CN104697175B - Flange assembly and water heater - Google Patents
Flange assembly and water heater Download PDFInfo
- Publication number
- CN104697175B CN104697175B CN201510095129.XA CN201510095129A CN104697175B CN 104697175 B CN104697175 B CN 104697175B CN 201510095129 A CN201510095129 A CN 201510095129A CN 104697175 B CN104697175 B CN 104697175B
- Authority
- CN
- China
- Prior art keywords
- flange
- connecting rod
- depression bar
- seat
- blind
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Mutual Connection Of Rods And Tubes (AREA)
- Connection Of Plates (AREA)
Abstract
The invention discloses the flange assembly on a kind of inner bag for water heater, the flange assembly includes, flange seat that flange assembly includes setting along the courage mouthful of inner bag, on flange seat to close between courage mouthful and heater the blind flange in gap and blind flange is fastened the connector on flange seat by least one;Connector includes connecting rod and depression bar, and connecting rod has relative first end and the second end, and first end and the flange seat of connecting rod are connected, and blind flange is run through at the second end of connecting rod, is connected with depression bar rotation;The pivot center of depression bar is vertical with connecting rod;One end that depression bar is connected with connecting rod is provided with top, when being connected in the top of depression bar on blind flange, and depression bar fastens blind flange on flange seat.The invention also discloses a kind of water heater.The present invention realizes non-bolt and the supporting installation of nut, you can blind flange is fastened on flange seat, has the advantages that easy to operate, efficiency of assembling is higher.
Description
Technical field
The present invention relates to a kind of flange assembly and water heater.
Background technology
The inner bag flange of existing water heater is mainly made up of parts such as flange seat, blind flange and packing rings.Wherein blind flange
Coordinated by multiple (generally 5) screw bolt and nut and be installed on flange seat.It is readily apparent that in assembling or disassembly method
It is required for carrying out nutting operation during orchid lid so that installation and removal process is all more time-consuming, particularly when bolt and spiral shell
When female quantity is excessive, the efficiency of assembling of blind flange will be substantially reduced, while also result in the inconvenience of subsequent maintenance.
The content of the invention
It is a primary object of the present invention to provide a kind of flange assembly, it is intended to realize the non-bolt and nut peace of blind flange
Dress, makes the installation operation of blind flange easier.
To achieve the above object, the present invention provides a kind of flange assembly, and the flange assembly is used for the inner bag of water heater, should
Flange assembly include the flange seat set along the courage mouthful of the inner bag and on the flange seat to close the courage mouthful with
The blind flange in gap between heater, the flange assembly also includes at least one and fastens the blind flange in the flange seat
On connector;The connector includes connecting rod and depression bar, and the connecting rod has relative first end and the second end, the connecting rod
First end be connected with the flange seat, the blind flange is run through at the second end of the connecting rod, rotates and connects with the depression bar
Connect;The pivot center of the depression bar is vertical with the connecting rod;One end that the depression bar is connected with the connecting rod is provided with top,
When the top of the depression bar is connected on the blind flange, the depression bar fastens the blind flange on the flange seat.
Preferably, the first end of the connecting rod is provided with limiting section, is formed between the flange seat and the outer wall of the inner bag
There is cavity, the position of the flange seat correspondence connecting rod is provided with the first through hole passed through for the limiting section of the connecting rod and limitation
The second through hole that the limiting section of the connecting rod is passed through, the first through hole is connected with second through hole, for the connecting rod from
The first through hole is moved in the second through hole.
Preferably, the position of the correspondence connecting rod is provided with the 3rd passed through for the second end of the connecting rod on the blind flange
Through hole.
Preferably, the connector also includes rotating shaft, and the connecting rod is provided with the first axle being adapted to the axis of rotation
Hole, the depression bar is connected with the axis of rotation.
Preferably, the second end of the connecting rod is provided with installation portion in disk form, and the axis hole is on the installation portion.
Preferably, the depression bar is connected in cylinder, and the diameter of the cylindrical depression bar by the depression bar with the connecting rod
One end to the other end of the depression bar successively decrease.
Preferably, the quantity of the connector is multiple, and the line of connector described at least two passes through the courage mouthful
Center.
