A kind of dam foundation high-pressure grouting structure and grouting method
Technical field
The invention belongs to High Pressure Consolidation Grouting field, be specifically related to a kind of dam foundation high-pressure grouting structure and grouting method.
Background technology
Typically will use the method for High Pressure Consolidation Grouting that it is processed after dam foundation excavation, to improve the physical and mechanical property of joint fissure or crushed zone, and then reduce the permeability of the dam foundation.The way of dam foundation High Pressure Consolidation Grouting comparative maturity is to use to have lid to be heavily in the milk, and this method is owing to needing to pour thicker concrete layer as lid weight, and therefore the duration is longer, but also can cause unnecessary waste, increase cost.For accelerating construction progress cost-effective, some engineerings use nongravity capping concretion grouting.
At present conventional uncovered weight grouting technique has: 1. at the surface-closed formula nongravity capping concretion grouting filling out pool closed concrete or leveling concrete surface is carried out;2. the thin cover-plate type nongravity capping concretion grouting carried out on blinding concrete or thin cover plate (toe board);3. the naked rock consolidation grouting directly carried out on naked scar.
Wherein, 1., 2. two ways be possible to prevent serosity to overflow, but under bigger grouting pressure effect, the thin cover plate in top layer or enclosed construction are easily broken off;3. the plant mode then can cause the dam foundation surface grout phenomenon occur, and grouting effect is undesirable, and the dam foundation water penetration after grouting treatment is the biggest.
It follows that uncovered weight grouting technique is because lacking covering weight, so relatively low grouting pressure can only be used at dam foundation top layer (0 ~ 5m), and it is very easy to produce grout phenomenon.Although injection rate large hole section can being taked current limliting, limit the quantity, wait measures such as coagulating, but the effect of these measures being the most very limited, the most also grouting quality can be caused certain negative effect.
Summary of the invention
Cover, to upper, the present situation that weight excessively relies on for existing High Pressure Consolidation Grouting technology, it is desirable to provide a kind of dam foundation high-pressure grouting structure and grouting method, this grouting structure and grouting method propose one and have the dam foundation High Pressure Consolidation Grouting technical scheme of " having lid weight " and " uncovered weight " grouting technique advantage concurrently, can reach and improve grouting efficiency and reduce the purpose of construction cost.
To achieve these goals, the technical solution adopted in the present invention is:
A kind of dam foundation high-pressure grouting structure, it is structurally characterized in that, including
The grout hole offered downwards from dam foundation surface of bedrock, this grout hole top is provided with only starches structure, and this grout hole is arranged at joint fissure or crushed zone;
Grout pipe, through described structure of only starching, and the port of export of grout pipe is arranged on and only starches in the grout hole below structure;
Removable hood weight, is supported on above basement rock by gripper shoe, and is provided with antiseepage dividing plate between gripper shoe and basement rock upper surface.
Thus, under " having lid weight " effect of removable hood weight, high pressure can be used to carry out being in the milk without producing grout phenomenon, slurry is injected in joint fissure or crushed zone by grout hole, can effectively ensure grouting quality, prevent the dam foundation from seeping water.
It is below the technical scheme of further improvement of the present invention:
Further, described antiseepage dividing plate and gripper shoe are removable frame, and thus, after this grout hole is in the milk, recyclable antiseepage dividing plate, gripper shoe and removable hood are reused in next grout hole grouting.
Preferably, described only slurry structure is stop grouting plug.
Further, described antiseepage dividing plate is rubber antiseepage dividing plate, is provided with releasing agent between lower surface and the basement rock upper surface of this antiseepage dividing plate.
Further, present invention also offers a kind of method using above-mentioned dam foundation high-pressure grouting structure that the dam foundation is carried out high-pressure grouting, it comprises the steps:
S1, the grout hole offered downwards at dam foundation surface of bedrock, and install only slurry structure and grout pipe;
S2, antiseepage dividing plate is set at basement rock upper surface, antiseepage dividing plate arranges gripper shoe, removable hood weight is set in gripper shoe;
S3, this grout hole being carried out by grout pipe high-pressure grouting from top to bottom, grouting plus-pressure is 1MPa-5MPa.
