CN104775433A - 一种拔桩施工的方法 - Google Patents
一种拔桩施工的方法 Download PDFInfo
- Publication number
- CN104775433A CN104775433A CN201510168290.5A CN201510168290A CN104775433A CN 104775433 A CN104775433 A CN 104775433A CN 201510168290 A CN201510168290 A CN 201510168290A CN 104775433 A CN104775433 A CN 104775433A
- Authority
- CN
- China
- Prior art keywords
- stake
- pile
- steel sleeve
- pile pulling
- vibration
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D9/00—Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof
- E02D9/02—Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof by withdrawing
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Abstract
一种拔桩的施工方法,首先用地震物探法初步定出废桩的大体位置再用小螺钻探测确定具体桩位,采用此种方法对废桩定位更准确;在钢管沉设过程中利用高压射气射水进行套管内清洗桩边土层,确保桩外侧摩擦力降到最小限度,便于起桩;此拔桩方法不仅比之前的传统方法进度快,更确保了后期新基础承载力。
Description
技术领域
本发明涉及一种拔桩的施工方法。
背景技术
在进行拔桩施工中,一般是首先用地震物探法初步定出废桩的大体位置再用小螺钻探测确定具体桩位,当定位不精确时,拔桩过程中会出现断桩情况,严重影响后续施工。传统的方法有:(1)采用高压水枪将废旧周围的土壤冲松,消除桩与土壤之间的摩阻力,采用该方案的缺点是对原土地基、基土破坏影响较大,其原因在用高压水枪刷时,不可能达到垂直冲刷的效果。如桩深在10m-15m左右时,经高压水枪冲刷后,桩周围的基土影响面一般只在4-5m范围左右。(2)采用机械在废旧桩周围开槽挖土,来消除摩擦力。但由于挖土机机械壁长不够,挖土的深度不一定能满足拔桩效果的要求,而且对废旧桩周围的基土破坏面较大,也会影响新基础的承载力。
发明内容
为了克服采用传统的拔桩方法对废桩拔除不彻底,本发明所要解决的技术问题是提供一种新型的拔桩方法,废桩定位更精确,并利用高压射气射水清理桩周边的土层便于起桩,确保拔桩更彻底。
本发明的目的是这样实现的:一种拔桩施工的方法,它包括下述步骤:
废桩定位:用地震物探法初步定出废桩的位置后,再用小型螺旋钻机探测确定具体桩位;
开挖沟槽:废桩定位后用挖机开挖在桩位上开挖沟槽,边挖边支护,挖到地表下后用钢钎探出方桩的准确位置,确定需要拔除的桩位;
振动沉放设置钢套管:根据现场的桩径、截面积和深度,将加工的含有若干水路和气路,刚度满足要求的套管通过吊车,在振动锤振动下沉钢管至桩底标高以下,下沉就位后移除固定在钢套管顶部的振动锤,并在钢套管上固定钢丝绳;
吊拔桩体:将钢套管固定到下节桩的中下部,用吊机收紧起吊拔桩并吊运至附近空地;
振动拔除钢套管:启动固定在钢套管上的振动锤,用吊机起吊边振动边拔除钢管套。
在振动沉设钢套管过程中,水路和气路,开启空压机和高压水泵进行套管内桩侧泥土的破碎置换,并对桩体的冲刷清洗至桩被独立剥离出来。
在开挖沟槽过程中采用毛竹筒式支护。
在完成拔桩施工作业后,对桩孔回填、加固。
本发明取得了以下的技术效果:采用此种方法对废桩定位更准确,利用高压射气射水进行套管内清洗桩边土层,确保桩外侧摩擦力降到最小限度,便于起桩;采用水泥搅拌桩进行加固后,不会影响新基础的承载力。
附图说明
下面结合附图和实施案例对本发明作进一步说明。
图1为本发明的施工示意图。
图2为本发明的结构示意图。
图中,1、振动锤,2、钢套管,3、进水孔,4、进气孔,5,吊车。
具体实施方式
实施例:参见图1:一种拔桩的施工方法,它包括以下步骤:
1)首先用地震物探法初步定出废桩的大体位置后再用小螺钻探测确定具体桩位,然后用挖机开挖1米深的沟槽,在沟槽中采取常规的人工挖孔桩施工工艺人工开挖直径1000mm深度2米,边挖边支护,挖到地表下2米处用钢钎探出方桩的准确位置,确定需要拔除的桩位。
2)考虑到桩顶埋深较深,有必要采取毛竹筒式支护措施,另配备水泵进行降水处理。考虑桩与桩之间距离较小,采取跳拔法,拔完孔洞及时回填振捣密实,防止邻桩串孔塌方。
3)振动沉放设置钢套管2:根据现场的桩径、截面积和深度等,将加工的含几个水路和几个气路的刚度满足要求的钢套管,用150T履带吊车吊住135KW零电流启动的1振动锤振动下沉钢管至桩底标高下50-100CM处,在下沉过程中,控制好垂直度。下沉就位后移除固定在钢套管顶部的振动锤1。
4)高压射水射气:在下沉过程中,通过进水孔3和进气孔4,利用空压机和高压水泵进行套管内桩侧泥土的破碎置换和对桩体的冲刷清洗至桩被独立剥离出来。
5)吊拔桩体:钢丝绳(已预设在套管内某一深度)固定到下节桩的中下部。用150T履带式吊车5收紧起吊拔桩并吊运至附近空地。
6)振动拔除钢套管:启动固定在钢套管上的1振动锤,使用150T履带式吊机起吊边振动边拔除钢管套。
7)旧桩拔除后要进行桩孔回填、加固,加固采用500水泥搅拌桩,水泥掺量5%,桩长同旧方桩。
Claims (4)
1.一种拔桩施工的方法,其特征在于:它包括下述步骤:
废桩定位:初步定出废桩的位置后,再用螺旋钻机探测确定具体桩位;
开挖沟槽:废桩定位后用挖机开挖在桩位上开挖沟槽,边挖边支护,挖到地表下后用钢钎探出方桩的准确位置,确定需要拔除的桩位;
振动沉放设置钢套管:根据现场的桩径、截面积和深度,将加工的含有若干水路和气路,刚度满足要求的钢套管通过吊车,在振动锤振动下沉钢管至桩底标高以下,下沉就位后移除固定在钢套管顶部的振动锤,并在钢套管上固定钢丝绳;
吊拔桩体:将钢套管固定到下节桩的中下部,用吊机收紧起吊拔桩并吊运至附近空地;
振动拔除钢套管:启动固定在钢套管上的振动锤,用吊机起吊边振动边拔除钢管套。
2.根据权利要求1所述的拔桩施工的方法,其特征在于:在振动沉设钢套管过程中,利用水路和气路,开启空压机和高压水泵进行套管内桩侧泥土的破碎置换,并对桩体的冲刷清洗至桩被独立剥离出来。
3.根据权利要求1所述的拔桩施工的方法,其特征在于:在开挖沟槽过程中采用毛竹筒式支护。
4.根据权利要求1所述的拔桩施工的方法,其特征在于:在完成拔桩施工作业后,对桩孔回填、加固。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510168290.5A CN104775433B (zh) | 2015-04-11 | 2015-04-11 | 一种拔桩施工的方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510168290.5A CN104775433B (zh) | 2015-04-11 | 2015-04-11 | 一种拔桩施工的方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104775433A true CN104775433A (zh) | 2015-07-15 |
CN104775433B CN104775433B (zh) | 2017-03-29 |
Family
ID=53617173
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510168290.5A Active CN104775433B (zh) | 2015-04-11 | 2015-04-11 | 一种拔桩施工的方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104775433B (zh) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105544544A (zh) * | 2015-12-16 | 2016-05-04 | 上海市城市建设设计研究总院 | 低净空条件下快速拔桩的方法 |
CN105735318A (zh) * | 2016-03-25 | 2016-07-06 | 上海建工四建集团有限公司 | 一种振动套管及使用方法 |
CN106320340A (zh) * | 2016-10-12 | 2017-01-11 | 中建港务建设有限公司 | 拔桩用振动套管及高压射水拔桩工艺 |
CN109440801A (zh) * | 2018-12-19 | 2019-03-08 | 长沙恒德岩土工程技术有限公司 | 一种用于桩基的补强方法 |
JP2020193534A (ja) * | 2019-05-30 | 2020-12-03 | 株式会社設計室ソイル | 鋼管杭の撤去方法 |
CN113653054A (zh) * | 2021-09-17 | 2021-11-16 | 中建八局第二建设有限公司 | 一种拔桩施工方法 |
JP2021188378A (ja) * | 2020-05-30 | 2021-12-13 | 株式会社マルシン | 杭抜埋戻工法 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2003155747A (ja) * | 2002-09-27 | 2003-05-30 | Inomata Juki Kogyo Kk | 杭引き抜き用作業機 |
CN2806566Y (zh) * | 2005-06-21 | 2006-08-16 | 上海建仕建筑工程有限公司 | 钢套水气喷射法拔桩装置 |
CN101130988A (zh) * | 2007-08-16 | 2008-02-27 | 江苏华东建设基础工程总公司 | 一种拔桩机及其拔桩的施工方法 |
CN101550697A (zh) * | 2008-04-03 | 2009-10-07 | 上海宝冶建设有限公司 | 地下桩套管振动冲孔拔除方法 |
-
2015
- 2015-04-11 CN CN201510168290.5A patent/CN104775433B/zh active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2003155747A (ja) * | 2002-09-27 | 2003-05-30 | Inomata Juki Kogyo Kk | 杭引き抜き用作業機 |
CN2806566Y (zh) * | 2005-06-21 | 2006-08-16 | 上海建仕建筑工程有限公司 | 钢套水气喷射法拔桩装置 |
CN101130988A (zh) * | 2007-08-16 | 2008-02-27 | 江苏华东建设基础工程总公司 | 一种拔桩机及其拔桩的施工方法 |
CN101550697A (zh) * | 2008-04-03 | 2009-10-07 | 上海宝冶建设有限公司 | 地下桩套管振动冲孔拔除方法 |
Non-Patent Citations (2)
Title |
---|
广东省地方史志编纂委员会: "《广东省志•公路交通志》", 30 September 1996 * |
韩泽亮: ""钻孔灌注桩拔除工艺研究"", 《岩土工程学报》 * |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105544544A (zh) * | 2015-12-16 | 2016-05-04 | 上海市城市建设设计研究总院 | 低净空条件下快速拔桩的方法 |
CN105735318A (zh) * | 2016-03-25 | 2016-07-06 | 上海建工四建集团有限公司 | 一种振动套管及使用方法 |
CN106320340A (zh) * | 2016-10-12 | 2017-01-11 | 中建港务建设有限公司 | 拔桩用振动套管及高压射水拔桩工艺 |
CN106320340B (zh) * | 2016-10-12 | 2019-11-22 | 中建港务建设有限公司 | 拔桩用振动套管及高压射水拔桩工艺 |
CN109440801A (zh) * | 2018-12-19 | 2019-03-08 | 长沙恒德岩土工程技术有限公司 | 一种用于桩基的补强方法 |
JP2020193534A (ja) * | 2019-05-30 | 2020-12-03 | 株式会社設計室ソイル | 鋼管杭の撤去方法 |
JP2021188378A (ja) * | 2020-05-30 | 2021-12-13 | 株式会社マルシン | 杭抜埋戻工法 |
CN113653054A (zh) * | 2021-09-17 | 2021-11-16 | 中建八局第二建设有限公司 | 一种拔桩施工方法 |
Also Published As
Publication number | Publication date |
---|---|
CN104775433B (zh) | 2017-03-29 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104775433B (zh) | 一种拔桩施工的方法 | |
CN104563098B (zh) | 一种超大直径全钢护筒干作业成孔灌注桩施工方法 | |
CN101328712A (zh) | 一种适用于软土及带障碍物土层中的咬合桩施工方法 | |
CN102587380A (zh) | 一种钻孔桩桩头整体破除施工方法 | |
CN102644275A (zh) | 复杂地质条件下旋挖组合成桩施工方法 | |
CN101550697A (zh) | 地下桩套管振动冲孔拔除方法 | |
CN105780763A (zh) | 中孔振动套管护壁长螺旋钻孔压灌桩的施工方法 | |
JP2006214241A (ja) | ドレーンパイプ埋設工法及び建築物等の傾斜,沈下又は浮上防止構造 | |
CN106545007A (zh) | 在下部为硬质岩层的地层中成桩的方法 | |
CN104746519A (zh) | 一种清障施工方法 | |
CN103046931A (zh) | 一种竖井/导井冲击式钻机冲击成孔施工方法 | |
JP2021165468A (ja) | 鋼管杭の施工方法 | |
CN101982614A (zh) | 全套管钻机凿取岩石成桩的方法 | |
CN201169773Y (zh) | 清除地下原有桩子的施工装置 | |
CN112281880A (zh) | 一种复杂地层长螺旋引孔插打锁口钢管桩围堰的施工方法 | |
Lande et al. | Effects of drilling for tieback anchors on surrounding ground: Results from field tests | |
CN107653878A (zh) | 钻孔灌注桩可重复使用纵向分离式钢护筒施工工法 | |
KR100543727B1 (ko) | 암반 이중굴착을 통한 지반천공 공법 | |
JP2007332559A (ja) | 既設地中杭の撤去方法 | |
CN212716407U (zh) | 一种岩溶地区桩基钻孔装置 | |
CN111877344A (zh) | 一种旧管桩破除方法 | |
CN105113976A (zh) | 钢丝刷钻头回旋钻机及解决埋钻、掉钻、卡钻的方法 | |
KR20090115702A (ko) | 대구경 기초파일 시공을 위한 지반 굴착공법 | |
KR101139708B1 (ko) | 대구경 파일 시공을 위한 지반 굴착 가이드 케이싱 및 이를 이용한 지반 굴착공법 | |
CN104452776B (zh) | 遭遇孤石时地下连续墙的一种施工处治方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
EXSB | Decision made by sipo to initiate substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
CB02 | Change of applicant information |
Address after: 443000 Hubei city of Yichang Province, Jianshe Road No. 40 Applicant after: CGGC FOUNDATION ENGINEERING CO., LTD. Address before: 443000 Hubei city of Yichang Province, Jianshe Road No. 40 Applicant before: Gezhouba Group Foundation Engineering Co., Ltd. |
|
COR | Change of bibliographic data | ||
GR01 | Patent grant | ||
GR01 | Patent grant |