Preferably, the quantity of the connector is multiple, and each connector is surround on the flange seat and blind flange
The courage mouthful is evenly arranged.
Preferably, the flange seat is set in annular, and the blind flange is also set in annular, and the blind flange
The flange in the flange seat direction is provided with outward flange.
In addition, to achieve the above object, the present invention also provides a kind of water heater, the water heater includes method as described above
Blue component;The flange assembly includes the flange seat set along the courage mouthful of the inner bag and on the flange seat to close
The blind flange in gap between the courage mouthful and heater, the flange assembly also includes at least one and fastens the blind flange
Connector on the flange seat;The connector includes connecting rod and depression bar, and the connecting rod has relative first end and second
End, the first end of the connecting rod is connected with the flange seat, and the second end of the connecting rod is and described through the blind flange
Depression bar rotates connection;The pivot center of the depression bar is vertical with the connecting rod;One end that the depression bar is connected with the connecting rod is set
There is top, when being connected in the top of the depression bar on the blind flange, the depression bar fastens the blind flange in institute
State on flange seat.
The present invention by set flange seat that the courage mouthful along inner bag is set and on the flange seat it is described to close
The blind flange in gap between courage mouthful and heater, the blind flange is fastened in the flange seat by one or more connector
On;Wherein, the connector includes connecting rod and depression bar, and the connecting rod has relative first end and the second end, the first of the connecting rod
End is connected with the flange seat, and the blind flange is run through at the second end of the connecting rod, rotates and is connected with the depression bar;The pressure
The pivot center of bar is vertical with the connecting rod;One end that the depression bar is connected with the connecting rod is provided with top.During installation, rotate
The depression bar, when the top of the depression bar is connected on the blind flange, the depression bar fastens the blind flange in institute
State on flange seat, blind flange can be fastened on flange seat by realization without screw bolt and nut, and during dismounting, as long as rotating pressure
Bar to corresponding position can be such that blind flange is loosened on flange seat, operate very convenient.
Brief description of the drawings
Fig. 1 is the structural representation of the embodiment of flange assembly one of the present invention;
Fig. 2 is another visual angle figure of the flange assembly shown in Fig. 1;
Fig. 3 is the flange assembly and the assembling figure of inner bag shown in Fig. 1;
Fig. 4 is another visual angle figure that the flange assembly shown in Fig. 3 is assembled with inner bag;
Fig. 5 is the flange assembly and another assembling figure of inner bag shown in Fig. 1.
The realization, functional characteristics and advantage of the object of the invention will be described further referring to the drawings in conjunction with the embodiments.
Embodiment
It should be appreciated that the specific embodiments described herein are merely illustrative of the present invention, it is not intended to limit the present invention.
The present invention provides a kind of flange assembly, and the flange assembly is applied on the inner bag of water heater, to by the courage of inner bag
Gap closing between mouth and heater, plays a part of preventing inner bag courage mouthful leak.
Referring to figs. 1 to Fig. 5, in one embodiment, the flange assembly includes the method set along the courage mouthful 5a of the inner bag 5
Blue seat 10 and on the flange seat 10 to close the blind flange 20 in gap between the courage mouthful 5a and heater, wherein,
The blind flange 20 is fastened on the flange seat 10 by one or more connector 30.
In the present embodiment, the connector 30 includes connecting rod 31 and depression bar 32, and the connecting rod 31 has relative first end
With the second end, the first end of the connecting rod 31 is connected with the flange seat 10, and the second end of the connecting rod 31 is through described
Blind flange 20, rotates with the depression bar 32 and is connected;The pivot center of the depression bar 32 is vertical with the connecting rod 31;The depression bar 32
The one end being connected with the connecting rod 31 is convexly equipped with top 32a, and top 32a is curved or circular arc is set, it is necessary to say
Bright, after the blind flange 20 is installed, the beeline of top 32a to flange seat 10 is equal to or slightly less than blind flange 20
Thickness.When fixed, the depression bar 32 is rotated, the depression bar 32 can be made to promote blind flange 20 to be moved to the direction of flange seat 10,
And when the top 32a of the depression bar 32 is connected on the blind flange 20, the depression bar 32 fastens the blind flange 20
On the flange seat 10, blind flange 20 can be fastened on flange seat 10 by realization without screw bolt and nut, and during dismounting, only
Rotating depression bar 32 to corresponding position can be such that blind flange 20 is loosened on flange seat 10, operate very convenient.Also,
Because the installation operation of blind flange 20 is very easy so that overall efficiency of assembling is higher, and then reduces assembly cost.