Thus, serosity solidifies in being injected into joint fissure or crushed zone by grout hole, can be effectively prevented dam foundation infiltration.
After the grouting of step S3 terminates, antiseepage dividing plate, gripper shoe and removable hood are heavily moved above the most next grout hole and next grout hole is in the milk.
Compared with prior art, the invention has the beneficial effects as follows: the present invention, by reasonable Arrangement antiseepage dividing plate on the dam foundation, support plate and removable hood weight, i.e. accelerating construction progress, effectively can reduce cost on the premise of not affecting High Pressure Consolidation Grouting quality.The i.e. present invention not only has the advantage of " having lid weight " and " uncovered weight " grouting technique concurrently, and overcomes the shortcoming of the two, and the most reasonable in design, technique is simple and convenient to operate.
Below in conjunction with drawings and Examples, the present invention is further elaborated.
Accompanying drawing explanation
Fig. 1 is the structure principle chart of one embodiment of the invention.
In the drawings
1-grout hole;2-grout pipe;3-stop grouting plug;4-antiseepage dividing plate;5-steel plate;6-removable hood weight;7-joint fissure or crushed zone.
Detailed description of the invention
A kind of dam foundation high-pressure grouting structure, as it is shown in figure 1, include that grout hole 1, grout pipe 2, antiseepage dividing plate 4, gripper shoe 5 and removable hood weigh 6.
Grout hole 1 top offered downwards from dam foundation surface of bedrock is provided with stop grouting plug 3, this grout hole 1 is arranged at joint fissure or crushed zone 7, the general grout hole degree of depth is according to geological conditions, such as the degree of crushing of rock, depth of weathering, crack size, dam dam type and height and the multiple condition such as the distribution of basis stress and size, depending on considering;Generally 5-10m, aperture is generally 50-91mm.Described grout pipe 2 is through described stop grouting plug 3, and the port of export of grout pipe 2 is arranged on and only starches in the grout hole 1 below structure.Described removable hood weighs 6 and is supported on above basement rock by gripper shoe 5, and is provided with antiseepage dividing plate 4 between gripper shoe 5 and basement rock upper surface.Described antiseepage dividing plate 4 is rubber antiseepage dividing plate, is provided with releasing agent between lower surface and the basement rock upper surface of this antiseepage dividing plate 4.It can be precast concrete block, truck or other preloading that described lid weighs 6.
During grouting, grout hole 1, grout pipe 2 and stop grouting plug 3 is arranged at the dam foundation, coverage according to serosity lays rubber antiseepage dividing plate 4 on dam foundation top layer, brushing releasing agent between antiseepage dividing plate 4 and basement rock, on antiseepage dividing plate 4, lay steel plate 5 successively and removable hood weighs 6, its middle cover weighs 6 can make corresponding adjustment according to the condition of the size of grouting pressure and job site, and makes it be evenly arranged on steel plate 5, carries out high-pressure grouting the most from top to bottom.
The present invention is by arranging that on the dam foundation rubber antiseepage dividing plate 4, steel plate 5 weigh 6 with removable hood, and just can reach routine has the effect of lid weight High Pressure Consolidation Grouting, it is possible to effectively control earth's surface lifting and the grout phenomenon caused because of grouting.But, removable hood weight is cast-in-place without using concrete to carry out, but prefabricated concrete block, truck or other heap carrier material, it is possible to substantially reduction of erection time, accelerating construction progress;Can reclaim after high-pressure grouting terminates reuse additionally, rubber antiseepage dividing plate 4, steel plate 5 and removable hood weigh 6, effectively control cost, waste can't be caused.
The content that above-described embodiment illustrates should be understood to that these embodiments are only used for being illustrated more clearly that the present invention, rather than restriction the scope of the present invention, after having read the present invention, those skilled in the art each fall within the application claims limited range to the amendment of the various equivalent form of values of the present invention.