CN104775433A - 一种拔桩施工的方法 - Google Patents

一种拔桩施工的方法 Download PDF

Info

Publication number
CN104775433A
CN104775433A CN201510168290.5A CN201510168290A CN104775433A CN 104775433 A CN104775433 A CN 104775433A CN 201510168290 A CN201510168290 A CN 201510168290A CN 104775433 A CN104775433 A CN 104775433A
Authority
CN
China
Prior art keywords
stake
pile
steel sleeve
pile pulling
vibration
Prior art date
Application number
CN201510168290.5A
Other languages
English (en)
Other versions
CN104775433B (zh
Inventor
李林娟
陶志斌
Original Assignee
葛洲坝集团基础工程有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 葛洲坝集团基础工程有限公司 filed Critical 葛洲坝集团基础工程有限公司
Priority to CN201510168290.5A priority Critical patent/CN104775433B/zh
Publication of CN104775433A publication Critical patent/CN104775433A/zh
Application granted granted Critical
Publication of CN104775433B publication Critical patent/CN104775433B/zh

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D9/00Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof
    • E02D9/02Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof by withdrawing

Abstract

一种拔桩的施工方法,首先用地震物探法初步定出废桩的大体位置再用小螺钻探测确定具体桩位,采用此种方法对废桩定位更准确;在钢管沉设过程中利用高压射气射水进行套管内清洗桩边土层,确保桩外侧摩擦力降到最小限度,便于起桩;此拔桩方法不仅比之前的传统方法进度快,更确保了后期新基础承载力。

Description

一种拔粧施工的方法
技术领域
[0001] 本发明涉及一种拔粧的施工方法。
背景技术
[0002] 在进行拔粧施工中,一般是首先用地震物探法初步定出废粧的大体位置再用小螺钻探测确定具体粧位,当定位不精确时,拔粧过程中会出现断粧情况,严重影响后续施工。传统的方法有:(I)采用高压水枪将废旧周围的土壤冲松,消除粧与土壤之间的摩阻力,采用该方案的缺点是对原土地基、基土破坏影响较大,其原因在用高压水枪刷时,不可能达到垂直冲刷的效果。如粧深在10m-15m左右时,经高压水枪冲刷后,粧周围的基土影响面一般只在4-5m范围左右。(2)采用机械在废旧粧周围开槽挖土,来消除摩擦力。但由于挖土机机械壁长不够,挖土的深度不一定能满足拔粧效果的要求,而且对废旧粧周围的基土破坏面较大,也会影响新基础的承载力。
发明内容
[0003] 为了克服采用传统的拔粧方法对废粧拔除不彻底,本发明所要解决的技术问题是提供一种新型的拔粧方法,废粧定位更精确,并利用高压射气射水清理粧周边的土层便于起粧,确保拔粧更彻底。
[0004] 本发明的目的是这样实现的:一种拔粧施工的方法,它包括下述步骤:
废粧定位:用地震物探法初步定出废粧的位置后,再用小型螺旋钻机探测确定具体粧位;
开挖沟槽:废粧定位后用挖机开挖在粧位上开挖沟槽,边挖边支护,挖到地表下后用钢钎探出方粧的准确位置,确定需要拔除的粧位;
振动沉放设置钢套管:根据现场的粧径、截面积和深度,将加工的含有若干水路和气路,刚度满足要求的套管通过吊车,在振动锤振动下沉钢管至粧底标高以下,下沉就位后移除固定在钢套管顶部的振动锤,并在钢套管上固定钢丝绳;
吊拔粧体:将钢套管固定到下节粧的中下部,用吊机收紧起吊拔粧并吊运至附近空地;
振动拔除钢套管:启动固定在钢套管上的振动锤,用吊机起吊边振动边拔除钢管套。
[0005] 在振动沉设钢套管过程中,水路和气路,开启空压机和高压水泵进行套管内粧侧泥土的破碎置换,并对粧体的冲刷清洗至粧被独立剥离出来。
[0006] 在开挖沟槽过程中采用毛竹筒式支护。
[0007] 在完成拔粧施工作业后,对粧孔回填、加固。
[0008] 本发明取得了以下的技术效果:采用此种方法对废粧定位更准确,利用高压射气射水进行套管内清洗粧边土层,确保粧外侧摩擦力降到最小限度,便于起粧;采用水泥搅拌粧进行加固后,不会影响新基础的承载力。
附图说明
[0009] 下面结合附图和实施案例对本发明作进一步说明。
[0010] 图1为本发明的施工示意图。
[0011] 图2为本发明的结构示意图。
[0012] 图中,1、振动锤,2、钢套管,3、进水孔,4、进气孔,5,吊车。
具体实施方式
[0013] 实施例:参见图1: 一种拔粧的施工方法,它包括以下步骤:
I)首先用地震物探法初步定出废粧的大体位置后再用小螺钻探测确定具体粧位,然后用挖机开挖I米深的沟槽,在沟槽中采取常规的人工挖孔粧施工工艺人工开挖直径1000_深度2米,边挖边支护,挖到地表下2米处用钢钎探出方粧的准确位置,确定需要拔除的粧位。
[0014] 2)考虑到粧顶埋深较深,有必要采取毛竹筒式支护措施,另配备水泵进行降水处理。考虑粧与粧之间距离较小,采取跳拔法,拔完孔洞及时回填振捣密实,防止邻粧串孔塌方。
[0015] 3)振动沉放设置钢套管2:根据现场的粧径、截面积和深度等,将加工的含几个水路和几个气路的刚度满足要求的钢套管,用150T履带吊车吊住135KW零电流启动的I振动锤振动下沉钢管至粧底标高下50-100CM处,在下沉过程中,控制好垂直度。下沉就位后移除固定在钢套管顶部的振动锤I。
[0016] 4)高压射水射气:在下沉过程中,通过进水孔3和进气孔4,利用空压机和高压水泵进行套管内粧侧泥土的破碎置换和对粧体的冲刷清洗至粧被独立剥离出来。
[0017] 5)吊拔粧体:钢丝绳(已预设在套管内某一深度)固定到下节粧的中下部。用150T履带式吊车5收紧起吊拔粧并吊运至附近空地。
[0018] 6)振动拔除钢套管:启动固定在钢套管上的I振动锤,使用150T履带式吊机起吊边振动边拔除钢管套。
[0019] 7)旧粧拔除后要进行粧孔回填、加固,加固采用500水泥搅拌粧,水泥掺量5%,粧长同旧方粧。

Claims (4)

1.一种拔粧施工的方法,其特征在于:它包括下述步骤: 废粧定位:初步定出废粧的位置后,再用螺旋钻机探测确定具体粧位; 开挖沟槽:废粧定位后用挖机开挖在粧位上开挖沟槽,边挖边支护,挖到地表下后用钢钎探出方粧的准确位置,确定需要拔除的粧位; 振动沉放设置钢套管:根据现场的粧径、截面积和深度,将加工的含有若干水路和气路,刚度满足要求的钢套管通过吊车,在振动锤振动下沉钢管至粧底标高以下,下沉就位后移除固定在钢套管顶部的振动锤,并在钢套管上固定钢丝绳; 吊拔粧体:将钢套管固定到下节粧的中下部,用吊机收紧起吊拔粧并吊运至附近空地; 振动拔除钢套管:启动固定在钢套管上的振动锤,用吊机起吊边振动边拔除钢管套。
2.根据权利要求1所述的拔粧施工的方法,其特征在于:在振动沉设钢套管过程中,利用水路和气路,开启空压机和高压水泵进行套管内粧侧泥土的破碎置换,并对粧体的冲刷清洗至粧被独立剥离出来。
3.根据权利要求1所述的拔粧施工的方法,其特征在于:在开挖沟槽过程中采用毛竹筒式支护。
4.根据权利要求1所述的拔粧施工的方法,其特征在于:在完成拔粧施工作业后,对粧孔回填、加固。
CN201510168290.5A 2015-04-11 2015-04-11 一种拔桩施工的方法 CN104775433B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510168290.5A CN104775433B (zh) 2015-04-11 2015-04-11 一种拔桩施工的方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510168290.5A CN104775433B (zh) 2015-04-11 2015-04-11 一种拔桩施工的方法

Publications (2)

Publication Number Publication Date
CN104775433A true CN104775433A (zh) 2015-07-15
CN104775433B CN104775433B (zh) 2017-03-29

Family

ID=53617173

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510168290.5A CN104775433B (zh) 2015-04-11 2015-04-11 一种拔桩施工的方法

Country Status (1)

Country Link
CN (1) CN104775433B (zh)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105544544A (zh) * 2015-12-16 2016-05-04 上海市城市建设设计研究总院 低净空条件下快速拔桩的方法
CN105735318A (zh) * 2016-03-25 2016-07-06 上海建工四建集团有限公司 一种振动套管及使用方法
CN106320340A (zh) * 2016-10-12 2017-01-11 中建港务建设有限公司 拔桩用振动套管及高压射水拔桩工艺
CN109440801A (zh) * 2018-12-19 2019-03-08 长沙恒德岩土工程技术有限公司 一种用于桩基的补强方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003155747A (ja) * 2002-09-27 2003-05-30 Hitachi Constr Mach Co Ltd 杭引き抜き用作業機
CN2806566Y (zh) * 2005-06-21 2006-08-16 上海建仕建筑工程有限公司 钢套水气喷射法拔桩装置
CN101130988A (zh) * 2007-08-16 2008-02-27 江苏华东建设基础工程总公司 一种拔桩机及其拔桩的施工方法
CN101550697A (zh) * 2008-04-03 2009-10-07 上海宝冶建设有限公司 地下桩套管振动冲孔拔除方法

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003155747A (ja) * 2002-09-27 2003-05-30 Hitachi Constr Mach Co Ltd 杭引き抜き用作業機
CN2806566Y (zh) * 2005-06-21 2006-08-16 上海建仕建筑工程有限公司 钢套水气喷射法拔桩装置
CN101130988A (zh) * 2007-08-16 2008-02-27 江苏华东建设基础工程总公司 一种拔桩机及其拔桩的施工方法
CN101550697A (zh) * 2008-04-03 2009-10-07 上海宝冶建设有限公司 地下桩套管振动冲孔拔除方法

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
广东省地方史志编纂委员会: "《广东省志•公路交通志》", 30 September 1996 *
韩泽亮: ""钻孔灌注桩拔除工艺研究"", 《岩土工程学报》 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105544544A (zh) * 2015-12-16 2016-05-04 上海市城市建设设计研究总院 低净空条件下快速拔桩的方法
CN105735318A (zh) * 2016-03-25 2016-07-06 上海建工四建集团有限公司 一种振动套管及使用方法
CN106320340A (zh) * 2016-10-12 2017-01-11 中建港务建设有限公司 拔桩用振动套管及高压射水拔桩工艺
CN106320340B (zh) * 2016-10-12 2019-11-22 中建港务建设有限公司 拔桩用振动套管及高压射水拔桩工艺
CN109440801A (zh) * 2018-12-19 2019-03-08 长沙恒德岩土工程技术有限公司 一种用于桩基的补强方法

Also Published As

Publication number Publication date
CN104775433B (zh) 2017-03-29

Similar Documents

Publication Publication Date Title
CN106400782B (zh) 一种利用旋挖钻机施工基坑围护钻孔咬合桩的施工方法
CN101122130B (zh) 一种建筑物或桥梁基础用的随钻跟管桩的施工方法
CN104818712B (zh) 一种适用于溶洞地质的冲击成孔灌注桩的施工方法
CN104278667B (zh) 一种地下溶洞的充填处理方法
CN105735251B (zh) 桥梁桩基旋挖钻机切削式全护筒跟进成桩施工方法及系统
CN102561330B (zh) 人工挖孔桩与钢管混凝土柱一体化的施工方法
CN103603342B (zh) 大直径组合套管超长灌注桩施工方法
KR100964796B1 (ko) 암반 매립 일체화 구조의 강관-콘크리트 복합 말뚝 시공 방법 및 말뚝 구조물
CN1986975A (zh) 全套管大直径振动取土灌注桩施工方法
CN104652436B (zh) 钢套管高压注水松土拔桩施工方法
KR100718942B1 (ko) 연약지반 강관 압입용 터널굴착기 및 굴착시공 방법
CN105649083B (zh) 全套管一次性旋切式清桩装置及其清桩方法
CN104563098B (zh) 一种超大直径全钢护筒干作业成孔灌注桩施工方法
CN102071683A (zh) 水钻挖孔桩施工方法
CN106192971B (zh) 一种承压水水位观测井结构及多层水位观测的方法
JP4282022B2 (ja) ドレーンパイプ埋設工法及び建築物等の傾斜,沈下又は浮上防止構造
CN101737005B (zh) 一种用于套取锚索的钻具及跟管套取锚索的施工方法
CN204199335U (zh) 一种减小phc管桩施工挤土效应的泄压井
CN109594564A (zh) 一种地铁深基坑明挖防坍塌施工方法
CN104060615B (zh) 利用新建基坑支护结构清除地下障碍物的施工方法
CN102852141B (zh) 一种桩芯灌注混凝土桩侧静压注浆的嵌岩管桩基础及其施工方法
CN104963346A (zh) 复杂地质的深基坑围护施工方法
KR100543727B1 (ko) 암반 이중굴착을 통한 지반천공 공법
CN103046931B (zh) 一种竖井/导井冲击式钻机冲击成孔施工方法
CN106437798B (zh) 一种穿过盾构掘进断面的锚索群的预处理方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
COR Change of bibliographic data
CB02 Change of applicant information

Address after: 443000 Hubei city of Yichang Province, Jianshe Road No. 40

Applicant after: CGGC FOUNDATION ENGINEERING CO., LTD.

Address before: 443000 Hubei city of Yichang Province, Jianshe Road No. 40

Applicant before: Gezhouba Group Foundation Engineering Co., Ltd.

GR01 Patent grant
GR01 Patent grant