In the present embodiment, the first end of the connecting rod 31 can also be to be detachably connected with the flange seat 10:The company
The first end of bar 31 is provided with limiting section 311, and cavity is formed between the outer wall of the flange seat 10 and the inner bag 5, and (figure is not marked
Show), the position of the correspondence of flange seat 10 connecting rod 31 is provided with the first through hole passed through for the limiting section 311 of the connecting rod 31
101 the second through holes 102 passed through with the limiting section 311 for limiting the connecting rod 31, the first through hole 101 and second through hole
102 connections, so that the connecting rod 31 is moved in the second through hole 102 from the first through hole 101.
Specifically, the limiting section 311 can be cylindrical, preferably cylindrical, and is structure as a whole with connecting rod 31, the cylinder
The diameter with diameter greater than the connecting rod 31 of the limiting section 311 of structure and the aperture of the second through hole 102, less than or equal to
The aperture of one through hole 101.
During installation, the limiting section 311 of connecting rod 31 is passed through from first through hole 101, to stretch in cavity, the then company of stirring
Bar 31 makes the connecting rod 31 move in the second through hole 102, is coordinated by the second through hole 102 and limiting section 311, limits connecting rod 31
With the position of flange seat 10, to realize that connecting rod 31 is connected with the flange seat 10;And when dismantling, connecting rod 31 need to only be dialed to the
In one through hole 101, then pull connecting rod 31, you can limiting section 311 is exited from cavity, realize the dismounting of connecting rod 31.
In addition, in reference picture 3, the present embodiment, the position of the correspondence connecting rod 31 is provided with for described on the blind flange 20
The third through-hole 103 that second end of connecting rod 31 is passed through, during in order to mounting flange lid 20, connecting rod 31 passes through blind flange 20.
In the present embodiment, when the quantity of the connector 30 is multiple, the line of connector 30 is worn described at least two
Cross the courage mouthful 5a center (when courage mouthful 5a is rounded, namely the circular courage mouthful 5a the center of circle), so that blind flange 20 is locked at
Relative securement after on the flange seat 10.Certainly or, each connector 30 is on the flange seat 10 and blind flange 20
It is evenly arranged around the courage mouthful 5a, so that blind flange 20 is more consolidated after being locked on the flange seat 10.Originally it is preferable to carry out
In example, the quantity of the connector 30 is five, such as Fig. 2.
In the present embodiment, the flange seat 10 can be square, can also be set in annular, certainly, the blind flange
20 shape and the shape of the flange seat 10 are correspondingly arranged, and the flange is provided with the outward flange of the blind flange 20
The annular flange 21 in 10 directions of seat.It can be readily appreciated that the annular formation of flange 21 tube-in-tube structure so that during installation, the flange
Lid 20 can be socketed on flange seat 10 by the tube-in-tube structure, facilitated and carried out installation positioning to blind flange 20, and make method
Blue lid 20 is more consolidated after installing.
In the present embodiment, the depression bar 32 is rotated with the connecting rod 31 by rotating shaft 33 and is connected, wherein, the rotating shaft 33 can
To be affixed on the connecting rod 31 or be fixed on the depression bar 32, it can also be respectively at the connecting rod 31 and pressure
Bar 32 is rotated in connection, the present embodiment, it is preferred to use latter implementation mode, reference picture 3 to Fig. 5 is in this embodiment, described
Connecting rod 31 is provided with rotates the first axis hole 301 being adapted to the rotating shaft 33, and the depression bar 32 is provided with and 33 turns of the rotating shaft
Second axis hole 302 of dynamic adaptation.During installation, rotating shaft 33 only need to be sequentially passed through to the first axis hole 301 and the second axis hole 302, you can
Realize that depression bar 32 is rotated with connecting rod 31 to be connected.
