CN104766177A - 一种基于工业化建设项目的预制构件信息库构建方法 - Google Patents

一种基于工业化建设项目的预制构件信息库构建方法 Download PDF

Info

Publication number
CN104766177A
CN104766177A CN201510193854.0A CN201510193854A CN104766177A CN 104766177 A CN104766177 A CN 104766177A CN 201510193854 A CN201510193854 A CN 201510193854A CN 104766177 A CN104766177 A CN 104766177A
Authority
CN
China
Prior art keywords
information
group
prefabricated components
code
construction project
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510193854.0A
Other languages
English (en)
Inventor
胡凯
陈云琪
李庆武
瞿革
蒋瓅
丁嘉卿
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Shipbuilding NDRI Engineering Co Ltd
Original Assignee
China Shipbuilding NDRI Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Shipbuilding NDRI Engineering Co Ltd filed Critical China Shipbuilding NDRI Engineering Co Ltd
Priority to CN201510193854.0A priority Critical patent/CN104766177A/zh
Publication of CN104766177A publication Critical patent/CN104766177A/zh
Pending legal-status Critical Current

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

本发明公开了一种基于工业化建设项目的预制构件信息库构建方法,其特点是对建设项目中每一预制构件按构件编号、设计、生产、运输、堆场、吊装和工艺信息进行编码和数据录入的方式架构计算机管理的信息库,由构件编号通过信息库进行检索可快速查询预制构件的详尽信息,所述信息编码分别为一组由字母与数字组成表示的信息代码,各组信息代码之间由空格隔开;所述数据录入为预制构件的具体参数与其表示的信息代码一一对应。本发明与现有技术相比具有快速识别和查询预制构件的详尽信息,有效管理和指导预制构件的运输、堆场、吊装及施工,提高施工质量和工作效率。

