CN104762859B - Mountain skin stone processes soft soil roadbed method - Google Patents
Mountain skin stone processes soft soil roadbed method Download PDFInfo
- Publication number
- CN104762859B CN104762859B CN201510114383.XA CN201510114383A CN104762859B CN 104762859 B CN104762859 B CN 104762859B CN 201510114383 A CN201510114383 A CN 201510114383A CN 104762859 B CN104762859 B CN 104762859B
- Authority
- CN
- China
- Prior art keywords
- mountain
- soft soil
- soil roadbed
- roadbed
- skin stone
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Road Paving Structures (AREA)
Abstract
A kind of mountain skin stone processes soft soil roadbed method, comprises the steps:Soft soil roadbed clear table, surveying and locating, particle diameter is transported to scene less than or equal to 60cm mountain skin building stones, then material is paved, shaping, roll, health preserving;After the completion of the first Rotating fields health preserving, carry out second layer structure sheaf construction:The mountain calculating skin stone is shakeout by design width, thickness, carry out again shaping, roll, health preserving.The soft soil roadbed intensity processing through mountain skin stone improves 35 times, and plastic deformation reduces 70% 80%.Frost resistance improves, and after enduring cold, degree of compaction is unchanged, and the coefficient of expansion reduces 60% 80%;Effectively accelerating construction progress, shortens the completion time of project, this construction method is applied to various soft soil roadbed.
Description
Technical field
The present invention relates to the method building different kinds of roads, the soft soil roadbed method of particularly a kind of mountain skin stone process, it is suitable for
In building different kinds of roads on the soft foundations such as frozen soil, level of ground water height, spring soil, salt-soda soil.
Background technology
At present, China coast industrial base geological condition is complicated, usually occurs that frozen soil, level of ground water be high, spring is native, saline and alkaline
Multiple soft foundations such as ground, had both needed the longer duration using conventional Soft Soil Subgrade Treatment Method, required there is 12 as roadbed
The sedimentation of more than individual month just can carry out pavement construction, can not fundamentally solve subgrade stability sex chromosome mosaicism again, as earth roadbed in Calx
Contractility is big, easily ftracture, should not be used in moist section, and needs to waste substantial contribution.
As can be seen here, in order to overcome drawbacks described above present in conventional soft base processing method construction, seek one kind both economical
Can gather materials on the spot again, convenient construction, and the effective ways of coastal soft subgrade treatment can be solved in shorter time, be current edge
One very urgent task of marine products industry construction of base person.
Content of the invention
The present invention is directed to the defect of prior art, provides a kind of mountain skin stone to process soft soil roadbed method, this construction method is fitted
For various soft soil roadbed, effectively shorten the duration, fundamentally solve the stability problem of roadbed.
Realize this technical scheme below of above-mentioned purpose:
A kind of mountain skin stone processes soft soil roadbed method it is characterised in that comprising the steps:
A. soft soil roadbed clear table:Full width is down dug from original ground first, detects the mark after original ground absolute altitude and clear table at any time
Height, to ensure that ground eliminating impurities are clean and protect
Card filling-up thickness;Measure bottom width degree after clear table, to meet roadbed filling width, road
Place soil during the clear table of base and be more than 2m from clear table boundary;
B, surveying and locating:Lay double-direction control stake on the basis of SURVEYING CONTROL NETWORK, form 10*10m and control net, run into curved
It is encrypted at road, and mark the elevation after empty paving elevation and compacting;
C, particle diameter is transported to scene less than or equal to 60cm mountain skin building stones, then material is paved, shaping, roll, health preserving;Stand
Laying method is to be paved using man-machine cooperation, is first shakeout roughly with bull-dozer, then adopts land leveller essence flat, after land leveller
The group that paves of 10m fit on 3-5 people, timely treated aggregate non-uniform phenomenon;Using the rolling method that first quiet rear shake is quiet again,
The road roller speed of travel is 1.5-1.7km/h, first uses road roller static pressure 2-3 time, in place of finding out injustice, uses artificial filling-in, then
Roll 4-5 time with vibrated roller, finally adopt road roller static pressure 2-3 time;
D., after the completion of the first Rotating fields health preserving, carry out second layer structure sheaf construction:By the mountain calculating skin stone by design
Width, thickness shakeout, carry out again shaping, roll, health preserving.
