CN104881726A CN201410843774.0A CN201410843774A CN104881726A CN 104881726 A CN104881726 A CN 104881726A CN 201410843774 A CN201410843774 A CN 201410843774A CN 104881726 A CN104881726 A CN 104881726A
Authority
CN
China
Prior art keywords
analysis report
safety analysis
calculation
control manipulation
ticket
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410843774.0A
Other languages
Chinese (zh)
Other versions
CN104881726B (en
Inventor
李群山
李宝磊
余建明
刘坚强
杨超
付伟
赖宏毅
李鑫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Beijing Kedong Electric Power Control System Co Ltd
Central China Grid Co Ltd
Original Assignee
State Grid Corp of China SGCC
Beijing Kedong Electric Power Control System Co Ltd
Central China Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Beijing Kedong Electric Power Control System Co Ltd, Central China Grid Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201410843774.0A priority Critical patent/CN104881726B/en
Publication of CN104881726A publication Critical patent/CN104881726A/en
Application granted granted Critical
Publication of CN104881726B publication Critical patent/CN104881726B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a method for realizing integration of regulation-control operation orders and on-line combined calculation. The method comprises the steps of: S1, interacting a regulation-control operation order application with on-line combined calculation service, and generating calculation and analysis results and a safety analysis report; S2, associating the calculation and analysis results, the safety analysis report and a dispatching circulation process; S3, and adopting a database synchronization technology and a small mail transmission technology, so that information of first and third regions of an intelligent power grid dispatching technology supporting system are synchronized, and an OMS system of the third region can directly retrieve the calculation results and the safety analysis report, thereby facilitating a dispatching management personnel to perform supervision and management and guide a dispatching personnel to carry out system adjustment. The method provided by the invention adopts an online model and real-time power grid data for analysis and calculation, can effectively improve safety of regulation-control operation and enhance safe and stable operation level of the power grid.

