tall and be the rib wall 7 of 1.25m, rib wall 7 progressively reduces from top to bottom, the Breadth Maximum that outer ribs wall 7 exceeds sheet pile 6 is 0.2m, the Breadth Maximum that interior side rib wall 7 exceeds sheet pile 6 is 0.3m, in upside-down triangle shape, be provided with in the sheet pile 6 at rib wall 7 position one long × wide × be the slot 9 of 0.56m × 0.56m × 1.00m deeply, for the connection with top preformed pile 8.
The making length of side is 0.55m, is highly the square preformed pile 8 of 3m, the offside of square preformed pile 8 arranges the groove be convenient to Ecological Wall 1 and connected, groove shapes is consistent with the shape of the plug 4 in Ecological Wall 1, the thickness of Ecological Wall 1 is 0.35m, highly for 3m, length are 2.5m, up and down an ecological hole 2 is set every 0.5m, ecological hole 2 is by outer and inner large from little change, diameter gradually changes to 20cm from 10cm, by dowel 3, ribs 5 is connected with Ecological Wall 1, the length of ribs 5 is 3m, and wide height is respectively 0.25cm.Prefabricated Ecological Wall 1 is inserted connection respectively along the groove of preformed pile 8 both sides.
After the connection work of preformed pile 8, Ecological Wall 1, sheet pile 6, rib wall 7 completes, rolling earth behind retaining wall 10 domatic on the anchor cable 11 that diameter is 10cm, length is 5 ~ 10m is set, and the thick pervious concrete layer 12 of about 20cm is sprayed on domatic, for anchoring anchor cable 11, then laterally bury vegetation 15 underground in the ecological hole 2 in Ecological Wall 1, between Ecological Wall 1 and rolling earth behind retaining wall 10, build the absolute altitude place, ecological hole 2 of eco-concrete 13 to row on afterwards.
Reach until eco-concrete 13 backfilling working carrying out planting soil 14 after design strength, and vegetation 15 is set on planting soil 14, finally complete the construction working of environmentally friendly ecology wallboard type barricade with ribbing shore protection.
Above-mentioned detailed description of the invention does not limit technical scheme of the present invention in any form, and the technical scheme that the mode that every employing is equal to replacement or equivalent transformation obtains all drops in protection scope of the present invention.
Claims (3)
1. a construction method for environmentally friendly ecology wallboard type barricade with ribbing shore protection, is characterized in that, described barricade shore protection is primarily of Ecological Wall, sheet pile, rib wall, preformed pile, anchor cable, eco-concrete, pervious concrete layer, planting soil and vegetation composition; Sheet pile sets along shore protection, and sheet pile interval arranges rib wall, in the sheet pile of rib wall portion position, be provided with slot, and preformed pile is fixed in slot; Ecological Wall is connected with preformed pile by the plug at its two ends; Ecological Wall forms by eco-concrete is prefabricated, and in the wall body of Ecological Wall, be provided with ecological hole and dowel, ribs is connected with Ecological Wall by dowel; On shore protection is domatic, is inserted with anchor cable, and sprays pervious concrete layer; Built eco-concrete between Ecological Wall and pervious concrete layer, eco-concrete lays planting soil, vegetation is planted in the ecological hole of planting soil and Ecological Wall;
Shown construction method mainly comprises the following steps:
(1) according to designing requirement, set sheet pile at the scene, sheet pile arranges rib wall every 2-3m, in the sheet pile of rib wall portion position, arrange slot;
(2) make preformed pile and Ecological Wall, Ecological Wall two ends arrange plug, arrange ribs in Ecological Wall wall body, and plug and ribs are fixed by dowel and Ecological Wall, are provided with groove in preformed pile, for being connected with the plug at Ecological Wall two ends;
(3) be inserted in by preformed pile in the default slot of sheet pile, concrete perfusion connects;
(4) after preformed pile has connected, the plug of Ecological Wall by its two ends is connected with preformed pile;
(5) anchor cable is set on shore protection is domatic, and sprays pervious concrete layer on domatic; In the ecological hole of Ecological Wall, plant vegetation, build the ecological hole absolute altitude place of eco-concrete to row at Ecological Wall and pervious concrete interlayer;
(6) on eco-concrete, backfill planting soil, planting soil plants vegetation, complete the construction of environmentally friendly ecology wallboard type barricade with ribbing shore protection.
2. construction method according to claim 1, it is characterized in that ecological hole by outer and in large from little change, horizontally set vegetation in ecological hole.
3. construction method according to claim 1, is characterized in that rib wall progressively reduces from top to bottom, in upside-down triangle shape.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510313886.XA CN104895008B (en) | 2015-06-09 | 2015-06-09 | The construction method of environmentally friendly ecology wallboard type with ribbing barricade shore protection |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510313886.XA CN104895008B (en) | 2015-06-09 | 2015-06-09 | The construction method of environmentally friendly ecology wallboard type with ribbing barricade shore protection |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104895008A true CN104895008A (en) | 2015-09-09 |
CN104895008B CN104895008B (en) | 2016-11-09 |
Family
ID=54027938
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510313886.XA Expired - Fee Related CN104895008B (en) | 2015-06-09 | 2015-06-09 | The construction method of environmentally friendly ecology wallboard type with ribbing barricade shore protection |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104895008B (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110318370A (en) * | 2019-07-06 | 2019-10-11 | 南通市规划设计院有限公司 | A kind of ecological revetment and its construction method |
CN110424328A (en) * | 2019-07-19 | 2019-11-08 | 杭州江润科技有限公司 | Ecological sheet pile shore protection and its construction method |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US6048139A (en) * | 1998-01-21 | 2000-04-11 | Donovan, Iii; Murtha Vincent | Arrangement for shoreline construction, maintenance, and protection, and methods for making and using the same |
CN1632231A (en) * | 2004-12-27 | 2005-06-29 | 河海大学 | Landscape type multi-stage stepwise artificial wetland protection slope forming method |
KR20110051474A (en) * | 2009-11-10 | 2011-05-18 | (주)부전 이엔씨 | Eco-friendly retaining wall using phc pile |
CN102352632A (en) * | 2011-07-29 | 2012-02-15 | 重庆大学 | Anchor rod sheet pile combined structure and method for reinforcing high filling body on one side of slope |
CN203808009U (en) * | 2014-04-12 | 2014-09-03 | 江阴市江港堤闸管理处 | Ecological harbor dyke protection bank |
-
2015
- 2015-06-09 CN CN201510313886.XA patent/CN104895008B/en not_active Expired - Fee Related
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US6048139A (en) * | 1998-01-21 | 2000-04-11 | Donovan, Iii; Murtha Vincent | Arrangement for shoreline construction, maintenance, and protection, and methods for making and using the same |
CN1632231A (en) * | 2004-12-27 | 2005-06-29 | 河海大学 | Landscape type multi-stage stepwise artificial wetland protection slope forming method |
KR20110051474A (en) * | 2009-11-10 | 2011-05-18 | (주)부전 이엔씨 | Eco-friendly retaining wall using phc pile |
CN102352632A (en) * | 2011-07-29 | 2012-02-15 | 重庆大学 | Anchor rod sheet pile combined structure and method for reinforcing high filling body on one side of slope |
CN203808009U (en) * | 2014-04-12 | 2014-09-03 | 江阴市江港堤闸管理处 | Ecological harbor dyke protection bank |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110318370A (en) * | 2019-07-06 | 2019-10-11 | 南通市规划设计院有限公司 | A kind of ecological revetment and its construction method |
CN110424328A (en) * | 2019-07-19 | 2019-11-08 | 杭州江润科技有限公司 | Ecological sheet pile shore protection and its construction method |
Also Published As
Publication number | Publication date |
---|---|
CN104895008B (en) | 2016-11-09 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204780764U (en) | Ecological wallboard formula barricade shore protection with ribbing of environment friendly | |
CN201762710U (en) | Pile-wall combined enclosing structure for offshore deep foundation pit | |
CN103437370A (en) | Method and supporting structure for slip resisting and soil retaining of abrupt slope | |
CN103290848B (en) | Large diameter arc-shaped steel sheet pile combined foundation pit retaining structure and construction method thereof | |
CN111877397A (en) | Rapid construction cutting retaining wall and construction method thereof | |
CN206752667U (en) | A kind of basement barrier wall structure | |
CN206204972U (en) | A kind of prefabricated tubular pile as well-points dewatering | |
CN104929142B (en) | A kind of combined cofferdam structure and construction construction method thereof | |
CN106120822B (en) | A kind of method for protecting support and device that prevent mud stone from coming down | |
CN104895008B (en) | The construction method of environmentally friendly ecology wallboard type with ribbing barricade shore protection | |
CN204356788U (en) | Flexibility subtracts swollen ecological revetment structure | |
CN206157760U (en) | Honeycomb geotechnique check room retaining wall with ecological recovery function | |
CN105040707A (en) | Combined densely-arrayed pile deep foundation pit supporting and enclosure structure used as basement external wall | |
CN107299646B (en) | Ecological retaining wall structure and construction method thereof | |
CN210658432U (en) | Assembled concrete box retaining wall | |
CN204825787U (en) | Gabion barricade protective structure | |
CN206143783U (en) | Supporting device for preventing mud rock landslide | |
CN212294737U (en) | Rapid construction cutting retaining wall | |
CN212078000U (en) | Assembled cistern bottom basis | |
CN103866779A (en) | Construction method of water stopping surrounding and protecting structure of soft soil foundation building foundation pit | |
CN203855933U (en) | Piling plate-inserting type revetment | |
CN103195077A (en) | Dam foundation reinforcement frame structure and dam foundation reinforcement method | |
CN203129163U (en) | Reinforcing framework structure for dam foundation | |
CN206722391U (en) | Basement barricade moulding wall formwork erecting structure based on brick fetal membrane | |
CN105839661A (en) | Anti-pulling open caisson foundation for power transmission tower |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right |
Effective date of registration: 20181224 Address after: Room 212, Room 212, Room 215-220 and Room 515, 35 Changjiang Road, Zhenjiang City, Jiangsu Province, 2002 Patentee after: JIANGSU HUAYUAN ENVIRONMENT CONSTRUCTION Co.,Ltd. Address before: 310015 office room 1901, block C, Wanda Plaza, intersection of Gongshu District Shi Xiang Road and Hang Hang Road, Hangzhou, Zhejiang. Patentee before: HANGZHOU JIANGRUN TECHNOLOGY Ltd. |
|
TR01 | Transfer of patent right | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20161109 |
|
CF01 | Termination of patent right due to non-payment of annual fee |