D., after the completion of the first Rotating fields health preserving, carry out second layer structure sheaf construction:By the mountain calculating skin stone by design
Width, thickness shakeout, carry out again shaping, roll, health preserving.
Preferably, the coefficient of loose laying of empty paving elevation is 1.30, concrete numerical value determines according to test section.
Preferably, mountain skin stone filling-up thickness is more than or equal to 90cm.
Using technique scheme, compared with prior art, the soft soil roadbed intensity processing through mountain skin stone improves 3-5
Times, plastic deformation reduces 70%-80%.Frost resistance improves, and after enduring cold, degree of compaction is unchanged, and the coefficient of expansion reduces 60%-80%;Effectively
Accelerating construction progress, shorten the completion time of project, this construction method is applied to various soft soil roadbed, and can be used for moist section even
Roadbed be applied to water, effectively overcomes the differential settlement of roadbed, decreases settlement of subgrade cracking in useful life
Maintenance number of times, reduce late maintaining cost, decrease job site dust granules, reduce the ring in road construction
Border cost, ensures that workmen is healthy.
Brief description
Fig. 1 is road structure schematic diagram of the present invention:
In figure:Mountain skin stone 1, removes table soil thickness 2.
Specific embodiment
The present invention will be further described below in conjunction with the accompanying drawings.
Specific construction process of the present invention is as follows:
1. preparation of construction
Before present invention construction, mountain skin stone 1 is tested, material maximum particle diameter is not more than 60cm, exceed this part and buying
Ground is crushed;Coordinate control point and vertical control point are carried out in scene.
2. surveying and locating
The present invention lays double-direction control stake on the basis of SURVEYING CONTROL NETWORK, forms 10*10m and controls net, runs into corner
It is being encrypted, marking elevation after empty paving elevation and compacting with red paint.Coefficient of loose laying typically takes 1.30, and concrete numerical value is according to examination
Test section to determine.
3. soft soil roadbed clear table
Full width is down dug from original ground first, and removing table soil thickness 2 is 40-60cm, at any time detection original ground absolute altitude and clear
Absolute altitude after table, to ensure ground debris(As weeds, miscellaneous tree, humus)Remove clean and ensure filling-up thickness;Measure clear table
Bottom width degree afterwards, to meet roadbed filling width, will consider the gradient of side slope during the clear table of roadbed, place soil will from clear table boundary 2m with
On;
4. mountain skin stone transport
The mountain skin stone 1 meeting design requirement particle diameter is transported to scene using dump truck, during transport, carries out finished product protection,
Never allow heavy-duty truck transportation, prevent to drive over the speed limit, carry out security protection;Computed in advance unload following distance, then unloaded
Car, backfill, the shaping that paves, roll, health preserving;
5. backfill
Thickness is backfilled according to the different characteristics design mountain skin stone 1 of various roadbeds, thickness is more than or equal to 90cm.
6. pave shaping
The present invention is paved using man-machine cooperation, is first shakeout roughly with bull-dozer, then adopts land leveller essence flat, level land
The group that paves of 10m fit on 3-5 people after machine, timely treated aggregate non-uniform phenomenon.
7. roll
The present invention is using shaking rolling method quiet again after first quiet, it then follows first gently weigh afterwards, first slowly after overlapping former of fast, wheelmark
Then;The road roller speed of travel is 1.5-1.7km/h, and degree of compaction can suitably accelerate rolling speed after increasing, and round trip is one time,
First adopt road roller static pressure 2-3 time, in place of finding out injustice, use artificial filling-in, then roll 4-5 time with vibrated roller, finally
Using road roller static pressure 2-3 time.