In the present embodiment, the second end of the connecting rod 31 is provided with installation portion 312 in disk form, first axis hole 301
On the installation portion 312;One end that the depression bar 32 is connected with the connecting rod 31 is respectively provided with described provided with two
Formed between the installation journal stirrup 321 of two axis holes 302, this two installation journal stirrups 321 and insert the installation installed for the installation portion 312
Groove 322.During installation, installation portion 312 is inserted into mounting groove 322 first, then by rotating shaft 33 through the first axis hole 301 and the
After two axis holes 302, the two ends of the rotating shaft 33 are processed, so that rotating shaft 33 is to installation portion 312 and two installation journal stirrups
321 progress are spacing;Wherein the rotating shaft 33 can be realized in the form of pin, and only its one end need to be processed after installation,
Such as welding metal block, realizes that the rotating shaft 33 is carried out to installation portion 312 and two installation journal stirrups 321 spacing.
In the present embodiment, the top 32a be located at the depression bar 32 circumferential side wall on, and close to the depression bar 32 with
One end that the connecting rod 31 is connected, when being connected in order to top 32a on the blind flange 20, the accumbency of depression bar 32 exists
On blind flange 20, it is to avoid space-consuming.
In the present embodiment, the shape of the depression bar 32 can be the shape of rule, such as cylindricality, plate shape or not advise
In shape then, this preferred embodiment, the cylinder of the depression bar 32, the diameter of the cylindrical depression bar 32 by the depression bar 32 with it is described
One end to the other end of the depression bar 32 that connecting rod 31 is connected successively decreases, and it is larger that the top 32a is located at the volume of depression bar 32
One end, so can preferably ensure that top 32a is connected on the blind flange 20.
To sum up, the integral installation process below in conjunction with 1 to 5 pair of flange assembly of the present invention of accompanying drawing carries out overall elaboration:
Gone forward blind flange 20 is installed on into flange seat 10, connecting rod 31 and depression bar 32 can be installed on blind flange 20 in advance
On, its specific installation process is:Installation portion 312 is inserted into mounting groove 322 first, rotating shaft 33 is then passed through into the first axis hole
301 and second after axis hole 302, are processed to the two ends of the rotating shaft 33, so that rotating shaft 33 is pacified to installation portion 312 and two
Dress journal stirrup 321 carries out spacing;Install after connecting rod 31 and depression bar 32, it is possible to convenient that blind flange 20 is installed on flange seat 10
On;Now, then by the limiting section 311 of connecting rod 31 passed through from first through hole 101, to stretch in cavity, then stir connecting rod 31
The connecting rod 31 is moved in the second through hole 102, coordinated by the second through hole 102 and limiting section 311, limit connecting rod 31 and method
The position of blue seat 10, then blind flange 20 is socketed on flange seat 10, depression bar 32 is then rotated, the depression bar 32 is promoted blind flange
20 move to the direction of flange seat 10, until when the top 32a of the depression bar 32 is connected on the blind flange 20, stopping turning
Dynamic, now the depression bar 32 fastens the blind flange 20 on the flange seat 10, it is ensured that blind flange 20 is firmly fixed
On flange seat 10, and whole assembling process is without twisting screw bolt and nut so that operates very convenient, improves assembling effect
Rate, reduces assembly cost.
The present invention also provides a kind of water heater, and the water heater includes above-mentioned flange assembly;The detailed knot of the flange assembly
Structure can refer to above-described embodiment, and here is omitted;It is understood that due to having used above-mentioned flange group in water heater
Part, therefore, the embodiment of the water heater include whole technical schemes of above-mentioned flange assembly whole embodiments, and the skill reached
Art effect is also identical, will not be repeated here.
The preferred embodiments of the present invention are these are only, are not intended to limit the scope of the invention, it is every to utilize this hair
Equivalent structure or equivalent flow conversion that bright specification and accompanying drawing content are made, or directly or indirectly it is used in other related skills
Art field, is included within the scope of the present invention.
Claims (9)
1. a kind of flange assembly, for the inner bag of water heater, the flange assembly includes what is set along the courage mouthful of the inner bag
Flange seat and on the flange seat to close the blind flange in gap between the courage mouthful and heater, it is characterised in that
The flange assembly also includes at least one and the blind flange is fastened into the connector on the flange seat;The connector bag
Include connecting rod and depression bar, the connecting rod has relative first end and the second end, the first end of the connecting rod connects with the flange seat
Fixation is connect, the second end of the connecting rod runs through the blind flange, rotates and be connected with the depression bar;The pivot center of the depression bar with
The connecting rod is vertical;One end that the depression bar is connected with the connecting rod is provided with top, and the top is curved or circular arc
Shape is set, when being connected in the top of the depression bar on the blind flange, and the depression bar fastens the blind flange described
On flange seat;
The first end of the connecting rod is provided with limiting section, and cavity is formed between the flange seat and the outer wall of the inner bag, described
The position of the flange seat correspondence connecting rod is provided with the first through hole passed through for the limiting section of the connecting rod and limits the connecting rod
The second through hole that limiting section is passed through, the first through hole is connected with second through hole, so that the connecting rod is logical from described first
Hole is moved in the second through hole.
2. flange assembly as claimed in claim 1, it is characterised in that the position of the correspondence connecting rod is provided with the blind flange
The third through-hole passed through for the second end of the connecting rod.
3. flange assembly as claimed in claim 2, it is characterised in that the connector also includes setting on rotating shaft, the connecting rod
There is the first axis hole being adapted to the axis of rotation, the depression bar is connected with the axis of rotation.
4. flange assembly as claimed in claim 3, it is characterised in that the second end of the connecting rod is provided with installation in disk form
Portion, the axis hole is on the installation portion.
5. flange assembly as claimed in claim 1, it is characterised in that the depression bar is in cylinder, and the cylindrical depression bar
One end to the other end of the depression bar that is connected by the depression bar with the connecting rod of diameter successively decrease.
6. flange assembly as claimed in claim 1, it is characterised in that the quantity of the connector be it is multiple, and at least two
The line of the connector passes through the center of the courage mouthful.
7. flange assembly as claimed in claim 1, it is characterised in that the quantity of the connector is multiple, each connection
Part is evenly arranged on the flange seat and blind flange around the courage mouthful.
8. flange assembly as claimed in claim 1, it is characterised in that the flange seat is set in annular, the blind flange
Also set in annular, and the flange in the flange seat direction is provided with the outward flange of the blind flange.
9. a kind of water heater, it is characterised in that the water heater includes the flange assembly as described in claim any one of 1-8.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510095129.XA CN104697175B (en) | 2015-03-03 | 2015-03-03 | Flange assembly and water heater |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510095129.XA CN104697175B (en) | 2015-03-03 | 2015-03-03 | Flange assembly and water heater |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104697175A CN104697175A (en) | 2015-06-10 |
CN104697175B true CN104697175B (en) | 2017-07-11 |
Family
ID=53344558
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510095129.XA Active CN104697175B (en) | 2015-03-03 | 2015-03-03 | Flange assembly and water heater |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104697175B (en) |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE10203854A1 (en) * | 2002-01-31 | 2003-08-07 | Eisenwerke Fried Wilh Dueker A | Connecting flange for flanged pipes is made up of two halves with overlapping sections, one section being fastened together by bolt so that halves can pivot without slipping while other is e.g. loosely bolted together |
CN201145392Y (en) * | 2007-08-16 | 2008-11-05 | 赛德隆国际电器(中国)有限公司 | Heating pipe and inner container insulating electric water heater |
CN201359001Y (en) * | 2009-02-06 | 2009-12-09 | 黄好忠 | Suction cup |
CN102062466A (en) * | 2011-01-05 | 2011-05-18 | 广东格美淇电器有限公司 | Quick heating and heat storage integrated electric water heater |
CN203532737U (en) * | 2013-11-06 | 2014-04-09 | 天津埃柯特测控技术有限公司 | Rapid and efficient sealing structure |
CN104006238A (en) * | 2014-04-23 | 2014-08-27 | 浙江固的管业有限公司 | Flange |
CN204494813U (en) * | 2015-03-03 | 2015-07-22 | 芜湖美的厨卫电器制造有限公司 | Flange assembly and water heater |
-
2015
- 2015-03-03 CN CN201510095129.XA patent/CN104697175B/en active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE10203854A1 (en) * | 2002-01-31 | 2003-08-07 | Eisenwerke Fried Wilh Dueker A | Connecting flange for flanged pipes is made up of two halves with overlapping sections, one section being fastened together by bolt so that halves can pivot without slipping while other is e.g. loosely bolted together |
CN201145392Y (en) * | 2007-08-16 | 2008-11-05 | 赛德隆国际电器(中国)有限公司 | Heating pipe and inner container insulating electric water heater |
CN201359001Y (en) * | 2009-02-06 | 2009-12-09 | 黄好忠 | Suction cup |
CN102062466A (en) * | 2011-01-05 | 2011-05-18 | 广东格美淇电器有限公司 | Quick heating and heat storage integrated electric water heater |
CN203532737U (en) * | 2013-11-06 | 2014-04-09 | 天津埃柯特测控技术有限公司 | Rapid and efficient sealing structure |
CN104006238A (en) * | 2014-04-23 | 2014-08-27 | 浙江固的管业有限公司 | Flange |
CN204494813U (en) * | 2015-03-03 | 2015-07-22 | 芜湖美的厨卫电器制造有限公司 | Flange assembly and water heater |
Also Published As
Publication number | Publication date |
---|---|
CN104697175A (en) | 2015-06-10 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107813261A (en) | Split type torque adjusting mechanism for disassembling and assembling threaded locking ring | |
CN106133331A (en) | Ceiling fan | |
CN104697175B (en) | Flange assembly and water heater | |
CN206682462U (en) | A kind of quick be hinged handling flange | |
CN204494813U (en) | Flange assembly and water heater | |
CN207454482U (en) | It is a kind of to facilitate the installation adjustable U-bolts of width | |
CN208713841U (en) | A kind of extracting tool for cigarette unit spider oil seal | |
CN107542984A (en) | It is blown pipe flange Quick Connect Kit and its application method | |
CN207145825U (en) | A kind of ready-packaged joint of toilet seat water intaking valve | |
CN106697168A (en) | Coaxial middle motor driving system hanging bracket | |
CN206071703U (en) | Vehicle and its fan ring flange | |
CN205253992U (en) | Straining device of medical metal intubate braider | |
CN209335502U (en) | A kind of adjustable sleeve of electric wrench | |
CN107842657A (en) | A kind of pipe breakage of Fast Installation, which is speedily carried out rescue work, uses anchor ear | |
CN205744563U (en) | Nuclear power axial flow blower high-intensity protective net | |
CN207267794U (en) | Fixer for mandrel for the cold dismounting of scraper winch | |
CN201723602U (en) | Draw bail of socked shaft | |
CN205350258U (en) | Initiative spiral bevel gear | |
CN206154224U (en) | Split type torque adjusting mechanism for disassembling and assembling threaded locking ring | |
CN203641207U (en) | Expanded connection component | |
CN104643941B (en) | A kind of retaining mechanism | |
CN221186357U (en) | Bolt dismouting frock in restricted space | |
CN207920848U (en) | A kind of star-wheel worm pump star-wheel work knuckle-tooth mounting structure | |
CN209687925U (en) | A kind of tensioning nut for the adjustment of double row tapered roller bearing clearance | |
CN207261929U (en) | A kind of radial plunger type motor |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right |
Effective date of registration: 20221228 Address after: 241000 west side of 3 / F, No.5 office building, new energy and new materials gathering area, Fuzhou Road, Jiangbei District, Wuhu City, Anhui Province Patentee after: Wuhu Midea intelligent kitchen electricity Manufacturing Co.,Ltd. Address before: 241009 Wan Chun East Road, East Wuhu economic and Technological Development Zone, Wuhu, Anhui Patentee before: WUHU MIDEA KITCHEN AND BATH APPLIANCES MFG. Co.,Ltd. |
|