CN1048309C - 高压输电杆塔 - Google Patents
高压输电杆塔 Download PDFInfo
- Publication number
- CN1048309C CN1048309C CN 95100907 CN95100907A CN1048309C CN 1048309 C CN1048309 C CN 1048309C CN 95100907 CN95100907 CN 95100907 CN 95100907 A CN95100907 A CN 95100907A CN 1048309 C CN1048309 C CN 1048309C
- Authority
- CN
- China
- Prior art keywords
- tower
- power transmission
- voltage power
- mobile jib
- main pole
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Jib Cranes (AREA)
Abstract
一种高压输电杆及其它高耸塔桅结构的改进。该高压输电杆塔主杆1上设有两层或两层以上的叉梁2,主杆1的上部设有挂线架3或其它设施,叉梁2的高压h为0.3~40米,两叉梁2之间的距离L为0<L≤50米。该高压输电杆塔的主杆受力均匀,主杆及叉梁受力合理,主杆及叉梁截面积减小,从而使耗材量大大减少,杆塔载荷能力和抗超载能力得到增强,更为安全可靠。
Description
本发明涉及一种高压输电杆塔及高耸塔桅结构的改进。
高压输电杆塔和其它高耸塔桅结构等均为国家建设重要项目。已有的高压输电杆塔和高耸塔桅结构需花费大量的钢材、水泥,投资巨大。已有的高压输电叉梁混凝土杆由主杆、叉梁及掛线架等构成,其计算图中上下叉梁交于一点,存在主杆受力不均,配筋大,叉梁长,截面大,耗材多,运输安装量大,设计使用范围小(即导线型号小),主杆载荷能力和抗超载能力弱的缺陷。已有的铁塔结构上下斜材交于一点,各层斜材、横材、横隔材、主材均为钢材,且耗量大,同时斜材常由长细比构造控制设计未充分发挥受力作用,耗量较大,并且防腐,维修量较大,造价高。
本发明的目的在于克服已有高压输电杆塔和高耸塔桅结构所存在的缺陷,提供一种主杆受力均匀、合理,主杆及叉梁截面积减小耗材量大大减少,杆塔载荷能力和抗超载能力强的高压输电杆塔。
本发明的技术解决方案是:将两层叉梁拉开距离,具体地说,主杆上设有两层或两层以上的叉梁,主杆的上部设有掛线架或其它设施,其特征是,叉梁的高度h为0.3~40米,两叉梁之间的距离L为:0<L≤50米,h.L值及叉梁层数随杆塔高度,荷载和根开而变。
本发明的技术方案可用于单面、双面或多面立体的单、双,多层叉梁杆塔的设计,主杆及叉梁可为钢筋混凝土等各种材料,也可用于主、斜材为组合截面柱的高耸杆塔结构。本发明中的主杆高度不限,主杆上部设有掛线架,也可为其它设施,掛线架形成不限。
本发明与已有的高压输电杆塔及高耸塔桅结构相比具有以下优点:1.叉梁间拉开距离之后,主杆受力均匀,故可减小主杆截面,以220KV钢筋混凝土叉梁杆为例,主杆直径可由原来的400mm减小至300mm,由于叉梁之间拉开了距离,则叉梁长度缩短,截面减小,可较大幅度地节约材料,减少运输安装量,降低造价;2.本发明用于双面或多面立体的、双层或多层叉梁杆结构,可替代铁塔结构,即用钢筋混凝土等材料替代铁塔所用的型钢钢材,可大大节约钢材,加工也较容易;3.本发明用于V型拉线杆结构时,对小分裂导线,可将拉线下移到上叉梁抱箍上,从而可节省两个拉线抱箍和部分拉线材料;4.杆塔的载荷能力和抗超载能力明显增强,更为安全;5.与其它拉线杆塔相比,占地范围小,安全可靠程度高。
本发明的具体结构由附图和实施例给出。
图1为本发明用于单面双层叉梁杆塔的结构示意图;
图2为本发明用于双面立体三层叉梁杆塔的结构示意图;
图3为本发明用于单面双层叉梁拉线杆塔的结构示意图。
下面结合附图和实施例对本发明作更为详细的描述。
实施例1:
参照图1,一种用于220KV高压的通用型钢筋混凝土杆塔,主杆1上设有两层叉梁2,主杆1的上部设有掛线架3,主杆1的高度H为15米,叉梁2的高度h为3米,两层叉梁2之间的距离L为2.5米。
实施例2:
参照图2,一种用于220KV高压的双面立体三层叉梁杆塔,主杆1上设有三层叉梁2,主杆1的上部设有掛线架3,主杆1的高度H为180米,叉梁2的高度h为25米,叉梁2之间的距离L为40米。
实施例3:
参照图3,一种用于220KV高压的通用钢筋混凝土杆塔,主杆1为等径杆,主杆1上设有两层叉梁2,主杆1的上部设有掛线架3,杆塔前后设有V型拉线4,主杆1的高度H为24米,叉梁2的高度h为5米,叉梁2之间的距离L为8米。
Claims (1)