8., after the completion of the first Rotating fields health preserving, carry out second layer structure sheaf construction:By the mountain calculating skin stone by certain
Width, thickness shakeout, carry out again shaping, roll, health preserving.
The present invention is applied to build advanced road and ordinary road, is particularly suited for coastal cities road foundation and once builds
The needs becoming.It can make, and China is wet, soft, freeze, saline and alkaline earth roadbed compaction quality and intensity are reached advanced world standards.
Claims (3)
1. a kind of mountain skin stone processes soft soil roadbed method it is characterised in that comprising the steps:
A. soft soil roadbed clear table:Full width is down dug from original ground first, and removing table soil thickness is 40-60cm, detects original place at any time
Absolute altitude after face absolute altitude and clear table, to ensure that ground eliminating impurities are clean and ensure filling-up thickness;Measure bottom width degree after clear table, with
Meet roadbed filling width, place soil during the clear table of roadbed and be more than 2m from clear table boundary;
B, surveying and locating:Lay double-direction control stake on the basis of SURVEYING CONTROL NETWORK, form 10*10m and control net, run into corner
It is encrypted, and mark the elevation after empty paving elevation and compacting;
C, particle diameter is transported to scene less than or equal to 60cm mountain skin building stones, then material is paved, shaping, roll, health preserving;The side of paving
Method is to be paved using man-machine cooperation, is first shakeout roughly with bull-dozer, then adopts land leveller essence flat, 10m after land leveller
The group that paves of fit on 3-5 people, timely treated aggregate non-uniform phenomenon;Using the rolling method that first quiet rear shake is quiet again, press road
The machine speed of travel is 1.5-1.7km/h, first uses road roller static pressure 2-3 time, in place of finding out injustice, uses artificial filling-in, then with shaking
Dynamic road roller rolls 4-5 time, finally adopts road roller static pressure 2-3 time;
D., after the completion of the first Rotating fields health preserving, carry out second layer structure sheaf construction:By the mountain calculating skin stone by design width,
Thickness shakeouts, carry out again shaping, roll, health preserving.
2. mountain according to claim 1 skin stone processes soft soil roadbed method it is characterised in that the pine of empty paving elevation spreads system
Number is 1.30.
3. mountain according to claim 1 skin stone processes soft soil roadbed method it is characterised in that described mountain skin stone fills
Thickness is more than or equal to 90cm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510114383.XA CN104762859B (en) | 2015-03-17 | 2015-03-17 | Mountain skin stone processes soft soil roadbed method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510114383.XA CN104762859B (en) | 2015-03-17 | 2015-03-17 | Mountain skin stone processes soft soil roadbed method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104762859A CN104762859A (en) | 2015-07-08 |
CN104762859B true CN104762859B (en) | 2017-03-01 |
Family
ID=53644928
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510114383.XA Active CN104762859B (en) | 2015-03-17 | 2015-03-17 | Mountain skin stone processes soft soil roadbed method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104762859B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108611930A (en) * | 2018-06-07 | 2018-10-02 | 重庆工业职业技术学院 | A kind of laying method of track bed |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109235389B (en) * | 2018-11-20 | 2023-06-30 | 国家电网有限公司 | Pumped storage power station storehouse basin levels device |
CN113106926A (en) * | 2021-05-12 | 2021-07-13 | 中国二十二冶集团有限公司 | Construction method for foundation backfill of blown-fill sand reclamation foundation in coastal region |
Family Cites Families (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CH664405A5 (en) * | 1983-09-01 | 1988-02-29 | Plana Eng Ag | METHOD FOR STABILIZING A SOIL LAYER. |
NL1023902C2 (en) * | 2003-07-11 | 2005-01-12 | Ooms Avenhorn Holding Bv | Method for reinforcing a soil for a traffic route, such as a road or a railroad track. |
JP5166790B2 (en) * | 2007-07-23 | 2013-03-21 | 祐一 塚田 | Artificial turf base roadbed and its construction method |
CN202232063U (en) * | 2011-09-20 | 2012-05-30 | 北京正和恒基滨水生态环境治理有限公司 | Saline-alkali soil treatment system |
CN102493305A (en) * | 2011-11-29 | 2012-06-13 | 上海市城市建设设计研究总院 | Subgrade treatment structure of soft soil areas and construction technology thereof |
CN102912784A (en) * | 2012-11-08 | 2013-02-06 | 沈阳建筑大学 | Geotechnical cloth, twig and mountain stone combined treatment soft soil foundation |
CN102912702A (en) * | 2012-11-08 | 2013-02-06 | 沈阳建筑大学 | Soft soil subgrade treatment method adopting spodosol and hill-skill soil |
CN203475269U (en) * | 2013-07-24 | 2014-03-12 | 盘锦斯比瑞涂装有限公司 | Embossed terrace |
-
2015
- 2015-03-17 CN CN201510114383.XA patent/CN104762859B/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108611930A (en) * | 2018-06-07 | 2018-10-02 | 重庆工业职业技术学院 | A kind of laying method of track bed |
Also Published As
Publication number | Publication date |
---|---|
CN104762859A (en) | 2015-07-08 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103628363B (en) | Construction method for filling and building subgrade by using silty-fine sand as filling materials | |
CN103790166B (en) | Method for treating foundation of loess area saturated zone slope filling and digging joint part | |
CN104358188A (en) | Filling construction method for collapsible loess subgrade | |
CN105297571B (en) | A kind of mud stone filled-up ground structure and its construction method | |
CN113445396B (en) | High-fill road foundation filling construction method for high liquid limit soil road section | |
CN106522074A (en) | Construction technology for gravel-pebble-soil roadbed of expressway | |
CN106245503A (en) | A kind of for rendzinas control debulking methods in roadbed filling | |
CN206828898U (en) | A kind of roadbed for filling high liquid limit soil | |
CN104762859B (en) | Mountain skin stone processes soft soil roadbed method | |
CN106192698A (en) | Highway pavement rubblization processes recycling laying construction structure and technique | |
CN101311418A (en) | Exchange filling method for deep-foundation pit and large area equipment foundation | |
CN104652238A (en) | Barrier-free base construction method for urban roads | |
CN104179105B (en) | A kind of contrary sequence method rigid pile composite foundation construction method | |
CN107489137A (en) | A kind of method that collapsible loess foundation is handled using cement soil padding | |
CN103161109A (en) | Method for subgrade filling of peat soil subgrade by sea sand | |
CN105464069A (en) | Compaction process of collapsible loess roadbeds | |
CN107653758A (en) | Laterite bound edge wind-blown sand fill subgrade construction method | |
CN116815733A (en) | Construction process for quality control of high-fill roadbed in collapsible loess area | |
CN110761137B (en) | Non-damage layered rolling construction method using cement-modified fine silt as roadbed filler | |
CN109183541A (en) | A kind of roadbed construction method and application using gravelly sand group material | |
CN112359688A (en) | Construction method for in-situ cold regeneration of highway cement stabilized macadam base | |
CN105297572B (en) | A kind of ever-frozen ground embankment construction method | |
CN104863031A (en) | Karst region ductile anti-collapse roadbed structure and construction method of Karst region ductile anti-sag roadbed structure | |
CN109736155A (en) | Building castoff Filling Expressway Subgrade construction | |
CN111676951A (en) | Construction method for treating shallow soft soil layer by combining stone throwing, silt squeezing and sand bag well treatment |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
EXSB | Decision made by sipo to initiate substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CP03 | Change of name, title or address | ||
CP03 | Change of name, title or address |
Address after: 212300, No. 88, south two ring road, Danyang, Jiangsu, Zhenjiang Patentee after: Kao ecological engineering Limited by Share Ltd Address before: 212300 Zhenjiang City, Danyang Province, South Ring Road No. 99, No., No. two Patentee before: Jiangsu Huawang Horticultural Co.,Ltd. |