Description

一种基于工业化建设项目的预制构件信息库构建方法
技术领域
本发明涉及建筑工程信息技术领域,尤其是一种用于计算机信息管理的大型工业化建设项目的预制构件信息库构建方法。
背景技术
工业化的建设是建筑工程的发展方向,尤其在建筑行业的人力成本不断上升时期,环保及节能减排的重要性不断提高以及国家政策的巨大推力下,预制装配式建筑技术的发展和应用势在必行。然而,预制装配式建筑,尤其是大型的工业化建设项目存在大量的预制构件,尚未形成有效实用的预制构件管理方法。
目前,大量的预制构件未建立信息库,对预制构件的工程管理还是沿用传统的人工管理方法,不但劳动强度大,工作效率低,而且还容易造成差错,影响工程进度和施工质量。在生产、供应、运输、施工以及使用阶段对这些预制构件实施有效的全寿命周期管理将大幅度的提高工程的建造质量和效率。
发明内容
本发明的目的是针对现有技术的不足而设计的一种基于工业化建设项目的预制构件信息库构建方法,采用编码信息方法将每一预制构件的设计、生产、安装等相关信息设置在一组由字母和数字组成的编码中,对整个建设项目中全部预制构件的信息进行编码后录入数据库,根据此编码信息对预制构件的运输、堆场、吊装及施工等阶段的详细信息可以进行快速识别和查询,指导预制构件的堆场、吊装和施工,实现预制装配式建筑构件的有效管理,使预制构件在运输阶段可以迅速确定运输对象及运输数量,在进场堆放时可以根据安装时间对预制构件是否进行堆场进行判别,对需堆放的构件根据堆放区域代码信息堆放,核对同批次同种构件数量避免出现数量问题,在吊装和安装阶段可以快速对预制构件的安装位置进行定位和确定安装工艺类型,提高工业化建设项目的预制装配式的管理效率,尤其是大型工程项目的建设效率。同时,结合智能感知技术,实现对关键构件的全寿命周期的追踪管理。
本发明的目的是这样实现的:一种基于工业化建设项目的预制构件信息库构建方法,其特点是对建设项目中每一预制构件按项目、设计、生产、运输、堆场、吊装和工艺信息进行编码和数据录入的方式架构计算机管理的信息库,由构件编号通过信息库进行检索可快速查询预制构件的详尽信息,所述信息编码分别为一组由字母与数字组成表示构件编号、设计、生产、运输、堆场、吊装、工艺和扩展的信息代码,各组信息代码之间由空格隔开;所述数据录入为预制构件的具体参数与其表示的信息代码一一对应。
所述构件编号由表示工程代码及单体号的A1和构件号的A2组成A1-A2的第一组信息。
所述设计信息由表示设计单位代码的B1、构件截面尺寸的B2和材质代号的B3组成B1 B2 B3的第二组信息。
所述生产信息由表示订单号的C1、生产商代码的C2 和生产日期的C3组成C1 C2 C3的第三组信息。
所述运输信息由表示运输商代码的D1、运输批次的D2和构件数量的D3组成D1 D2 D3的第四组信息。
所述堆场信息由表示吊装时间的E1、堆放区域的E2和同堆场构件数的E3组成E1 E2 E3的第五组信息。
所述吊装信息由表示吊装单位代码的F1、安装楼层的F2和安装区域的F3组成F1 F2 F3的第六组信息。
所述工艺信息由G表示安装工艺的第七组信息。
所述扩展信息由H表示预留的第八组信息。
本发明与现有技术相比具有快速识别和查询预制构件的详尽信息,有效管理和指导预制构件的运输、堆场、吊装及施工,在运输时可以迅速准确的确定运输对象及运输数量;在进场堆放时可以根据预制构件的预计安装时间对预制构件是否需要堆场进行评判,对需堆放的构件根据堆放区域代码信息堆放,核对同批次同种构件数量避免出现数量问题;通过吊装信息可以快速对预制构件的安装位置进行定位;通过安装工艺信息可以初步确定预制构件的安装工艺类型。根据以上架构建立的信息库的实施可以实现预制装配式建筑构件的有效管理,提高工业化建设项目,特别是大型工程项目的建设效率,结合智能感知技术,可以实现对关键构件的全寿命周期的追踪管理。
附图说明
图1为本发明信息库架构示意图。       
具体实施方式
参阅附图1,本发明信息库架构由表示构件编号的A1-A2、设计信息的B1 B2 B3、生产信息的C1 C2 C3、运输信息的D1 D2 D3、堆场信息的E1 E2 E3、工艺信息的G和扩展信息的H八部分组成。对建设项目中每一预制构件按构件编号、设计、生产、运输、堆场、吊装和工艺信息进行编码和数据录入的方式架构计算机管理的信息库,由构件编号通过信息库进行检索可快速查询预制构件的详尽信息,所述信息编码分别为一组由字母与数字组成表示构件编号、设计、生产、运输、堆场、吊装、工艺和扩展的信息代码,各组信息代码之间由空格隔开;所述数据录入为预制构件的具体参数与其表示的信息代码一一对应。
所述构件编号由表示工程代码及单体号的A1和构件号的A2组成A1- A2的第一组信息,同时也为构件在信息库中的编号,每个构件对应唯一编号,相同构件采用统一编号,其中A1由表示工程代码的四个字母及表示单体号的二个数字组成,A2由表示构件形式的三个字母及二个数字组成,采用与设计和施工图中相同的编码形式,两部分之间通过“-”连接,该信息为构件的编码信息,预制构件的详尽信息可通过该构件编号调用信息库查询。
所述设计信息由表示设计单位代码的B1、构件截面尺寸的B2和材质代号的B3组成B1 B2 B3的第二组信息,其中B1为设计单位代码;B2 由代表截面尺寸的符号(高为H,宽为B)加相应的数字表示,B3为构件材质的代号。
所述生产信息由表示订单号的C1、生产商代码的C2 和生产日期的C3组成C1 C2 C3的第三组信息。
所述运输信息由表示运输商代码的D1、运输批次的D2和构件数量的D3组成D1 D2 D3的第四组信息。运输商代码D1由字母表示,运输批次D2和构件数量D3均由数字表示,其中,D2为根据安装施工计划制定的运输批次,D3为同批次运输的同种构件数量。
所述堆场信息由表示吊装时间的E1、堆放区域的E2和同堆场构件数的E3组成E1 E2 E3的第五组信息。其中,E1为按施工计划确定的构件的预计吊装时间,可根据此信息判断预制构件是否需要堆场处理;E2为构件的堆场区域代码,可结合施工现场场地情况,根据施工方便原则进行分区,制定每个构件的堆放分区,采用大写英文字母的形式表示;E3为同批次堆场的同种构件数量,采用数字表示。
所述吊装信息由表示吊装单位代码的F1、安装楼层的F2和安装区域的F3组成F1 F2 F3的第六组信息。其中,F1为吊装单位代码信息,F2为构件所在楼层信息,用数字形式表示,F3为构件在楼层上的所处分区信息,用大写英文字母形式表示。
所述工艺信息由G表示安装工艺的第七组信息,施工单位可根据工程的预制装配体系、节点的施工方式等特点,将本单位相应构件的安装工艺进行编号,在施工时根据安装工艺编号确定安装工艺形式。
所述扩展信息由H表示预留的第八组信息,为根据具体项目的特殊情况进行相应的补充和扩展,对于一般工程此项信息为空白。
下面根据某工程预制构件采用上述的编码方法对本发明作进一步说明:
该构件为JYXC项目中第2座单体中预制框架梁构件,其在设计图纸中编号为PCL11;构件的设计单位代码为ZCJY,构件截面形式为高600mm,宽300mm,构件材性C30;订单号为11065,生产厂商代码为JYSC,生产日期为140623;运输商代码JYYS,运输批次为第1次,同批次运输同种产品数量21;预计吊装时间为140710,堆场区域为A区,同批次堆场的同种产品数量15;吊装单位代码为JYDZ,安装楼层为5楼,在5层安装区域为A区;安装工艺为节点钢筋焊接连接,并在节点区浇筑混凝土,其安装工艺代码定为GY1。
根据本发明该工程预制构件在信息库中的编码如下所示:
                                                
以上只是对本发明作进一步的说明,并非用以限制本专利,凡为本发明等效实施,均应包含于本专利的权利要求范围之内。

Claims (9)

1.一种基于工业化建设项目的预制构件信息库构建方法,其特征在于对建设项目中每一预制构件按构件编号、设计、生产、运输、堆场、吊装和工艺信息进行编码和数据录入的方式架构计算机管理的信息库,由构件编号通过信息库进行检索可快速查询预制构件的详尽信息,所述信息编码分别为一组由字母与数字组成表示构件编号、设计、生产、运输、堆场、吊装、工艺和扩展的信息代码,各组信息代码之间由空格隔开;所述数据录入为预制构件的具体参数与其表示的信息代码一一对应。
2.根据权利要求1所述基于工业化建设项目的预制构件信息库构建方法,其特征在于所述构件编号由表示工程代码及单体号的A1和构件号的A2组成A1-A2的第一组信息。
3.根据权利要求1所述基于工业化建设项目的预制构件信息库构建方法,其特征在于所述设计信息由表示设计单位代码的B1、构件截面尺寸的B2和材质代号的B3组成B1 B2 B3的第二组信息。
4.根据权利要求1所述基于工业化建设项目的预制构件信息库构建方法,其特征在于所述生产信息由表示订单号的C1、生产商代码的C2 和生产日期的C3组成C1 C2 C3的第三组信息。
5.根据权利要求1所述基于工业化建设项目的预制构件信息库构建方法,其特征在于所述运输信息由表示运输商代码的D1、运输批次的D2和构件数量的D3组成D1 D2 D3的第四组信息。
6.根据权利要求1所述基于工业化建设项目的预制构件信息库构建方法,其特征在于所述堆场信息由表示吊装时间的E1、堆放区域的E2和同堆场构件数的E3组成E1 E2 E3的第五组信息。
7.根据权利要求1所述基于工业化建设项目的预制构件信息库构建方法,其特征在于所述吊装信息由表示吊装单位代码的F1、安装楼层的F2和安装区域的F3组成F1 F2 F3的第六组信息。
8.根据权利要求1所述基于工业化建设项目的预制构件信息库构建方法,其特征在于所述工艺信息由G表示安装工艺的第七组信息。
9.根据权利要求1所述基于工业化建设项目的预制构件信息库构建方法,其特征在于所述扩展信息由H表示预留的第八组信息。
CN201510193854.0A 2015-04-23 2015-04-23 一种基于工业化建设项目的预制构件信息库构建方法 Pending CN104766177A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510193854.0A CN104766177A (zh) 2015-04-23 2015-04-23 一种基于工业化建设项目的预制构件信息库构建方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510193854.0A CN104766177A (zh) 2015-04-23 2015-04-23 一种基于工业化建设项目的预制构件信息库构建方法

Publications (1)

Publication Number Publication Date
CN104766177A true CN104766177A (zh) 2015-07-08

Family

ID=53647991

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510193854.0A Pending CN104766177A (zh) 2015-04-23 2015-04-23 一种基于工业化建设项目的预制构件信息库构建方法

Country Status (1)

Country Link
CN (1) CN104766177A (zh)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106869308A (zh) * 2017-03-13 2017-06-20 同济大学 一种基于bim的装配式建筑支撑体系快速周转方法
CN107729703A (zh) * 2017-11-27 2018-02-23 中船第九设计研究院工程有限公司 一种基于“Ruby”语言的“Sketch Up”厂房工艺设计方法
CN108427787A (zh) * 2017-08-12 2018-08-21 中民筑友科技投资有限公司 一种基于bim的装配式堆场布局管理方法及系统
CN109577654A (zh) * 2017-09-29 2019-04-05 中国二十冶集团有限公司 基于bim技术的装配式混凝土构件物流组织吊装方法
CN110498343A (zh) * 2019-06-27 2019-11-26 六安远大住宅工业有限公司 Pc构件智能吊装入库控制系统及方法
CN110528881A (zh) * 2019-08-12 2019-12-03 成都市新宏建筑工程有限公司 一种基于bim的装配式建筑支撑体系快速周转方法
CN111915157A (zh) * 2020-07-14 2020-11-10 襄阳微时间网络科技有限公司 一种基于信息编码的预制构件施工管理方法
CN112508151A (zh) * 2020-11-09 2021-03-16 上海建工集团股份有限公司 整体爬升钢平台模架构件的重复使用方法
CN113627130A (zh) * 2021-06-29 2021-11-09 广东二十冶建设有限公司 一种确定钢-混凝土结构构件编码的方法及系统

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN200969111Y (zh) * 2005-08-18 2007-10-31 福建英特莱信息技术咨询有限公司 一种计算机用电网系统设备标识代码器
CN101183373A (zh) * 2007-12-17 2008-05-21 渤海船舶重工有限责任公司 船舶物资计算机管理的编码编制方法
CN202177927U (zh) * 2011-07-29 2012-03-28 罗勇 物资统一编码化清查管理系统
JP2012123589A (ja) * 2010-12-08 2012-06-28 Kubota Corp 配管施工管理システム、携帯端末及び施工情報管理サーバ
CN102750609A (zh) * 2012-05-23 2012-10-24 索菲亚家居股份有限公司 定制家居组件的管理方法
CN103559525A (zh) * 2013-10-21 2014-02-05 沈阳建筑大学 一种植入无线射频芯片预制混凝土构件
CN103793783A (zh) * 2014-01-09 2014-05-14 中建钢构有限公司 一种钢结构全过程跟踪方法及跟踪系统

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN200969111Y (zh) * 2005-08-18 2007-10-31 福建英特莱信息技术咨询有限公司 一种计算机用电网系统设备标识代码器
CN101183373A (zh) * 2007-12-17 2008-05-21 渤海船舶重工有限责任公司 船舶物资计算机管理的编码编制方法
JP2012123589A (ja) * 2010-12-08 2012-06-28 Kubota Corp 配管施工管理システム、携帯端末及び施工情報管理サーバ
CN202177927U (zh) * 2011-07-29 2012-03-28 罗勇 物资统一编码化清查管理系统
CN102750609A (zh) * 2012-05-23 2012-10-24 索菲亚家居股份有限公司 定制家居组件的管理方法
CN103559525A (zh) * 2013-10-21 2014-02-05 沈阳建筑大学 一种植入无线射频芯片预制混凝土构件
CN103793783A (zh) * 2014-01-09 2014-05-14 中建钢构有限公司 一种钢结构全过程跟踪方法及跟踪系统

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106869308A (zh) * 2017-03-13 2017-06-20 同济大学 一种基于bim的装配式建筑支撑体系快速周转方法
CN108427787A (zh) * 2017-08-12 2018-08-21 中民筑友科技投资有限公司 一种基于bim的装配式堆场布局管理方法及系统
CN109577654A (zh) * 2017-09-29 2019-04-05 中国二十冶集团有限公司 基于bim技术的装配式混凝土构件物流组织吊装方法
CN107729703B (zh) * 2017-11-27 2020-08-28 中船第九设计研究院工程有限公司 一种基于“Ruby”语言的“Sketch Up”厂房工艺设计方法
CN107729703A (zh) * 2017-11-27 2018-02-23 中船第九设计研究院工程有限公司 一种基于“Ruby”语言的“Sketch Up”厂房工艺设计方法
CN110498343A (zh) * 2019-06-27 2019-11-26 六安远大住宅工业有限公司 Pc构件智能吊装入库控制系统及方法
CN110498343B (zh) * 2019-06-27 2020-11-27 六安远大住宅工业有限公司 Pc构件智能吊装入库控制系统及方法
CN110528881A (zh) * 2019-08-12 2019-12-03 成都市新宏建筑工程有限公司 一种基于bim的装配式建筑支撑体系快速周转方法
CN111915157A (zh) * 2020-07-14 2020-11-10 襄阳微时间网络科技有限公司 一种基于信息编码的预制构件施工管理方法
CN111915157B (zh) * 2020-07-14 2023-12-08 襄阳微时间网络科技有限公司 一种基于信息编码的预制构件施工管理方法
CN112508151A (zh) * 2020-11-09 2021-03-16 上海建工集团股份有限公司 整体爬升钢平台模架构件的重复使用方法
CN113627130A (zh) * 2021-06-29 2021-11-09 广东二十冶建设有限公司 一种确定钢-混凝土结构构件编码的方法及系统
CN113627130B (zh) * 2021-06-29 2024-06-25 广东二十冶建设有限公司 一种确定钢-混凝土结构构件编码的方法及系统

Similar Documents

Publication Publication Date Title
CN104766177A (zh) 一种基于工业化建设项目的预制构件信息库构建方法
Hopkinson et al. Recovery and reuse of structural products from end-of-life buildings
Kadir et al. Construction performance comparison between conventional and industrialised building systems in Malaysia
CN109146118B (zh) 一种基于优化算法的预制构件堆场优化系统及其优化方法
CN110008648B (zh) 一种基于bim模型的智慧工地集成实施方法
Lu et al. Investigating waste reduction potential in the upstream processes of offshore prefabrication construction
CN106295078A (zh) 一种基于bim技术的钢筋翻样计算‑模块化加工系统及方法
CN207739529U (zh) 拼装装配式楼梯
CN112560134B (zh) 一种基于cad与bim的装配式结构叠合板批量深化设计方法
CN110543674A (zh) 一种基于bim的装配式楼板的自动拆分方法
CN112101905A (zh) 一种基于区块链技术的装配式建筑集成建造协同管理方法及其系统
Abdul Kadir et al. Construction performance comparison between conventional and industrialised building systems in Malaysia
CN112288384A (zh) 一种基于p-bias装配式建筑全生命周期管理的应用
Laurini et al. Technology 4.0 for buildings management: from building site to the interactive building book
Sun et al. Overview of modular design strategy of the shipping container architecture in cold regions
CN104778564A (zh) 一种基于信息编码的预制构件施工管理方法
CN100570757C (zh) 用于核电站核岛的模块化建造方法
CN116933368A (zh) 一种基于人机交互的建筑结构智能设计方法
CN101752017B (zh) 用于核电站核岛的模块化建造方法
CN101736925B (zh) 用于核电站核岛的模块化建造方法
CN112836285A (zh) 一种建筑结构复杂模块钢筋快速建模方法
Chougule et al. Review of Time and Cost Analysis for Prefabricated Prefinished Volumetric Construction (PPVC)
Wang et al. Additive manufacturing: a revolutionized power for construction industrialization
CN113128011A (zh) Epc模式下基于最优成本目标的装配式建筑设计方法
KR20200097462A (ko) Bim 기반 pc 구조물 시공 및 관리 방법

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20150708