1.一种高压输电杆塔,主杆(1)上设有两层或两层以上的叉梁(2),主杆(1)的上部设有掛线架(3),其特征在于:叉梁(2)的高度h为0.3~40米,两叉梁(2)之间的距离L为:0<L≤50米。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 95100907 CN1048309C (zh) | 1995-02-16 | 1995-02-16 | 高压输电杆塔 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 95100907 CN1048309C (zh) | 1995-02-16 | 1995-02-16 | 高压输电杆塔 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN1110360A CN1110360A (zh) | 1995-10-18 |
CN1048309C true CN1048309C (zh) | 2000-01-12 |
Family
ID=5073676
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 95100907 Expired - Fee Related CN1048309C (zh) | 1995-02-16 | 1995-02-16 | 高压输电杆塔 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN1048309C (zh) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101494428B (zh) * | 2008-12-09 | 2011-01-12 | 北京中电飞华通信股份有限公司 | 一种高压输电线路杆塔设备安装装置 |
CN101906896A (zh) * | 2010-07-23 | 2010-12-08 | 中国电力工程顾问集团华北电力设计院工程有限公司 | 750kv变电构架结构 |
-
1995
- 1995-02-16 CN CN 95100907 patent/CN1048309C/zh not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
CN1110360A (zh) | 1995-10-18 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN211447708U (zh) | 一种超高层建筑施工电梯进料平台悬挑支撑体系 | |
CN112412707A (zh) | 一种装配式风电机组圆截面混凝土支撑结构 | |
CN102330470B (zh) | 一种单层预应力框架结构 | |
CN1048309C (zh) | 高压输电杆塔 | |
CN1740473A (zh) | 用于高层建筑中的拱式转换梁 | |
CN210139389U (zh) | 一种钢管堆放装置 | |
CN212893364U (zh) | 一种路桥施工用多功能施工梯 | |
CN201753475U (zh) | 下撑式预应力正交空间管桁架钢网格结构 | |
CN1134581C (zh) | 输电铁塔 | |
CN87201968U (zh) | 离心钢管混凝土结构构件 | |
CN2371270Y (zh) | 输电铁塔 | |
CN212715980U (zh) | 一种装配式建筑整体倒装施工系统 | |
CN1270261A (zh) | 减力板式挡土墙 | |
CN2150185Y (zh) | 建造混凝土筒体的附着提升式门架 | |
CN205476155U (zh) | 预制装配梁式楼梯 | |
CN2589598Y (zh) | 钢管和空心钢管混凝土架空输电线组合结构 | |
CN211338558U (zh) | 简易吊装装置 | |
CN217205704U (zh) | 配电杆防倾斜底部加固结构 | |
CN220412639U (zh) | 一种异形屋面面板吊装结构 | |
CN220908670U (zh) | 一种双层筒式钢结构景观灯塔 | |
CN219117011U (zh) | 一种货物提升塔架 | |
CN220486872U (zh) | 高炉矿粉超高性能混凝土装配式钢筋桁架楼承板 | |
CN209210181U (zh) | 一种用于超长钢结构桅杆提升的支撑装置 | |
CN213087395U (zh) | 一种建筑施工吊篮升降装置 | |
CN220640786U (zh) | 适用于砼结构构件储存基座 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C06 | Publication | ||
PB01 | Publication | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C19 | Lapse of patent right due to non-payment of the annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |