CN104775602A - Brick paving method and special brick paving clamp - Google Patents
Brick paving method and special brick paving clamp Download PDFInfo
- Publication number
- CN104775602A CN104775602A CN201510184550.8A CN201510184550A CN104775602A CN 104775602 A CN104775602 A CN 104775602A CN 201510184550 A CN201510184550 A CN 201510184550A CN 104775602 A CN104775602 A CN 104775602A
- Authority
- CN
- China
- Prior art keywords
- tile work
- connector
- adjacent
- floor block
- tile
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Finishing Walls (AREA)
Abstract
The invention discloses a brick paving method which is characterized in that during brick paving, at least one brick paving clamp is adopted for clamping two adjacent decorative bricks; the lower part of the brick paving clamp is clung to the bottoms of the two adjacent decorative bricks; the upper part of the brick paving clamp is compressed to the upper surfaces of the two adjacent decorative bricks, so that the two decorative bricks are leveled; after brick paving is finished, connecting pieces connected with the upper and lower parts of the brick paving clamp are broken off, the upper part of the brick paving clamp and the connecting pieces are taken out, and a seam between the two adjacent decorative bricks are trowelled by use of a joint mixture. Compared with the prior art, the brick paving method has the characteristics of simplicity in leveling and convenience in operation, and capable of improving the brick paving efficiency while improving the brick paving flatness. The invention further provides the special brick paving clamp.
Description
Technical field
The present invention relates to the realm of building construction, particularly relate to a kind of tile work method and tile work exclusive clamps.
Background technology
When carrying out house decoration, usually need laying floor brick on the ground.And whether smooth wood floor bolck laid directly have influence on overall decorative effect.At present, in building operations, conventional leveling method carries out water to note levelling.That is, first water pipe is injected water, with water pipe point, measure level point a point, then do upper mark with pen.
But, when laying floor brick, because construction level line and ground are very close, so the horizon that water pipe is measured is usually high than the horizon of practice of construction.Thus, after measurement completes, also need to move down with ruler is unified, draw two lines, can tile work after two line form right angle shapes.During tile work, also need the constructor with certain plastering technique and experience, with trowel, cement is smeared into the cement square of floor tile size.It is consistent that thickness due to cement is difficult to the equilibrium of smearing, therefore need after putting floor tile, then according to visual experience, or beat downwards with hammer, or again open prize floor tile after add cement again or remove unnecessary cement.Operation is inconvenience very, time-consumingly takes a lot of work; And due to the existence of the collimation error, construction quality is difficult to ensure.
Summary of the invention
For the defect existed in prior art, the object of the present invention is to provide a kind of easy construction, the tile work method that ground tile paving planarization is good.
The present invention also provides a kind of tile work exclusive clamps based on above-mentioned tile work method.
For reaching above object, the present invention adopts following technical scheme.
A kind of tile work method, it is characterized in that, during tile work, at least one tile work is adopted to press from both sides tight for adjacent two packaged decorations brick clamps, the lower part of tile work folder is close to the bottom of adjacent two pieces of decorative floor block, the upper part of tile work folder is pressed on the upper surface of adjacent two pieces of decorative floor block, makes adjacent two pieces of decorative floor block levelling; After tile work completes, the connector connecting tile work folder upper part and lower part is broken disconnected, take out upper part and the connector of tile work folder, and with gap filler by floating for the gap between adjacent two pieces of decorative floor block.
As further illustrating of above-mentioned tile work method, the upper part of described tile work folder is movably connected on connector, when disconnection fitting broken by needs, is thrown off by the upper surface of upper part and adjacent two pieces of decorative floor block.
As further illustrating of above-mentioned tile work method, between described upper part and connector, be provided with multiple locking position, the decorative floor block of various different size can be adapted to.
As further illustrating of above-mentioned tile work method, described decorative floor block comprises wall brick, floor tile, one or more in stone material product.
The present invention also provides a kind of tile work exclusive clamps, it is characterized in that, comprising: the upper part connected together by connector and lower part, and described lower part is fixedly connected with connector, and described upper part is flexibly connected with connector; During tile work, described upper part and lower part are close to upper surface and the soffit of adjacent two decorative floor block respectively, by adjacent two decorative floor block clamping, levelling.
As further illustrating of above-mentioned tile work exclusive clamps, described lower part is a flat board, and described connector is be arranged on dull and stereotyped middle part and be provided with the junction plate upwards extended; Described upper part is the elastic pressuring plate be arranged on junction plate, and elastic pressuring plate is provided with buckle, and junction plate is provided with the catching groove corresponding with buckle.
As further illustrating of above-mentioned tile work exclusive clamps, described elastic pressuring plate is two panels, is separately positioned on the left and right sides of junction plate; The front and back sides of junction plate is respectively equipped with the catching groove corresponding from different elastic pressuring plate.
As further illustrating of above-mentioned tile work exclusive clamps, described connector is to be arranged in the middle part of lower part and the joint pin protruded upward, and the side surface on joint pin is provided with screw thread, and described upper part is the wedge be threaded on joint pin.
As further illustrating of above-mentioned tile work exclusive clamps, threaded column is provided with nut, wedge is provided with the through hole corresponding with joint pin, described wedge is spacing on joint pin by nut.
As further illustrating of above-mentioned tile work exclusive clamps, described connector is connected by multiple connecting band spaced apart from each other with between lower part, and the thickness of described connecting band is less than the thickness of connector.
Compared with prior art, a kind of tile work method provided by the invention, adopts when tile work tile work folder by levelling for adjacent two blocks of ceramic tiles, and then realizes the smooth of whole paved surface.After laying completes, only need break the disconnected upper part removing tile work folder, realize simple, easy to operate, while raising tile work planarization, greatly improve tile work efficiency.
A kind of tile work exclusive clamps provided by the invention, between connector with lower part, adopt the connecting band opened each other to be connected, during tile work, can ensure, between the upper part of tile work exclusive clamps and lower part, there is good tensile strength, after tile work completes, only need inflection be several times dynamic can break disconnection tape splicing, realize the disengaging of tile work exclusive clamps upper part, very convenient to use.Especially, the present invention also by connector is arranged to threaded column, conveniently realizes the adjustment of upper part and lower part lockout span, can be applicable to the decorative floor block of various different size, and versatility is good.
Accompanying drawing explanation
Figure 1 shows that the structural representation of special tile work folder embodiment one provided by the invention;
Figure 2 shows that Fig. 1 middle plateform structural representation;
Figure 3 shows that the structural representation of special tile work folder embodiment two provided by the invention;
Figure 4 shows that the structural representation of special tile work folder provided by the invention enforcement three.
Description of reference numerals:
1, upper part, 2, lower part, 3, joint pin, 4, connecting band, 5, nut;
11, buckle, 12, catching groove;
21, through hole;
31, screw thread.
Detailed description of the invention
Understand essence of the present invention better for convenience of those skilled in the art, below in conjunction with accompanying drawing, the specific embodiment of the present invention is described in detail.
Tile work embodiment of the method
A kind of tile work method, is applicable to the laying of wall brick, floor tile or other stone material products.
During concrete tile work, at least one tile work is adopted to press from both sides tight for adjacent two packaged decorations brick clamps, the lower part of tile work folder is close to the bottom of adjacent two pieces of decorative floor block, and the upper part of tile work folder is pressed on the upper surface of adjacent two pieces of decorative floor block, makes adjacent two pieces of decorative floor block levelling.
After tile work completes, the connector connecting tile work folder upper part and lower part is broken disconnected, take out upper part and the connector of tile work folder, and with gap filler by floating for the gap between adjacent two pieces of decorative floor block.
Successfully connector is broken disconnected for ease of user, in the present embodiment, the upper part of preferred tile work folder is movably connected on connector, when disconnection fitting broken by needs, the upper surface of upper part and adjacent two pieces of decorative floor block is thrown off, so that swinging of connector can be realized, and then reach the object of breaking disconnection fitting fast.
Further, for adapting to various different-thickness decorative floor block, between the upper part of preferred tile work folder and connector, be provided with multiple locking position.When the thickness of decorative floor block to be laid changes, the locking position of tile work folder upper part only need be adjusted, without the need to changing tile work folder, very convenient to use.
Compared with prior art, a kind of tile work method that the present embodiment provides, adopts when tile work tile work folder by levelling for adjacent two blocks of ceramic tiles, and then realizes the smooth of whole paved surface.After laying completes, only need break the disconnected upper part removing tile work folder, realize simple, easy to operate, while raising tile work planarization, greatly improve tile work efficiency.
Special tile work folder embodiment one
As shown in Figure 1, a kind of tile work exclusive clamps, comprising: the upper part 1 connected together by connector 3 and lower part 2.Described lower part 2 is fixedly connected with connector 3, and described upper part 1 is flexibly connected with connector 3.During tile work, upper part 1 compresses with the upper surface of adjacent two decorative floor block, after tile work completes, is thrown off by the upper surface of upper part and adjacent two decorative floor block, breaks disconnected upper part 1 and the connector 3 of removing tile work exclusive clamps.
Wherein, described lower part 2 is a flat board, and described connector 3 is for being arranged on dull and stereotyped middle part and being provided with the junction plate upwards extended.Described upper part 1, for being arranged on the elastic pressuring plate on junction plate, elastic pressuring plate is provided with buckle 11, and junction plate is provided with the catching groove 12 corresponding with buckle 11.
In the present embodiment, preferred elastomeric compressing tablet is two panels, is separately positioned on the left and right sides of junction plate; The front and back sides of junction plate is respectively equipped with the catching groove 12 corresponding from different elastic pressuring plate.Like this, effectively can keep side, the front and back stress balance of junction plate when two panels elastic pressuring plate and junction plate snap together, practicality is good.
Further, for ease of breaking disconnection fitting 3, preferred connector 3 is connected by multiple connecting band 4 spaced apart from each other with between lower part 2, and the thickness of described connecting band 4 is less than the thickness of junction plate.In the present embodiment, the thickness of junction plate is no more than 1mm, and the thickness of connecting band is no more than 0.2mm.
Further, after ensureing that decorative floor block is spread, below flat board can be fastened on bottom decorative floor block, avoid when breaking disconnection fitting, causing the decorative floor block completed to loosen, on flat board, be preferably also provided with the through hole 21 of multiple through dull and stereotyped upper and lower surface, as shown in Figure 3.Due to the existence of through hole 21, during tile work, the adhesive energy automatic fillings such as cement enter in through hole, and adhesion strength is large.
Special tile work folder embodiment two
As shown in Figure 3, a kind of tile work exclusive clamps that the present embodiment provides, its structure and embodiment one basically identical, difference is;
Described connector 3 is for being arranged in the middle part of lower part and the joint pin protruded upward, and the side surface on joint pin is provided with screw thread 31, and described upper part is the wedge be threaded on joint pin.
During actual tile work, according to the difference of decorative floor block thickness to be laid, user regulates the interval between wedge and lower part by rotation wedge, highly versatile.After ceramic tile lays, wedge is rotated rise and can break connection breaking post very easily.
Special tile work folder embodiment three
As shown in Figure 4, a kind of tile work exclusive clamps that the present embodiment provides, its structure and embodiment two basically identical, difference is; Threaded column is provided with nut 5, wedge is provided with the through hole corresponding with joint pin, described wedge is spacing on joint pin by nut 5.
In other embodiments, connecting band omit, directly the junction of joint pin and lower part is attenuated, preferably the diameter control of joint pin lower end within 2mm, when tile work completes, directly rotation whole upper part, joint pin and lower part are departed from; Be not limited to the present embodiment.
Above detailed description of the invention has been described in detail essence of the present invention, but can not limit protection scope of the present invention with this.Apparently, under the enlightenment of essence of the present invention, the art those of ordinary skill also can carry out many improvement and modification, it should be noted that these improve and modify and all drops within claims of the present invention.
Claims (10)
1. a tile work method, it is characterized in that, during tile work, at least one tile work is adopted to press from both sides tight for adjacent two packaged decorations brick clamps, the lower part of tile work folder is close to the bottom of adjacent two pieces of decorative floor block, the upper part of tile work folder is pressed on the upper surface of adjacent two pieces of decorative floor block, makes adjacent two pieces of decorative floor block levelling; After tile work completes, the connector connecting tile work folder upper part and lower part is broken disconnected, take out upper part and the connector of tile work folder, and with gap filler by floating for the gap between adjacent two pieces of decorative floor block.
2. a kind of tile work method according to claim 1, is characterized in that, the upper part of described tile work folder is movably connected on connector, when disconnection fitting broken by needs, is thrown off by the upper surface of upper part and adjacent two pieces of decorative floor block.
3. a kind of tile work method according to claim 2, is characterized in that, is provided with multiple locking position between described upper part and connector, can adapt to the decorative floor block of various different size.
4. a kind of tile work method according to claim 1, it is characterized in that, described decorative floor block comprises wall brick, floor tile, one or more in stone material product.
5. a tile work exclusive clamps, is characterized in that, comprising: the upper part connected together by connector and lower part, and described lower part is fixedly connected with connector, and described upper part is flexibly connected with connector; During tile work, described upper part and lower part are close to upper surface and the soffit of adjacent two decorative floor block respectively, by adjacent two decorative floor block clamping, levelling.
6. a kind of tile work exclusive clamps according to claim 5, is characterized in that, described lower part is a flat board, and described connector is be arranged on dull and stereotyped middle part and be provided with the junction plate upwards extended; Described upper part is the elastic pressuring plate be arranged on junction plate, and elastic pressuring plate is provided with buckle, and junction plate is provided with the catching groove corresponding with buckle.
7. a kind of tile work exclusive clamps according to claim 6, it is characterized in that, described elastic pressuring plate is two panels, is separately positioned on the left and right sides of junction plate; The front and back sides of junction plate is respectively equipped with the catching groove corresponding from different elastic pressuring plate.
8. a kind of tile work exclusive clamps according to claim 5, it is characterized in that, described connector is to be arranged in the middle part of lower part and the joint pin protruded upward, and the side surface on joint pin is provided with screw thread, and described upper part is the wedge be threaded on joint pin.
9. a kind of tile work exclusive clamps according to claim 8, is characterized in that, threaded column is provided with nut, and wedge is provided with the through hole corresponding with joint pin, and described wedge is spacing on joint pin by nut.
10. a kind of tile work exclusive clamps according to claim 5, is characterized in that, described connector is connected by multiple connecting band spaced apart from each other with between lower part, and the thickness of described connecting band is less than the thickness of connector.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510184550.8A CN104775602A (en) | 2015-04-16 | 2015-04-16 | Brick paving method and special brick paving clamp |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510184550.8A CN104775602A (en) | 2015-04-16 | 2015-04-16 | Brick paving method and special brick paving clamp |
Publications (1)
Publication Number | Publication Date |
---|---|
CN104775602A true CN104775602A (en) | 2015-07-15 |
Family
ID=53617334
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510184550.8A Pending CN104775602A (en) | 2015-04-16 | 2015-04-16 | Brick paving method and special brick paving clamp |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104775602A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110462147A (en) * | 2017-01-17 | 2019-11-15 | 达文西意大利/美国集团有限责任公司 | For being directed at and leveling the component and method of ceramic tile |
CN111827636A (en) * | 2019-04-22 | 2020-10-27 | 克林顿·D·邦奇 | Device for aligning and aligning tiles and method for aligning and aligning tiles |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2196659Y (en) * | 1994-07-11 | 1995-05-10 | 彭进铺 | Flating device for floor tile |
CN201610628U (en) * | 2009-09-28 | 2010-10-20 | 上海金博石材建设有限公司 | Stone laying leveling device |
CN102220805A (en) * | 2005-02-22 | 2011-10-19 | 达芬奇意大利/美国集团有限责任公司 | Tile alignment and leveling device and method for using the same |
CN202248809U (en) * | 2011-07-22 | 2012-05-30 | 上海沃能实业有限公司 | Tile positioning and horizontal installation device |
US20130255182A1 (en) * | 2012-03-29 | 2013-10-03 | Edward A. Kufner | Tile Alignment and Leveling Device |
CN204139562U (en) * | 2014-09-19 | 2015-02-04 | 厦门市坤腾精密配件工业有限公司 | A kind of ceramic tile leveling apparatus |
CN204531325U (en) * | 2015-04-16 | 2015-08-05 | 新中源建材有限公司 | A kind of tile work exclusive clamps |
-
2015
- 2015-04-16 CN CN201510184550.8A patent/CN104775602A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2196659Y (en) * | 1994-07-11 | 1995-05-10 | 彭进铺 | Flating device for floor tile |
CN102220805A (en) * | 2005-02-22 | 2011-10-19 | 达芬奇意大利/美国集团有限责任公司 | Tile alignment and leveling device and method for using the same |
CN201610628U (en) * | 2009-09-28 | 2010-10-20 | 上海金博石材建设有限公司 | Stone laying leveling device |
CN202248809U (en) * | 2011-07-22 | 2012-05-30 | 上海沃能实业有限公司 | Tile positioning and horizontal installation device |
US20130255182A1 (en) * | 2012-03-29 | 2013-10-03 | Edward A. Kufner | Tile Alignment and Leveling Device |
CN204139562U (en) * | 2014-09-19 | 2015-02-04 | 厦门市坤腾精密配件工业有限公司 | A kind of ceramic tile leveling apparatus |
CN204531325U (en) * | 2015-04-16 | 2015-08-05 | 新中源建材有限公司 | A kind of tile work exclusive clamps |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110462147A (en) * | 2017-01-17 | 2019-11-15 | 达文西意大利/美国集团有限责任公司 | For being directed at and leveling the component and method of ceramic tile |
CN110462147B (en) * | 2017-01-17 | 2021-06-01 | 达文西意大利/美国集团有限责任公司 | Assembly and method for aligning and leveling tiles |
CN111827636A (en) * | 2019-04-22 | 2020-10-27 | 克林顿·D·邦奇 | Device for aligning and aligning tiles and method for aligning and aligning tiles |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107366421A (en) | A kind of tile laying levelling device and method | |
CN206829569U (en) | A kind of T-shaped ceramic tile screeder | |
CN104863342A (en) | Cylinder plastering device and method | |
RU159255U1 (en) | TILE LEVELING DEVICE | |
CN204609254U (en) | A kind of screw clamp compact form tile leveling devices | |
CN204174898U (en) | A kind of ceramic tile smoother for building | |
US8973206B1 (en) | Trowel with depth adjustment | |
CN104775602A (en) | Brick paving method and special brick paving clamp | |
CN203879028U (en) | Slurry laying machine | |
CN102605938B (en) | Building wall-whitewashing, plastering and leveling or ground leveling guiding rule and assorted punched ribs | |
CN204531325U (en) | A kind of tile work exclusive clamps | |
CN203347196U (en) | Auxiliary jig for tile laying | |
CN203867134U (en) | Structure of indoor tile floor | |
CN204703535U (en) | Equipment built by laying bricks or stones by brick wall | |
CN203769273U (en) | Rapid floor tile laying leveling device | |
CN203684619U (en) | Device for jointing of exterior wall tiles | |
KR101312023B1 (en) | Construction method using a trowel and tile angle adjustable | |
CN202530724U (en) | Guiding rule for building wall whitewashing and plastering leveling or ground leveling and matched impact fillet | |
CN201730303U (en) | Ceramic tile positioning device | |
CN206917229U (en) | A kind of nut type ceramic tile screeder | |
CN105507568B (en) | A kind of tile work device and tile work method | |
CN206158117U (en) | Wall ground floating screed instrument of making level | |
CN209011510U (en) | Dual-purpose trowel for pointing and plastering | |
CN209837564U (en) | Novel wall ceramic tile dry-hanging bracket | |
CN202248387U (en) | Light steel keel gypsum board vitrified tile decorative wall |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
EXSB | Decision made by sipo to initiate substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20150715 |