CN104847407A - Roof plate spraying and gushing water collecting combination device and assembly method thereof - Google Patents

Roof plate spraying and gushing water collecting combination device and assembly method thereof Download PDF

Info

Publication number
CN104847407A
CN104847407A CN201510256839.6A CN201510256839A CN104847407A CN 104847407 A CN104847407 A CN 104847407A CN 201510256839 A CN201510256839 A CN 201510256839A CN 104847407 A CN104847407 A CN 104847407A
Authority
CN
China
Prior art keywords
top board
water burst
combination unit
collecting pipe
threeway
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510256839.6A
Other languages
Chinese (zh)
Inventor
刘人太
张红军
李术才
李海燕
白继文
冯啸
郑卓
李红伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong University
Original Assignee
Shandong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong University filed Critical Shandong University
Priority to CN201510256839.6A priority Critical patent/CN104847407A/en
Publication of CN104847407A publication Critical patent/CN104847407A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention relates to a roof plate spraying and gushing water collecting combination device and an assembly method of the roof plate spraying and gushing water collecting combination device. The roof plate spraying and gushing water collecting combination device mainly comprises a trapezoid drum, wherein flange plates are arranged on the edges of the upper portion of the trapezoid drum, the bottom of the trapezoid drum is communicated with a flange through a sleeve, the flange is further communicated with a flow guide tube, and the other end of the flow guide tube is communicated with a collecting tube through a tee. After the roof plate spraying and gushing water collecting combination device is installed in a pit and/or a tunnel, the problem that spraying and gushing water cannot be easily collected can be well solved, and the occupied construction space is small.

Description

A kind of top board drenches water burst collects combination unit and assembly method thereof
Technical field
The present invention relates to and belong to colliery, iron ore, tunnel and mine tunnel engineering water hazard prediction field, specifically, relate to a kind of top board and drench water burst collection combination unit and assembly method thereof.
Background technology
Along with coal in China demand constantly rises and the exhaustion of coal resources, the coal seam of hydrogeological relative complex is obliged to go to exploit in increasing colliery.Some coal mine roadways are in digging process, and because the original mechanical balance of top board is broken, roof fracture constantly to deep expansion, is directly communicated with water producing fractures or aquifer, causes top board to occur large area trickle phenomenon.
Rig is also as easy as rolling off a log when playing anchor pole, anchor cable boring to be got through containing water producing fractures, causes anchor pole, anchor cable hole water burst serious.Top board large area trickle and anchor pole (rope) hole large discharge water burst be difficult to administer, safeguard to roadway construction and some corrosion-prone hardwares and cause very large difficulty, especially the working environment of underground labour can be worsened further, not only certain hidden danger is caused to the safety of workman, cause certain shade at heart more to underground labour, affect efficiency of construction.
In prior art, drench water burst gathering-device and method from top board and mainly contain two kinds:
One is publication number is that CN103075167A lays top board water-stop sheet or water proof cloth method, and top board trickle flows directly on water-stop sheet or water proof cloth, flows directly into gutter along coal side.Its major defect has four: 1. because closure when every block water-stop sheet or the splicing of water proof cloth is poor, complex process, top board trickle easily flows out in stitching portion, and secondary causes top board to drench water burst and flows directly into tunnel; 2. be not suitable for top board, anchor pole (rope) holes the water outlet of large area large discharge, very easily on water-stop sheet or water proof cloth, forms string bag phenomenon, to wire lath build-up of pressure; 3. water-stop sheet or water proof cloth are very easily broken in top board exterior portion by anchor pole, anchor cable, cause water proof to lose efficacy; 4. top board trickle along coal side enter gutter by directly causing side portion's anchor pole, wire lath gets rusty, and brings new potential safety hazard to tunnel.
The top board trickle collector of the second to be publication number be CN202039899U, this kind of top board trickle collector major defect has three: 1. volume is larger, not too be applicable to the working environment that down-hole coal road is narrower and small, especially the gutter of its underpart causes larger difficulty by directly to transport, pedestrian; 2. this water collector gathering-device be mainly applicable to back drenching area not quite, particularly single anchor pole (rope) to hole the situation of water outlet, to large area top board trickle because cannot combinationally use no longer applicable; 3. adopt magnet to hang on wire lath, tunnel safety hidden danger will be caused, do not meet safety of coal mines regulation.
Therefore, how to design a kind of brand-new device, solve the problems referred to above, be those skilled in the art faced by.
Summary of the invention
The object of the invention is for overcoming above-mentioned the deficiencies in the prior art, providing a kind of top board to drench water burst and collecting combination unit and assembly method thereof.This device is in down-hole and/or tunnel after installation, and the problem that water burst is collected is drenched in solution that can be good, and it is less to take construction space.
In order to reach above-mentioned purpose, the present invention adopts following technical scheme:
A kind of top board drenches water burst collects combination unit, comprising:
Trapezoidal cylinder, the top edge of this trapezoidal cylinder is provided with frange plate, and the bottom of trapezoidal cylinder is connected with flange through sleeve pipe, and flange is connected with mozzle again, and the other end of mozzle is connected with collecting pipe through threeway.
Preferably, described trapezoidal cylinder is that tin plate rolling forms.
Preferably, described frange plate is provided with multiple bolt hole.
Preferably, frange plate is also tin plate material.
Preferably, the collecting pipe that described collecting pipe connects rear least significant end by threeway or two-way is positioned at gutter.
Preferably, described mozzle and collecting pipe are pvc pipe.
Preferably, described trapezoidal cylinder is forge piece of step type structure.
Present invention also offers above-mentioned top board and drench the assembly method that water burst collects combination unit, comprise the steps:
A, trapezoidal cylinder, frange plate, sleeve pipe, flange, mozzle, threeway and collecting pipe are transported in tunnel;