Description

A kind ofly realize the control manipulation ticket method integrated with online combined calculation
Technical field
The present invention relates to and a kind ofly realize the control manipulation ticket method integrated with online combined calculation, belong to electric power system dispatching technical field.
Background technology
Scheduling institution is the tissue of Operation of Electric Systems, commander, guidance and coordination organization, and power grid regulation operation is the key factor maintaining generating and balancing the load, the stable operation of maintenance security of system in real time.Along with the expansion of electrical network scale, power grid regulation operation is day by day frequent and increasingly sophisticated.
Operation scheduling on transmission net of electric power is the important management system ensureing electric power netting safe running; operation scheduling on transmission net of electric power is under consideration system operation mode, protection cooperation, code of safe practice etc. require, ensures the correct change of the equipment method of operation and the strict operation steps formulated.Existing control manipulation ticket software simulating stops the security management and control flow process such as establishment, examination & verification, issue, execution, filing of operation order in power transmission or Start-up and Adjustment process, and operation scheduling on transmission net of electric power is the important evidence of regulation and control grid switching operation.
State due to electrical network is real-time change, only carries out safety analysis verification based on on-time model and real time data to operation order, just farthest can ensure security and the correctness of operation order.Therefore in the urgent need to the method for research power grid regulation operation order Security Checking.
In order to solve the problem, be in the Chinese patent application of 201310170387.0 at application number, disclose a kind of operation order Security Checking method based on disturbance assessment and trend analysis, comprising the steps: (1) statistics; (2) calculating of trend and stability check is carried out; (3) the disturbance assessment of Forming Electrical Dispatching Command Tickets is carried out; (4) stable tendency analysis before and after operation is carried out; (5) provide operation order Security Checking conclusion and show.The method realizes the security and stability analysis to operation scheduling on transmission net of electric power, the disturbance of assessment scheduling operation is on the impact of power grid security, and the variation tendency of electricity net safety stable level before and after analysis operation, for scheduling operation personnel provide the technical support of operation order security and stability analysis, and then improve the safety and stability level of electrical network.
But, the safety analysis such as online combined calculation, the aid decision making service of intelligent grid supporting system technology is not used well, fail and control manipulation ticket integral fusion in system, the electrical network level security that can not realize the control manipulation ticket before control manipulation is checked, effective technological means differentiation is not had to operate the impact that may cause the safety and stability of electrical network, there is potential safety hazard, the security requirement of electrical network can not be met.
Summary of the invention
Technical matters to be solved by this invention is that providing a kind of realizes the control manipulation ticket method integrated with online combined calculation.
For achieving the above object, the present invention adopts following technical scheme:
Realize the method that control manipulation ticket is integrated with online combined calculation, comprise the steps:
S1, carries out alternately by the application of control manipulation ticket with online combined calculation service, generates Calculation results and safety analysis report;
S2, associates Calculation results, safety analysis report with Scheduling Flow turn of tidal stream journey;
S3, adopt database synchronization technology and little mail transmission technology, make one of intelligent grid supporting system technology, the information in 3rd district carries out synchronously, making the OMS in 3rd district directly have access to Calculation results and safety analysis report, instruct dispatcher to carry out system call interception.
Wherein more preferably, in step sl, described control manipulation ticket application comprises the steps: alternately with online combined calculation service
S11, the plan ticket of control manipulation ticket, preview, execute phase, carries out Security Checking function;
After S12, step S11 trigger, according to the ticket information of current control manipulation ticket, generating run sequence E text, adopts file service mode, by sequence of operation E text cross-node to the transmission of online combined calculation server;
S13, adopts messenger service mode, sends message cross-node and triggers online combined calculation service routine;
S14, after online combined calculation service routine starts, the operation task E text transmitted in automatic analyzing step S12, obtains sequence of operation content, adopts real-time grid data section to carry out computational analysis;
S15, after online combined calculation service compute is analyzed, generates the Calculation results of E text formatting and the safety analysis report of DOC form respectively.
Wherein more preferably, in step s 2, the described list that Calculation results, safety analysis report and scheduling circulated carries out associating comprising the steps:
S21, the application of control manipulation ticket carries out text resolution to Calculation results, and the Calculation results of parsing is inserted automatically the Calculation results part in scheduling circulation list, carries out associating of Calculation results and Scheduling Flow turn of tidal stream journey;
S22, the application of control manipulation ticket obtains safety analysis report file name, and file name is automatically inserted in the attachment content of the Calculation results of scheduling circulation list;
S23, under safety analysis report being sent to the particular category of control manipulation ticket server, checks Calculation results and safety analysis report in the control manipulation ticket server in a district of intelligent grid supporting system technology.
Wherein more preferably, in step s3, Calculation results is realized and safety analysis report comprises the steps: in the process that one, three districts of intelligent grid supporting system technology are synchronous
S31, adopts database automatic synchronization mechanism, is sent in tables of data identical in three district's databases by related content in district's database;
S32, adopts messenger service mode, triggers little mail service on control manipulation ticket server, safety analysis report text is sent to three district's OMS server assigned catalogues from district's control manipulation ticket server;
S33, OMS carries out dispatching circulation list and the consulting of safety analysis report.
Wherein more preferably, in step S31, when adopting database automatic synchronization mechanism, carry out increment synchronization mechanism, only newly-increased record is sent in the database in 3rd district.
Wherein more preferably, in step s 32, after safety analysis report text is sent to three district's OMS server assigned catalogues, scheduling circulation list is associated in 3rd district with safety analysis report.
Wherein more preferably, step S33, consults scheduling circulation list and safety analysis report adopts different forms.
Wherein more preferably, when consulting described scheduling circulation list, consult described scheduling circulation form information by clicking to enter;
Safety analysis report file name in scheduling circulation form attachment is hyperlink pattern, when consulting described safety analysis report, by clicking safety analysis report file name, the incidence relation of list and the safety analysis report of circulating according to scheduling, obtains corresponding safety analysis report file and consults.
Provided by the present inventionly realize the control manipulation ticket method integrated with online combined calculation, carry out alternately by the application of control manipulation ticket with online combined calculation service, the data-pushing of the sequence of operation is carried out to online combined calculation service, and trigger online combined calculation, carry out the safety analysis of control manipulation ticket, and generate Calculation results and safety analysis result.Online combined calculation, more accurate, practical compared with the calculating of off-line.In addition, adopt database synchronization technology and little mail transmission technology, realize one of intelligent grid supporting system technology, the synchronizing information in 3rd district, be supported in three district's OMS and directly have access to Calculation results and safety analysis report, instruct dispatcher to carry out necessary system call interception, improve scheduling operation lean management level.
Accompanying drawing explanation
Fig. 1 is the fundamental diagram realizing the control manipulation ticket method integrated with online combined calculation provided by the invention;
Fig. 2 is that control manipulation ticket provided by the invention application carries out mutual process flow diagram with online combined calculation service;
Fig. 3 is in one embodiment of the present of invention, the schematic diagram of Dispatching nominal value content.
Embodiment
Below in conjunction with the drawings and specific embodiments, technology contents of the present invention is described in further detail.
As shown in Figure 1, provided by the inventionly realize the control manipulation ticket method integrated with online combined calculation, specifically comprise the steps: the ticket information first reading control manipulation ticket, and on-line analysis calculating is carried out to content of operation, generate Calculation results and safety analysis report; Then the Calculation results online combined calculation generated and safety analysis report, dispatch with operation order the list that circulates and carry out auto-associating, realizes scheduling circulation list and safety analysis report integral fusion; Finally adopt database synchronization technology and little mail transmission technology, realize one of intelligent grid supporting system technology, the synchronizing information in 3rd district, be supported in three district's OMS and directly have access to Calculation results and safety analysis report, instruct dispatcher to carry out necessary system call interception.Detailed specific description is done to this process below.
S1, the application of control manipulation ticket is carried out alternately with online combined calculation service, reads the ticket information of control manipulation ticket, and carries out on-line analysis calculating to content of operation, generates Calculation results and safety analysis report.
In embodiment provided by the present invention, the intelligent grid supporting system technology (being called for short D5000 system) released based on State Grid Corporation of China realizes, on the basis of real-time data of power grid, realize the application of control manipulation ticket and carry out alternately with online combined calculation service.Linearize control manipulation ticket application with online combined calculation service as intelligent grid supporting system technology in two methods, relatively independent, general dispatcher needs to intend ticket under the application of control manipulation ticket, arrive again online combined calculation service under for control manipulation ticket content again formulation content of operation carry out safety analysis, process is more loaded down with trivial details, and both realizations are in conjunction with significant.Because the application of control manipulation ticket is deployed on different servers from online combined calculation service, and both are separate, need to arrange its communication modes, Content of communciation form, triggering account form etc., to realize the integration of the two.
When the application of control manipulation ticket is carried out mutual with online combined calculation service, first the ticket information of control manipulation ticket is read, the data-pushing of the sequence of operation is carried out to online combined calculation service, and trigger online combined calculation, carry out the safety analyses such as static security analysis, transient stability analysis, Voltage Stability Analysis, Analysis of Short-Circuit Current, Small signal stability analysis, stability margin analysis, and generate Calculation results and safety analysis result.Online combined calculation, adopts online model and real-time grid data analysis to calculate, more accurate, practical compared with the calculating of off-line.In embodiment provided by the present invention, realize the control manipulation ticket application of intelligent grid supporting system technology (power grid regulation platform) integration and online combined calculation service convergence, adopt the Public service mechanism that power grid regulation platform provides, definition interactive information form, realize information communication therebetween, can effectively improve control manipulation security, improve power network safety operation level.
Wherein, as shown in Figure 2, the application of control manipulation ticket comprises the steps: alternately with online combined calculation service
S11, the plan ticket of control manipulation ticket, preview, execute phase, carries out Security Checking function automatically.
After S12, step S11 trigger, according to the ticket information of current control manipulation ticket, the sequence of operation E text of formation object, adopts file service mode, sequence of operation E text cross-node is sent to online combined calculation server.
After control manipulation ticket carries out Security Checking automatically, online combined calculation service read operation ticket ticket information, in an embodiment provided by the present invention, as shown in Figure 3, for the synthetic operation instruction ticket (control manipulation ticket) of Qin Bei electricity Chang, read the ticket information such as operation task, relevant way, time of issuing an order, report time, points for attention of control manipulation ticket, analysis operation task, generating run sequence E text; Sequence of operation E text packets is containing information such as operation task, operating equipment key word, operating equipment title, device type, action type, running times.Wherein, sequence of operation E content of text is as follows:
<Union_Compute::XX area 1357566733904>
ID Name Type State_Ope Time_Ope
# 115404741122457661 XX becomes 500kV#1 main transformer 50 20141124_23:02:55
</Union_Compute XX area >
Then, adopt file service mode, sequence of operation E text cross-node is sent to online combined calculation server.
S13, adopts messenger service mode, sends message cross-node and triggers online combined calculation service routine.
S14, after online combined calculation service routine starts, the operation task E text transmitted in automatic analyzing step S12, obtains sequence of operation content, adopts real-time grid data section to carry out computational analysis.
S15, after online combined calculation service compute is analyzed, generates the Calculation results of E text formatting and the safety analysis report of DOC form respectively.
After online combined calculation service compute is analyzed, generate the Calculation results of E text formatting and the safety analysis report of DOC form respectively.Calculation results comprises the result tables such as static security analysis, transient stability analysis, Voltage Stability Analysis, Analysis of Short-Circuit Current, Small signal stability analysis, stability margin analysis.Safety analysis report, adopt and generate DOC formatted file mode, comprise the contents such as the electrical network basis method of operation, transient stability analysis, Small signal stability analysis (setting of minor interference task, minor interference result of calculation, minor interference result curve), Voltage Stability Analysis, static security analysis (static security analysis setting, static security result of calculation), Analysis of Short-Circuit Current (Analysis of Short-Circuit Current setting, calculation of short-circuit current result), the analysis of section stability margin, conclusions and recommendations.
Realize serving with the online safety analysis such as combined calculation, aid decision making in intelligent grid supporting system technology effectively combining, electrical network level security before control manipulation is checked, effectively differentiation can operate the impact that may cause the safety and stability of electrical network, drastically increase the security of operation.Dispatching plan ticket, preview, each link of ordering realizes checking the interlock of function with safety on line, can effectively improve control manipulation security, raising power network safety operation level.
Wherein, Calculation results E content of text is as follows:
<!system=type=time='19000000_00:00:00'!>
<SAOUT::soft=/home/d5000/psaexplore/task/PS ASP_SA_1>---static security analysis detailed results table
case_no id_name c_range type salimit satype oleflag fault_current data_type prog_type flow_time
// task number excision element element component type the limit value that crosses the border that crosses the border crosses the border the type alert type calculated value region trade name section time
# 0 NOFAULT0000 XX line 5 1.706 00 3.3744 "/home/d5000/psaexplore/task/PSASP_SA_1 "
……
</SAOUT::>
<STOUT::soft=/home/d5000/psaexplore/task/PS ASP_ST_2>---transient stability analysis result table
fault_no fault_desc id_type id_name istable tstable al freq island gen_max_crit gen_min_crit gena_max_crit bus_min_crit vol_min_crit genw_min_crit wmin_crit genw_max_crit wmax_crit vtime ftime basa bvsa bfsa data_type prog_type flow_time
// fault group number failure-description fault element type fault element scheduling name stable case Maximum risk moment, (s) damping ratio frequency unstability island title, generator least work angle, (area-name) maximum work angle generator maximum work angular difference minimum voltage bus minimum voltage, (p.u.) low-limit frequency generator low-limit frequency, (Hz) highest frequency generator highest frequency, (Hz) whether merit angle safety whether voltage security whether frequency security region trade name section time minimum voltage duration frequency shift (FS) maximum duration
Forever, two ends disconnect NULL XX line 22 2.53 1 1.08646e-311 Group1 XX and become 20kV.2# unit XX factory 10kV.#2 machine 142.983 XX change 20kV.#7 female 0.87728 XX factory 20kV.16# unit 0.99909 # 0 XX line--end three "-nan 00111 "/home/d5000/psaexplore/task/PSASP_ST_2NULL
……
</STOUT::>
<VSOUT::
Soft=/home/d5000/psaexplore/task/PSASP_VS_1GreatT.GreaT. GT----Voltage Stability Analysis result table
no fault_no fault_desc id_name fault_ele vsl bus_min_crit vol_min_crit【bus_max_crit】tra_power cur_power data_type prog_type flow_time 14
// sequence number task number failure-description limit title fault element voltage stability margin minimum voltage bus minimum voltage (kV) [the maximum bus of voltage stability sensitivity] transmission power (MW) section current transmission power (MW) the region trade name section time
" " 0.055498 XX becomes 220kV. I section of bus 0.890055 # 00 " " 00 "/home/d5000/psaexplore/task/PSASP_VS_1 "
……
</VSOUT::>
<SCCOUT::
Soft=/home/d5000/psaexplore/task/PSASP_SCC_1GreatT.GreaT .GT----Analysis of Short-Circuit Current result
Fault_no faultelem_name elemtype lk shorttype scclimit faultcurrent note brkname data_type prog_type flow_time 12//task number fault element component type abort situation short-circuit-type breaking current short-circuit current remarks out-of-limit circuit breaker zone trade name section time
It is normal that # 0 XX becomes 500kV.2 bus 101 63 33.7485 short-circuit current " "/home/d5000/psaexplore/task/PSASP_SCC_1 "
……
</SCCOUT::>
<SSTOUT::
Soft=/home/d5000/psaexplore/task/PSASP_SST_2GreatT.GreaT .GT-----Small signal stability analysis
no mode_no re im al f ratio max_gen min_gen damp_type max_sen min_sen data_type prog_type flow_time 15
// task number eigenwert sequence number eigenwert real part eigenwert imaginary part damping ratio oscillation frequency (Hz) electromechanical circuit correlation ratio group of planes 1 represents a unit group of planes 2 and represents unit area oscillation/local oscillations unit 1 participation factors unit 2 participation factors region trade name section time
# 0 17-0.023291 7.07944 0.00328993 1.12673 37.0437 XX factory 10kV.2# generator XX factory 20kV.3# generator 000 "/home/d5000/psaexplore/task/PSASP_SST_2 "
……
</SSTOUT::>
<TTCOutput::soft=PSASP>-----stability margin analysis result table
id interface_name fault_id fault_name pcut pstc offline offline_limit Staangcoef type slmtmax tlmtmax dlmtmax data_type prog_type flow_time 16
// section numbering section describes the limited fault number limited failure-description current meritorious upper-bound limit reference value lower limit reference value quiet steady reserve factor section constrained type section static limit section transient state limit section dynamic limit region trade name section time
# 5 XX section 29 heat is surely limited, excision [XX line], and [XX line] crosses the border 11.48%7.73971 39.0361 0.0 0.0 0.0 0.0 0.0 0.0 0.0 " PSASP "
</TTCOutput::>
S2, the list that Calculation results, safety analysis report and scheduling circulated associates, and realizes scheduling circulation table list and safety analysis report integral fusion.
In embodiment provided by the present invention, Calculation results, safety analysis report and the scheduling list that circulates associate, wherein, Calculation results adopts text resolution, the mode of Auto-writing scheduling circulation list, safety analysis report adopts interpolation Scheduling Flow automatically to turn form attachment, mode uploaded by annex text, realize online combined calculation result (Calculation results and safety analysis report) and dispatch associating of the list that circulates, yardman can check Calculation results by consulting scheduling circulation list, safety analysis report, simple and convenient, improve work efficiency.Wherein, the list that Calculation results, safety analysis report and scheduling circulated carries out associating specifically comprising the steps:
S21, the application of control manipulation ticket carries out text resolution to Calculation results, and the Calculation results of parsing is inserted automatically Calculation results part in scheduling circulation list, realizes associating of Calculation results and Scheduling Flow turn of tidal stream journey.
S22, the application of control manipulation ticket obtains safety analysis report file name, and file name is automatically inserted in the attachment content of the Calculation results of scheduling circulation list.
S23, under safety analysis report being sent to the particular category of control manipulation ticket server, can check Calculation results and safety analysis report in the control manipulation ticket server in a district of intelligent grid supporting system technology.
S3, adopt database synchronization technology and little mail transmission technology, realize one of intelligent grid supporting system technology, the synchronizing information in 3rd district, be supported in three district's OMS and directly have access to result of calculation and safety analysis report, instruct dispatcher to carry out necessary system call interception.
Completing Calculation results and safety analysis report file and scheduling circulates after list associates, be sent to three district's OMS by one, three district's synchronization mechanisms of intelligent grid supporting system technology, support the download of having access to of control manipulation ticket, scheduling circulation list and safety analysis report annex in OMS.Wherein, realize Calculation results and safety analysis report is synchronous in one, three districts of intelligent grid supporting system technology, the database synchronization function and little mail transmission function that utilize intelligent grid supporting system technology to provide, adopt database synchronization mode, realize scheduling circulation list content and be sent to three district's databases by a district, adopt little mail transmitting function, realize safety analysis report text and be sent to three district's OMS servers by district's control manipulation ticket server.Realize Calculation results and safety analysis report comprises the steps: in the process that one, three districts of intelligent grid supporting system technology are synchronous
S31, adopt database automatic synchronization mechanism, operation order task list (OPT_TITLE), content of operation table (OPT_CONTENT), the newly-increased record of scheduling circulation table (OPT_OMS) in district's database are sent in tables of data identical in three district's databases.
When completing Calculation results, safety analysis report and scheduling circulate after associating of list, and scheduling circulation submission of sheet Calculation results and safety analysis report file name filled in, content is saved in district's database.Related content, by database synchronization mechanism, is sent in three district's databases by a district by scheduling circulation list automatically.Wherein, the related content of transmission comprises the newly-increased record in operation order task list (OPT_TITLE), content of operation table (OPT_CONTENT), scheduling circulation table (OPT_OMS).Only newly-increased record is sent to three district's databases decreases redundant data, improves the efficiency of transmission and the efficiency of data syn-chronization.
S32, adopts messenger service mode, triggers little mail service on control manipulation ticket server, safety analysis report text is sent to three district's OMS server assigned catalogues from district's control manipulation ticket server.
In intelligent grid supporting system technology, be generally divided into multiple district according to severity, between each district, adopt spacer assembly to separate, to improve security, and support the transregional transmission of text.Little mail function is the mechanism that system provides, and can realize transregionally carrying out transmission of textual data.In embodiment provided by the present invention, adopt messenger service mode, trigger little mail service on control manipulation ticket server, safety analysis report text is sent to three district's OMS server assigned catalogues from district's control manipulation ticket server, realizes analysis report the associating in 3rd district of scheduling circulation list and DOC form.
S33, carries out control manipulation ticket at the OMS management and running production management page in 3rd district, scheduling circulates having access to of list, Calculation results and safety analysis report, and support the download of safety analysis report text.
In the OMS in 3rd district, dispatch annex text on circulation list and server in database and keep real time correlation, at the OMS management and running production management page, support to consult scheduling circulation list, control manipulation ticket content, in scheduling circulation list, attachment content is hyperlink pattern, by selecting to download annex, the safety analysis report text on server is downloaded to this locality.Wherein, in embodiment provided by the present invention, have access in OMS and annex downloading mode as follows:
1) in three district's OMS management and running production management pages, the list of control manipulation ticket can be checked, for certain control manipulation ticket, can click to enter and consult this control manipulation ticket content and scheduling circulation form information.
2) in scheduling circulation form attachment, safety analysis report file name is hyperlink pattern, and during download file, system obtains corresponding safety analysis report file automatically from three district's servers.
In sum, provided by the present inventionly realize the control manipulation ticket method integrated with online combined calculation, carry out alternately by the application of control manipulation ticket with online combined calculation service, the data-pushing of the sequence of operation is carried out to online combined calculation service, and trigger online combined calculation, carry out the safety analysis of control manipulation ticket, and generate Calculation results and safety analysis result.Online combined calculation, more accurate, practical compared with the calculating of off-line.Then, the list that Calculation results, safety analysis report and scheduling circulated associates, and realizes scheduling circulation table list and safety analysis report integral fusion, facilitates consulting Calculation results and safety analysis report, improves work efficiency.In addition, adopt database synchronization technology and little mail transmission technology, realize one of intelligent grid supporting system technology, the synchronizing information in 3rd district, be supported in three district's OMS and directly have access to result of calculation and safety analysis report, instruct dispatcher to carry out necessary system call interception, improve scheduling operation lean management level.
Above the method realizing control manipulation ticket integrated with online combined calculation provided by the present invention is described in detail.For one of ordinary skill in the art, to any apparent change that it does under the prerequisite not deviating from connotation of the present invention, all by formation to infringement of patent right of the present invention, corresponding legal liabilities will be born.

Claims (8)

1. realize the method that control manipulation ticket is integrated with online combined calculation, it is characterized in that comprising the steps:
S1, carries out alternately by the application of control manipulation ticket with online combined calculation service, generates Calculation results and safety analysis report;
S2, associates Calculation results, safety analysis report with Scheduling Flow turn of tidal stream journey;
S3, adopt database synchronization technology and little mail transmission technology, make one of intelligent grid supporting system technology, the information in 3rd district carries out synchronously, make three district's OMS directly have access to Calculation results and safety analysis report, instruct dispatcher to carry out system call interception.
2. realize the control manipulation ticket method integrated with online combined calculation as claimed in claim 1, it is characterized in that in step sl, described control manipulation ticket application comprises the steps: alternately with online combined calculation service
S11, the plan ticket of control manipulation ticket, preview, execute phase, carries out Security Checking function automatically;
After S12, step S11 trigger, according to the ticket information of current control manipulation ticket, generating run sequence E text, adopts file service mode, by sequence of operation E text cross-node to the transmission of online combined calculation server;
S13, adopts messenger service mode, sends message cross-node and triggers online combined calculation service routine;
S14, after online combined calculation service routine starts, the operation task E text transmitted in automatic analyzing step S12, obtains sequence of operation content, adopts real-time grid data section to carry out computational analysis;
S15, after online combined calculation service compute is analyzed, generates the Calculation results of E text formatting and the safety analysis report of DOC form respectively.
3. realize the control manipulation ticket method integrated with online combined calculation as claimed in claim 1, it is characterized in that in step s 2, the described list that Calculation results, safety analysis report and scheduling circulated carries out associating comprising the steps:
S21, the application of control manipulation ticket carries out text resolution to Calculation results, and the Calculation results of parsing is inserted automatically the Calculation results part in scheduling circulation list, carries out associating of Calculation results and Scheduling Flow turn of tidal stream journey;
S22, the application of control manipulation ticket obtains safety analysis report file name, and file name is automatically inserted in the attachment content of the Calculation results of scheduling circulation list;
S23, under safety analysis report being sent to the particular category of control manipulation ticket server, checks Calculation results and safety analysis report in the control manipulation ticket server in a district of intelligent grid supporting system technology.
4. realize the control manipulation ticket method integrated with online combined calculation as claimed in claim 1, it is characterized in that in step s3, realize Calculation results and safety analysis report comprises the steps: in the process that one, three districts of intelligent grid supporting system technology are synchronous
S31, adopts database automatic synchronization mechanism, is sent in tables of data identical in three district's databases by related content in district's database;
S32, adopts messenger service mode, triggers little mail service on control manipulation ticket server, safety analysis report text is sent to three district's OMS server assigned catalogues from district's control manipulation ticket server;
S33, OMS carries out dispatching circulation list and the consulting of safety analysis report.
5. realize the control manipulation ticket method integrated with online combined calculation as claimed in claim 4, it is characterized in that:
In step S31, when adopting database automatic synchronization mechanism, carry out increment synchronization mechanism, only newly-increased record is sent in the database in 3rd district.
6. realize the control manipulation ticket method integrated with online combined calculation as claimed in claim 4, it is characterized in that:
In step s 32, after safety analysis report text is sent to three district's OMS server assigned catalogues, scheduling circulation list is associated in 3rd district with safety analysis report.
7. realize the control manipulation ticket method integrated with online combined calculation as claimed in claim 4, it is characterized in that:
Step S33, consults scheduling circulation list and safety analysis report adopts different forms.
8. realize the control manipulation ticket method integrated with online combined calculation as claimed in claim 7, it is characterized in that:
When consulting described scheduling circulation list, consult described scheduling circulation form information by clicking to enter;
Safety analysis report file name in scheduling circulation form attachment is hyperlink pattern, when consulting described safety analysis report, by clicking safety analysis report file name, the incidence relation of list and the safety analysis report of circulating according to scheduling, obtains corresponding safety analysis report file and consults.
CN201410843774.0A 2014-12-31 2014-12-31 Method for realizing integration of regulation and control operation order and online joint calculation Active CN104881726B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410843774.0A CN104881726B (en) 2014-12-31 2014-12-31 Method for realizing integration of regulation and control operation order and online joint calculation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410843774.0A CN104881726B (en) 2014-12-31 2014-12-31 Method for realizing integration of regulation and control operation order and online joint calculation

Publications (2)

Publication Number Publication Date
CN104881726A true CN104881726A (en) 2015-09-02
CN104881726B CN104881726B (en) 2020-12-01

Family

ID=53949213

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410843774.0A Active CN104881726B (en) 2014-12-31 2014-12-31 Method for realizing integration of regulation and control operation order and online joint calculation

Country Status (1)

Country Link
CN (1) CN104881726B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105279392A (en) * 2015-09-28 2016-01-27 深圳华大基因科技服务有限公司 Cloud platform-based big data analysis device
CN105389482A (en) * 2015-09-28 2016-03-09 深圳华大基因科技服务有限公司 Massive data analysis method based on cloud platform
CN107066597A (en) * 2017-04-19 2017-08-18 国家电网公司 Appraisal report generation method and system after a kind of electric network fault
CN107092222A (en) * 2017-05-23 2017-08-25 国网辽宁省电力有限公司 Power grid regulation operational administrative system based on the integration of anti-error check analysis
CN109428907A (en) * 2017-08-23 2019-03-05 南京南瑞继保电气有限公司 Across the power scheduling area's network operation bill system of one kind

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101527454A (en) * 2009-04-27 2009-09-09 国网电力科学研究院 Method for automatically generating annual running mode report of power grid
CN101546922A (en) * 2009-04-22 2009-09-30 西北电网有限公司 Intelligent program-control error-locking prevention system based on integrated design for substations
CN102646223A (en) * 2012-02-17 2012-08-22 中国电力科学研究院 Multi-user remote parallel computation system
US20140351285A1 (en) * 2011-12-29 2014-11-27 State Grid Information & Telecommunication Branch Platform and method for analyzing electric power system data

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101546922A (en) * 2009-04-22 2009-09-30 西北电网有限公司 Intelligent program-control error-locking prevention system based on integrated design for substations
CN101527454A (en) * 2009-04-27 2009-09-09 国网电力科学研究院 Method for automatically generating annual running mode report of power grid
US20140351285A1 (en) * 2011-12-29 2014-11-27 State Grid Information & Telecommunication Branch Platform and method for analyzing electric power system data
CN102646223A (en) * 2012-02-17 2012-08-22 中国电力科学研究院 Multi-user remote parallel computation system

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
何锡点 等: "文本典型票的操作序列解析算法", 《电力系统保护与控制》 *
刘强 等: "具有计算分析功能的电网调度操作票系统", 《电网技术》 *
李功新 等: "基于D5000平台的调控操作与防误一体化系统", 《电力自动化设备》 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105279392A (en) * 2015-09-28 2016-01-27 深圳华大基因科技服务有限公司 Cloud platform-based big data analysis device
CN105389482A (en) * 2015-09-28 2016-03-09 深圳华大基因科技服务有限公司 Massive data analysis method based on cloud platform
CN105389482B (en) * 2015-09-28 2018-09-14 深圳华大基因科技服务有限公司 A kind of big data analysis method based on cloud platform
CN107066597A (en) * 2017-04-19 2017-08-18 国家电网公司 Appraisal report generation method and system after a kind of electric network fault
CN107092222A (en) * 2017-05-23 2017-08-25 国网辽宁省电力有限公司 Power grid regulation operational administrative system based on the integration of anti-error check analysis
CN107092222B (en) * 2017-05-23 2019-08-20 国网辽宁省电力有限公司 Based on the integrated power grid regulation operational administrative system of anti-error check analysis
CN109428907A (en) * 2017-08-23 2019-03-05 南京南瑞继保电气有限公司 Across the power scheduling area's network operation bill system of one kind
CN109428907B (en) * 2017-08-23 2021-05-28 南京南瑞继保电气有限公司 Cross-power dispatching area network operation ticket system

Also Published As

Publication number Publication date
CN104881726B (en) 2020-12-01

Similar Documents

Publication Publication Date Title
Hartmann et al. Effects of decreasing synchronous inertia on power system dynamics—Overview of recent experiences and marketisation of services
Zecchino et al. Large-scale provision of frequency control via V2G: The Bornholm power system case
CN104881726A (en) Method for realizing integration of regulation-control operation order and on-line combined calculation
Fischer et al. Operational experiences with inertial response provided by type 4 wind turbines
CN101236575B (en) Black start assistant decision making support/training system and its method
CN104915750A (en) Intelligent operation ticket management method and system for achieving integration with an EMS and an OMS
CN104933535A (en) An intelligent monitoring operation ticket management method and a system thereof
CN105576660B (en) Local distribution network in-circuit emulation analytical equipment and system
CN109787356B (en) Transformer substation remote control anti-misoperation method and system based on IEC61850 protocol
CN102812663A (en) Method and apparatus for control of a commodity distribution system
CN103093303A (en) Outage schedule management apparatus and method in ems
CN101719690A (en) Dispatching method of electric network
CN106993002B (en) Cloud release method of fault recording information
CN104504483A (en) Method for realizing integration of anti-misoperation operation order provincial dispatching and local dispatching
CN102064602A (en) Operating method of B/S framework networked electronic simulation drawing board system
CN107168265A (en) Fixed value adjusting system and the automatic identification docking calculation for protecting letter system
CN106570775A (en) Power grid fault countermeasure plan combining compilation method and device
Zhang et al. Real-time power management for microgrids with dynamic boundaries and multiple source locations
Kucuk et al. Load management of industrial facilities electrical system using intelligent supervision, control and monitoring systems
JP6675043B2 (en) Monitoring and control system
CN106026047A (en) Optimized control method of high-reliability distribution automation based on multi-source coordination and cooperation
CN106059073A (en) Programmed control method based on cooperative misoperation prevention of master station and substation
Kawabe et al. Reactive power control of photovoltaic power generation systems by a wide‐area control system for improving transient stability in power systems
JP4597076B2 (en) Power system blackout work plan setting method and system
CN106254438A (en) A kind of power distribution network of based on open communication CPS main website

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant