CN104842460B - A kind of main building structure of concrete mixing plant and its installation method of Fast Installation - Google Patents
A kind of main building structure of concrete mixing plant and its installation method of Fast Installation Download PDFInfo
- Publication number
- CN104842460B CN104842460B CN201410103368.0A CN201410103368A CN104842460B CN 104842460 B CN104842460 B CN 104842460B CN 201410103368 A CN201410103368 A CN 201410103368A CN 104842460 B CN104842460 B CN 104842460B
- Authority
- CN
- China
- Prior art keywords
- layer platform
- underframe
- building structure
- main building
- mixing plant
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B28—WORKING CEMENT, CLAY, OR STONE
- B28C—PREPARING CLAY; PRODUCING MIXTURES CONTAINING CLAY OR CEMENTITIOUS MATERIAL, e.g. PLASTER
- B28C9/00—General arrangement or layout of plant
- B28C9/02—General arrangement or layout of plant for producing mixtures of clay or cement with other materials
Abstract
The invention discloses the main building structure of concrete mixing plant and its installation method of a kind of Fast Installation.The main building structure of concrete mixing plant of the Fast Installation includes:Underframe;Stirring layer platform;Measuring layer platform;And column, which is in the way of being pivotally connected, the underframe, stirring layer platform and measuring layer platform are linked into an integrated entity, so as to column can switch between raised state and tilt state, in the raised state, the uprights vertical is in the underframe, stirring layer platform and measuring layer platform, in the tilt state, the column parallel to the underframe, stirring layer platform and measuring layer platform, or with the underframe, stirring layer platform and measuring layer platform into one less than 15 degree of angle.The main part of the main building structure of concrete mixing plant of the Fast Installation of the present invention is linked together by articulated manner such that it is able to is switched between raised state and tilt state, easily can be transported and install.
Description
Technical field
The present invention relates to technical field of engineering machinery, the concrete mixing plant main building knot of more particularly to a kind of Fast Installation
Structure.
Background technology
In the prior art, the main building structure of concrete mixing plant mainly includes stirring layer column, measuring layer column, stirring
Layer platform, measuring layer platform, stirring host, powder metering bucket, middle aggregate bin, level meter batch box and other equipment, it is above-mentioned
Each component or part be absolute construction.
The part of this main building structure independence of prior art is more.A kind of pattern for playing with building blocks is belonging to during installation, from
Under up in layer install.Platform is with bolts with column.When part is assembled together with part, overall sending out is not easy to
Goods.So, it is scattered before the mounting, is also scattered during delivery transport.Although, after individual part can be assembled together
Deliver again, but the relatively decentralized state of existing main building structure member can not be changed on the whole.
The problem that this main building structure is present is:As parts are more, look for material to spend the time long, assembling easily occur wrong
By mistake, field installation time is longer, and installation cost is high.Another question is not assembled together during delivery, the handling of part
It is cumbersome.This main building structure, in order to realize that some install facility, it has to stirring layer platform turns over, in its structure
After installing column, then overturn back.Do so, needs larger vacant lot, also there is very big potential safety hazard.
For this reason, it may be necessary to there is a kind of main building structure, overcome or at least mitigate to a certain extent the above-mentioned of prior art and lack
One or more in falling into.
The content of the invention
Concrete mixing plant is the combined unit for concentrated compactness concrete, also known as concrete prefabricated field.Due to it
Mechanization, automaticity are higher, so productivity ratio is also very high, and can guarantee that the quality of concrete and save cement, are usually used in
The engineerings such as concrete works amount is big, long in time limit, the large and medium-sized water conservancy that building site is concentrated, electric power, bridge.With urban construction etc.
Development, is had an enormous advantage using the mixing plant tool of concentrated compactness, offer commerical ready-mixed concrete, thus is developed rapidly, and
To promote Concrete Pumping Construction, realization is stirred, is conveyed, pouring mechanical integration of operation and create conditions.
Main building structure is the agent structure of concrete mixing plant, generally includes to stir layer platform, measuring layer platform, powder meter
Batch box, middle aggregate bin and level meter batch box etc..
Stirring layer platform is the platform for installing stirring host.
Measuring layer platform is the platform for installing powder metering bucket, middle aggregate bin, level meter batch box etc..
Powder metering bucket is for measuring powder(Such as cement, breeze, flyash)Sealing container, it is possible to temporarily store
Powder, which is installed on measuring layer platform.
Middle aggregate bin is used for the sandstone aggregate that temporarily storage is come up by the conveying of oblique belt feeder, and which is installed on measuring layer platform
On.
Level meter batch box is the sealing container for measuring water, liquid additive etc., it is possible to temporarily store water and liquid
Additive, which is installed on measuring layer platform.
It is an object of the invention to provide a kind of main building structure of concrete mixing plant of Fast Installation is overcoming or at least subtract
One or more in the drawbacks described above of light prior art.
For achieving the above object, the present invention provides a kind of main building structure of concrete mixing plant of Fast Installation, described quick
The main building structure of concrete mixing plant of installation includes:
Underframe;
Stirring layer platform;
Measuring layer platform;And
Column, the underframe, stirring layer platform and measuring layer platform are linked into an integrated entity in the way of being pivotally connected by which,
So as to column can be cut between raised state and tilt state relative to the underframe, stirring layer platform and measuring layer platform
Change,
In the raised state, the uprights vertical in the underframe, stirring layer platform and measuring layer platform,
In the tilt state, the column parallel to the underframe, stirring layer platform and measuring layer platform, or with it is described
Underframe, stirring layer platform and measuring layer platform are into an angle less than 15 degree.
Preferably, the lower end of the column is pivotally connected with the underframe;The upper end of the column is flat with the measuring layer
Platform is pivotally connected;The middle part of the column is pivotally connected with the stirring layer platform.
Preferably, the quantity of the column is four.
Preferably, in raised state, four root post projection in the horizontal plane is in rectangle or foursquare four
On individual summit.
The two root posts of side and being pivotally connected highly for underframe are preferably located at, are stood higher than two positioned at opposite side
Post is pivotally connected height with underframe.
The two root posts of the side and being pivotally connected highly for measuring layer platform are preferably located at, higher than positioned at described
The two root posts of opposite side are pivotally connected height with measuring layer platform.
It is preferably located at the two root posts of the side and being pivotally connected highly, higher than the upper table of the underframe for underframe
Face.
It is preferably located at the two root posts of the opposite side and being pivotally connected highly, less than the meter for measuring layer platform
The lower surface of amount layer platform.
Be preferably located at the two root posts of the side and underframe the upper surface for being pivotally connected height and the underframe it
Between distance, be pivotally connected height and the measuring layer platform equal to two root posts and the measuring layer platform of the opposite side
The distance between lower surface.
The distance between two root posts of the side are preferably located at more than the stirring layer platform and/or the meter
Amount size of the layer platform on the range direction.
The present invention also provides a kind of installation method of the main building structure of concrete mixing plant of Fast Installation, and methods described includes
Following step:Under tilt state, by the main building structure of concrete mixing plant whole Transporting of Fast Installation as above to peace
Holding position;The main building structure of concrete mixing plant of described Fast Installation is sling to raised state from the tilt state;With
And the main building structure of concrete mixing plant of described Fast Installation is fastenedly connected, it is allowed to keep the raised state.
The main part of the main building structure of concrete mixing plant of the Fast Installation of the present invention is connected to one by articulated manner
Rise such that it is able to switch between raised state and tilt state, easily can transport and install.
Description of the drawings
Fig. 1 is that the installment state of the main building structure of concrete mixing plant of Fast Installation according to an embodiment of the invention is faced
Schematic diagram.
Fig. 2 is the installment state schematic side view of the main building structure of concrete mixing plant of Fast Installation shown in Fig. 1.
Fig. 3 is the installment state schematic top plan view of the main building structure of concrete mixing plant of Fast Installation shown in Fig. 1.
Fig. 4 is schematic diagram of the main building structure of concrete mixing plant of Fast Installation shown in Fig. 1 when in tilt state.
Fig. 5 is the main building structure of concrete mixing plant of Fast Installation shown in Fig. 1 in the schematic diagram during erecting.
Reference:
1 | Underframe | 8 | Stirring host |
2 | Bearing pin | 9 | Powder metering bucket |
3 | First column | 10 | Middle aggregate bin |
4 | Second column | 11 | Level meter batch box |
5 | 3rd column | 12 | Measuring layer platform |
6 | 4th column | 13 | Support |
7 | Stirring layer platform |
Specific embodiment
To make purpose, technical scheme and the advantage of present invention enforcement clearer, below in conjunction with the embodiment of the present invention
Accompanying drawing, the technical scheme in the embodiment of the present invention is further described in more detail.In the accompanying drawings, identical from start to finish or class
As label represent same or similar element or the element with same or like function.Described embodiment is the present invention
A part of embodiment, rather than the embodiment of whole.It is exemplary below with reference to the embodiment of Description of Drawings, it is intended to use
It is of the invention in explaining, and be not considered as limiting the invention.Based on the embodiment in the present invention, ordinary skill people
The every other embodiment obtained under the premise of creative work is not made by member, belongs to the scope of protection of the invention.Under
Face combines accompanying drawing and embodiments of the invention is described in detail.
In describing the invention, it is to be understood that term " " center ", " longitudinal direction ", " horizontal ", "front", "rear",
The orientation or position relationship of the instruction such as "left", "right", " vertical ", " level ", " top ", " bottom " " interior ", " outward " is based on accompanying drawing institute
The orientation for showing or position relationship, are for only for ease of the description present invention and simplify description, rather than indicate or imply the dress of indication
Put or element with specific orientation, with specific azimuth configuration and operation, therefore it is not intended that must be protected to the present invention
The restriction of scope.
Included according to the main building structure of concrete mixing plant of the Fast Installation of a broad embodiment of the invention:Underframe;Stirring
Layer platform;Measuring layer platform;And column.The column in the way of being pivotally connected, by the underframe, stirring layer platform and meter
Amount layer platform links into an integrated entity.Column can relative to the underframe, stirring layer platform and measuring layer platform in raised state and
Switch between tilt state.That is, whole main building structure of concrete mixing plant can raised state and tilt state it
Between switch.
In the raised state(Referring to Fig. 1), the uprights vertical is flat in the underframe, stirring layer platform and measuring layer
Platform.In the tilt state(Referring to Fig. 4), the column parallel to the underframe, stirring layer platform and measuring layer platform, or with
The underframe, stirring layer platform and measuring layer platform are into an angle less than 15 degree.
The main part of the main building structure of concrete mixing plant of above-mentioned Fast Installation is linked together by articulated manner,
So as to switch between raised state and tilt state, easily can transport and install.
Fig. 1 is that the installment state of the main building structure of concrete mixing plant of Fast Installation according to an embodiment of the invention is faced
Schematic diagram.Fig. 2 is the installment state schematic side view of the main building structure of concrete mixing plant of Fast Installation shown in Fig. 1.Fig. 3 is figure
The installment state schematic top plan view of the main building structure of concrete mixing plant of Fast Installation shown in 1.
The main building structure of concrete mixing plant of the Fast Installation shown in Fig. 1 to Fig. 3 includes underframe 1;Stirring layer platform 7;Meter
Amount layer platform 12;And four root posts:First column 3, the second column 4, the 3rd column 5 and the 4th column 6.The column is with pivot
Turn the mode of connection, the underframe 1, stirring layer platform 7 and measuring layer platform 12 are linked into an integrated entity.
In the height direction, stir layer platform 7 to be arranged between underframe 1 and measuring layer platform 12.Stirring layer platform 7 is to use
In the platform for installing stirring host 8.Advantageously, stirring host 8 is mounted on stirring layer platform 7 in advance, as stirring layer platform 7 is transported
Defeated and installation.As such, it is possible to greatly reduce the time needed for in-site installation.Certainly, stirring host 8 also can as needed in peace
Installed at dress scene.
Measuring layer platform 12 is located at the top of main building structure of concrete mixing plant, is for installing powder metering bucket 9, centre
The platform of aggregate bin 10 and level meter batch box 11 etc..Advantageously, powder metering bucket 9, middle aggregate bin 10 and level meter batch box
One or more pre- in 11 is mounted on measuring layer platform 12, with the transport of measuring layer platform 12 with install.As such, it is possible to big
The big time reduced needed for in-site installation.Certainly, in powder metering bucket 9, middle aggregate bin 10 and level meter batch box 11
Or more also can be installed in erecting bed as needed.Powder metering bucket 9 is for measuring powder(Such as cement, ore deposit
Powder, flyash)Sealing container, it is possible to temporarily store powder.It is defeated by oblique belt feeder that middle aggregate bin 10 is used for temporarily storage
The sandstone aggregate sent up.Level meter batch box 11 is the sealing container for measuring water, liquid additive etc., it is possible to temporarily deposited
Water storage and liquid additive.
Further it will be understood that underframe 1;The shape and construction of stirring layer platform 7 and measuring layer platform 12 is not limited to figure
The embodiment shown, and can be to be arranged as required to.For example, underframe can be simple welding type frame structure, or may be used also
To carry reinforcement structure as needed.
First column 3, the second column 4, the 3rd column 5 and the 4th column 6 are at its lower end by bearing pin 2 and 1 pivot of underframe
Turn connection;It is pivotally connected with stirring layer platform 7 by bearing pin 2 in center;By bearing pin 2 and measuring layer platform 12 at top
It is pivotally connected.It is understood that the axis of the bearing pin is parallel to each other, the pivot axis being pivotally connected described in other words
It is parallel to each other.So, the first column 3, the second column 4, the 3rd column 5 and the 4th column 6 can relative to the underframe,
Stirring layer platform and measuring layer platform switch between raised state and tilt state.That is, whole concrete mixing plant
Main building structure can switch between raised state and tilt state.
In the raised state shown in Fig. 1, column vertically extends, flat perpendicular to the underframe, stirring layer platform and measuring layer
Platform.At this point it is possible to further column and the underframe, stirring layer platform and measuring layer platform are fixed(For example, by weldering
Connect or be threadedly coupled), whole main building structure of concrete mixing plant is maintained at into raised state.
In the tilt state shown in Fig. 4, column is parallel to the underframe, stirring layer platform and measuring layer platform.At this
In bright, " parallel " refers to general parallel orientation, i.e. both angles are within the scope of 5 degree.It is understood that as needed,
Tilt state, column and the underframe, stirring layer platform and measuring layer platform can be arranged to some larger angle, and such as 6
Degree, 10 degree etc., it is advantageous to the angle is less than or less than 15 degree.
Advantageously, in raised state, the projection in the horizontal plane of four root posts is in rectangle or foursquare four
On summit.
Referring to Fig. 1, positioned at the two root posts in left side(First column 3 and the second column 4)Height is pivotally connected with underframe 1
Degree, higher than the two root posts positioned at right side(3rd column 5 and the 4th column 6)With being pivotally connected highly for underframe.This is conducive to
Under tilt state form certain gap to accommodate corresponding component between underframe 1 and measuring layer platform 12, or avoid doing
Relate to.
Also for gap is formed, positioned at the two root posts in the left side(First column 3 and the second column 4)With metering
Layer platform 12 be pivotally connected height, higher than positioned at right side side two root posts(3rd column 5 and the 4th column 6)With measuring layer
Platform 12 be pivotally connected height.This is pivotally connected height and is combined together with the difference in height that is pivotally connected mentioned in the preceding paragraph,
So that the space of a generally cuboid is formed between underframe 1 and measuring layer platform 12, this is big by two differences in height
On body it is identical and realize.Two differences in height are substantially the same to be meaned:Connect with the pivot of underframe positioned at the two root posts in left side
Height is connect the distance between with the upper surface of the underframe, essentially equal to the pivot of the two root posts on right side and measuring layer platform
Connection height is the distance between with the lower surface of the measuring layer platform.
Advantageously, as shown in figure 1, positioned at the two root posts in left side and being pivotally connected highly, higher than the bottom for underframe
The upper surface of frame.Positioned at the two root posts on right side and being pivotally connected highly, less than the measuring layer platform for measuring layer platform
Lower surface.This be conducive to avoiding column topple over erect during with underframe and/or the measuring layer intervening platform.
Referring to Fig. 2, linked together by supporting 13 between first column 3 and the second column 4 in left side, it is whole so as to improve
The intensity of individual structure.It is understood that support 13 is not provided with where position is higher than stirring layer platform 7, so as to avoid
Interfere with the possibility of stirring layer platform 7 when toppling over.
Preferably, the distance between the first column 3 and the second column 4 are more than the stirring layer platform and/or the meter
Amount size of the layer platform on the range direction.This be conducive to avoiding column topple over erect during with stirring layer platform
And/or the measuring layer intervening platform.
The present invention is assembled together between column and platform by way of bearing pin connection from the beginning of pillar construction is changed.
Powder metering bucket, middle aggregate bin, level meter batch box are arranged on measuring layer platform;Stirring host is arranged on stirring layer platform
On.Whole main building structure is assembled together entirely.During delivery, column is kept flat with platform, parallel to the ground.During installation, around one
Two columns of common axis of rotation rotation are installed in a rotating manner to erect and(Pilot process is referring to Fig. 5), and due to known
Kinematic reasons, the platform of previous level remains in that level, meanwhile, propped up by column high come the installation site needed for reaching
Degree.When this main building structure is delivered, overall to deliver, integral hoisting can improve installation rate, and installation process is very convenient.
According to one embodiment of the invention, the installation method of the main building structure of concrete mixing plant comprises the steps:
Under tilt state, by the main building structure of concrete mixing plant whole Transporting of Fast Installation as above to installation site;By institute
The main building structure of concrete mixing plant of the Fast Installation stated is sling to raised state from the tilt state;And to described fast
The main building structure of concrete mixing plant that speed is installed is fastenedly connected, and is allowed to keep the raised state, i.e., so that the first column
3rd, the second column 4, the 3rd column 5 and the 4th column 6 are no longer able to relative to underframe 1, stirring layer platform 7 and measuring layer platform 12
Pivot.The concrete mode being fastenedly connected to main building structure of concrete mixing plant can be taken as needed so that mode.
In one embodiment, associated components are welded to connect.In another embodiment, will be threadedly coupled between associated components or
Riveting.In a further embodiment, support bar is set between associated components.It is understood that various companies can also be adopted
Connect the combination of mode to be fastenedly connected.Advantageously, in transport, stirring host 8, powder metering bucket 9, middle aggregate bin
The device such as 10 and level meter batch box 11 is already installed on the main building structure of concrete mixing plant.
The main building structure of concrete mixing plant of the present invention includes a underframe.Underframe is used to connect four root posts, allows four
Column is respectively on the position of four points of rectangle.Column is connected with the bearing pin that is connected by of underframe, and column can be the bottom of parallel to
Frame is rotated with the spaced winding bearing pin perpendicular to underframe position.Column can fall, during this fell, drive two platforms and
Stirring host on platform gradually smoothly reduces height together with hopper, until column is laid flat completely.In the process, pass through
The optimization of physical dimension, each part will not be interfered.When installing this main building structure, then the flow process contrary with the process of falling can
In the case of not interfering, it is quickly installed.The characteristics of main building structure, in addition to meeting and installing quickly, also meet
Overall structure disposably integrally can be lifted under the state of falling, and main building structure integrally can be transported by a transport vehicle
It is defeated, it is not necessary in addition the position of each part is adjusted.Additionally, the characteristics of in terms of this main building structure also has layout.Full
While foot entirety Fast Installation, the powder metering bucket and level meter batch box installed on measuring layer is placed in the two of middle aggregate bin
Side, has enough spaces to allow personnel to pass through between powder metering bucket and middle aggregate bin, level meter batch box and middle aggregate bin it
Between also leave the space that personnel pass through.
It is last it is to be noted that:Above example only to illustrate technical scheme, rather than a limitation.To the greatest extent
Pipe has been described in detail to the present invention with reference to the foregoing embodiments, it will be understood by those within the art that:Which is still
Technical scheme described in foregoing embodiments can be modified, or equivalent is carried out to which part technical characteristic and replace
Change;And these modifications or replacement, do not make the essence of appropriate technical solution depart from the essence of various embodiments of the present invention technical scheme
God and scope.
Claims (10)
1. a kind of main building structure of concrete mixing plant of Fast Installation, it is characterised in that include:
Underframe(1);
Stirring layer platform(7);
Measuring layer platform(12);And
Column, its in the way of being pivotally connected, by the underframe(1), stirring layer platform(7)With measuring layer platform(12)Connect into
Integrally, so as to column can be relative to the underframe(1), stirring layer platform(7)With measuring layer platform(12)In raised state and
Switch between tilt state,
In the raised state, the uprights vertical is in the underframe(1), stirring layer platform(7)With measuring layer platform(12),
In the tilt state, the column is parallel to the underframe(1), stirring layer platform(7)With measuring layer platform(12), or
With the underframe(1), stirring layer platform(7)With measuring layer platform(12)Into an angle less than 15 degree.
2. the main building structure of concrete mixing plant of Fast Installation as claimed in claim 1, it is characterised in that under the column
End and the underframe(1)It is pivotally connected;The upper end of the column is pivotally connected with the measuring layer platform;The middle part of the column
With the stirring layer platform(7)It is pivotally connected.
3. the main building structure of concrete mixing plant of Fast Installation as claimed in claim 1, it is characterised in that the number of the column
Measure as four.
4. the main building structure of concrete mixing plant of Fast Installation as claimed in claim 3, it is characterised in that in raised state,
Four root post projection in the horizontal plane is on rectangle or foursquare four summits.
5. the main building structure of concrete mixing plant of Fast Installation as claimed in claim 4, it is characterised in that positioned at the two of side
Root post is pivotally connected height with underframe, higher than being pivotally connected highly for the two root posts and underframe positioned at opposite side.
6. the main building structure of concrete mixing plant of Fast Installation as claimed in claim 5, it is characterised in that positioned at the side
Two root posts and measuring layer platform(12)Be pivotally connected height, higher than positioned at the opposite side two root posts and measuring layer
Platform(12)Be pivotally connected height.
7. the main building structure of concrete mixing plant of Fast Installation as claimed in claim 6, it is characterised in that positioned at the side
Two root posts and underframe be pivotally connected height, higher than the upper surface of the underframe.
8. the main building structure of concrete mixing plant of Fast Installation as claimed in claim 7, it is characterised in that positioned at described another
The two root posts of side and measuring layer platform(12)Be pivotally connected height, less than the measuring layer platform(12)Lower surface.
9. the main building structure of concrete mixing plant of Fast Installation as claimed in claim 8, it is characterised in that positioned at the side
Two root posts and underframe be pivotally connected the distance between height and upper surface of the underframe, equal to the two of the opposite side
Root post and measuring layer platform(12)Be pivotally connected height and the measuring layer platform(12)The distance between lower surface.
10. a kind of installation method of the main building structure of concrete mixing plant of Fast Installation, it is characterised in that comprise the steps:
Under tilt state, by the main building structure of concrete mixing plant of Fast Installation as claimed in any one of claims 1-9 wherein
Whole Transporting is to installation site;
The main building structure of concrete mixing plant of described Fast Installation is sling to raised state from the tilt state;And
The main building structure of concrete mixing plant of described Fast Installation is fastenedly connected, is allowed to keep the raised state.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410103368.0A CN104842460B (en) | 2014-03-19 | 2014-03-19 | A kind of main building structure of concrete mixing plant and its installation method of Fast Installation |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410103368.0A CN104842460B (en) | 2014-03-19 | 2014-03-19 | A kind of main building structure of concrete mixing plant and its installation method of Fast Installation |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104842460A CN104842460A (en) | 2015-08-19 |
CN104842460B true CN104842460B (en) | 2017-04-05 |
Family
ID=53842632
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410103368.0A Active CN104842460B (en) | 2014-03-19 | 2014-03-19 | A kind of main building structure of concrete mixing plant and its installation method of Fast Installation |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104842460B (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110253762A (en) * | 2019-06-03 | 2019-09-20 | 长沙爱达环保科技有限公司 | A kind of integrated form concrete mixing plant main building |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
NL7604126A (en) * | 1976-04-20 | 1977-10-24 | Mulder Maschf B V | Large scale concrete mixing system - has frame in two hinging parts forming vehicle or mixing unit |
JP2008302646A (en) * | 2007-06-11 | 2008-12-18 | Shimizu Corp | Concrete manufacturing and supply plant |
CN201342733Y (en) * | 2008-12-05 | 2009-11-11 | 四川现代建设机电集团有限公司 | Packaged mixing plant |
CN201633136U (en) * | 2010-03-17 | 2010-11-17 | 中铁轨道系统集团有限公司 | Concrete mixing main building |
CN101979771A (en) * | 2010-11-09 | 2011-02-23 | 无锡锡通工程机械有限公司 | Tower whole movement lifting device |
CN102528935A (en) * | 2012-02-06 | 2012-07-04 | 三一重工股份有限公司 | Fast mounting mixing station main building and mixing station with same |
CN202498641U (en) * | 2012-03-26 | 2012-10-24 | 阜新市和美工程机械有限公司 | Folding movable-type concrete mixing station |
CN202666761U (en) * | 2012-07-16 | 2013-01-16 | 郝志付 | Foldable asphalt mixing equipment |
CN103465380A (en) * | 2013-09-04 | 2013-12-25 | 三一汽车制造有限公司 | Mortar stirring station |
-
2014
- 2014-03-19 CN CN201410103368.0A patent/CN104842460B/en active Active
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
NL7604126A (en) * | 1976-04-20 | 1977-10-24 | Mulder Maschf B V | Large scale concrete mixing system - has frame in two hinging parts forming vehicle or mixing unit |
JP2008302646A (en) * | 2007-06-11 | 2008-12-18 | Shimizu Corp | Concrete manufacturing and supply plant |
CN201342733Y (en) * | 2008-12-05 | 2009-11-11 | 四川现代建设机电集团有限公司 | Packaged mixing plant |
CN201633136U (en) * | 2010-03-17 | 2010-11-17 | 中铁轨道系统集团有限公司 | Concrete mixing main building |
CN101979771A (en) * | 2010-11-09 | 2011-02-23 | 无锡锡通工程机械有限公司 | Tower whole movement lifting device |
CN102528935A (en) * | 2012-02-06 | 2012-07-04 | 三一重工股份有限公司 | Fast mounting mixing station main building and mixing station with same |
CN202498641U (en) * | 2012-03-26 | 2012-10-24 | 阜新市和美工程机械有限公司 | Folding movable-type concrete mixing station |
CN202666761U (en) * | 2012-07-16 | 2013-01-16 | 郝志付 | Foldable asphalt mixing equipment |
CN103465380A (en) * | 2013-09-04 | 2013-12-25 | 三一汽车制造有限公司 | Mortar stirring station |
Also Published As
Publication number | Publication date |
---|---|
CN104842460A (en) | 2015-08-19 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CA2953504C (en) | System and method for delivery of oilfield materials | |
US11141882B2 (en) | Concrete batching plant having reduced cycle time and reduced installation and dismantling time | |
KR101208629B1 (en) | Portable batcher plant | |
CN109397547A (en) | Integrated folded foundation-free concrete mixing station | |
CN109760212A (en) | Integrated folded foundation-free vehicle-mounted mobile mixing plant | |
CN111852552A (en) | Filling slurry preparation system and preparation method thereof | |
CN104842460B (en) | A kind of main building structure of concrete mixing plant and its installation method of Fast Installation | |
CN103899091A (en) | Long-distance gentle slope concrete conveying device | |
CN203856209U (en) | Long distance gentle slope concrete conveying device | |
CN202753283U (en) | Movable concrete mixing device | |
CN203403420U (en) | Concrete vertical conveying pouring system | |
JP2008302646A (en) | Concrete manufacturing and supply plant | |
CN205471315U (en) | Autoloading system of grit material for concrete | |
CN105821883A (en) | Rotary type concrete feed divider for round-section vertical shaft | |
CN206765100U (en) | Sunk type concrete mixing plant | |
CN205416035U (en) | Remove grit feed proportioning system at stirring station | |
CN204566381U (en) | Bavin electricity mixing forced action type stirs and drags pump machine | |
CN209538194U (en) | Sliding slot equipment | |
CN208930492U (en) | Integrated folded foundation-free vehicle-mounted mobile mixing plant | |
CN109403674B (en) | Assembled prefabrication factory for bridge construction and construction method thereof | |
CN210100374U (en) | Concrete feeding device of mixing plant | |
CN113183326A (en) | Construction method for refilling silo of mixing station under complex geological condition | |
CN102409856B (en) | Method and device suitable for concrete transportation on complex terrain | |
CN206307286U (en) | A kind of new additives machine | |
CN109987381B (en) | Close-range three-dimensional concrete transportation system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
EXSB | Decision made by sipo to initiate substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right | ||
TR01 | Transfer of patent right |
Effective date of registration: 20200928 Address after: No.202 Xuanfu street, Xuanhua District, Zhangjiakou, Hebei Province Patentee after: Hebei Leisa Heavy Construction Machinery Co., Ltd Address before: 102206 Changping District City, Shahe, Sha Yang Road, Beijing Patentee before: BEIQI FOTON MOTOR Co.,Ltd. |