B, according to be followed successively by from top to bottom trapezoidal cylinder, frange plate, sleeve pipe, flange, mozzle and threeway order assemble, form top board and drench water burst and collect combination unit, two other interface of threeway is connected with collecting pipe;
C, assemble multiple top board and drench water burst and collect combination unit, adjacent top board being drenched water burst, to collect the frange plate of combination unit overlapping, utilizes securing member that frange plate is fastening;
D, utilize two-way and/or threeway to be connected collecting pipe, the delivery port of the collecting pipe of least significant end is positioned at gutter.
The invention has the beneficial effects as follows: the present invention has the following advantages:
1, a difficult problem for back large area, large discharge pouring water burst is solved.This captation is connected between two by bottom pvc plastic conduit, pouring water burst in the most any one section of tunnel length is pooled to a place, be discharged in default gutter, portion of side, solve and the difficult problem that water burst cannot collect place discharge is drenched for tunnel large area, large discharge in the past;
2, closure is good.Multiple bolt hole is reserved with in this captation top frange plate, by bolt, the frange plate that adjacent four top boards pouring water burst collects combination unit is overlaped, so exposed at the basic no-top plate of the surrounding of this captation, top board drenches water burst and substantially all falls in trapezoidal cylinder, and sealing is also good between bottom pvc plastic pipe and threeway, overflow without the globule, solve a difficult problem for device closure difference in roof water improvement in the past;
3, reusable edible, long service life.Captation of the present invention detachably reuses, and after the top board pouring water burst in one section of tunnel terminates, this captation in this section of tunnel can be removed, when required in the tunnel being installed to another section of water outlet;
4, lane space is taken little.Captation upper design of the present invention becomes three notch cuttypes, greatly reduces device volume, and the present invention only takies very little space, top, tunnel, can not counteract effect to bottom pedestrian and transport;
5, any one section of tunnel inside ceiling panel unit area trickle amount can accurately be measured.Captation in any one section of tunnel is linked together by bottom pvc plastic pipe and pvc Three-way Union, pouring water burst in this section of tunnel is pooled to a place, namely carry out accurate measurement by corresponding measurement mechanism, solve is all the difficult problem blindly guessed by experience in the past;
6, a whole set of captation structure is simple, and be easy to processing and install, and the material that this device adopts is cheap material common on market, processing cost is low, economical rationality.
Accompanying drawing explanation
Fig. 1 is elevation section of the present invention;
Fig. 2 is side view cross section of the present invention;
Fig. 3 is top view of the present invention;
Fig. 4 is final installation design sketch of the present invention
Wherein: 1, trapezoidal cylinder, 2, sleeve pipe, 3, flange, 4, mozzle, 5, threeway, 6, collecting pipe, 7, bolt, 8, frange plate, 9, top board, 10, tunnel, 11, gutter.
Detailed description of the invention
Below in conjunction with accompanying drawing, the present invention is described in detail.
Embodiment 1: a kind of top board drenches water burst collects combination unit, its structure as Figure 1-3, comprise: trapezoidal cylinder 1, the top edge of this trapezoidal cylinder 1 is provided with frange plate 8, the bottom of trapezoidal cylinder 1 is connected with flange 3 through sleeve pipe 2, flange 3 is connected with mozzle 4 again, and the other end of mozzle 4 is connected with collecting pipe 6 through threeway 5.
Described trapezoidal cylinder 1 for thickness be that the rolling of 2mm tin plate forms, cylindrical shell section be three trapezoidal stepped, the rectangle length of side of the first bench is all 40cm, the rectangle four limit length of side of the second step is 20cm, the 3rd bench rectangle four limit length of side is 10cm, in the middle of 3rd bench rectangular slab, reserved diameter is the circular hole of 4.8cm, and circular hole is convenient to be communicated with sleeve pipe 2;
Described frange plate 8 is for stretch out trapezoidal cylinder 1 first bench rectangle four edges rectangle respectively, be of a size of 40*3cm, the white iron sheet rolling being all thickness 2mm with trapezoidal cylinder one forms, and each frange plate 8 opens apart from minor face mid point 10cm place the bolt hole 7 that two diameters are 2cm respectively; Better is chosen as, and frange plate 8 is one-body molded with trapezoidal cylinder 1.
Described sleeve pipe 2 material is identical with trapezoidal cylinder 1, and diameter is 5cm, and length is generally 5 ~ 10cm;
After described collecting pipe 6 is connected by threeway or two-way, the collecting pipe of least significant end is positioned at gutter 11.
Described mozzle 4 is pvc pipe with collecting pipe 6.
Described pvc plastic pipe is that special white refractory material is made, and internal diameter specification is 5cm, and length can need to intercept according to scene, and length is generally 5 ~ 10cm;
Described threeway can be pvc plastic pipe tee junction, and for special white refractory material is made, three termination consistent size, diameter is advisable slightly larger than irony sleeve pipe.
The present embodiment additionally provides above-mentioned top board and drenches the assembly method that water burst collects combination unit, comprises the steps:
A, trapezoidal cylinder 1, frange plate 8, sleeve pipe 2, flange 3, mozzle 4, threeway 5 and collecting pipe 6 are transported in tunnel 10;
B, the carrying out of trapezoidal cylinder 1, frange plate 8, sleeve pipe 2, flange 3, mozzle 4 and threeway 5 to be assembled, form above-mentioned top board and drench water burst collection combination unit, two other interface of threeway 5 is connected with collecting pipe 6, and any one top board drenches water burst collection combination unit all should be close to top board 9;
C, assemble multiple top board and drench water burst and collect combination unit, adjacent top board being drenched water burst, to collect the frange plate 8 of combination unit overlapping, and utilize securing member by fastening for frange plate 8, securing member can select bolt 7;
D, utilize two-way and/or threeway to be connected collecting pipe 6, the delivery port of the collecting pipe 6 of least significant end is positioned at gutter.
The effect in tunnel 10 of this device, as shown in Figure 4.The frange plate 8 of adjacent multiple gathering-devices overlaps, and collecting pipe 6 is passed through by aqueous reflux in gutter 11 in bottom.
In said structure and method, the item that should be noted that is:
1, four frange plates of each pouring water burst gathering-device should ensure the equal and smooth surface of size, prevent the frange plate of adjacent pouring water burst gathering-device during connecting bolt 7 from cannot overlap, thus do not reach the effect of closed roof rock, have trickle to flow into tunnel;
2, should ensure the sealing of welding when sleeve welds with trapezoidal cylinder, anti-sealing is gushed out from weld seam;
3, mozzle 4 and collecting pipe 6 should ensure to insert threeway 5 more than interface 2cm, prevent because the too small pvc of the causing plastic pipe of frictional force is gone out by flowing water;
4, trapezoidal cylinder 1 surrounding application iron wire is wrapped on the steel mesh reinforcement of back, and the steel wire winding number of turns should not be less than 5 circles, prevents trapezoidal cylinder from falling and injures pedestrian by a crashing object;
5, tunnel is when transporting higher object, first can be unloaded by this device, prevent owing to colliding too quickly, this device is broken or touched off, cause potential safety hazard or accident.
Application examples:
It is domestic that Wang Lou colliery is positioned at Yu Tun town, Shizhong District, Jining City, and be under the jurisdiction of Linyi Mining Group Co., Ltd, the coal seam of 11307,13301 liang of working face minings is 3 oncoal, exploitation 3 onthe direct water filling aquifer of coal is 3 onthe upper Jurassic system sandy conglomerate aquifer of Seam Roof And Floor sandstone aquifer and Local topography.11307,13301 liang of face up and down trough are in tunneling process, owing to lacking the accurate judgement to tunnel roof and floor lithologic and hydrogeology, cause tunnel in tunneling process, back occurs that large area drenches water burst phenomenon, and local anchor pole (rope) water outlet of holing reaches 15m 3/ h, in tunnel, the operating environment of workman constantly worsens, and has had a strong impact on the normal driving in tunnel, has caused certain economic loss.
Finally, it has been decided through consideration adopt top board of the present invention drench water burst collect combination unit carry out top board drench water burst collect after in the gutter that gutter enters portion of side, tunnel, then discharge tunnel.After adopting this device, tunnel has substantially been stopped top board and has been drenched the phenomenon that water burst flows directly into tunnel, to the operating environment that operating personnel in tunnel creates a basic no-top plate trickle, accelerates construction speed, for ore deposit side has retrieved certain economic loss.
To the above-mentioned explanation of the disclosed embodiments, professional and technical personnel in the field are realized or uses the present invention.To be apparent for those skilled in the art to the multiple amendment of embodiment, General Principle as defined herein can be without departing from the spirit or scope of the present invention, realize in other embodiments, the part be not described in detail, for prior art, do not repeat at this.Therefore, the present invention can not be restricted to these embodiments shown in this article, but will meet the widest scope consistent with principle disclosed herein and feature.

Claims (8)

1. top board drenches a water burst collection combination unit, it is characterized in that, comprising:
Trapezoidal cylinder, the top edge of this trapezoidal cylinder is provided with frange plate, and the bottom of trapezoidal cylinder is connected with flange through sleeve pipe, and flange is connected with mozzle again, and the other end of mozzle is connected with collecting pipe through threeway.
2. top board according to claim 1 drenches water burst collection combination unit, and it is characterized in that, described trapezoidal cylinder is that tin plate rolling forms.
3. top board according to claim 1 drenches water burst collection combination unit, and it is characterized in that, described frange plate is provided with multiple bolt hole.
4. top board according to claim 3 drenches water burst collection combination unit, and it is characterized in that, frange plate is also tin plate material.
5. top board according to claim 1 drenches water burst collection combination unit, it is characterized in that, after described collecting pipe is connected by threeway or two-way, the collecting pipe of least significant end is positioned at gutter.
6. top board according to claim 1 drenches water burst collection combination unit, and it is characterized in that, described mozzle and collecting pipe are pvc pipe.
7. top board according to claim 1 drenches water burst collection combination unit, and it is characterized in that, described trapezoidal cylinder is forge piece of step type structure.
8. utilize any one of claim 1-7 top board to drench an assembly method for water burst collection combination unit, it is characterized in that, comprise the steps:
A, trapezoidal cylinder, frange plate, sleeve pipe, flange, mozzle, threeway and collecting pipe are transported in tunnel;
B, according to be followed successively by from top to bottom trapezoidal cylinder, frange plate, sleeve pipe, flange, mozzle and threeway order assemble, form top board and drench water burst and collect combination unit, two other interface of threeway is connected with collecting pipe;
C, assemble multiple top board and drench water burst and collect combination unit, adjacent top board being drenched water burst, to collect the frange plate of combination unit overlapping, utilizes securing member that frange plate is fastening;
D, utilize two-way and/or threeway to be connected collecting pipe, the delivery port of the collecting pipe of least significant end is positioned at gutter.
CN201510256839.6A 2015-05-19 2015-05-19 Roof plate spraying and gushing water collecting combination device and assembly method thereof Pending CN104847407A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510256839.6A CN104847407A (en) 2015-05-19 2015-05-19 Roof plate spraying and gushing water collecting combination device and assembly method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510256839.6A CN104847407A (en) 2015-05-19 2015-05-19 Roof plate spraying and gushing water collecting combination device and assembly method thereof

Publications (1)

Publication Number Publication Date
CN104847407A true CN104847407A (en) 2015-08-19

Family

ID=53847332

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510256839.6A Pending CN104847407A (en) 2015-05-19 2015-05-19 Roof plate spraying and gushing water collecting combination device and assembly method thereof

Country Status (1)

Country Link
CN (1) CN104847407A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106351693A (en) * 2016-09-09 2017-01-25 山东大学 Water seepage drainage device used for tunnel and drainage method
CN107228696A (en) * 2017-06-15 2017-10-03 山东大学 A kind of tunnel bulk water yield real time automatic measuring device and its application method
CN109322703A (en) * 2018-11-29 2019-02-12 亢建华 Top plate water drenching collector
CN110068484A (en) * 2019-04-29 2019-07-30 中国矿业大学 A kind of underground water drenching water sample collection device and its method
CN110486085A (en) * 2019-03-12 2019-11-22 浙江交工宏途交通建设有限公司 A kind of Karst Geological Landscape constructing tunnel drainage arrangement
CN112031870A (en) * 2020-07-21 2020-12-04 中铁武汉勘察设计研究院有限公司 Tunnel local water burst protection device and application method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20060062492A (en) * 2004-12-03 2006-06-12 현대자동차주식회사 Auto drain device for surge tank of bus
CN101285397A (en) * 2008-05-29 2008-10-15 中交第二公路勘察设计研究院有限公司 Submarine tunnel transverse water collecting tank
CN101498628A (en) * 2009-03-16 2009-08-05 刘宪武 Door-based calibration method for water turbidometer and its sample collection system
CN201581928U (en) * 2009-11-28 2010-09-15 中煤第五建设公司 Intelligent drainage device in subway tunnels
CN202337485U (en) * 2011-10-28 2012-07-18 中国一冶集团有限公司 Combined material cabin funnel
CN203835447U (en) * 2014-03-26 2014-09-17 南京梅山冶金发展有限公司 Automatic storing and discharging device for underground laneway top plate gushing water

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20060062492A (en) * 2004-12-03 2006-06-12 현대자동차주식회사 Auto drain device for surge tank of bus
CN101285397A (en) * 2008-05-29 2008-10-15 中交第二公路勘察设计研究院有限公司 Submarine tunnel transverse water collecting tank
CN101498628A (en) * 2009-03-16 2009-08-05 刘宪武 Door-based calibration method for water turbidometer and its sample collection system
CN201581928U (en) * 2009-11-28 2010-09-15 中煤第五建设公司 Intelligent drainage device in subway tunnels
CN202337485U (en) * 2011-10-28 2012-07-18 中国一冶集团有限公司 Combined material cabin funnel
CN203835447U (en) * 2014-03-26 2014-09-17 南京梅山冶金发展有限公司 Automatic storing and discharging device for underground laneway top plate gushing water

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106351693A (en) * 2016-09-09 2017-01-25 山东大学 Water seepage drainage device used for tunnel and drainage method
CN107228696A (en) * 2017-06-15 2017-10-03 山东大学 A kind of tunnel bulk water yield real time automatic measuring device and its application method
CN109322703A (en) * 2018-11-29 2019-02-12 亢建华 Top plate water drenching collector
CN110486085A (en) * 2019-03-12 2019-11-22 浙江交工宏途交通建设有限公司 A kind of Karst Geological Landscape constructing tunnel drainage arrangement
CN110486085B (en) * 2019-03-12 2020-12-11 浙江交工宏途交通建设有限公司 Karst geology tunnel construction drainage device
CN110068484A (en) * 2019-04-29 2019-07-30 中国矿业大学 A kind of underground water drenching water sample collection device and its method
CN110068484B (en) * 2019-04-29 2024-02-20 中国矿业大学 Underground water sample collecting device and method
CN112031870A (en) * 2020-07-21 2020-12-04 中铁武汉勘察设计研究院有限公司 Tunnel local water burst protection device and application method thereof

Similar Documents

Publication Publication Date Title
CN104847407A (en) Roof plate spraying and gushing water collecting combination device and assembly method thereof
CN103775127B (en) A kind of low-permeable high gas layer group topping Comprehensive Gas Control method
CN100593630C (en) Caving zone edge inclined drill hole bushing burying method for extracting and discharging gas for goaf and adjacent layer
CN105756700B (en) Large section tunnel wears the construction method and hole sealing structure of coal measure strata section
CN111335944B (en) Coal face gangue slurry pipeline collaborative filling method
CN105507938A (en) Construction method of hydraulic flushing and presplit blasting combined permeability-increasing extraction system in drill holes
CN104314569B (en) The exploitation method of a kind of deep Pore brine and low-grade solid kalium mine
CN104033151A (en) Safe mining method of ten million-ton mine under complicated conditions of dual-system coal seams
CN103277129B (en) One prevents Top Corner Gas on Coal Face to transfinite technology
CN104975868A (en) Top plate high-position boring large-diameter long-drill-hole gas extraction method based on directional drilling
CN205089360U (en) Large aperture collecting space area pipe laying gas drainage device
CN103306714A (en) Gas control method for triple-purpose use of drilled holes in coal floor of close distance seam group
CN105240024A (en) Parallel shield tunneling method for extended construction of subway station
CN208605228U (en) A kind of mine laneway top plate seepage drainage device
CN110067597A (en) A kind of mine angle of depression negative pressure visits the method for putting old dead zone ponding
CN204267058U (en) A kind of erecting tools for anchor cable resin explosive roll
CN105065009A (en) Method for shield expanding construction of subway station
CN102797469A (en) Method for constructing inclined shaft by applying TBM (Tunnel Boring Machine) with earth pressure balancing function
CN104234716B (en) The packed cofferdam method of mining by the way of filling
CN205689216U (en) A kind of reinforced combined retaining structure of pipe-plate lining
CN102619521B (en) Construction method for vertical shaft bedrock section wall structure
CN201991548U (en) Drainage, slag discharge and gas extraction integrated device
CN206360720U (en) A kind of novel flexible filling isolation barricade
CN103397881B (en) A kind of engineering method expanding mineral building stopping area
CN103557026A (en) Method for removing upper corner gas based on pipe-jacking tunneling device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20150819