CN104878916B - With the dismantled and assembled simple and easy four-wheel Mobile operating platform of constructional materials elevating function - Google Patents

With the dismantled and assembled simple and easy four-wheel Mobile operating platform of constructional materials elevating function Download PDF

Info

Publication number
CN104878916B
CN104878916B CN201510354779.1A CN201510354779A CN104878916B CN 104878916 B CN104878916 B CN 104878916B CN 201510354779 A CN201510354779 A CN 201510354779A CN 104878916 B CN104878916 B CN 104878916B
Authority
CN
China
Prior art keywords
steel
constructional materials
welded
operating platform
mobile operating
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510354779.1A
Other languages
Chinese (zh)
Other versions
CN104878916A (en
Inventor
张明亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan No6 Engineering Co Ltd
Original Assignee
Hunan No6 Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hunan No6 Engineering Co Ltd filed Critical Hunan No6 Engineering Co Ltd
Priority to CN201510354779.1A priority Critical patent/CN104878916B/en
Publication of CN104878916A publication Critical patent/CN104878916A/en
Application granted granted Critical
Publication of CN104878916B publication Critical patent/CN104878916B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

With the dismantled and assembled simple and easy four-wheel Mobile operating platform of constructional materials elevating function, comprise rubber tire, jack, base, main body frame, cat ladder, construction operation platform, constructional materials lifting gear and guardrail.It is convenient that the present invention forms accessory selection, it is convenient to install, band constructional materials elevating function, low cost of manufacture, detachable assembling, simple to operate, long service life, weight capacity is large, resistance to overturning is good, applied widely, and safe and reliable, construction site high-rise working Mobile operating platform can be widely used in.

Description

With the dismantled and assembled simple and easy four-wheel Mobile operating platform of constructional materials elevating function
Technical field
The present invention relates to a kind of operating platform, be specifically related to a kind of dismantled and assembled simple and easy four-wheel Mobile operating platform with constructional materials elevating function.
Background technology
At construction site, curtain wall, civil engineering wall plastering, interior/exterior decoration is fitted up, electric HVAC is installed, the engineerings such as Steel Structure Installation, all need to set up frame pin hand cradle or movable door-type scaffold operating platform to meet high-rise working, but it all has certain limitation, be mainly reflected in frame pin hand cradle and move inconvenience, set up and to require great effort and consuming time with dismantling, and the supporting capacity of movable door-type scaffold is limited, and the stability of self is inadequate, potential danger is there is during high-rise working, in addition, operating personnel was when operation platform operation in the past, general employing is manually drawn and is hung or hoist engine, other implement lift constructional materials such as crane, more consuming time and high-rise working personnel exist potential safety hazard.For needing the frequent ascend operation changing construction operation place, and when construction operation platform need bear that on larger load and eminence operating platform, constructional materials lifting is more, these two kinds of modes are all improper.
Summary of the invention
Technical problem to be solved by this invention is, the above-mentioned defect had when overcoming the engineering high-rise working such as existing job site curtain wall, civil engineering wall plastering, interior/exterior decoration finishing, electrically HVAC installation, Steel Structure Installation, there is provided a kind of installation convenient, conveniently moving, simple to operate, weight capacity is large, and resistance to overturning is good, the dismantled and assembled simple and easy four-wheel Mobile operating platform of safe and reliable band constructional materials elevating function.
The technical solution adopted for the present invention to solve the technical problems is: the dismantled and assembled simple and easy four-wheel Mobile operating platform of band constructional materials elevating function, comprises rubber tire, jack, base, main body frame, cat ladder, construction operation platform, constructional materials lifting gear and guardrail; Described base is welded by shaped steel or is bolted and forms, in sphere of movements for the elephants shape; Described main body frame is made up of steel post, gooseneck and hound I, the suspension column welding edges of described steel post has steel plate, described steel plate is welded to connect with base shaped steel top flange plate or bolt is connected, described gooseneck is along being highly distributed on steel post, to be welded to connect with steel post or bolt is connected, described hound I draws establish with steel post, gooseneck diagonal angle, and is welded to connect or bolt connection; Described cat ladder is located at main body frame sidepiece, extends to construction operation platform from base, is welded to connect with base shaped steel, main body frame gooseneck and construction operation platform limit girder steel; Described construction operation platform is located at main body frame steel post top; Described constructional materials lifting gear is located at above construction operation platform, be made up of steel pipe column, cantilever girder steel and electric block, described steel pipe column is provided with hoop location-plate and sleeve pipe, described casing pipe sleeve is at steel pipe column top, sleeve bottom drops on hoop location-plate, one end of described cantilever girder steel is connected with sleeve pipe vertical welding or bolt connects, and the other end installs electric block; Described guardrail is located at construction operation platform surrounding, is welded to connect or bolt is connected bottom guardrail with construction operation platform limit girder steel.
Further, described rubber tire totally 4, point walking rubber tire and universal rubber wheel, to be welded to connect with base shaped steel bottom wing listrium or bolt is connected respectively by each 2.
Further, described jack is hand-operated vertical hydraulic jack, totally 6, lays respectively at below main body frame steel post, and jack top and base shaped steel bottom wing listrium are welded and fixed.
Further, the steel pipe column of described constructional materials lifting gear doubles as the steel post of main body frame.
Further, hound II is set up between described cantilever girder steel and sleeve pipe.
Further, described cat ladder is made up of steel pipe or round steel.
Further, described guardrail is made up of steel pipe or round steel.
In the present invention, base shaped steel can utilize the steel profile defective material of job site, also can purchase in building materials market; Main body frame component can utilize the steel beam column defective material of job site, also can purchase in building materials market; Cat ladder component can utilize steel pipe or the round steel defective material of job site, also can purchase in building materials market; Constructional materials lifting gear component can utilize steel pipe or the shaped steel defective material of job site, also can purchase in building materials market; Guardrail component can utilize steel pipe or the round steel defective material of job site, also can purchase in building materials market.
In the present invention, described rubber tire is mainly used in changing the operating location of Mobile operating platform, its supporting capacity must meet Mobile operating platform self and attach the weight of facility, wherein universal rubber wheel also has guide function when being movably walking.
In the present invention, the quantity of described jack and single lifting capacity should be determined according to the load of operation on operating platform.
In the present invention, described main body frame not only should meet the stability of structure self, also should meet load-carrying ability during operating platform operation simultaneously.
In the present invention, described construction operation platform, on construction operation platform, lay bamboo slab rubber when it is implemented, bamboo slab rubber must be firm with the colligation of construction operation platform girder steel.
In the present invention, described constructional materials lifting gear, arranges electric block in its Steel Cantilever beam end, for being elevated the constructional materials needing to install or remove on operation platform.Its cantilever girder steel and steel pipe column are rotate in horizontal plane to be articulated and connected, and cantilever girder steel is free to rotate within the scope of horizontal plane certain angle, facilitate the colligation of constructional materials on operation platform and discharging or eminence installation and removal.
In the present invention, when the height of described guardrail should meet high-rise working, the safety of operating personnel, meanwhile, is the safety strengthening operating personnel, can lays closely-knitted safety net on guardrail.
Before when use, the present invention carries out high-rise working, it is smooth that compacting is carried out on reply ground, and when preventing high-rise working, Mobile operating platform tilts and collapses; At jack place, chock is leveled up, and checks that whether jack work is normal simultaneously, and makes the load balancing of each jack.
Establish bamboo slab rubber on base frames upper berth of setting a roof beam in place, what can be used as the interim appliance material of construction shelves platform.
During high-rise working, by adjusting the height of jack, rubber tire is made to be in unsettled off working state.
During high-rise working, Mobile operating platform load passes to ground mainly through jack, and jack can be used as the fulcrum on construction operation platform and ground, enhances safety during high-rise working.
For strengthening the resistance to overturning of Mobile operating platform, constructional materials lifting gear cantilever girder steel operating radius above construction operation platform, should make to be unlikely to during its operation departing from excessive and causing tilting and collapsing of operating platform because of operating platform center of gravity.
It is convenient that the present invention forms accessory selection, it is convenient to install, band constructional materials elevating function, low cost of manufacture, detachable assembling, simple to operate, long service life, weight capacity is large, resistance to overturning is good, applied widely, and safe and reliable, construction site high-rise working Mobile operating platform can be widely used in.
Accompanying drawing explanation
Fig. 1 is that the dismantled and assembled simple and easy four-wheel Mobile operating platform three-dimensional shaft of band constructional materials elevating function measures intention;
Fig. 2 is the dismantled and assembled simple and easy four-wheel Mobile operating platform elevation of band constructional materials elevating function;
Fig. 3 is the dismantled and assembled simple and easy four-wheel Mobile operating platform side view of band constructional materials elevating function.
Detailed description of the invention
Below in conjunction with drawings and Examples, the invention will be further described.
With reference to Fig. 1-3, the present embodiment comprises rubber tire, jack 3, base 4, main body frame, cat ladder 8, construction operation platform 9, constructional materials lifting gear and guardrail 15; Described base 4 is welded (being also formed by connecting by bolt), in sphere of movements for the elephants shape by shaped steel; Described main body frame is made up of steel post 5, gooseneck 6 and hound I 7, the suspension column welding edges of described steel post 5 has steel plate, described steel plate is welded to connect with base 4 shaped steel top flange plate (also can bolt be connected), described gooseneck 6 is along being highly distributed on steel post 5, be welded to connect with steel post 5 (also can bolt be connected), described hound I 7 and steel post 5, gooseneck 6 diagonal angle draw and establish, and are welded to connect (also can bolt connect); Described cat ladder 8 is located at main body frame sidepiece, extends to construction operation platform 9 from base 4, is welded to connect with base 4 shaped steel, main body frame gooseneck 6 and construction operation platform 9 limit girder steel; Described construction operation platform 9 is located at main body frame steel post 5 top; Described constructional materials lifting gear is located at above construction operation platform 9, be made up of steel pipe column 10, cantilever girder steel 11 and electric block 12, described steel pipe column 10 is provided with hoop location-plate 13 and sleeve pipe, described casing pipe sleeve is at steel pipe column 10 top, sleeve bottom drops on hoop location-plate 13, one end of described cantilever girder steel 11 is connected with sleeve pipe vertical welding (also can bolt connect), and the other end installs electric block 12; Described guardrail 15 is located at construction operation platform 9 surrounding, is welded to connect (also can bolt be connected) bottom guardrail with construction operation platform 9 limit girder steel.Hound II 14 is set up between described cantilever girder steel 11 and sleeve pipe.
In the present embodiment, described rubber tire divides walking rubber tire 1 and universal rubber wheel 2, each 2, be 10 cun of rubber wheels, diameter of tyres is 253mm, and width is 80mm, single-wheel maximum load is 120Kg, and rubber tire base plate 35cm long Φ 63.5 × 3 steel pipe welds with base 4 shaped steel bottom wing listrium.
In the present embodiment, described jack 3 is hand-operated vertical hydraulic jack, totally 6, lay respectively at below main body frame steel post 5, separate unit jack stand weight is 2 tons, and height is adjustable at 150 ~ 315mm, stroke is 165mm, and jack 3 top and base 4 shaped steel bottom wing listrium are welded and fixed.
In the present embodiment, described base 4 is welded by shaped steel, and the shaped steel selected is No. 14 i iron, the long 3m of base, wide 1.5m, and flat shape becomes sphere of movements for the elephants shape, becomes twin shaft symmetrical structure, upper laying bamboo slab rubber, and when can be used as construction, interim appliance material shelves platform.
In the present embodiment, described main body frame is made up of steel post 5, gooseneck 6 and hound I 7, and be weld seam welding between each component, main body frame height 4.5m, gooseneck 6 interval 1.5m is arranged along high uniformity, and hound I 7 diagonal angle draws to be established.
In the present embodiment, described steel post 5, material is Q235B, the model side of being, cross section 120 × 4, single long 4.5m, suspension column welding edges 8mm steel plate, is welded to connect with base 4 shaped steel top flange plate.
In the present embodiment, described gooseneck 6, material is Q235B, and cross section model is Φ 50 × 3.5 welded steel pipe, is welded to connect with steel post 5.
In the present embodiment, described hound I 7, material is Q235B, and cross section model is Φ 45 × 3.5 steel pipe, draws and establishes, be welded to connect between component with steel post 5, gooseneck 6 diagonal angle.
In the present embodiment, the width of described cat ladder 8 is 40cm, ladder step pitch is 30cm, diameter 20mm tri-grades of round bars of job site are utilized to be welded, cat ladder 8 is arranged at main body frame sidepiece, extend to construction operation platform 9 from base 4, be welded to connect with base 4 shaped steel, main body frame gooseneck 6 and construction operation platform 9 limit girder steel.
In the present embodiment, described construction operation platform 9 is welded by rectangular steel pipe, prop up and be located at main body frame steel post 5 top, the each steel beam column cross section of construction operation platform 9 is square 100 × 50 × 3, material is Q235B, for being welded to connect between each steel beam column, construction operation platform 9 lays bamboo slab rubber, bamboo slab rubber and the colligation of construction operation platform girder steel firm.
In the present embodiment, described constructional materials lifting gear is arranged at above construction operation platform 9, adopt cantilever construction, be made up of steel pipe column 10, cantilever girder steel 11 and electric block 12, cantilever girder steel 11 is articulated and connected for rotating in horizontal plane with steel pipe column 10, and cantilever girder steel 11 is free to rotate within the scope of horizontal plane certain angle; Wherein steel pipe column 10 cross section is Φ 114 × 4, the double steel post doing main body frame, and material is Q235B, is highly 6.3m, arranges the thick hoop location-plate 13 of 10mm from 0.9m place, top, hoop location-plate 13 with steel pipe column 10 for twin fillet wolt is connected; Cantilever girder steel 11, cross section is square 150 × 100 × 3, and material is Q235B, long 2.2m, and end is connected with Φ 119 × 4 sleeve pipe vertical welding of long 0.8m, and Φ 119 × 4 sleeve pipe is inserted in steel pipe column 10 top, and bottom falls within hoop location-plate 13; For strengthening the receive strength rationality of lifting gear cantilever girder steel and steel pipe column, between cantilever girder steel 11 and steel pipe column 10, set up hound II 14, cross section model is square 100 × 50 × 3, and material is Q235B, connects to be to be welded to connect between each component; Install electric block 12 at cantilever girder steel 11 other end, electric block 12 carrying capacity is 1 ton.
In the present embodiment, described guardrail 15 is welded by job site round steel pipe, is arranged at construction operation platform 9 surrounding, and bottom and construction operation platform 9 limit girder steel are welded to connect, guardrail height 0.9m, level is to establishing twice cross bar, and cross bar is Φ 32 × 3 steel pipe, wherein sheer pole distance construction operating platform height 20cm, guardrail 15 vertical rod cross section is Φ 45 × 3.5 steel pipe, adjacent vertical pole ' s span is 0.75m, at the wide 0.9m of cat ladder place opening, for the upper and lower cat ladder of operating personnel.
Before when use, the present invention carries out high-rise working, it is smooth that compacting is carried out on reply ground, and when preventing high-rise working, Mobile operating platform tilts and collapses.
Before use the present invention carries out high-rise working, should level up at jack place chock, check that whether jack work is normal simultaneously, and make the load balancing of each jack.
When using the present invention to carry out high-rise working, for strengthening the safety of operating personnel, lay closely-knitted safety net at guardrail place.
When using the present invention to carry out high-rise working, by adjusting the height of jack, rubber tire is made to be in unsettled off working state.
When using the present invention to carry out constructional materials lifting, lifting gear cantilever girder steel operating radius should be positioned at above construction operation platform, makes to be unlikely to during its operation departing from excessive and causing tilting and collapsing of operating platform because of operating platform center of gravity.
When using the present invention to carry out constructional materials lifting, the lifting capacity of constructional materials should not exceed the carrying capacity scope of electric block, and should meet the requirement for bearing capacity of main body frame.
Before when use, the present invention carries out constructional materials lifting, should in lifting gear sleeve pipe coating lubricating oil, be conducive to the rotation of cantilever girder steel in horizontal plane.
When using the present invention to carry out high-rise working, eminence pendant thing on construction operation platform should be prevented, avoid damaging ground operating personnel.

Claims (7)

1. be with the dismantled and assembled simple and easy four-wheel Mobile operating platform of constructional materials elevating function, comprise rubber tire, base, main body frame, it is characterized in that: be also provided with jack, cat ladder, construction operation platform, constructional materials lifting gear and guardrail; Described base is welded by shaped steel or is bolted and forms, in sphere of movements for the elephants shape; Described main body frame is made up of steel post, gooseneck and hound I, the suspension column welding edges of described steel post has steel plate, described steel plate is welded to connect with base shaped steel top flange plate or bolt is connected, described gooseneck is along being highly distributed on steel post, to be welded to connect with steel post or bolt is connected, described hound I draws establish with steel post, gooseneck diagonal angle, and is welded to connect or bolt connection; Described cat ladder is located at main body frame sidepiece, extends to construction operation platform from base, with base shaped steel, main body frame gooseneck and construction operation platform limit girder steel is welded to connect or bolt is connected; Described construction operation platform is located at main body frame steel post top; Described constructional materials lifting gear is located at above construction operation platform, be made up of steel pipe column, cantilever girder steel and electric block, described steel pipe column is provided with hoop location-plate and sleeve pipe, described casing pipe sleeve is at steel pipe column top, sleeve bottom drops on hoop location-plate, one end of described cantilever girder steel is connected with sleeve pipe vertical welding or bolt connects, and the other end installs electric block; Described guardrail is located at construction operation platform surrounding, is welded to connect or bolt is connected bottom guardrail with construction operation platform limit girder steel.
2. the dismantled and assembled simple and easy four-wheel Mobile operating platform of band constructional materials elevating function according to claim 1, it is characterized in that: described rubber tire totally 4, point walking rubber tire and universal rubber wheel, to be welded to connect with base shaped steel bottom wing listrium or bolt is connected respectively by each 2.
3. the dismantled and assembled simple and easy four-wheel Mobile operating platform of band constructional materials elevating function according to claim 1 and 2, it is characterized in that: described jack is hand-operated vertical hydraulic jack, totally 6, lay respectively at below main body frame steel post, jack top and base shaped steel bottom wing listrium are welded and fixed.
4. the dismantled and assembled simple and easy four-wheel Mobile operating platform of band constructional materials elevating function according to claim 1 and 2, is characterized in that: the steel pipe column of described constructional materials lifting gear doubles as the steel post of main body frame.
5. the dismantled and assembled simple and easy four-wheel Mobile operating platform of band constructional materials elevating function according to claim 1 and 2, is characterized in that: set up hound II between described cantilever girder steel and sleeve pipe.
6. the dismantled and assembled simple and easy four-wheel Mobile operating platform of band constructional materials elevating function according to claim 1 and 2, is characterized in that: described cat ladder is made up of steel pipe or round steel.
7. the dismantled and assembled simple and easy four-wheel Mobile operating platform of band constructional materials elevating function according to claim 1 and 2, is characterized in that: described guardrail is made up of steel pipe or round steel.
CN201510354779.1A 2015-06-25 2015-06-25 With the dismantled and assembled simple and easy four-wheel Mobile operating platform of constructional materials elevating function Active CN104878916B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510354779.1A CN104878916B (en) 2015-06-25 2015-06-25 With the dismantled and assembled simple and easy four-wheel Mobile operating platform of constructional materials elevating function

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510354779.1A CN104878916B (en) 2015-06-25 2015-06-25 With the dismantled and assembled simple and easy four-wheel Mobile operating platform of constructional materials elevating function

Publications (2)

Publication Number Publication Date
CN104878916A CN104878916A (en) 2015-09-02
CN104878916B true CN104878916B (en) 2016-03-30

Family

ID=53946573

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510354779.1A Active CN104878916B (en) 2015-06-25 2015-06-25 With the dismantled and assembled simple and easy four-wheel Mobile operating platform of constructional materials elevating function

Country Status (1)

Country Link
CN (1) CN104878916B (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105239783A (en) * 2015-09-11 2016-01-13 方流生 Water-cooled lifting device for building engineering
CN105133858A (en) * 2015-09-30 2015-12-09 兰州兰石重型装备股份有限公司 Adjustable ladder stand for safety construction
CN105720520A (en) * 2016-04-25 2016-06-29 邹平县供电公司 Auxiliary construction tool for power supply station
CN107152162A (en) * 2017-05-26 2017-09-12 大唐环境产业集团股份有限公司 A kind of novel site inspection platform
CN107419889B (en) * 2017-06-24 2022-12-13 浙江省二建建设集团有限公司 Operation platform for indoor roof construction
CN109577657B (en) * 2018-11-21 2020-10-27 义乌市研创工业设计有限公司 Brick conveying frame for wall building
CN113982239A (en) * 2021-10-28 2022-01-28 中化二建集团有限公司 Steel structure wall panel installation construction method

Family Cites Families (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4275797A (en) * 1979-04-27 1981-06-30 Johnson Raymond R Scaffolding power attachment
CN2254926Y (en) * 1996-07-26 1997-05-28 周德龙 Composed scaffold
CN2383905Y (en) * 1998-09-17 2000-06-21 宋永军 Portable combined lift scaffold
DE20008581U1 (en) * 2000-05-15 2000-08-10 Vill Josef Scaffolding
CN2828210Y (en) * 2005-10-13 2006-10-18 张含廉 Movable lifting working platform
CN201261939Y (en) * 2008-09-10 2009-06-24 中建五局第三建设有限公司 Overhead vehicle for construction
CN201865323U (en) * 2010-11-24 2011-06-15 山西四建集团有限公司 Movable ultrahigh multilayer combinational scaffold for complex ground
JP5869526B2 (en) * 2013-06-17 2016-02-24 ソフトバンク株式会社 Exercise equipment and exercise equipment set
CN204781879U (en) * 2015-06-25 2015-11-18 湖南省第六工程有限公司 Dismantled and assembled simple and easy four -wheel of taking building material raising and lowering functions removes operation platform

Also Published As

Publication number Publication date
CN104878916A (en) 2015-09-02

Similar Documents

Publication Publication Date Title
CN104878916B (en) With the dismantled and assembled simple and easy four-wheel Mobile operating platform of constructional materials elevating function
CN204781879U (en) Dismantled and assembled simple and easy four -wheel of taking building material raising and lowering functions removes operation platform
CN102383588A (en) Lifting platform for protecting safety of high-level construction
WO2014015757A1 (en) Bridge maintenance vehicle with hinge-connected type hanging bracket and capable of avoiding bridge-side obstacles
US3302749A (en) Derrick scaffold structure
CN201240787Y (en) Flat-top tower crane
CN105271011A (en) Multifunctional micro hoister
CN104291222A (en) Rigid protection and crane integration system inside super high-rise building core tube
CN102587643A (en) Large-tonnage long-stroke cylinder jacking formwork
CN209193460U (en) A kind of movable lifting Large-size rebar cage weld job operating platform
CN209038882U (en) A kind of moveable suspended bracket for lifting pipeline in piping lane
CN204311717U (en) Detachable combined Mobile operating platform
CN214462660U (en) Fixed turret and working machine provided with same
CN210134344U (en) Trolley for mounting bridge center joint drain pipe
CN209989034U (en) A hoisting frame for factory building piping erection
CN209957241U (en) Steel hanger
CN208791035U (en) Solid concrete roabed assembles portal frame with rail
CN105970893A (en) Combined round rack pile leg construction platform
CN207027352U (en) Large-size machine is unpowered attaching/detaching apparatus
CN109607437B (en) Method for quickly installing wear-resistant lining plate in large funnel by using movable lifting vehicle
CN204661109U (en) Two-layer single-column lifting working platform
CN204898518U (en) Bridge drain pipe installation device
CN204661108U (en) Two-layer twin columns lifting working platform
CN210081078U (en) Floor type belt replacing auxiliary tool
CN216074809U (en) Bridge rail guard template installation platform truck

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant