CN104790288A - 钢结构-混凝土板结合桥梁的钢筋配筋结构 - Google Patents

钢结构-混凝土板结合桥梁的钢筋配筋结构 Download PDF

Info

Publication number
CN104790288A
CN104790288A CN201510161962.XA CN201510161962A CN104790288A CN 104790288 A CN104790288 A CN 104790288A CN 201510161962 A CN201510161962 A CN 201510161962A CN 104790288 A CN104790288 A CN 104790288A
Authority
CN
China
Prior art keywords
steel reinforcement
steel
reinforcement arrangement
combined
transverse
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510161962.XA
Other languages
English (en)
Other versions
CN104790288B (zh
Inventor
胥润东
廖慕捷
侯鹏飞
梅新咏
杨建军
刘小林
周杰
肖小艳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Major Bridge Reconnaissance and Design Institute Co Ltd
China Railway Bridge and Tunnel Technologies Co Ltd
Original Assignee
China Railway Major Bridge Reconnaissance and Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Major Bridge Reconnaissance and Design Institute Co Ltd filed Critical China Railway Major Bridge Reconnaissance and Design Institute Co Ltd
Priority to CN201510161962.XA priority Critical patent/CN104790288B/zh
Publication of CN104790288A publication Critical patent/CN104790288A/zh
Application granted granted Critical
Publication of CN104790288B publication Critical patent/CN104790288B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced
    • E01D2101/268Composite concrete-metal

Abstract

本发明涉及一种钢结构-混凝土板结合桥梁的钢筋配筋结构,横向主筋在结合槽口弯折形成环箍,并延伸过钢结构顶面,环箍与其上的横向主筋形成整体筋结构,整体筋结构与槽口中的剪力钉错开布置,形成钢筋配筋结构,钢筋配筋结构同时作为顶板束、结合槽口箍筋、底板束。钢筋配筋结构根据具体施工要求,采用不同间距布置。现浇混凝土将结合槽口、剪力钉、钢筋配筋结构浇筑成桥面板。本发明的钢筋配筋结构在结合部位形成的横向封闭钢筋环箍混凝土区,可提高混凝土承载能力。横向钢筋连续通过结合槽口,其横向受力性能没有受到影响,而峰值负弯矩由两根主筋承担更安全可靠。施工简便,而且由于环箍由一根完整钢筋形成,更能适应施工误差的影响。

Description

钢结构-混凝土板结合桥梁的钢筋配筋结构
技术领域
本发明涉及一种钢结构-混凝土板结合桥梁的钢筋配筋结构,主要应用领域在公路桥梁、铁路桥梁以及其他采用钢混结合的建筑结构领域。
背景技术
结合槽口是钢筋-混凝土组合结构的受力复杂区域,此区域通常配置有剪力钉、纵向普通钢筋、横向普通钢筋、横向预应力钢筋和现浇混凝土。
成桥以后,横向钢筋不仅需要承担桥面板作为第一体系顶板带来的纵向应力,也同时受到车辆荷载带来的横向弯矩和竖向剪力的影响。因此这一区域的横向钢筋往往需要考虑与剪力钉相互作用的抗剪需要,还要考抵抗横向弯矩的拉压构造和竖向剪力构造。
目前世界上钢混结合梁实际中基本有三种布置形式:在中国往往仅考虑横向刚束的直线连续通过,这种构造的缺陷是对剪力钉的抵抗完全由底板钢筋承担,受力薄弱。欧洲规范中,在此区域增加了独立的竖向环形箍筋,虽然增加了底板抗剪钢筋的数量,但顶板的环箍上缘却是材料浪费。美洲的做法是采用增加开口U形箍筋的方法,同样增加了底板的抗剪钢筋数量,但U形钢筋在顶面是开口的,不能抵抗局部区域的横向弯矩。
随着结合梁桥的日益广泛应用,结合槽口的结构需要优化。
发明内容
本发明的目的是针对上述现状,旨在提供一种可提高混凝土承载能力、抗剪能力;能在局部区域对混凝土形成环箍效应,提供横向弯矩抗力,能适应施工误差的影响的钢结构-混凝土板结合桥梁的钢筋配筋结构。
本发明目的的实现方式为,钢结构-混凝土板结合桥梁的钢筋配筋结构,横向主筋在结合槽口弯折形成环箍,并延伸过钢结构顶面,环箍与其上的横向主筋形成整体筋结构,整体筋结构与槽口中的剪力钉错开布置,形成钢筋配筋结构,钢筋配筋结构同时作为顶板束、结合槽口箍筋、底板束。
本发明的钢筋配筋结构在结合部位形成的横向封闭钢筋环箍混凝土区,可提高混凝土承载能力、抗剪能力。横向钢筋连续通过结合槽口,其横向受力性能没有受到影响,而峰值负弯矩由两根主筋承担更安全可靠。施工简便,而且由于环箍由一根完整钢筋形成,更能适应施工误差的影响。
附图说明
图1是本发明结构正视图,
图2是本发明结构示意图,
图3是本发明结构放大图,
图4是本发明钢结构、剪力钉的结构关系图
具体实施方式
下面参照附图详述本发明。
参照图1、图2、图3、图4,横向主筋在结合槽口弯折形成环箍4,并延伸过钢结构1顶面,环箍4与其上的横向主筋5形成整体筋结构,整体筋结构与结合槽口6中的剪力钉3错开布置,形成钢筋配筋结构,钢筋配筋结构同时作为顶板束、结合槽口箍筋、底板束。钢筋配筋结构根据具体施工要求,采用不同间距布置。
采用本发明施工时,由环箍4与其上的横向主筋5构成的整体筋结构在工厂制造,并运输到桥位现场。施工过程中,首先架设钢结构1,根据桥面板的位置和结合槽口的位置现场焊接剪力钉3,按所设计的间距布置整体筋结构,并与结合槽口6中的剪力钉3错开,现浇混凝土将结合槽口、剪力钉3、钢筋配筋结构浇筑成桥面板2。
具体的施工顺序可根据力学分析进行调整,本结构与施工顺序无关。
本发明的钢筋配筋结构在结合部位形成的横向封闭钢筋环箍混凝土区,可提高混凝土承载能力、抗剪能力。横向钢筋连续通过结合槽口,其横向受力性能没有受到影响,而峰值负弯矩由两根主筋承担更安全可靠。施工简便,而且由于环箍由一根完整钢筋形成,更能适应施工误差的影响。

Claims (2)

1.钢结构-混凝土板结合桥梁的钢筋配筋结构,其特征在于:横向主筋在结合槽口弯折形成环箍,并延伸过钢结构顶面,环箍与其上的横向主筋形成整体筋结构,整体筋结构与槽口中的剪力钉错开布置,形成钢筋配筋结构,钢筋配筋结构同时作为顶板束、结合槽口箍筋、底板束。
2.根据权利要求1所述的钢结构-混凝土板结合桥梁的钢筋配筋结构,其特征在于:钢筋配筋结构采用不同间距布置。
CN201510161962.XA 2015-04-07 2015-04-07 钢结构-混凝土板结合桥梁的钢筋配筋结构 Active CN104790288B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510161962.XA CN104790288B (zh) 2015-04-07 2015-04-07 钢结构-混凝土板结合桥梁的钢筋配筋结构

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510161962.XA CN104790288B (zh) 2015-04-07 2015-04-07 钢结构-混凝土板结合桥梁的钢筋配筋结构

Publications (2)

Publication Number Publication Date
CN104790288A true CN104790288A (zh) 2015-07-22
CN104790288B CN104790288B (zh) 2016-12-07

Family

ID=53555448

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510161962.XA Active CN104790288B (zh) 2015-04-07 2015-04-07 钢结构-混凝土板结合桥梁的钢筋配筋结构

Country Status (1)

Country Link
CN (1) CN104790288B (zh)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112176850A (zh) * 2020-09-30 2021-01-05 长沙理工大学 一种钢-uhpc组合结构剪力连接件及其制作安装方法

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AU2004224895A1 (en) * 2003-10-28 2005-05-19 Bluescope Steel Limited Structural element
CN201873942U (zh) * 2010-11-20 2011-06-22 大连理工大学 一种纤维增强塑料-混凝土组合梁
KR101102450B1 (ko) * 2011-06-10 2012-01-05 고재욱 콘크리트 합성강관 트러스 빔 및 이를 이용한 교량시공방법
CN102561213A (zh) * 2012-02-15 2012-07-11 中南大学 一种结构负弯矩区的钢板-混凝土组合结构加固方法
CN102926505A (zh) * 2011-08-09 2013-02-13 同济大学 一种组合梁构件
CN103422603A (zh) * 2013-09-11 2013-12-04 南京工业大学 一种螺旋箍筋剪力连接件及制备安装方法
CN103643625A (zh) * 2013-12-29 2014-03-19 长安大学 一种基于抗剪连接构造的钢桁架-混凝土板组合梁
CN104264575A (zh) * 2014-09-15 2015-01-07 同济大学 一种预应力钢箱混凝土组合连续梁桥构造及施工工艺

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AU2004224895A1 (en) * 2003-10-28 2005-05-19 Bluescope Steel Limited Structural element
CN201873942U (zh) * 2010-11-20 2011-06-22 大连理工大学 一种纤维增强塑料-混凝土组合梁
KR101102450B1 (ko) * 2011-06-10 2012-01-05 고재욱 콘크리트 합성강관 트러스 빔 및 이를 이용한 교량시공방법
CN102926505A (zh) * 2011-08-09 2013-02-13 同济大学 一种组合梁构件
CN102561213A (zh) * 2012-02-15 2012-07-11 中南大学 一种结构负弯矩区的钢板-混凝土组合结构加固方法
CN103422603A (zh) * 2013-09-11 2013-12-04 南京工业大学 一种螺旋箍筋剪力连接件及制备安装方法
CN103643625A (zh) * 2013-12-29 2014-03-19 长安大学 一种基于抗剪连接构造的钢桁架-混凝土板组合梁
CN104264575A (zh) * 2014-09-15 2015-01-07 同济大学 一种预应力钢箱混凝土组合连续梁桥构造及施工工艺

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112176850A (zh) * 2020-09-30 2021-01-05 长沙理工大学 一种钢-uhpc组合结构剪力连接件及其制作安装方法
CN112176850B (zh) * 2020-09-30 2022-07-01 长沙理工大学 一种钢-uhpc组合结构剪力连接件及其制作安装方法

Also Published As

Publication number Publication date
CN104790288B (zh) 2016-12-07

Similar Documents

Publication Publication Date Title
CN106677049B (zh) 装配式钢-混凝土组合结构桥梁及施工方法
CN105839510B (zh) 一种钢‑超高性能混凝土组合连续梁桥结构及其施工方法
CN104389261B (zh) 预制超高性能混凝土π形梁单元、桥梁结构及其施工方法
CN204252345U (zh) 一种预制混凝土板与钢梁的连接构造
CN103114524A (zh) 轻型波形钢-高强活性粉末混凝土组合桥面板
CN109082998A (zh) 整体预制钢板组合梁结构及施工方法
CN106087739A (zh) 一种组合u肋型钢桥面板及其制作方法
CN103741577B (zh) 一种设置下平联的t型梁桥及其施工方法
CN108867319A (zh) 一种用于斜拉桥的钢-uhpc组合梁及施工方法
CN203200656U (zh) 轻型波形钢-高强活性粉末混凝土组合桥面板
CN110578289A (zh) 一种新型钢混组合梁剪力连接键
CN103321153A (zh) 一种中小跨径槽形梁桥的施工方法
CN103205930B (zh) 一种既有简支空心板梁桥连续化改造的结构及其施工方法
CN104790288A (zh) 钢结构-混凝土板结合桥梁的钢筋配筋结构
CN204112200U (zh) 翼缘增强型波形钢腹板组合箱梁
CN107012986A (zh) 多层外包钢混凝土组合连梁
CN109183615B (zh) 一种多主梁式钢混组合连续梁
CN105019349B (zh) 几字形预制梁及其制备方法和安装施工方法
CN103911948A (zh) 应用于宽混凝土肋板梁的横向桁式钢结构及其施工方法
CN109505237A (zh) 一种钢混组合桥梁伸缩缝处主梁纵向连接构造及施工方法
CN205474785U (zh) 一种钢-超高性能混凝土组合连续梁桥结构
CN203256627U (zh) 一种既有简支空心板梁桥连续化改造的结构
CN204691033U (zh) 一种用于预制整浇井字形楼盖结构的叠合梁预制构件
CN203639814U (zh) 一种装配整体式空心板桥
CN103276663A (zh) 用于钢筋混凝土板桥的装配整体式板的制作方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Xu Rundong

Inventor after: Liao Mujie

Inventor after: Hou Pengfei

Inventor after: Mei Xinyong

Inventor after: Liu Hua

Inventor after: Yang Jianjun

Inventor after: Liu Xiaolin

Inventor after: Zhou Jie

Inventor after: Xiao Xiaoyan

Inventor before: Xu Rundong

Inventor before: Liao Mujie

Inventor before: Hou Pengfei

Inventor before: Mei Xinyong

Inventor before: Yang Jianjun

Inventor before: Liu Xiaolin

Inventor before: Zhou Jie

Inventor before: Xiao Xiaoyan

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20170615

Address after: 210061, 8, pan Neng Road, hi tech Zone, Jiangsu, Nanjing

Co-patentee after: China Railway Bridge Survey and Design Institute Co Ltd

Patentee after: China Railway Bridge (Nanjing) Co., Ltd. and Bridge

Address before: 430050 8, erudite Road, Wuhan economic and Technological Development Zone (Zhuankou), Hubei, Wuhan

Patentee before: China Zhongtie Major Bridge Reconnaissance & Design Institute Co., Ltd.

CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 210061 No.8 Panneng Road, Jiangbei new district, Nanjing City, Jiangsu Province

Patentee after: China Railway Bridge and Tunnel Technology Co.,Ltd.

Patentee after: CHINA RAILWAY MAJOR BRIDGE RECONNAISSANCE & DESIGN INSTITUTE Co.,Ltd.

Address before: 210061 No.8 Panneng Road, high tech Zone, Nanjing, Jiangsu Province

Patentee before: CHINA RAILWAY MAJOR BRIDGE (NANJING) BRIDGE AND RUNNEL INSPECT & RETROFIT Co.,Ltd.

Patentee before: China Railway Bridge Survey and Design Institute Limited Group